Sequence of Construction:
1. Install perimeter silt fencing and inlet protection 2 days
2. Install stabilized construction entrance 2 days
3. Remove any remaining pavements, antennae, cables, fencing, etc. from site 10 days
4. Strip topsoil, stockpile, temporarily stabilize, and encompass with silt fence 3 days
5. Begin Building construction -
6. Relocate overhead utilities 10 days
7. Rough grade site 4 days
8. Extend utilities to building 10 days
9. Install curbing and pavement base courses 15 days
10. Permanently stabilize disturbed areas where possible, temporarily stabilize all other disturbed areas 5 days
11. Complete building construction 180 days
12. Complete paving operations 1 day
13. Permanently stabilize all disturbed areas 30 days
14. Remove all temporary stabilization methods once all areas are permanently stabilized 1 day
NOTES:
1. WETLANDS / STATE OPEN WATERS LINES PER "US ARMY
TACOM-ARDEC (PICATINNY ARSENAL) BRAC WETLAND
DELINEATIONS FOR SIX (6) SITES" AS PREPARED BY THE RBA
GROUP, OCTOBER 2008.
2. ENTIRE DEVELOPMENT SITE FALLS WITHIN 150' EXCEPTIONAL
RESOURCE VALUE WETLANDS BUFFER.
3. AREAS WITHIN LIMIT OF DISTURBANCE:
EXISTING:
IMPERVIOUS 11,681 SF
PERVIOUS (DISTURBED, GRASS) 8,659 SF
PERVIOUS (UNDISTURBED, WOODED) 0 SF
TOTAL AREA 20,340 SF
PROPOSED:
IMPERVIOUS 8,084 SF
PERVIOUS (DISTURBED, GRASS) 12,256 SF
PERVIOUS (UNDISTURBED, WOODED) 0 SF
TOTAL AREA 20,340 SF
4. REFER TO DEVELOPMENT PLANS 3C-001 THROUGH 3C-006 FOR
ENLARGEMENT OF DEVELOPMENT AREA.
EXISTING CONDITIONS PLAN
| BLDG 3215 - 03-SITE PLAN |
| 001-EXG COND PLAN |
| 002-DEMOLITION PLAN |
| 003-SITE PLAN |
| 004-GRADING PLAN |
| 005-DRAINAGE & UTILITY PLAN |
| 006-SOIL EROSION |
| 007-WETLANDS |