Request For Proposal
Repair Dormitory Building 98 Thule Air Base, Greenland
05 May 2017
THIS PAGE INTENTIONALLY LEFT BLANK
REQUEST FOR PROPOSAL: DESIGN BUILD
RENOVATE DORMITORY BUILDING 98, THULE AIR BASE, GREENLAND
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 10 PROJECT DESCRIPTION AND DESIGN REQUIREMENTS
01 12 00.00 18 DESIGN AND RECORD DRAWING REQUIREMENTS
01 12 00.01 DESIGN SUBMISSION REQUIREMENTS AFTER AWARD
01 32 01.00 18 PROJECT SCHEDULE
01 33 00.00 18 SUBMITTAL PROCEDURES DESIGN-BUILD CONSTRUCTION
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 02.00 18 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 18 CONTRACTOR QUALITY CONTROL DESIGN-BUILD CONSTRUCTION
01 45 20.00 18 TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS
01 52 60.00 18 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 62 35 RECYCLED/RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00.00 18 CLOSEOUT SUBMITTALS
01 78 23.00 18 OPERATION AND MAINTENANCE DATA
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
REQUEST FOR PROPOSAL: DESIGN BUILD 05 OCTOBER 2016
SECTION 01 10 10
PROJECT DESCRIPTION AND DESIGN REQUIREMENTS
08/11
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes renovation of Dormitory Building 98 at Thule Air Base, Greenland and incidental related work. Refer to Part 3 of this Section and other documents of this Request For Proposal (RFP) for more information.
1.1.2 Location
The work is located at and within Building 98 and its immediate proximity.
The exact limits of work shall be determined by the Design/Builder and submitted to the Contracting Officer or his/her representative for approval.
1.2 OCCUPANCY OF PREMISES
Building will not be occupied during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF ABOVEGROUND UTILITIES
Design-Build Contractor shall comply with requirements of Thule Air Base Standards for above ground utilities.
1.4.1 Notification
Notify the Contracting Officer in writing at least 15 days prior to starting excavation work.
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause, the Government will furnish materials and equipment for installation by the Contractor.
SECTION 01 10 10 Page 1
REQUEST FOR PROPOSAL: DESIGN BUILD 05 OCTOBER 2016
It is the intention of the Government to furnish all quantities of the items required to complete the work as specified.
1.5.1 Delivery Schedule
Deliveries to Thule are limited to a short period each year during the summer. Arrange all deliveries with the COR far enough in advance that materials and equipment can be transported efficiently and without damage to the materials or delay to the Work.
1.5.2 Delivery Location
The materials and equipment are to be delivered to a location approved by the COR.
1.6 GOVERNMENT-INSTALLED WORK
Not applicable.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government. Refer to Contract Special Provisions for particulars.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
SECTION 01 10 10 Page 2
SECTION 01 10 10 Page 3
ARTICLE1 – DESIGN OBJECTIVES
1.1 SCOPE OF WORK
Prepare design/build construction documents and provide construction for the renovation of approximately 29,750 square foot (existing), three (3) story dormitory facility with an addition of approximately 1,701 square feet (567 sq. ft. per floor) to accommodate mechanical rooms, multi-purpose area(Optional Bid Item), and 270 square feet for the canopy entrance areas. The design-builder shall provide connections to a base heating hot water distribution system. Refer to Appendix BB for the concept floor layout. Design drawings shall use coordinate system WGS84 UTM Zone 19 North, as this is the official coordinate system for Thule Air Base.
The building was originally constructed in 1959. The requirements for this project work include selective demolition and construction of structural and non-structural interior elements, MEP equipment and associate piping and conduits.
The Civil base bid scope of work includes construction of fire main, fire hydrant and sanitary sewer lateral. The proposed bid option is the construction of a multi-story building addition that will serve as a multi-purpose room. Building 98 is an existing dormitory and the majority of work discussed in this RFP is to its interior.
The scope of the exterior renovation work on the existing building will include the following:
1. Removal of existing cladding and metal infill panels at blocked off windows and providing new cladding to match existing. The existing exterior envelope to remain at all other areas.
2. Removal of existing roofing and insulation assembly on the attic floor and providing new vapor barrier, insulation and roofing membrane.
3. Removal of existing insulation and metal cover at the underside of the 1ST floor structure and providing new insulation.
4. Removal of existing exterior stairs and entrances and providing new metal stairs and canopies.
The new building addition (Optional Bid Item) will be a steel framed structure on concrete foundations with insulated metal panel cladding and corrugated metal roofing. Refer to elevation and wall section drawings in Appendix BB.
The Air Force goal is to provide nine (9) remodeled apartment units on the first floor and twenty (20) remodeled apartment units on each of the upper two (2) floors for a total of forty-nine (49) apartment
SECTION 01 10 10 Page 4 modules for E5/E6 NCO’s. Also, to be included are new entrance canopies and a centrally-located multi-purpose room addition on each floor (see Appendix BB - Optional Bid concept floor layout). In case the Optional Bid cannot be accomplished due to limited project funding, a Base Bid of nine (9) remodeled apartment units on the first floor and twenty (20) remodeled apartment units on each of the upper two (2) floors for a total of forty-nine (49) apartment modules for E5/E6 NCO’s shall be considered (see Appendix BB - Base Bid concept floor layout).
Each reconfigured first floor apartment unit shall consist of a living room, kitchen (complete under this contract with all cabinetry, counters and counter tops, sinks and plumbing fixtures and under cabinetry lighting for counter tops, etc. as shown on the drawings), bedrooms, bathrooms, and entry area. The existing demising partition between the bathroom and closet area of the bedroom suites shall be removed along with one of the two existing lavatory locations. The reconfigured suites shall receive new finishes and plumbing fixtures throughout with high efficient, low flow fixtures. The existing central mechanical room will provide access to a new electrical/telecom room. New modular closets are to be provided at all apartment units. Code-compliant egress stairs shall be provided at each end of the building. A code-compliant central stair shall also be provided.
The upper floors apartment units shall remain largely unchanged in their current configurations and shall receive new finishes and plumbing fixtures throughout with high efficient, low flow fixtures.
New electrical closets shall be centrally located and are conceptually located adjacent to the central stair.
The existing plumbing pipes, carriers and hanger shall remain in place.
The building addition (Optional Bid Item) shall include new Multi-purpose Rooms, Kitchens, first floor Entry vestibule, Janitor’s Closets, Electrical and Telecom Rooms, and uni-sex restrooms. The Optional Bid Item shall include the necessary power, lighting, communications, HVAC and plumbing systems to support the additional space including modifications to the systems in the base bid.
HVAC (Heating Ventilating and Air Conditioning) work shall include, but not be limited to:
1. Pre-design system testing.
2. Demolition, and salvage of equipment and piping in mechanical room. Ductwork and piping shall be prepared for new connections.
SECTION 01 10 10 Page 5
3. Selective demolition of existing makeup air handling unit and exhaust air unit.
4. Selective demolition of existing hot water heating panels.
5. Selective demolition of registers and grilles.
6. Examination, testing, and repair of existing piping and ductwork to be re-used.
7. Provide new makeup air handling unit and exhaust air unit.
8. Provide new hot water heating panels.
9. Provide new registers and grilles.
Electrical Base Bid scope consists of the complete demolition and replacement of the existing power, lighting, communications, public address, television, and security systems within the building. This includes, but is not limited to, voice, data, CATV, Public Address, and access control devices, equipment, and associated wiring and conduits; lighting fixtures and control devices, receptacles, wiring devices, panelboards, disconnecting means, control devices, and associated wiring and conduit up to and including the main switchboard. Existing boxes and raceways may be reused for new devices and wiring where they are appropriately located and in good condition, as determined by the COR.
The Optional Bid Item electrical scope of work includes new power, lighting, communications, public address, television, and security systems to be installed in the building addition. The new systems shall be connected to and integrated with the systems installed under the Base Bid.
The fire protection scope of work includes providing automatic fire suppression sprinkler systems throughout the building, Class 1 standpipes in stairs 1 and 3, and replacing all fire alarm initiating devices throughout the building. The existing fire alarm control panel shall be reused. A new 6-inch water supply main shall be provided to supply the fire suppression sprinkler system and standpipes.
The following items shall be salvaged and hand over to the Base Maintenance Contract (BMC).
1. Interior doors and related hardware where being removed/replaced.
2. Water Closets on each of the three floors
3. Lavatories and faucet on each of the three floors
4. Kitchen Sinks and faucet on each of the three floors
5. Showers on each of the three floors
6. Mop Sinks and faucet.
7. Washers and Dryers on each of the three floors.
8. Notifier Display Alarm Panel at the main center entrance.
SECTION 01 10 10 Page 6
9. DDC sensors.
10. Heat tracing.
11. Digitrace heat tracing controllers.
12. Pumps.
13. Main Heat Tracing setup & Modern Square D Power Panel Supply on the outer wall of the first floor Mechanical Room.
14. Backflow Preventer Unit at the outer wall of the first floor
Mechanical Room.
15. Fire Pump Unit and Control in the first floor Mechanical
Room.
16. Approximately twelve (12) Fire Extinguishers and fifteen (15)
Electrical Exit Signs throughout the facility.
17. Fiver Termination Boxes and ONT and Network Distribution
Center (encapsulated in Black Box) in the first floor Mechanical Room.
18. Approximately twelve (12) Wireless Dorm Net Transmitters mounted throughout the hallway ceilings.
19. Six (6) fire hose cabinets and valves.
20. Fire alarm system addressable initiating devices (smoke detectors, heat detectors, etc.).
The facility shall be provided with all necessary utility upgrades, communications, and site improvements to accommodate vehicles (number of heaters and vehicles to be maximized per available space on the north face of Building 98. The work under this contract does not include preparation of a Comprehensive Interior Design (CID) document this work will be performed by others; The CID will also include Structural Interior Design (SID) components. In general terms, the contractor provides all items included with the SID as part of the building in accordance with the SID; e.g., painted surfaces; counter tops; carpet, floor tiles, windows and doors and their trim/molding;
ceiling tiles, ceramic tiles, etc. For the purpose of coordinating the SID with the CID, the contractor shall provide all necessary drawing files and finish sample, as may be necessary or required, to the government or it's Architect-Engineer (AE) for the preparation of a complete CID brochure. The concept CID documents (Appendix EE) and Product Data Sheets (Appendix DD) are provided to assist the Contractor with the design. Plumbing fixtures, faucets, sinks, and lighting fixtures (not lamps) if shown in the CID or Product Data Sheets indicate the type, style, finish and level of quality that the Government expects to be provided under this project.
Furniture, pictures and appliances are not part of the scope of work.
In general terms these are items that are not built in; i.e., hard wired, bolted into place or piped/plumbed with water supply and/or sanitary sewer connection. Exceptions to this rule are for example
SECTION 01 10 10 Page 7 stove top ranges mounted in counter tops and kitchen range/stove top exhaust hoods, if so indicated on the drawings or elsewhere herein.
As part of the Base Bid, the Design-Build Contractor shall provide a detail 3D Building Information Modeling (BIM) in both native and pdf formats as part of the Final Design Submission. The BIM file shall show all rough-in framing of walls, doors and windows, ductwork, plumbing, electrical lighting/power, electrical face plate locations and heating, etc. A major Air Force objective is to provide unaccompanied contractor personnel with housing conducive to their proper rest, relaxation, and personal well-being. Properly designed and furnished quarters providing individual privacy are essential to the successful accomplishment of the increasingly complicated and essential jobs these people perform at this remote arctic location;
e.g. compliant with current UFC/Air Force criteria for dormitory buildings and Federal/DOD energy standards as specified in this RFP.
This project is in accordance with Air Staff guidance for quality of life improvement and meets the Air Force Unaccompanied Housing Design Guide criteria unless specified otherwise in this RFP. ATFP, UFAS, ADA-ABA/ADAAG do not apply nor are there any LEED objectives or certification requirements. Federal/DOD Energy standards and goals that are lifecycle justifiable apply.
1.2 BID OPTIONS
Please see Bid Schedule (Section 00 10 00) for complete details.
1.3 DESIGN CRITERIA
The conceptual building design shown in this RFP is based on:
• DD Form 1391
• UFC 1-200-01 General Building Requirement
• Thule Air Base Standards and Design Guidelines – Refer to Appendices for details.
Design development, construction drawings, technical specifications and construction shall at minimum comply with the requirements and quality standards outlined herein and in the Unified Facilities Guide Specifications (UFGS). The Architect-Engineer (AE) shall employ safety and health standards promulgated under the Occupational Safety and Health Act (OSHA) of 1970 as published in the Federal Register, October 18, 1972, Volume 37, Number 202, Part II (Title 29, Chapter 17, Part 1910) and subsequently issued OSHA standards or standards consistent therewith in the design of this facility. In addition, the
SECTION 01 10 10 Page 8
AE shall follow the National Institute of Occupational Safety and Health (NIOSH) Standards.
Air Force Criteria is available from the National Institute of Building Sciences Whole Building Design Guide Construction Criteria Base (CCB) 2 in CD-ROM, from their website for CCB subscribers (http://www.wbdg.org/ccb), or via the USACE website (http://www.usace.army.mil). The resources found on the CCB include US Army Corps of Engineers requirements and Air Force Base Design Guides (AFDG), Engineering Technical Letters (AFETL), Pamphlets (AFP), and Regulations (AFR).
Applicable design and construction criteria is specifically indicated, but not limited to that mentioned in the following sections of this document. Criteria shall be taken from the most current references as of the date of issue of the RFP, unless noted otherwise. Referenced codes and standards are minimum acceptable criteria. Administrative, contractual, and procedural features of the contract shall be as described in other sections of this RFP.
1.4 SPECIFICATIONS
The technical specifications shall be developed from those provided with this RFP and the Unified Facilities Guide Specifications (UFGS) by the Designers of Record. Danish Architect-Engineers may deliver Specification in the Danish BIPS system. BIPS must be modified for requirements for standard forms, submittals, and Contracting Officer (CO) approval. If not available in UFGS, the Designer of Record shall develop specific sections using a SpecIntact template. The Design- Build Contractor is also directed to Section 01 12 00.01, Paragraph
1.16.1 Technical Specification for additional requirements. The Design-Build Contractor may use specifications other than from UFGS as long as the specifications meet Master Format 2016 and meet the technical requirements for the RFP.
1.5 DESIGN QUALITY
The main objectives of this solicitation are to obtain a design for the Building 98 renovation, including associated site development within funds and gross square footage available while maximizing design and material quality. Utility systems should be integrated within the building and on the site. Building systems should be selected for low-cost maintenance and operation. Therefore, there should be an overall balance of aesthetics and functionality within the parameters provided in this RFP.
SECTION 01 10 10 Page 9
1.6 DESIGN FREEDOM
Requirements stated and illustrated in this RFP are minimums.
Innovative, creative, or cost saving proposals which meet or exceed these requirements are encouraged and shall be considered during design submittal reviews. The drawings provided establish project floor area requirements and spatial relationships that have been reviewed for user function and preliminary code compliance. Floor plans may change with government approval to enhance design, comply with codes, incorporate options, include betterments, or support constructability.
1.7 ENERGY STANDARD COMPLIANCE
All components utilized shall meet the minimum requirements of ASHRAE
90.1 in addition to any other applicable project criteria. As a separate part or section of the Design Analysis demonstrate exceeding ASHRAE 90.1-2010 with calculations, vendor literature, equipment catalog sheets, compliance forms, worksheets, and narrative descriptions of the HVAC systems, service water heating, electrical power, lighting, and other equipment and systems.
1.8 PERMITS
Not applicable.
1.9 VALUE ENGINEERING STUDY (VE)
The contractor shall conduct a VE study utilizing an independent entity (Architect/Engineering (AE) Firm) utilizing the following requirements:
Level of Development at time of study: 50% Design Location: TBD Duration of VE excluding travel and report: 3 Days The Value Engineering Team Shall Compose of minimum of the following disciplines:
Discipline Function/experience Value Engineer Lead Professional Engineer-Architect whom is a Certified Value Specialist (CVS)
VE Team Members (CANNOT BE ON THE DESIGN TEAM) Facilitator to record & support to update data & presentation materials Architect Mechanical Engineer
SECTION 01 10 10 Page 10
Electrical Engineer Structural Engineer Cost Estimator
1.9.1 Scope of independent A/E Services:
Engineering Services; the work calls for the AE to provide a team, as designated by project above, of professional engineers and architects under the leadership of a Certified Value Specialist (CVS) for the purpose of conducting Value Engineering Study, complete with a draft reports for the projects listed in 1.0, above. VE team members conducting the study will not be members of the project development team. The VE study, which will be conducted at the location and times prescribed above, shall be executed in accordance with the SAVE International Standard and consist of the following:
The Value Engineering Study:
In-Brief / Information Gathering: The project Design Team and Manager will in-brief the Facilitator and VE Study Team members on the project objectives and design features. The Facilitator/Team members shall review the project drawings and cost estimate to fully understand the work to be performed and the functions to be achieved. The VE facilitator will then develop a cost model to identify areas of relative high cost and ensure that the VE Team members focus on the parts of the project that offer the most potential for cost savings.
Function Analysis: The facilitator will lead the VE Team to identify the functions, expressed in noun-verb pairs and will assemble in logical sequence using the Function Analysis System Technique (FAST) Diagram.
Creative / Speculation: The facilitator will work with the VE Team members speculation phase by conducting brainstorming sessions to generate ideas for alternative designs. All team members are to contribute ideas and critical analysis of the ideas is discouraged.
Evaluation / Analysis: Evaluation, testing and critical analysis of all proposed ideas generated during Speculation is performed to determine potential for savings and possibilities for risk. Ideas are ranked by the facilitator to determine priority for development.
Development: The prioritized ideas are developed into written proposals by VE team members. Proposal descriptions, along with sketches, technical support documentation, and cost estimates will be prepared by the VE Team members to support the implementation of
SECTION 01 10 10 Page 11 ideas. Additional VE Team Comments are included for items of interest, such as Sustainable Design strategies that may not be developed entirely as proposals. If included, these comments are to follow the VE Study Proposals. The facilitator will be responsible for analyzing the proposals, then implementing the Proposals and Comments into the VE Report.
Out-Brief: VE Study Facilitator shall provide an itemized list of Proposals and Comments with associated cost savings for distribution to all parties in attendance. The contractor shall coordinate with the COR in advance (provide schedule) so that the government may plan on participating in the out-brief.
1.9.2 Products:
AE shall issue a Value Engineering Draft Report containing:
a. Table of Contents
b. Project Description and Background
c. Executive Summary
d. Summary of Team Findings and Proposals
e. Summary of Team Findings and Comments
f. Supporting Documentation
g. Contact Directory
h. Cost Model
i. Function Analysis System Technique (FAST) Diagram
j. Speculation and Analysis List
k. Report to be forwarded electronically to the NAN Value
Engineering Officer in Adobe (.pdf) format and also its native file (Word) for distribution. No hard-copies will be required.
1.9.3 Schedule:
The Value Engineering Draft Report shall be submitted seven (7) working days after commencement of the Value Engineering Study. All work must be completed within one hundred and eighty (180) calendar days of receipt of written notice to proceed. The value engineering work shall commence no later than the as directed by the Government.
1.9.4 References:
Engineering Regulation (ER) 11-1-321, with Change 1 Dated 1 Jan 2011
COVE Policy Letter #2015-02, USACE Value Engineering (VE) Standard & Evaluation
ARTICLE 2 – FUNCTION DESIGN REQUIREMENTS
SECTION 01 10 10 Page 12
2.1 GENERAL DEFINITIONS AND REQUIREMENTS
2.1.1 GROSS AREA DEFINITION
Gross building area is measured to the outside face of exterior enclosure walls. The Design-Build Contractor's proposal shall meet all requirements including Minimum or Maximum net areas indicated in this
RFP.
2.1.2 NET AREA DEFINITION
Net area is measured to the inside face of the room or partition walls.
2.1.3 NET AREA REQUIREMENTS
A programmed space is included on the floor plans under the room names. Net areas indicated for building circulation and utility rooms are for guidance only. These spaces shall be sized to accommodate the required function and equipment, comply with code requirements, enhance constructability, and comply with other requirements of the
RFP.
2.1.4 FINISH REQUIREMENTS
Room finishes stated in the following sections are the minimum requirements and must be coordinated with the furniture specified in the Comprehensive Interior Design (CID) which accompanies this RFP, Appendix EE.
2.1.5 FUNCTIONAL AREA REQUIREMENTS
During work sessions conducted with the user’s discussions resulted in some variations from the original functional requirements matrix. The total square footage of 29,750 SF in the original 1391 may be exceeded. The following columns are included to capture the specific breakdown:
• A breakdown of types of rooms as defined in the Project Definition.
• Area: Original Square footage in the requirements document.
• Number of Rooms.
• Total Net Area: SF without wall space or other multipliers.
• Number of Occupants per building.
• Approved Area.
SECTION 01 10 10 Page 13
Notes are included to capture client comments or requirements for each space that impacted the total size or adjacencies. Complete adjacencies can be found in the attached drawings.
ARTICLE 3 – DESIGN NARRATIVES
A10 FOUNDATIONS
As the geotechnical report for the dormitory building addition was not available at the time of preparing the RFP, for footing design, assumptions have been made based on available geotechnical information in as-built drawings. According to the foundation notes of the existing drawings, isolated column footings for the additions can be sized based on an allowable bearing capacity of 4000 psf. Based on 2013 Dorm Design, footing bearing elevation must be at a minimum of 8’-0” below from top of the grade.
A geotechnical report is recommended in order to provide an efficient design for new footings of the addition, and for retrofit and rehabilitation of the existing building (Building 98). In the case if a geotechnical report is not available, a conservative approach shall be used based on governing building code.
A1010 STANDARD FOUNDATIONS
A1010.1 COLUMN FOUNDATIONS
To avoid difficulties in pouring concrete for new foundations on the permafrost building site, it is recommended to use precast concrete footing elements to support the new steel columns proposed to support the proposed building addition. Steel column bases shall be attached to supporting footings using steel anchor bolts.
A1020 SPECIAL FOUNDATIONS
Not applicable.
A1030 SUBSURFACE FOUNDATION MONITORING – THERMISTOR INSTALLATION
Three (3) thermistor strings shall be installed in accordance with the reference drawing C-304, FY13 Dormitory, Thermistor Profiles (Appendix GG) of this solicitation. One shall be placed under each new Foyer/Multipurpose/Kitchen/Dining, as close to the dorm structure as possible; another shall be placed directly on the opposite of side of the new foyer/kitchen at the back of the building, and as close to the dorm structure as possible; the third shall be located at the back of the building and as far from the structure as possible but remaining
SECTION 01 10 10 Page 14 in the gravel pad. The exact location shall be approved by the Contracting Officer or his/her representative.
SECTION 01 10 10 Page 15
B10 SUPERSTRUCTURE
B1010 FLOOR CONSTRUCTION
B1010.1 FLOOR SYSTEM
The new floor structural system shall be sized to ensure that the new and existing finish floor heights are aligned. Refer to C1010 for additional requirements.
B1010.2 EXTERIOR STAIRS
Exterior stair treads and landings shall be fabricated and constructed of structural steel rolled sections and plates supporting metal grating. The grating material shall be specified to provide the required slip resistance and prevent deterioration in the Thule environment.
The open side of the stair shall be enclosed with steel panels to mitigate snow drift build up on the stairs treads and landings.
Treads and risers shall be sized to meet applicable code requirements.
The stairs framing shall be supported by an independent foundation system.
Handrails shall be fabricated from hardwood. Stiles, posts and other handrail structure shall be steel. Similarly with guardrails, framing and support members shall be fabricated from steel with a hardwood top handrail.
B1020 ROOF CONSTRUCTION
B1020.1 ROOF ASSEMBLY
The existing roofing assembly at the attic floor shall be removed to the top of metal deck. The corrugated metal panels at the sloped roof shall be removed to allow for installation of roofing at the attic and reinstalled after completion of work.
B1020.2 ROOF DECKS, SLABS AND SHEATHING
The existing roofing assembly at the attic floor shall be removed to top of deck and replaced with liquid applied membrane roofing installed on top of tapered polyiso insulation and cover board. Liquid applied roofing and flashing shall be provided to create a seamless watertight joint around all penetrations at the attic level. The
SECTION 01 10 10 Page 16 specifications shall provide all required performance and material approvals.
For the new addition (Optional Bid Item), the roofing shall consist of corrugated metal sheathing over insulated metal panels. The sheathing shall be connected to the insulated panels with metal furring/clips.
The prefabricated metal insulation panels shall be connected to the supporting structural framing with roof purlins.
B1020.3 CANOPIES
Canopies shall be provided at the three exterior stairs. Canopies shall be steel framed supporting a steel deck and corrugated metal siding walls with metal roofing to match the main roof.
B1020.4 ROOF CONSTRUCTION VAPOR RETARDERS, AIR BARRIERS AND INSULATION
Roof insulation at the existing building is provided by the tapered polyiso insulation and coverboard on the attic floor. The finished roof assembly shall have an R factor value of 62.5°F-ft2-h/Btu [SI:
11.1 K-m2/W]
Membrane underlayment compatible with the roofing and insulation assembly shall be provided
B1020.5 OTHER ROOF CONSTRUCTION
Flashings and other miscellaneous sheet metal components shall be fabricated from metal or other compatible sheet material. Lead, lead-coated metal and galvanized steel shall not be used. Fasteners shall conform to the requirements of the same specification and be compatible with the sheet metal selected. All flashing material and required preparation of existing surfaces shall be coordinated with the roofing membrane for compatibility.
B20 EXTERIOR ENCLOSURE
B2010 EXTERIOR WALLS
B2010.1 EXTERIOR WALL SKIN
The exterior envelope at the existing building shall remain except at the locations where a metal infill panel has been installed over window openings. The existing infill panels shall be removed along with the corrugated metal sidings with cutouts around them. The existing wood stud framing at these locations shall be filled with batt insulation and new corrugated metal panels to match existing shall be installed.
SECTION 01 10 10 Page 17
The exterior envelope for the new addition (Optional Bid Item) shall be comprised of an 8”insulated metal panel system supported on sub girts/sub framing. The overall R factor value for the exterior wall assembly, inclusive of the batt insulated interior skin shall be 64.5°F-ft2-h/Btu [SI: 11.37 K-m2/W]. The exterior insulated metal panel is shop finished in compliance with NAAMM AMP 500. Coating shall be baked-on type at both exterior and interior faces.
B2010.2 EXTERIOR WALL VAPOR RETARDERS AIR BARRIERS AND INSULATION
Existing insulation is maintained at the exterior envelope of the building. Insulation provided at areas of replacement of cladding shall match or exceed the insulation performance of the existing building envelope.
At the new addition (Optional Bid Item), insulation of the exterior wall assembly is primarily achieved by the interlocking 8” insulated wall panels. In combination with the batt-filled interior skin, the envelope is to provide an R factor value of 64.5°F-ft2-h/Btu [SI: 11.37 K-m2/W]
The existing 3” fiberglass insulation and 20 GA sheet metal paneling below the existing first floor structure (including vertical encasement at column stubs) will be removed. Foil faced Polyiso insulation appropriate for exposed use shall be installed on the underside of the deck, spanning between the insulated beams. All seams shall be taped and covered with compatible seam covering. The new insulation will not reduce the ground clearance below the existing portion of the building.
At the new addition(option 1), an insulated plenum shall be provided below the first floor slab to provide a freeze-protected area for new sanitary plumbing to be installed. The insulation shall be provided by a 9” insulated metal panels system supported by a new steel framework that supports the new first floor assembly. The new panel shall have an R factor value of approximately 64.5°F-ft2-h/Btu [SI: 11.37 K-m2/W].
The building shall be provided with a continuous air barrier system that shall be tested by an approved testing agency. A certified testing report shall be issued.
B2010.3 EXTERIOR WALL INTERIOR SKIN
The existing interior assembly for exterior walls shall remain at the existing building. The locations where infill panels are removed shall be framed with 2-1/2” wood studs, filled batt insulation and receive two layers of 5/8” gypsum board at the interior.
SECTION 01 10 10 Page 18
At the new addition (Optional Bid Item), the interior assembly of the exterior wall shall comprise of 2-1/2” 22 GA metal studs with 5/8” gypsum board applied to the exterior face and two layers of 5/8” gypsum board at the interior. The assembly shall be packed with batt insulation.
B2010.4 EXTERIOR LOUVERS, GRILLES AND SCREENS
Pre-finished storm resistant with bird screens AMCA 500-D and AMCAS 511 rated for air performance and water penetration; three coat fluorocarbon coating not less than 1.4 mil thick full strength 70% resin 3-coat Fluoropolymer finish. Color to match adjoining exterior wall color.
B2010.5 EXTERIOR SOFFITS
At the new addition (Optional Bid Item), exterior soffits shall be fabricated from sheet metal and pre-finished with baked on fluorocarbon coating, color to match surrounding wall/roof.
B2020 EXTERIOR WINDOWS
B2020.1 EXTERIOR STANDARD WINDOWS
Existing exterior windows shall remain for the base bid portion of the project.
At the new addition (Optional Bid Item), windows shall be triple glazed high performance units. Frames shall be fabricated from vinyl.
The single sash is operable with a tilt/turn ventilator style operation. Provide PVC, reinforcing members, fasteners, hardware, weather-stripping, and anchors conforming to AAMA/WDMA/CSA 101/I.S.2/A440. Windows shall have a typical assembly U factor value of 0.2 Btu/hr/sq ft°F [SI: 1.13 W/m2/ºC]. Windows shall be Energy Star qualified products as appropriate to Northern climate zone. Window frames shall be white.
Windows shall be provided with an operable ventilator set into the top of the operable sash framing.
B2030 EXTERIOR DOORS
B2030.1 EXTERIOR ENTRANCE DOORS
Existing exterior entrance doors to remain for the base bid portion.
Insulated steel doors and frames shall be provided at the new addition (Optional Bid Item). Door size(s), design, and material shall be as specified for standard steel doors as a minimum as Dan-Doors.
SECTION 01 10 10 Page 19
Insulated steel doors shall have a core of polyurethane foam and an R factor value of 10.0°F-ft2-h/Btu [SI: 1.76 K-m2/W] or more (based on a k value of 0.16); face sheets, edges, and frames of galvanized steel to be not lighter than 0.7 mm thick, 1.5 mm thick, and 1.5 mm respectively; magnetic weather-stripping; non-removable pin hinges;
thermal-break aluminum threshold; and vinyl door bottom. Doors and frames shall receive phosphate treatment, rust-inhibitive primer, and baked acrylic enamel finish. Doors shall have been tested in accordance with SDI/DOOR A250.4 and shall have met the requirements for Level C. Prepare doors to receive specified hardware.
B30 ROOFING
B3010 ROOF COVERINGS
B3010.1 DECK VAPOR RETARDER AND INSULATION
Refer to B1020 Roof Construction.
B3010.2 MANUFACTURED ROOFING
At the new addition (Optional Bid Item) only, provide corrugated metal roofing panels to match roofing over the existing building. Provide continuous sheet metal flashing below the metal roofing at the valley junction where roof of new addition interfaces with that of existing building. Soffits shall match the roofing color. Roof flashing shall match the roof material and color.
B3010.3 SHEET METAL ROOFING
See B3010.2 above.
B3010.4 FLASHING AND SHEET METAL
Flashings and other miscellaneous sheet metal components shall be fabricated from metal or other compatible sheet material. Lead, lead-coated metal and galvanized steel shall not be used. Fasteners shall conform to the requirements of the same specification and be compatible with the sheet metal selected.
C10 SUPERSTRUCTURE
All building structural systems and components shall comply with the requirements of the applicable codes, standards and criteria as well as industry standards and commonly accepted method of practice. The proposed building addition shall be limited to the middle part (multipurpose space and covered entry) of the existing dormitory building and shall extend for the full height as shown on the RFP
SECTION 01 10 10 Page 20 plans and sections. The superstructure of the middle part of the new addition shall match, as practically possible, the structural system of the existing building (i.e. steel moment frames and gabled roof).
Expansion joints need to be provided where the proposed addition is connected to the existing building. The proposed addition shall be enclosed using non-load bearing exterior walls to provide necessary fire rating of the egress. Covered entries shall consist of exterior steel stairs connecting the building’s first floor level to the grade and covered by a framed steel canopy.
C1002 STRUCTURAL SYSTEMS
C1002.1 GRAVITY SYSTEM
The existing dormitory building utilizes steel framing as the primary load-carrying system to support the building’s gravity loads (i.e.
dead, live, snow). The new addition shall match the existing building by using steel frames to support gravity loads from added floors and steel roof. Typical floors shall be constructed of composite floor slabs supported by composite steel beams that span between steel columns. All beam to girder connections are to be of the shear-type while all beam/girder-to-column connections are to be of the moment-resisting type.
The contractor is responsible for the detailed design of the framing system, floor slabs and the metal roofing system. The contractor is responsible for providing sufficient documentation to verify that all performance requirements have been met, the design configuration matched and may have to provide added substrate support to adequately resist imposed loads.
C1002.2 LATERAL SYSTEM
The existing dormitory building utilizes ordinary moment resisting steel frames in both orthogonal directions to provide resistance to lateral loads. Floor slabs and roof deck serve as rigid diaphragms transferring lateral loads due to wind or earthquake effects to supporting frames at various levels along the building height. The new building addition shall be connected to the existing building at all floor and/or roof levels in a manner to accommodate an expansion joint. The addition shall also utilize ordinary moment resisting frames in both directions to provide lateral stability to the addition. An expansion joint is required at the interface of the new and existing structures.
SECTION 01 10 10 Page 21
C1010 FLOOR CONSTRUCTION
C1010.1 FLOOR STRUCTURAL FRAME
The proposed floor structural system for the new addition consists of floor metal decks supported by steel floor beams that span between steel columns. Floor slab construction is indicated by Section C1010.2 below. All floor beam-to-column connections in both directions are to be of the moment-resisting type to provide lateral stability.
C1010.2 FLOOR DECKS, SLABS, AND TOPPINGS
From the 2013 Dorm Design, the floor slab construction for the new addition consists of three layers of gypsum board (from top down: one ¾” gypsum board over two layers of ½” gypsum board.) on top of 2” rigid mineral fiber insulation with an additional layer of ½” gypsum board underneath of the rigid insulation. The whole gypsum board and rigid insulation assembly is supported by a combination of one 1 5/16” metal deck and one 6” metal deck. The 1 5/16” metal deck must be laid on top of 6” metal deck. In addition, the 1 5/16” metal deck must be laid in the direction perpendicular to the span direction of the 6” metal deck. The 6” metal deck must be able to span between support steel beams for support of design loads.
For slab in fill at openings of the existing stair well where existing stairs being removed, floor system shall match existing floor construction, i.e. 2” concrete reinforced with weld wire fabric over 4 ½” metal deck.
C1010.3 EXTERIOR STAIRS
Exterior stairs and landings shall be fabricated and constructed of galvanized structural steel rolled sections and plates. The stairs framing shall be supported by an independent foundation system.
C1020 ROOF CONSTRUCTION
C1020.1 ROOF STRUCTURAL FRAME
The proposed gabled roof structural system for the new addition consists of insulated metal panels supported by roof steel purlins spanning between roof steel beams and columns. The roof sloped profile shall be planned to fit perpendicularly to the existing building gabled roof. Roof purlin-to-beam connections are to be of the shear-type while purlin and/or beam-to-column connections are of the moment-resisting type to provide lateral stability in addition to improved gravity load carrying capacity.
SECTION 01 10 10 Page 22
The new gabled roof of the addition shall have an expansion joint at the interface of the existing building. The gable shall continue on to the existing building as an over-build. Existing metal roof sheathing shall be removed where required to make purlin connections.
C1020.2 ROOF DECKS, SLABS, AND SHEATHING
Roof construction for the new addition consists of insulated metal panels spanning between steel purlins. Selected roof panel depth and thickness should be adequate to provide required flexural strength and satisfy serviceability requirements. The insulated metal roof panel is designed to support all out-of-plane applied loads and resist lateral loads, acting as a diaphragm to collect and transfer lateral loads to the building frames. The insulated metal roof panels shall be designed to run perpendicular to roof slope and spans between roof purlins. A standing seam metal roof is assumed to be installed over the metal panel diaphragm to serve as an aesthetic element and weather protection material.
Access to the attic space shall be via existing fixed ladders, insulated access hatches and ladders at the stairwell landings located at each end of the building.
C1020.3 CANOPIES
Steel framed canopies shall be provided at the three (3) exterior stairs and one new stair constructed with the Optional addition.
Canopies shall be constructed of galvanized metal deck supported by shallow galvanized beams/tubes that shall be resting on steel posts on one side and framing into the building’s exterior cladding support.
Connections to the building shall be provided with thermal breaks.
C20 EXTERIOR ENCLOSURE
See B20 Exterior Enclosure
C30 ROOFING
See B30 Roofing
SECTION 01 10 10 Page 23
D - INTERIORS
The facility shall provide an inviting atmosphere where customers/ tenants feel comfortable while living in there. This will reflect both the user's needs and functionality and provide a comfortable yet durable facility to support and assist the customers/tenants of those that serve.
The interior finishes shall be simple, yet functional and durable. The colors shall be soothing and pleasing to the eye with the overall scheme centered on warm neutral tones. Sustainable design in the selection of the finishes shall be incorporated to promote the environmental quality of the interior space. The flooring finishes offer durability, sustainability and safety while providing complementary accents. Wall colors shall be painted a soothing neutral with thoughts to complimentary accent colors in appropriate locations throughout the space. The restroom areas shall be finished with a ceramic porcelain through-color tile that will provide the areas with a pleasing look and ease of cleaning. The walls in these areas shall have a pattern of accent tile around the upper portion of the wall.
The floors shall have a similar corresponding pattern around the perimeter of the room.
The overall look and feel of the Building 98 at Thule Air Base in Greenland shall be one the occupants as well as the neighboring community will be proud of for many years to come.
D10 INTERIOR CONSTRUCTION
D1010 PARTITIONS
D1010.1 INTERIOR FIXED PARTITIONS
The existing demising partition between each dwelling unit and dwelling unit corridor shall be a full height partition and extends to the underside of the structural slab. Any new demising partitions shall be properly fire-rated and meet the requirements of IBC 2012.
Partitions between bathroom, bed room and living space shall have STC of 45 where newly constructed, and be non-fire-rated.
D1010.2 INTERIOR PARTITION FIRESTOPPING
Provide fire-stopping at all fire-rated assemblies.
SECTION 01 10 10 Page 24
D1020 INTERIOR DOORS
D1020.1 INTERIOR SWINGING DOORS
Entry doors to each dwelling units shall match Thule Air Base standard door type and be Solid-Core Wood (SCWD) with Hollow Metal (HM) door frame. Door hardware sets shall include: 1 ½ pair hinges, Thule Air Base standard lock & latch set, door closer, protective trim, door stop, threshold, door silencers and a wide-angle peephole for viewing visitors. The hardware and accessories shall meet BHMA A156.16 requirements. Provide acoustic strip seals and sweeps at all apartment unit doors with service to the corridor. Doors are to be prepared for electronic locking systems and appropriate fire-ratings.
Electronic lock hardware shall be mortise-type and installed in the door leaf. Electrified strikes are prohibited. Electronic lock hardware must be compatible with Thule Air Base standard Siemens Sipass locking. Coordinate door hardware specifications with Base Non- Secure Communications Department. Doors for the dwelling units and mechanical/electrical rooms shall include keypad for access by combined proximity card and PIN. Other doors without a keypad to have proximity card access only.
The entry doors shall be 3’-0” wide and 7’-0” high. The bathroom and bedroom doors shall be a minimum of 2’-6” wide and 7’-0” high.
D1020.2 INTERIOR ENTRANCE DOORS
The interior doors to vestibule, multipurpose room, separation doors within the corridors and laundry rooms shall be SCWD with insulated vision glass and HM frame.
D1020.3 INTERIOR FIRE DOORS
Doors to dwelling unit entry, utility rooms, egress stairs and storage rooms shall be fire door assemblies having a fire protection rating as per IBC section 702 &716.5.3 requirements.
D1020.4 OTHER INTERIOR DOORS
Interior doors to utility rooms including mechanical rooms, electrical rooms, laundry rooms and telecom rooms shall be hollow metal door and frame with proper fire-rating label. Electric locks shall be mortise-type and mounted at doors leaf. Electrified strikes are prohibited.
Coordinate specification of hardware with Base Non-Secure Communications Department.
SECTION 01 10 10 Page 25
D1030 FITTINGS
D1030.1 TELEPHONE CLOSET
Telecom/IT equipment may share space with security and other low voltage system equipment. Space shall be allocated in such a manner that recommended access for telecom/IT equipment complies with TIA standards and also address NEC clearances for electrical equipment.
Telecom closet locations shall stack vertically, where possible, with sleeves between floors to enable cable distribution between floors to be attained. Closet design shall incorporate space for two (2) full sized, enclosed cabinets. Space shall be made available for cable terminations and cabinets for systems described in E5030 of this RFP.
D1030.2 HANDRAILS
1 ½” diameter (exterior dimension) handrails painted, shall be installed on both sides of the egress stairs as required by IBC section 1009.12. The inner handrail shall be continuous and supported to the guardrail by steel brackets, while the outer handrail shall be supported at the wall by steel brackets.
D1030.3 INTERIOR IDENTIFYING DEVICES
The exterior and interior signage system shall conform to current Air Force Signs Standard (UFC 3-120-01) for sign standards design and placement.
Exterior signs include the facility directional and building entry identification sign to clearly direct visitors to the main entrance.
Interior signs include wall mounted signs for dwelling rooms, stairs, utility rooms and lounge room.