W912DQ18R3010_KSAAP_Bldg_1206.pdf

PDF 1 MB Posted

Attached to
KSAAP Bldg. 1206 Remediation
Solicitation number
W912DQ18R3010
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
Appendix_B.pdf PDF
Appendix_E.pdf PDF
Amended_SOW.pdf PDF
Appendix_H_Geochem.pdf PDF
Table_1_-_Submittals.pdf PDF
1206_access.pdf PDF
AppGKSAAP1206.pdf PDF
KSAAP_Appendix_F_-_DUAR.pdf PDF
Appendix_A.pdf PDF
Amendment_2_Released.pdf PDF
Appendix_G.pdf PDF
Appendix_C.pdf PDF
A.07.24_Amendment_0001.pdf PDF
A.07.23Table_4_-_Soil_Excavation_Volumes_revised.xlsx XLSX spreadsheet
A.07.23_Attachment_3_-_Assumptions.xlsx XLSX spreadsheet
A.07.23_Solicitation_Figures_Combined.pdf PDF
A.07.23_1c_DRAFT_Building_1206_Investigation_Report.pdf PDF
A.07.23_Attachment_4_-_Schedule_Spec.PDF PDF
A.07.23_Attachment_5_revised--RMS_Spec.pdf PDF
A.07.23_1b_Final_Corrective_Measures.pdf PDF
A.07.23_Attachment_2--KSAAP_1206_Item_Schedule.xlsx XLSX spreadsheet
A.07.23_1a_Final_Remedial_Action_Report.pdf PDF
A.07.23_1d_Building_1206_Construction_Drawings_(various_years).pdf PDF
A.07.23_Table_1_-_Submittals.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER, 1. SOLICITATION NO.

W912DQ18R3010

2. TYPE OF SOLICITATION

SEALED BID (IFB)

X NEGOTIATED (RFP)

3. DATE ISSUED

25-May-2018

PAGE OF PAGES

1 OF 103 AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

7. ISSUED BY CODE W912DQ 8. ADDRESS OFFER TO (If Other Than Item 7) CODE

USACE, KANSAS CITY +

FEDERAL BLDG CT-H 601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

TEL: 816-389-3812 FAX: 816-389-2030

See Item 7

TEL: FAX:

9. FOR INFORMATION

CALL:

A. NAME

DOMINIQUE C HOWARD

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

816-389-3812

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

KSAAP Bldg. 1206 Corrective Measure Implementation, Parsons, Kansas

11. The Contractor shall begin performance w ithin 15 calendar days and complete it w ithin 365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See 52.211-10 .)

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 4 copies to perform the w ork required are due at the place specified in Item 8 by 12:00 PM (hour) local time 25 Jun 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

14. NAME AND ADDRESS OF OFFEROR

(Include ZIP Code)

OFFE

R

(M ust be fully completed by offeror)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

See Item 14

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specified below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

20B. SIGNATURE 20C. OFFER DATE

21. ITEMS ACCEPTED:

AWARD (To be completed by Government)

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY: CODE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT

(Contractor is required to sign this 29. AWARD (Contractor is not required to sign this document.)

document and return _ copies to issuing office.) Contractor agrees Y our of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print) TO SIGN (Type or print)

30B. SIGNATURE

30C. DATE

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

NSN 7540-01-155-3212 STANDARD FORM 1442 BACK (REV. 4-85)

Section 00 11 00 - Solicitation/Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 Job

General Conditions

FFP

See Scope of Work for details.

FOB: Destination

NET AMT

0002 Job

Work Plans

FFP

0003 Job

Mobilization and Site Preparation

FFP

0004 Job

Concrete Slab Removal

FFP

0005 Job

Sub Slab Soil Removal

FFP

0006 Job

Transportation and Disposal

FFP

Transportation and Disposal of Contaminated Soil and Concrete -See Scope of Work for details.

0007 Job

Sampling and Analysis

FFP

0008 Job

Site Restoration and Demobilization

FFP

0009 Job

Soil Corrective Measures

FFP

Soils Corrective Measures Implementation Report- See Scope of Work for details.

CLAUSES INCORPORATED BY FULL TEXT

SCR_CT_002 FIELD OFFICE OVERHEAD (JUL 2002)(RFP)

NOTICE TO OFFERORS: you must declare below the single accounting practice that you apply to contracts to calculate field office overhead for all change orders, modifications and requests for equitable adjustment. Pursuant to Federal Acquisition Regulations (FAR) Parts 31.105(d)(3) and 31.203(d)(1), an accounting practice that varies from modification to modification is not allowable. Select one of the following:

1. TIME DISTRIBUTION BASE FOR A PER DIEM RATE

If you use this practice, see Special Clause “Field Office Overhead Per Diem Rate”

2. DIRECT COST DISTRIBUTION BASE FOR A PERCENTAGE MARKUP

If you use this practice, see Special Clause “Field Office Overhead Percentage Markup”

3. OTHER ACCOUNTING PRACTICE THAT IS ALLOWABLE

UNDER THE FAR AND THAT USES A SINGLE DISTRIBUTION BASE.

If you choose 3, you must describe the accounting practice in sufficient detail below to allow the contracting officer to determine what accounting practice is being utilized by your company and that it complies with the FAR.

FAILURE TO FULLY COMPLY WITH THE ABOVE REQUIREMENT OR, IF ALTERNATIVE 3 IS

DECLARED AND YOUR DESCRIPTION DOES NOT CLEARLY STATE OR DESCRIBE A CONSISTENT

ACCOUNTING PRACTICE USING A SINGLE DISTRIBUTION BASE, MAY CAUSE YOUR PROPOSAL

TO BE EVALUTED AS UNACCEPTABLE.

(End)

SCR_CT_003 FIELD OFFICE OVERHEAD PERCENTAGE MARKUP (JUN 2001)

If any change to the contract issued pursuant to the changes Clause, or otherwise, for which the Government is responsible, causes an increase or decrease in the Contractor’s cost, or in the time required for performance under the contract, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

Under such equitable adjustment, no per diem rate for field office overhead shall be allowed if the Contractor has elected a percentage markup in keeping with its standard accounting practices. In such a case, payment of field office overhead shall be allowed for any change on a percentage markup basis regardless of whether the completion of the contract is or is not extended by reason of the change, except for modifications issued pursuant to the Default Clause. The Contractor shall provide a detailed breakdown of its proposed increase or decrease of costs as required by Contract Clause DFARS 252.236-7000 MODIFICATION OF PROPOSALS – PRICE BREAKDOWN.

SCR_CT_007 MAGNITUDE OF PROJECT—CONSTRUCTION (Jul 2002)

The magnitude of this project is represented by the following estimated price range (contracting officer mark as appropriate):

X__Between $500,000 and $1,000,000

TPL_NWK_001 Points of Contact

CONTRACT

SPECIALIST:

Dominique Howard

PHONE: 816-389-3430 E-MAIL: Dominique.C. Howarrd@ usace.army.mil

PROJECT

MANAGER:

Kathy Baker PHONE: 816-389-3906 E-MAIL: Kathy.T.Baker@usace.army.mil

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Submittal Table Attachment 10 Building 1206

Construction Drawings

Attachment 11 Assumptions Attachment 2 Solicitation Figures

Combined

Attachment 3 Soil Excavation Volumes Attachment 4 Schedule Specs Attachment 5 RMS Specs Attachment 6 KSAAP Item Schedule mailto:Howarrd@usace.army.mil mailto:Howarrd@usace.army.mil mailto:Kathy.T.Baker@usace.army.mil

Attachment 7 Final Remedial Action Report

Attachment 8 Final Corrective Measures Attachment 9 Draft Building 1206

Investigation Report

Section 00 21 00 - Instructions, Conditions and Notices to Offeror

PROPOSAL SUBMISSION

1.0 GENERAL PROPOSAL INFORMATION

The proposal should be practical, legible, clear and coherent. Offerors are discouraged from providing information not required by the Solicitation.

2.0 GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

All offerors shall be required to submit a proposal with the minimum content as specified herein.

Proposals without the minimum content may be rejected. Proposals will be received until the date and time indicated on Standard Form 1442 at the following address:

U.S. Army Engineer District, Kansas City Federal Building Room 647 ATTN: CECT-NWK-H/Dominique Howard 601 East 12th Street Kansas City, Missouri 64106-2896

3.0 PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1. In order to be considered for award of a contract for the requirements of this solicitation, the offeror must submit a typed proposal with its offer. Failure to submit a complete typed proposalmay result in the entire offer being rejected.

The proposals shall be submitted in (2) Volumes as follows: Submit the proposal in tabbed, three-ring binders identified by the Solicitation Number, project title, name, address, and telephone number of the offeror. Arrange tabs as follows:

Volume 1, Technical Proposal:

FACTOR 1 Company Experience FACTOR 2 Past Performance FACTOR 3 Local Preference

Volume 2: Price Proposal

FACTOR 4 Price Proposal

2. Proposal Characteristics

a) Each Volume shall contain a table of contents and all pages of each factor shall be sequentially numbered. All text must be legible and easily read. Submit the SF 1442, completed and signed by a person authorized by the offeror, in Volume 2.

Offerors shall limit Volume 1, Technical Proposal, Factor 1, Company Experience, to a maximum of 5 pages (1 pages for each project) utilizing the form provided below. Pages in excess of 5 will not be evaluated. Factor 2 – Past Performance will not be counted towards this page limitation. All text shall be a minimum of size 10 font and 1 inch margins.

b) Volumes shall be submitted in both hard copy and electronic copy in the following quantities:

Volume 1 – Technical Proposal - Original & 4 copies. Electronic copies shall be submitted in PDF format.

Volume 2 – Price Proposal - Original & 2 copies. Electronic copies shall be submitted in Excel and PDF format.

Electronic copies should be equivalent to the printed original copy and be searchable or Optical Character Recognition (OCR) formatted. OCR is a common method of digitizing printed texts so that they can be electronically searched, stored more compactly, displayed on-line, and used in machine processes such as machine translation, text-to-speech, key data extraction and text mining.

c) Each Volume of the proposal shall be identified by the Solicitation Number, project title (Former Kansas Army Ammunition Plant – Bldg 1206 Corrective Measure Implementation, Parsons, Kansas), name, address, and telephone number of the offeror, and the following on the volume in bold letters:

VOLUME 1: TECHNICAL PROPOSAL

VOLUME 2: PRICE PROPOSAL

d) The Technical proposal shall not refer the reviewer to information contained in the Price proposal.

e) Additional Information to be provided in Volume 1.

Tab 1 - For joint ventures, the information required by paragraph "Joint Ventures" (if applicable).

Tab 2 - Subcontractor letters of commitment as required by paragraph “Subcontractors” (if applicable).

f) Additional Information to be provided in Volume 2.

Tab 1 - Pro Forma Requirements. The following information should be submitted with Volume 2 and labled “Pro Forma Requirements”.

This information consists of the following:

i.) Offeror will submit a cover letter containing:

a. Solicitation number

b. Name, address, email and telephone and fax numbers of the offeror

c. Names, title, email and telephone and fax numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this RFP.

d. Name, title and signature of the person authorized to sign the proposal

e. A statement specifying agreement with all terms, conditions and provisions included in the Solicitation

f. CAGE Codes for the offeror and all teaming partners who participated in the Factor 1 – Company Experience projects.

ii.) The Offer (the SF1442) duly executed with an original signature by an official authorized to bind the company. Include the offeror’s DUNS number in block 14.

iii.) Acknowledgement of all amendments to the Solicitation in accordance with the instructions on the Standard Form 30 (amendment form).

iv.) Complete Section 00 45 00 of the RFP (Representations and Certifications), Printed Entity Record from System for Award Management (SAM).

4.0 INQUIRIES/QUESTIONS

Technical inquiries and questions relating to this solicitation shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). To submit and review inquiry items, prospective offerors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective offeror who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective offeror once the reply is available for viewing.

***Please Note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected.

The Solicitation Number is: W912DQ-18-R-3010 The Bidder Inquiry Key is: VQN9GB-7F4AJW

Quick Access Key: G762CQ-8JFJG9

Instructions for first-time ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. Select agency USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and

Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Instructions for future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. Select agency USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

The Bidder Inquiry System will be unavailable for new inquiries on 08 June 2018 in order to ensure adequate time is allotted to form an appropriate response to inquiries and amend the solicitation if necessary.

Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) or by appointment for OCONUS. The telephone number for the Call Center is 1-800- 428-HELP. Email to staff@rcesupport.com.

5.0 JOINT VENTURES

Joint Ventures shall submit the following additional documentation regarding their business entities:

1) A certified copy of their Joint Venture agreement.

2) A detailed statement outlining the following in terms of percentages, where appropriate.

a. The relationship of the joint venture parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.

b. The management approach of the joint venture in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the Joint Venture and perform the duties necessary to complete the work.

c. The structure of the joint venture and decision-making responsibilities of the Joint mailto:staff@rcesupport.com

Venture parties in terms of who will control the manner and method of performance of the work.

d. Identification of the key personnel having authority to legally bind the Joint Venture to subcontracts and state who will provide or contract for the labor and materials for the Joint Venture.

e. Identification of party maintaining the Joint Venture bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the Joint Venture.

f. Identification of party furnishing the facilities, such as office supplies and telephone service.

g. Identification of party having overall control of the Joint Venture.

Other sections of the proposal shall identify, where appropriate, whether key personnel are employees of the individual Joint Venture parties and identify the party, or hired as employees of the Joint Venture.

The Joint Venture parties’ experience and/or past experience will be included as the experience and/or past experience of the Joint Venture.

6.0 SUBCONTRACTORS

If an offeror wishes to receive credit for the experience or past performance of a subcontractor, the offeror must submit a letter of commitment to use the proposed subcontractor on the project, signed both by the subcontractor and the offeror. The commitment letter must be submitted even if the subcontractor is in some way affiliated with the offeror (for example, the subcontractor is a subsidiary of a joint venture partner, or a subsidiary of a firm to which the joint venture partner is also a subsidiary). Include the subcontractor letters of commitment in Volume 1, Factor 1, Company Experience. Subcontractor letters of commitment will not be counted towards the page limit for that Factor.

SAMPLE LETTER OF COMMITMENT to USE SUBCONTRACTOR

[COMPANY LETTERHEAD]

TO: Contracting Officer, Kansas City District, United States Army Corps of Engineers

SUBJECT: Letter of Commitment for Proposed Contract for [insert project name]

Dear Sir or Madam:

[Insert name of offeror] and [insert name of subcontractor] hereby make the unequivocal commitment that, in the event that the company receives award of the Contract for [insert project name], [insert name of subcontractor] will perform the following work required by the Contract.

[Insert list of tasks to be performed by the subcontractor]

Sincerely, [Authorized Official]

[Legal Name of Offeror]

Date:

[Subcontractor]

[Legal Name of Subcontractor]

Date:

7.0 BASIS FOR AWARD

The Government reserves the right to enter into discussions. In the event that discussions are not necessary then the Government intends to award without discussions, to the responsible offeror whose proposal conforms to the solicitation and is determined to be the Best Value to the Government, utilizing the tradeoff process.

The technical factors, when combined are significantly more important than the Price Factor.

Factor 1 – Company Experience is the most important. Factors 2 and 3 are less important than Factor 1, and equal to each other. Offerors are cautioned that the award may not necessarily be made to the offeror providing the lowest priced proposal.

8.0 SOURCE SELECTION PROCESS

All proposals received in response to this solicitation will be evaluated in accordance with informal source selection procedures. The principal objective of this process is to select a responsible offeror who submits the offer that is the Best Value to the Government, utilizing the tradeoff process. The process is designed to ensure the impartial, equitable, and comprehensive evaluation of all proposals received in response to this solicitation.

(a) ) Source Selection Organization

The source selection organization is established as a separate organization and management chain of command whose only purpose is to accomplish the objective above. The organization consists of a Source Selection Authority (SSA) and a Source Selection Evaluation Board (SSEB). The SSEB is comprised of separate Technical Evaluation and Price Evaluation teams. The organization is designed to ensure active ongoing involvement of appropriate contracting, technical, logistics, legal, price analysis, small business, and other functional staff management expertise.

(b) Source Selection Procedure

The source selection procedures will begin with an initial review of proposals and continue with a technical and price evaluation conducted by the SSEB. The SSEB shall evaluate the proposals based solely on the evaluation criteria identified above. The proposals received in response to this solicitation will be evaluated individually to select the most advantageous proposal. The Government reserves the right to consider and evaluate information regarding past performance from sources outside the proposal. The results of the SSEB evaluations will be presented to the SSA, who will make the final source selection decision or determine whether it is appropriate to engage in clarifications or communications prior to the establishment of a competitive range, or to establish a competitive range and conduct discussions with those offerors that are included in the competitive range. All communications leading to establishment of the competitive range will be conducted in accordance with FAR Part 15.306(b).

If a competitive range is established, discussions will be conducted with offerors who are included in the competitive range. After conclusion of discussions and receipt of final revised proposals (if applicable), the SSEB will complete the evaluation and establish the final technical ratings and present them to the SSA. The SSA will then review the proposals and make the final source selection decision.

The Government is not responsible for information overlooked during the evaluation which is not located in the appropriate proposal section.

To ensure the evaluation credit is appropriately received for proposal material submitted, do not incorporate by reference documents not contained in the proposal.

9.0 DEBRIEFING OFFERORS

Offerors may request a debriefing in accordance with FAR 15.505 Pre-award Debriefing of Offerors, and FAR 15.506 Post-award Debriefing of offerors.

10.1 FACTORS TO BE EVALUATED

1. VOLUME 1 – TECHNICAL

Factor Location Description Relative Importance FACTOR 1 Vol. 1 Company Experience Most Important Technical Factor

FACTOR 2 Vol. 1 Past Performance Less important than Factor 1;

Equal to Factor 3.

FACTOR 3 Vol. 1 Local Preference Less important than Factor 1;

Equal to Factor 2.

2. VOLUME 2 – PRICE

Factor Location Description Relative Importance FACTOR 4 Vol. 2 Price Technical Factors, when combined, are significantly more important than Price.

VOLUME 1, FACTOR 1 – Company Experience.

Submission Requirements

The offeror shall submit a project portfolio of up to five (5) relevant projects to be evaluated for this factor; one page per project shall be submitted.If more than five projects are submitted, only the first five projects will be evaluated.

A project is defined as work performed at one site, or at a single installation. An Indefinite Delivery Contract (IDC) is not a project. The projects should describe the specific work, identify whether it was performed as the prime, or subcontractor. The projects should demonstrate experience with similar contaminants, materials and construction techniques necessary to complete the requirements included under this solicitation. A project will be considered relevant only if it is similar in size, scope, and complexity to the work described in this solicitation.

These projects must have been completed in the five (5) year period preceding the date of this solicitation or started within the past three (3) year period and be at least 50% complete at the time of this solicitation.

Projects included in the portfolio shall demonstrate the breadth and depth of the offeror’s experience as it relates to the work described in this solicitation.

The offeror shall use the form provided below in providing this information.

If the offeror is a Joint Venture combining two or more companies, state whether each project was performed by the same Joint Venture. Each member of a Joint Venture shall demonstrate experience commensurate with its proposed role on this project.

The Government may contact and interview project references. Reference information will not be revealed to other parties.

Factor 1 - Previous Experience Template Project Name: Site Location (City/State):

Client:

USACE USEPA Other – Describe:

Client POC Name and Phone Number:

Offeror:

Prime Sub-Contractor

Percent of Work Subcontracted: If other than Prime Offeror, name of Team Subcontractor or Contractor:

Start Date (mm/yyyy): Completion Date (mm/yyyy): Percent of Project Compete: Total Project Cost at Completion:

Contract Type:

Cost Reimbursable Firm Fixed Other – Describe:

Project Description:

Describe project experience conducting foundation and wall stabilization prior to excavation, if applicable:

Describe project experience with excavation of a slab within a building and the soil beneath, if applicable:

VOLUME 1, FACTOR 2 - Past Performance.

For each of the projects submitted under Factor 1, the offeror shall provide a Past Performance Questionnaire (Form PPQ) included in the solicitation to a representative of the owner that can provide the owner’s opinion of the offeror’s past performance for the project. Completed PPQ forms should be submitted with your proposal. The PPQ does not have to be sent directly from the client. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Dominique Howard via email at Dominique.C.Howard@usace.army.mil prior to proposal closing date. The offeror is responsible for ensuring that the completed questionnaires are submitted by the closing date. If you have questions regarding the attached questionnaire, or require assistance, please contact the Contract Specialist at (816) 389-3430.

For each of the projects submitted under Factor 1, to ensure the agency has all relevant past performance information, the offeror also should submit copies of Federal/DoD/Navy/Army performance reviews that are likely already in the agency’s databases or likely within the agency’s arm’s reach, i.e., Contractor’s copy of CCASS or CPARS evaluations. To improve accuracy of database searches, the offeror will also provide the CAGE Codes for the prime contractor and all teaming partners, i.e. key subcontractors, Joint Venture Partners, whose experience is being relied upon for Factor 1.

Offerors should organize all Past Performance Information based on the Factor 1 Projects, which normally have project titles and are numbered 1-5, so that reviewers can match the owner’s

Describe project experience with removal and disposal of hexavalent chromium contaminated soil, if applicable:

mailto:Dominique.C.Howard@usace.army.mil opinion with the corresponding Factor 1 Project. There is no page limit for this factor.

The Government will evaluate the responses from the customers from which Past Performance Questionnaires have been received. The Government may contact and interview the owner’s representative on the PPQ, and reserves the right to interview other individuals acting for the owner’s representative, if the owner’s representative is not available. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Past performance information may be obtained from any other sources available to the Government, to include, but not limited to, the Past Performance Information Retrieval System (PPIRS), Construction Contractor Appraisal Support System (CCASS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency.

At no time during this process, nor during the debriefing, nor after award, will the names of the individuals providing reference information about an offeror’s past performance be revealed to the offerors or to any other party. If discussions are held, offerors may be afforded the opportunity to respond to adverse comments made by references in accordance with guidelines identified in FAR Part 15.3. In this case, comments will be extracted and provided to the offeror.

Copies of the questionnaires will not be furnished to the offeror and will remain confidential.

SAMPLE TRANSMITTAL LETTER

AND

PAST PERFORMANCE QUESTIONAIRE

To:

Date

We have listed your firm as a reference for work we have performed for you as listed below. Our firm has submitted a proposal under a project advertised by the U.S. Army Corps of Engineers, Kansas City District. In accordance with Federal Acquisition Regulations (FAR), an evaluation of our firm’s past performance will be completed by the Corps of Engineers. Your candid response to the attached questionnaire will assist the evaluation team in this process.

We understand that you have a busy schedule and your participation in this evaluation is greatly appreciated. Please complete the enclosed questionnaire as thoroughly as possible. Space is provided for comments. Please respond in time for us to include the questionnaire with our proposal, which is due on . Only one response from each office is required. If at all possible, we suggest that you individually answer this questionnaire and then coordinate your responses with that of , to forge a consensus on one overall response from your organization. Please return completed questionnaires to the following:

If you would prefer to respond directly to USACE, your completed questionnaire may be sent to the following address:

U.S. Army Engineer District, Kansas City ATTN: CECT-NWK-H/Dominique Howard Federal Building Room 647 601 East 12thStreet Kansas City, Missouri 64106-2896

The questionnaires can also be e-mailed to Dominique.C.Howard@usace.army.mil.

mailto:Dominique.C.Howard@usace.army.mil

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture

Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES

THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE

OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED

QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY

DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON

USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO

SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER,

QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE.

PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION.

THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL

INFORMATION ON THIS FORM.

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner.

A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good

Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

ADJECTIVE RATINGS TO BE USED TO BEST REFLECT

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable

No information or did not apply to your contract

Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS YOUR

EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E N

VG S M U

b) Ability to meet quality standards specified for technical performance

E N

VG S M U

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E N

VG S M U

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E N

VG S M U

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E N

VG

S

M

U

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E N

VG S M U

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E N

VG S M U

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E N

VG S M U

d) Overall customer satisfaction E N

VG S M U

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

E VG S

N

M U

b) Ability to hire, apply, and retain a qualified workforce to this effort

E VG S

M U

c) Government Property Control E VG S

M U

d) Knowledge/expertise demonstrated by contractor personnel E VG S N

M U

e) Utilization of Small Business concerns E VG S N

M U

f) Ability to simultaneously manage multiple projects with multiple disciplines

E VG S

N

M U

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

E VG S

N

M U

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S

N

M U

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S

N

M U

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E VG S

N

M U

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.

Yes

No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

b) Contractor complied with all security requirements for the project and personnel security requirements.

E VG S

N

M U

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S

N

M U

b) Compliance with contractual terms/provisions (explain if specific issues)

E VG S

N

M U

c) Would you hire or work with this firm again? (If no, please explain below) Yes

d) In summary, provide an overall rating for the work performed by this contractor.

E VG S

M U

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

Volume 1, Factor 3: Local Preference

Section 2912 of the National Defense Authorization Act for Fiscal Year 1994, Pub. L. No.

103- 160 established a preference for contracting with local, small, and small disadvantaged businesses for work associated with closing or realigning military installations under a base closure law. This preference explicitly includes "contracts to carry out activities for the environmental restoration and mitigation" of such installations. Pub. L. No. 103-160, Sec.

2912(a) (set forth at 10 U.S.C. Sec. 2687 note (1994)). Businesses located in the vicinity of a military installation that is being closed or realigned under a base closure law, including 10 U.S.C. 2687, and small disadvantaged businesses shall be provided maximum practicable opportunity to participate in acquisitions that support the closure or realignment, including acquisitions for environmental restoration and mitigation. The Contracting Officer conducted market research, and determined that there is a reasonable expectation that offers will be received from responsible business concerns located in the vicinity of the military installation that is being closed or realigned.

Local area. Based on market research, the local area is: Labette County, KS; Cherokee County, KS; Crawford County, KS; Montgomery County, KS; Neosho County, KS; Wilson County, KS; Craig County, OK; Nowata County, OK.

Representations.

The Offeror shall complete the following representations.

The offeror represents that it [] does or [] does not reside or primarily do business in the designated local area. If the offeror represents that it resides or primarily does business in the area, the offeror shall furnish documentation to support its representation.

The offeror represents that it [] does or [] does not commit to hire residents of the local area. If the offeror represents that it commits to hire residents of the designated local area, the offeror shall furnish a plan to support its representation.

VOLUME 2, FACTOR 4 – Price

Offerors shall submit the price schedule (Attachment 2) consisting of the original signed Standard Form 1442 “Solicitation, Offer, and Award” providing a price for all line items in the corresponding price schedule and acknowledgement of all amendments to the solicitation.

Proposed prices must be entered for all items of the price schedule. The price schedule, shall be submitted in excel format.

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016

52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) - Alternate I

OCT 1997

52.215-22 Limitations on Pass-Through Charges--Identification of Subcontract Effort

OCT 2009

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3.0 million, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

USACE, Kansas City – Federal Building 601 E. 12th St., Room 647 Attention: Kori Hames Kansas City, MO 64106-2896

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) The pre-proposal site visit will occur on June 14th, 2018 starting at 1:00 pm Central Time. All attendees will meet inside the Great Plains Industrial Park gate. There is a parking lot to the left as you enter the facility; USACE representatives will meet all attendees at this parking lot at 1:00 pm Central Time, June 14th, 2018. All proposers wanting to attend need to RSVP to Kathy.T.Baker@usace.army.mil by June 8th at 5:00pm Central Time. All attendees must wear steel-toed shoes and hard hats.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/ mailto:Kathy.T.Baker@usace.army.mil http://farsite.hill.af.mil/

Section 00 24 00 - Evaluation Factors for Award

EVALUATION FACTORS

1. VOLUME 1, FACTOR 1 – Company Experience.

Evaluation Criteria

The Government will review the submitted projects to evaluate the extent and relevance of the offeror’s experience in order to determine how well they demonstrate the Offeror’s capability to successfully perform the requirements included in this solicitation. The Government will evaluate how well the Offeror demonstrates company experience using methods, materials, technologies, and construction techniques similar to those necessary to complete the current requirement. In determining strengths and weaknesses, the agency will give more credit to the following:

a. Experience with stabilization of foundations and walls prior to excavation.

b. Experience with excavation of foundation slab within a building and the soil beneath.

c. Experience with removal and disposal of hexavalent chromium contaminated soil.

1.1 TECHNICAL RATING

The evaluation ratings for the Technical Factors will be on an adjectival basis in conjunction with a narrative composed of the discussion of the particular strengths, weaknesses, and deficiencies of the proposal.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.