W912DS-12-R-0014 Amendment No. 0006.pdf

PDF 140 KB Posted

Attached to
Construction of a Ballistic Evaluation Center at Picatinny Arsenal New Jersey.
Solicitation number
W912DS-12-R-0014
Issued by

About this file

Amendment No. 6

View the file

Other files

File Type Posted
Amend9.pdf PDF
Amend8.pdf PDF
Amend7.pdf PDF
Amendment0007 Specs.pdf PDF
Amend5.pdf PDF
BEC Amendment 4 dwgs.pdf PDF
Amend4.pdf PDF
site visit sign in.pdf PDF
Amend3.pdf PDF
Amend2.pdf PDF
Amend.1.pdf PDF
BEC - RTA - Drawings.pdf PDF
DS-12-R-0014_BEC.pdf PDF
BEC - Specs.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W16ROE20597381

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Provide answ ers to Offerors' questions FOR INFORMATIONAL PURPOSES ONLY

2. Extend the proposal due date from 20 July 2012 at 2:00pm to 24 July 2012 at 2:00pm.

NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on the SF 1442, by separate letter, or by telegram by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jul-2012

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-12-R-0014

X 9B. DATED (SEE ITEM 11)

07-May-2012

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Jul-2012

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS-12-R-0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0006

Amendment #6 for W912DS-R-12-0014, Ballistic Evaluation Complex (BEC) Phase I & II, Picatinny Arsenal, NJ

Answers to Contractor Questions (For Informational Purposes Only)

Question 1:

Specification section 083953.2.2 defines Trolleys and Track Beam as the method with which to support the door weight. The track beam and trolleys are not shown anywhere in the drawings.

The orientation of a track beam and trolleys has inherent weakness for a blast resistant door in that both will be exposed to the blast effects. Also, it is impossible to run the track beam perpendicular to the hangar doors as intended as the track beam will intersect each of the hangar door top guides. The track beam cannot be discontinuous at the hangar doors, and the hangar door top guides cannot be discontinuous at the track beam. Please indicate how this is to be accomplished.

Response:

At each location the purpose of the sliding blast door is to protect the hangar door sections from overpressures/shockwaves when the hangar door sections are stored in the storage pocket. This requires the overhead tracks for the hangar door sections to be fabricated with a short gap along the length of travel that permits the blast door and hardware to pass through the hangar door tracks and close off the pocket completely. The width of the hangar door track gap is expected to be slightly larger than the thickness of the blast door and hardware. As each section of the hangar door is long enough in plan to accommodate numerous rollers at the head, no operational challenges are expected with regard to the hangar door design since multiple rollers of each door section will be on the overhead track at all times with no more than one roller passing over the gap at any instance. The drive linkage or festoons for the hanger doors would need to be located to accommodate the overhead track gap. With regard to the capacity of the blast door overhead track, the jambs of the blast door carry the blast loads while the blast door hanger track and floor track carry the door when being manually closed or opened. The floor tracks for the hangar and blast doors would be fabricated in to a machined plate where they cross recessed in to the floor slab permitting the slots to cross. The exposed hardware is to be designed, sized, and attached so as to resist repeated blast loading

W912DS-12-R-0014

within the elastic range while remaining operational for the life of the building. Subject to project requirements, the contractor may elect to submit alternate door configurations for consideration and coordination refinements during the submittal process.

See attached sketch.

(End of Summary of Changes)