Project Title:Replace Paint Booth and Drying Oven, Building 110, Watervliet Arsenal NY

1. This is a 100% Full and Open Competition w ith HUBZone preference procurement, and Design-Build Best Value Tradeoff.

2. NAICS Code: 236220, Size Standard: $45,000,000.

3. Project Magnitude Range: $10,000,000-$25,000,000.

4. Submit proposals no later than 2:00PM EST on 14 August 2023 via e-mail to mohenda.r.surage@usace.army.mil nicholas.p.emanuel@usace.army.mil. File size is limited to 25MB per email. It is advised to submit e-mail 2 hours in advance to ensure the proposal is submitted timely.

5. POC: Mohenda Surage, Contract Specialist. Tel: 917-790-8088, Email: mohenda.r.surage@usace.army.mil

MOHENDA R SURAGE 917-790-8088

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

13-Jul-2023

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______5 calendar days and complete it w ithin ________820 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Specif ications

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________14 Aug 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

212-264-3013FAX:TEL: 917-790-8026 TEL: FAX:

W912DS23R0006 148

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Source Selection Plan

W912DS23S0009

CUI

Paint Booth and Drying Oven

Watervliet, NY

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job All cost in connection to the SUPPLY

FFP

All cost in connection to the SUPPLY of the PAINT BOOTH in accordance with the RFP FOB: Destination

PSC CD: Y1JZ

NET AMT

0002 1 Job All cost in connection to the SUPPLY

FFP

All cost in connection to the SUPPLY of the CURING OVEN in accordance with the RFP

CUI

Paint Booth and Drying Oven

0003 1 Job All costs in connection to DEMOLITION

FFP

All costs in connection to the DEMOLITION and REMOVAL of the existing PAINT BOOTH AND CURING OVEN in accordance with the RFP.

0004 1 Job INSTALL of PAINT BOOTH AND CURING OVEN

FFP

All cost in connection to the INSTALL of the PAINT BOOTH AND CURING OVEN in accordance with the RFP.

CUI

Paint Booth and Drying Oven

0005 1 Job DESIGN of PAINT BOOTH AND CURING OVEN

FFP

All cost in connection to DESIGN of the PAINT BOOTH AND CURING OVEN SUPPORT FEATURES including, but not limited to, foundation and building system modifications/utility tie-ins in accordance with Section 01 10 00 of the

RFP.

0006 1 Job Cost associated with CONSTRUCTION

FFP

All cost associated with CONSTRUCTION of CLIN 0003 in accordance with Section 01 10 00 of the RFP.

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

CUI

Paint Booth and Drying Oven

0001 820 dys. ANP 1 WATERVLIET RESIDENCY

SCOTT KOSNICK

CONSTRUCTION DIVISION 1

BUFFINGTON STREET, BL

E 206

WATERVLIET NY 12189

518-266-6362

W912DS

0002 820 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0003 820 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0004 820 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0005 820 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0006 820 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

NOTES

Total Base Bid Items (CLINs 0001 through 0006) $_________________________________

NOTES:

(1) Total Offer shall include costs associated with each item number including all overhead and profit.

(2) Total Offer shall include bonding costs associated with each Construction item number.

(3) Offerors must submit a price for every CLIN. Failure to do so may result in Offer being unacceptable.

(4) CLINs 0001 and 0002 Supply, includes all costs for efforts related to design liability and completion of paint booth and curing oven design as well as any related costs for the contractor’s coordination. Designer coordination for efforts during construction shall be distributed amongst CLINs 0004 and 0005.

(5) Contract Duration is 820 days.

CUI

Paint Booth and Drying Oven

Section 00 21 00 - Instructions

ELECTRONIC PROPOSALS

(a) Definition.

Electronic proposal, as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via electronic commerce (see FAR Subpart 4.5 -- Electronic Commerce in Contracting).

(b) Offerors may submit electronic proposals as responses to this solicitation.

Electronic proposals are subject to the same rules as paper proposals.

(c) The format for electronic proposals in this solicitation is:

PDF documents sent via email, ONLY to the Contract Specialist and Contracting Officer, as listed below:

Mohenda Surage: Email Address: mohenda.r.surage@usace.army.mil Nicholas Emanuel: Email Address: nicholas.p.emanuel@usace.army.mil

(d) If any portion of an electronic proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document --

(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;

(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and

(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.

(e) The Government reserves the right to make award solely on the electronic proposal.

However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.

(End of Provision)

ELECTRONIC PROPOSAL SUBMISSION

Submit proposals no later than 2:00PM EST on 14 August 2023 via e-mail to:

mohenda.r.surage@usace.army.mil nicholas.p.emanuel@usace.army.mil File size is limited to 25MB per email. It is advised to submit e-mail 2 hours in advance to ensure the proposal is submitted timely.

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018

CUI

Paint Booth and Drying Oven

52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

NOV 2021

52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7008 Only One Offer DEC 2022

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-

CUI

Paint Booth and Drying Oven

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

District Contracting Chief New York District Directorate of Contracting U.S. Army Corps of Engineers 26 Federal Plaza Room 16-300 New York, NY 10278-0090

Francis.Cashman@usace.army.mil

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Raymond J Pifer Email: raymond.j.pifer@usace.army.mil

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by

CUI

Paint Booth and Drying Oven paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov.far

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov.far

(End of clause)

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR 201) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of clause)

252.215-7008 ONLY ONE OFFER (DEC 2022)

(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was received, the Offeror agrees to--

CUI

Paint Booth and Drying Oven

(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable (10 U.S.C. 3705) or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C.

3702 and FAR 15.403-3); and

(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.

(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:

(1) Profit rate or fee (as applicable).

(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).

(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable [U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].

(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.

(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.

CUI

Paint Booth and Drying Oven

Section 00 21 16 - Instructions to Proposers

CPARS

The Federal Acquisition Regulation (FAR) requires that Past Performance Information (PPI) be collected on DoD Contracts. The Contractor Performance Assessment Reporting System (CPARS) is a webenabled application the Supports the completion, distribution and retrieval of all contract performance evaluations.

Contractor Representatives are responsible for reviewing and commenting on evaluations submitted on the Contractor Performance Assessment Reporting System (CPARS) website at: https://www.cpars.gov/index.htm.

General information for offerors: The clauses listed such as Davis Bacon, Permits and Responsibilities, etc. apply to the construction portion of the line items. There are supply clauses listed that apply to the supply portion of the line items such as Default clause and Buy American clauses.

EVALUATION FACTORS

CRITERIA AND FACTORS FOR EVALUATION, BASIS OF AWARD, EVALUATION

CRITERIA, RATING SYSTEM AND DEFINITION

SECTION 00 22 10 – SELECTION PROCEDURES AND BASIS OF AWARD

BEST VALUE TRADE OFF

1.0 OVERVIEW

2.0 BASIS OF AWARD

3.0 GENERAL INSTRUCTIONS AND PROPOSAL SUBMISSION REQUIREMENTS

4.0 PROPOSAL INFORMATION AND RELATED EVALUATION FACTORS, SUBFACTORS AND

ELEMENTS

5.0 VOLUME 1 – PERFORMANCE CAPABILITY

5.1 TAB A – FACTOR 1 – PAST PERFORMANCE

5.2 TAB B – FACTOR 2 – PROPOSED CONTRACT DURATION, PHASING AND SUMMARY

SCHEDULE

5.3 TAB C – FACTOR 3 –TECHNICAL APPROACH

6.0 VOLUME 2 – SMALL BUSINESS

6.1 TAB A – FACTOR 4 – SMALL BUSINESS PARTICIPATION PLAN

6.2 TAB B – FACTOR 4 – PAST UTILIZATION OF SMALL BUSINESS

7.0 VOLUME 3 – FACTOR 5 – PRICE AND PRO FORMA INFORMATION

7.1 TAB A – PRICE (STANDARD FORM 1442, PROPOSAL DATA SHEET AND CONTRACT LINE

ITEM SCHEDULE)

7.2 TAB B – BID GUARANTEE

7.3 TAB C – SELF PERFORMED WORK

ATTACHMENTS

1 – PROPOSAL DATA SHEETS

2 – PAST PERFORMANCE EVALUATION QUESTIONNAIRE

3 – SPECIALIZED EXPERIENCE PRIME CONTRACTOR OR KEY SUB CONTRACTOR

4 – SMALL BUSINESS PARTICIPATION PLAN

CUI

Paint Booth and Drying Oven

1.0 OVERVIEW

This is a single-step "Best Value Trade Off" solicitation in accordance with Federal Acquisition Regulation (FAR) 15.101-1 for the Construction of the Paint Booth and Drying Oven located at Watervliet Arsenal, NY. The Government will evaluate the proposals in accordance with the criteria described herein, and award a firm fixed price contract to the responsible Offeror, whose proposal conforms to all the terms and conditions of the solicitation and whose proposal is the Best Value Tradeoff (BVTO), to the Government.

2.0 BASIS OF AWARD

This is a Best Value Trade Off procurement where the Contracting Officer will award a firm fixed price Construction contract to the responsible Offeror whose proposal the Source Selection Authority and Contracting Officer have determined conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, considering all non-price factors described herein, and price.

All technical factors 1-4 when combined are approximately equal in importance to price. Technical factor 4 is the least important technical factor. Technical factors 1, 2 and 3 are of equal importance to each other and are less important than technical factor 4. The intent of this solicitation is to obtain the best proposal within an acceptable range. After the Government individually evaluates and rates each proposal, the Source Selection Authority and Contracting Officer will compare proposals to determine which proposal represents the best value. Analysis of the price to determine which Offeror’s proposal represents the best value to the Government will be performed in two steps.

The price used in the trade-off analysis shall be the aggregate amount for the base items(CLINS 0001- 0006). The trade-off analysis will be conducted, and a best value proposal will be determined. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in FAR 15.001. If there is a lower priced, conforming offer(s), the Source Selection Official must determine that the added value of a more expensive proposal (within an acceptable range) would justify award to that Offeror. The magnitude of the project is between $15,000,000 and $25,000,000.

As part of the evaluation, the Government will evaluate betterments in proposals relative to the minimum standards in the RFP to determine if they offer additional value to the Government. In addition, innovations in proposals will be evaluated to determine if creative ideas of the Offeror are a better value to the Government compared to the minimum criteria.

3.0 GENERAL INSTRUCTIONS AND PROPOSAL SUBMISSION REQUIREMENTS

3.1 GENERAL INSTRUCTIONS

3.1.1 Who May Submit:

i. Competition will be unrestricted (i.e. open to all businesses regardless of Small

Business status). Any legally organized Offeror may submit a proposal.

3.1.2 Inquiries about this solicitation:

i. Prospective Offerors should submit inquiries related to this solicitation only by e-mail to: E-MAIL ADDRESS: Mohenda.R.Surage@usace.army.mil Include the solicitation number, and project title with any questions/clarifications. Written questions must be received by this office not later than 7 calendar days prior to the date set for receipt of offers.

TELEPHONE INQUIRIES WILL NOT BE ACCEPTED.

Oral explanations or instructions are not binding. Any information given to an Offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

CUI

Paint Booth and Drying Oven

As this is a competitive negotiation acquisition, there is no public proposal opening and no information will be given out as to the number of Offerors or the results of the competition until all awards are made.

3.1.3 Page Limit and Size of Electronic Materials shall be submitted in the following volumes:

In order to effectively and equitably evaluate all proposals, the Contracting Officer/PCO must receive information sufficiently detailed to clearly address submission requirements as outlined below. Pages containing text shall be submitted electronically on standard 8- 1/2 x 11 inch size paper. Schedules, Drawings and/or sketches may be submitted electronically on paper not exceeding 11 x 17 inch paper, (each 11 x 17 counts as two pages). Use of 'TAB' pages are encouraged to identify each section of the proposal and shall not count against proposal's total page count. Each page of text shall be minimally single spaced with a minimum 12-point font and one inch margins all around. Any sheet with printed material (text or graphics) shall be considered a page, excluding dividers, cover sheets, letters of commitment, team agreements, and/or Joint Venture agreements.

3.1.4 Joint Ventures

i. When an Offeror is submitting a proposal as a joint venture, all members of the joint venture must sign the SF 1442 and any financial surety instrument that is required, unless a written agreement by all members of the joint venture is furnished with the proposal designating one firm with the legal authority to bind the other member(s) of the joint venture. Signatures on the written agreement designating one member of the joint venture as having legal authority to bind all other members of the joint venture must be executed by the duly authorized representatives of the respective joint venture members. All joint venture members will remain jointly and severally liable for all actions, representations, and other activities by the joint venture and by other joint venture members in connection with this solicitation and subsequent contract. A copy of the joint venture agreement and agreement providing evidence of the authority to legally bind all other members of the joint venture must be submitted with the Offeror’s

Volume Tab Title Maximum Pages

1 A Factor 1: Past Performance No Page Limit

B Factor 2: Proposed Contract Duration, Phasing and Summary Schedule

C Factor 3: Technical Approach 20

A Factor 4: Small Business Participation Plan No page limit

2 B Factor 4: Past Utilization of Small Business No page limit

3 A Factor 5: Price (Standard Form 1442 & Contract Line Item Schedule)

No page limit

3 B Factor 5: Bid Guarantee No page limit

3 C Factor 5: Self-Performed Work No page limit

CUI

Paint Booth and Drying Oven proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration.

ii. If submitting a proposal as a joint venture, the experience, past performance, and other information about each of the joint venture partners can be submitted for the joint venture. The experience of each joint venture partner will be considered the experience of the joint venture entity. Joint ventures must also submit the following additional documentation:

3.1.4.ii.1 A copy of the Joint Venture Agreement.

3.1.4.ii.2 A detailed statement outlining the following in terms of percentages, where appropriate:

3.1.4.ii.3 The relationship of the joint venture parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.

3.1.4.ii.4 The structure of the joint venture and decision making responsibilities of the joint venture parties in terms of who will control the manner and method of performance of the work under the contract.

3.1.4.ii.5 Identification of key personnel having the authority to bind the joint venture to any and all agreements, including any subcontracts, executed by the joint venture.

3.1.4.ii.6 Identification of party or parties maintaining the joint venture bank accounts for the payment of all expenses and the deposit of all receipts, keeping the books and records of the joint venture, and paying applicable taxes for the joint venture.

3.1.4.ii.7 Identification of party or parties having overall control of the joint venture.

iii. Other sections of the proposal shall identify, where appropriate, whether key personnel are employees of the individual joint venture entities and identify the entity, or whether they are hired directly as employees of the joint venture.

iv. A complete and legally binding document with all information required under this section titles “Joint Ventures” shall be included in Volume I of the proposal.

3.2 PROPOSAL SUBMISSION REQUIREMENTS

3.2.1 Proposal Requirements and Submission

Proposals should be submitted initially on the most favorable terms. Do not assume that Offerors will be contacted or afforded an opportunity to clarify, discuss or revise their proposals.

Do not submit any material not required by this solicitation (such as company or system brochures). Offerors shall meet all technical portions (construction criteria) of the RFP.

The fact that the technical specifications and the drawings are not evaluated factors during solicitation does not relieve the Offerors from meeting all technical, or other, requirements of the RFP.

CUI

Paint Booth and Drying Oven

The Government will not make assumptions concerning the intent, capabilities, or experiences of the Offerors. Clear identification of proposal details shall rest as sole responsibility of the Offeror. Therefore, the proposal shall meet the following basic requirements:

i. Proposals shall be typed and easy to read. Margins (1-inch) shall be clean and clear.

ii. Shall contain a Proposal Cover Sheet, to include the Offeror’s e-mail address, cell phone number, Name, Address, DUNS, and CAGE code. The proposal cover sheet is required by Provision “FAR 52.215-1, Instructions to Offerors— Competitive Acquisition.”

iii. Proposals shall be organized, concise, and submitted in the volumes and in the order indicated herein. Volumes shall be clearly identified and tabbed. Each factor shall be described in a separate tabbed section.

iv. Proposals shall contain a Table of Contents and include at the bottom left side of each page the volume and page number.

v. Offerors shall submit a signed dated Standard Form 1442, Solicitation, Offer, and Award. Any and all amendments must be acknowledged by the Offeror in accordance with the instructions on the Standard Form 30, Amendment of Solicitation.

vi. Offerors are reminded that elaborate corporate marketing information, formatting, special reproduction techniques, and the like are not necessary.

However, proposals shall completely and adequately address the requirements of this solicitation.

vii. Failing to submit attachments or failing to properly complete the proposal, may result in rejection of the Offer without further evaluation. Therefore, Offerors are urged to follow instructions and contact the Contract Specialist if instructions are not understood.

3.2.2 Where to Submit:

The Offeror’s proposal shall be submitted electronically, as described below. The RFP will provide the Government address and receipt date for proposal submittal. The Offeror’s proposal shall not contain classified data. The use of hyperlinks in proposals is prohibited.

NOTE: The only authorized transmission method for proposals in response to this solicitation is electronically via EMAIL. NO OTHER TRANSMISSION

METHODS (FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.)

WILL BE ACCEPTED.

The government will not be responsible for late submissions or submissions delivered to any location or to anyone other than those designated to receive proposals. Offerors are responsible for ensuring that proposals are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the proposal to be received in accordance with the instructions provided.

3.3 VOLUME 1– MINIMUM SUBMISSION CRITERIA (TECHNICAL PROPOSAL): For purposes

CUI

Paint Booth and Drying Oven of this RFP, an “Offeror” may include a group of two (2) or more entities that have formed a “contractor team arrangement,” as that term is defined in the Federal Acquisition Regulation, Part

9.6. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently proposed contractor team arrangement, will be considered as a part of the evaluation of the Offeror’s proposal.

In the case of affiliates, past performance of an Offeror’s “affiliate,” as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate will participate meaningfully (e.g., roles, responsibilities, etc.) in the performance of the contract. This commitment, nature of each entity’s relationship and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate. If a teaming agreement or commitment is not provided, the projects and experience of any team members outside of the Prime Offeror will not be considered.

The contractor team agreement/commitment shall be provided at the beginning of the Offeror’s technical proposal, prior to Factor 1, and will not be included in the overall page count.

The following are to be used in determining the status of the Offeror’s team for the evaluation of project submissions under Factor 1:

3.3.1 In the case of contractor team arrangements involving a Prime Contractor and Subcontractor(s), where the Prime Contractor submits the proposal in response to this RFP, the Prime Contractor is considered the “Prime Offeror”.

3.3.2 In the case of joint ventures, the “Prime Offeror” experience is limited to entities with signed agreements.

3.3.3 In the case of mentor/protégé relationships, the relationship must be established by the two Offerors and approved by the chosen Government Agency prior to proposal submission. The “Prime Offeror” experience is limited to entities with signed agreements. The approved mentor/protégé document from the Government Agency must be submitted along with the teaming agreement.

3.3.4 In the case of additional projects submitted by subcontractors, the subcontractor must submit the final cost of their portion of the project along with total project cost and all other required information.

3.3.5 In the case of Offerors that are large, multi-function firms (consisting of subsidiaries), experience may be submitted by any segment of the firm (e.g., division, group, and unit) that is submitting a proposal in response to this RFP.

3.3.6 In the case of affiliates, Past performance of an Offeror's "affiliate," as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate will participate meaningfully in the performance of the contract. This commitment and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate.

3.3.7 If a teaming agreement or commitment is not provided, the projects of any team members outside of the Prime Offeror will not be considered. If the Joint Venture/Mentor Protégé is a Small and Large Business, the Small Business will be evaluated as the Prime Offeror.

4.0 PROPOSAL INFORMATION AND RELATED EVALUATION FACTORS, RATINGS AND

ELEMENTS

The SSEB will evaluate the proposals and assign a consensus rating for the evaluation factor.

Firms are cautioned to put forth their best efforts, and to furnish all information clearly to allow the Government to evaluate proposals. Firms should not assume that they will have an opportunity to clarify

CUI

Paint Booth and Drying Oven or correct anything in their proposal after submission. However, the Government reserves the right to hold discussions if it determines that discussions are necessary. Therefore, proposals should be submitted on the most favorable terms that the Offeror can submit to the Government. If discussions are necessary, the Contracting Officer reserves the right to limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

Determination of Competitive Range refers to the range of proposals that are identified as the most highly rated, unless the range is further reduced for the purposes of efficiency. Competitive range will be determined on the basis of the ratings of each proposal against all evaluation factors. The Government shall then indicate to, or discuss with, each Offeror still being considered for award, significant weaknesses, deficiencies, and other aspects of its proposal. The Contracting Officer will notify all contractors eliminated from the competitive range.

If discussions are held, the Government may engage in a broad give and take with those firms in the competitive range, in accordance with FAR 15.306 (d). The Government will provide the Firm an advance agenda for the discussions. During discussions, the Government may ask the Firm to further explain its proposal and to answer questions about it.

Upon conclusion of discussions, those firms still considered within the competitive range, will be afforded an opportunity to submit their proposal revisions for final evaluation and selection.

4.1 VOLUME 1 – PERFORMANCE CAPABILITY

LOCATION FACTOR

NUMBER

DESCRIPTION RELATIVE

IMPORTANCE

Volume 1 Tab A Factor 1 Past Performance Equally as Important as

Factor 2 and 3. Factor 4 is less important than other factors 1,2, and 3.

Volume 1 Tab B Factor 2 Proposed Contract Duration, Phasing & Summary Schedule

Volume 1 Tab C Factor 3 Technical Approach

4.2 VOLUME 2 – SMALL BUSINESS PARTICIPATION PLAN

DESCRIPTION RELATIVE

IMPORTANCE

Volume 2 TAB 1 Factor 4 Small Business Participation Plan

Factor 4 is less important than factors 1, 2, and 3.

Volume 2 TAB 2 Factor 4 Past Utilization Of Small Business

4.3 VOLUME 3 – PRICE

DESCRIPTION RELATIVE

IMPORTANCE

Vol 3 Factor 5 Price Factors (1-4) when combined are approximately equal in importance to price.

CUI

Paint Booth and Drying Oven

CUI

Paint Booth and Drying Oven

5.0 VOLUME 1 – PERFORMANCE CAPABILITY

GENERAL: The technical factors consist of examples of Past Performance that meet the relevant scope, complexity, and magnitude described below. This Volume also includes factors for a Proposed Contract Duration, Phasing & Summary Schedule, Technical Approach, and Small Business Participation Plan.

DEFINITIONS:

• Deficiency: A material failure of a response or proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. (FAR 15.001)

• Weakness: A flaw in the response or proposal that increases the risk of unsuccessful contract performance.

• Significant Weakness: A flaw in the response or proposal that appreciably increases the risk of unsuccessful contract performance. Denoted with an (S).

• Strength: Any aspect of a proposal that, when judged against a stated evaluation criterion, enhances the merit of the proposal or increases the probability of successful performance of the contract.

• Significant Strength: A significant strength appreciably enhances the merit of a proposal or appreciably enhances the probability of successful contract performance. Denoted with an (S).

• Deviation: Proposal implies or specifically offers a deviation below the specified criteria. The Offeror may or may not have called the deviation to the Government's attention. A deviation is a deficiency. The proposal must conform to the solicitation requirements for award.

• Uncertainty: Any aspect of a non-cost/price factor response or proposal for which the intent of the offer is unclear (e.g. more than one way to interpret the offer or inconsistencies in the response or proposal indicating that there may have been an error, omission, or mistake).

EVALUATION RATING SYSTEM

• General: The Government will review the proposals and rate the quality of each evaluation factor. The SSEB will rate each proposal against the specified evaluation criteria in the Solicitation requirements. They will not compare proposals at this time. After all proposals are rated, the Government will compare the ratings and relative advantages and disadvantages of proposals against each other.

• Review Write-up: The Government will support each rating with a narrative, separately listing all strengths or advantages, weaknesses or disadvantages, deficiencies, and required clarifications.

• Rating System: After listing proposal strengths, weaknesses and deficiencies, the SSEB will assign an adjective rating of "Outstanding", "Good", "Acceptable", "Marginal", or "Unacceptable" to each factor except the Past Performance Factor, which reflect the Government's confidence in each Offeror's ability, as demonstrated in its proposal, to perform the requirements stated in the RFP. The adjectival ratings shall be assigned, using the evaluation criteria, which incorporate a proposal risk assessment:

• All evaluation factors, other than price, when combined, are considered approximately equal to price. No award will be made to an Offeror receiving an Unacceptable rating in any Factor.

CUI

Paint Booth and Drying Oven

VOLUME 1 – FACTOR 1 – PAST PERFORMANCE

The Offeror will provide Past Performance information on relevant projects using the Past Performance and Specialized Experience Questionnaires included in the solicitation. Contractor Performance Assessment Reporting System (CPARS) shall be submitted for projects, when available. Your client should receive form ATTACHMENT 2 – PAST PERFORMANCE QUESTIONNAIRE (PPQ) with items 1 through 4 completed and the “Note” that appears on its reverse side as well as the “Adjective Rating and Definitions” that are used for the ratings in the form.

Ensure correct phone numbers and email addresses are provided for the client point of contact.

Completed Past Performance Questionnaires should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ form, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Contract Specialist prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Also include performance recognition documents received within the last five (5) years such as award fee determinations, customer letters of commendation, and any other forms of performance recognition.

The Government reserves the right to verify the experience by reviewing the Construction Contractor (or Architect-Engineer) Performance Assessment Reporting System (CPARS), other DoD or Government appraisal systems or to interview commercial owners or references. The Government may check any or all cited references to verify supplied information. The relevant experience of key personnel proposed for this project will not be evaluated or considered under this factor.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.

The source selection evaluation team will review this past performance information and determine the quality and usefulness as it applies to a performance competence assessment as described in the guidelines, below.

Less than satisfactory performance information includes the issuance of cure notices, terminations for default, or the requirement for excessive oversight in order to achieve satisfactory completion. A single example of less than satisfactory performance, if significant enough, may lead to a less than satisfactory rating for this factor. Likewise, multiple examples of less significant less than satisfactory performance may lead to a less than satisfactory rating for this factor.

In conducting the performance competence assessment, the Government will consider the relevancy of the past performance information available. Highly relevant projects are those that are similar in scope, magnitude, and complexity to the current solicitation, although the past performance may still be considered if the projects do not fully meet the criteria for Factor 1.

In addition, the Offeror is required to provide any information on past projects (within the past five (5) years) that were terminated (for any reason) or in which they have been issued a CURE NOTICE and provide accompanying information as to the details for such action(s) with an explanation of why they were terminated or issued a cure notice.

5.1.1 EVALUATION CRITERIA

The SSEB will evaluate the risks associated with an Offeror’s likelihood of success in

CUI

Paint Booth and Drying Oven performing the requirements stated in the RFP based on the Offeror’s demonstrated performance on recent, relevant contracts. A performance confidence assessment rating will be assigned to each past performance.

Rating Guidelines for Factor 1: Refer to the Table in section 5.1.3

NOTE: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the Offeror shall be determined to have unknown (or “neutral confidence”) past performance.

5.1.2 RELEVANT PAST PERFORMANCE

The Offeror will be evaluated on the relevancy of the past performance demonstrated in the submitted form, ATTACHMENT 3 - SPECIALIZED EXPERIENCE. The Offeror should list their experience of similar project scope, complexity, and magnitude.

Submit a minimum of two (2) projects but no more than four (4) projects. A minimum of one project should be completed and turned over to the customer and the second should be at least 75% construction complete. All the submitted projects shall be recent construction experience which means that completion should be no more than seven (10) years preceding the date of this solicitation. The projects should meet the descriptions of scope, complexity and magnitude as outlined below. At least one (1) project should be the design and construction of a Paint Booth and Dryer Oven or a chemical, industrial, or manufacturing facility. Other projects submitted should predominately relate to industrial engineering.

If any firm has multi-function firms, project examples should be limited to those performed by the division submitting the offer.

Letters of commitment (Signed by both the Subcontractor and Offeror) are required in order for the Government to consider Subcontractor experience in the proposal evaluation. Other divisions within the Offer’s company may be considered as subcontractors for the submitting division.

The projects submitted should include the following criteria. Projects do not have to include all of the complexity criteria; however, projects that meet many or all of the complexity criteria would be given a higher degree of relevancy. Projects should demonstrate a similar scope and similar magnitude.

i. Similar scope is defined as design and construction of a Paint Booth and Dryer Oven System or a large chemical, industrial, or manufacturing facility.

ii. Demonstrate the specialized experience of the Offeror and/or proposed team, including sub-contractors, on projects the same/similar in size, complexity, and magnitude as those described in the solicitation for same/similar construction services. Emphasis shall be placed on a large renovation project involving fully operational industrial facilities, to include paint facilities, or other specialized industrial processing facilities or fully operational processing facilities, to include processing facilities, include tank lines and associated equipment for chemical cleaning and/or plating processes.

iii. Similar complexity is defined as design and construction of a Paint Booth and Dryer Oven System and all supporting activities (e.g. electric, mechanical, controls) in an occupied facility. This includes demonstrating the management and coordination of a multi-disciplined construction team.

CUI

Paint Booth and Drying Oven

iv. Similar magnitude shall be considered for Paint Booth and Dryer Oven greater than $10,000,000 or similar repair/construction projects greater than $15,000,000. Offerors shall provide cost to each project submitted, for both the design, manufacturing, install, and construction projects submitted for consideration.

The Government will consider the experience demonstrated by the projects in…