Minish Contract No. 3A, NJ MINISH3A
SECTION 31 41 16
METAL SHEET PILING BULKHEAD SYSTEM
08/09
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
This work includes furnishing, delivering, handling, and installing (as applicable) all material, labor, equipment, tools and incidentals necessary to complete the work specified herein.
1.2 UNIT PRICES
1.2.1 Steel Sheet Piling, Type NZ26, Grade 50
1.2.1.1 Payment
Payment for sheet piling quantities will be made at the applicable contract price per linear foot for furnished and installed sheet piling.
Payment will cover all cost of furnishing, handling, storing and installing piling including placing, driving, cutting holes and other materials and work incident thereto.
1.2.1.2 Measurement
The length of sheet piling installed will be measured to the nearest tenth of a linear foot. For installed pilings directed to be cut off before reaching the penetration depth shown, the portion cut off will be measured for payment as the difference between the total length of piling shown on the plans for that location and the length of piling installed below the point of cut-off.
1.2.1.3 Unit of Measure
Unit of measure: linear foot.
1.2.2 Steel Fabricated Sections, Type NZ26 Plated Form 1, Grade 50
1.2.2.1 Payment
Payment for sheet piling quantities will be made at the applicable contract price per linear foot for furnished and installed sheet piling.
Payment will cover all cost of furnishing, handling, storing and installing piling including placing, driving, cutting holes and other materials and work incident thereto.
1.2.2.2 Measurement
The length of sheet piling installed will be measured to the nearest tenth of a linear foot. For installed pilings directed to be cut off before reaching the penetration depth shown, the portion cut off will be measured for payment as the difference between the total length of piling shown on the plans for that location and the length of piling installed below the point of cut-off.