Sea Bright to Manasquan Reach SEABRIGHTMANASQU
AMENDMENT 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and
(iii) complete the entire work ready for use, and remove all equipment from the contract area not later than 120 calendar days after the date the Contractor receives the notice to proceed. Additional time will be considered within 60 calendar days for any options that are exercised. The time stated for completion shall include final cleanup of the premises.
(FAR 52.212-3)a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and (iii) complete the entire base work ready for use, and remove all equipment from the contract area not later than March 1, 2020.
If options are exercised, options to be placed by March 1, 2020, will be exercised 60 days after NTP. If any other option is exercised within 150 days of NTP, work must be completed by March 1, 2021; this work shall be ready for use, with all equipment removed from the contract area not later March 1, 2021.
There is to be no construction activities between March 1, 2020 and October 15, 2020, unless approved by USACE upon further coordination with NJDEP and USFWS. The time stated for completion shall include final cleanup of the premises.(FAR 52.212-3)
All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes placement of the beach fill material and incidental related work, including advanced nourishment along the length of the design berm, and feeder beaches.
1.2.2 Location
The work is located from Sea Bright to Long Branch in New Jersey, approximately as indicated. The exact location is shown in the bid documents.
1.3 DFARS 236.204, Disclosure of the Magnitude of Construction Projects
This project is estimated between $25,000,00015,000,000 and $100,000,0003 5,000,000.
SECTION 01 11 00 Page 1
Sea Bright to Manasquan Reach SEABRIGHTMANASQU
AMENDMENT 1
1.4 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2