Section 01 10 00 - Scope of Work

SCOPE OF WORK

1. DESCRIPTION OF WORK

The Contractor shall be responsible for executing the Contract by: conducting the required environmental restoration services for the United States Army Corps of Engineers (USACE) on behalf of the U.S. Army Base Realignment and Closure (BRAC) office; addressing any and all environmental, scheduling, and regulatory issues;

and assuming contractual liability and responsibility for the achievement of the objectives for the Building 1206 Soil Removal at the former Kansas Army Ammunition Plant (KSAAP), Parsons, Kansas. Figures 1 and 2 show the locations of KSAAP and the 1200 Area, respectively. The Contractor shall comply with all applicable federal, state, and local laws and regulations, standard industry practices, and fulfill the requirements of the Scope of Work (SOW) in a manner that is consistent with any applicable orders or permits, all existing cleanup agreements or guidance for the KSAAP and relevant Department of Defense (DOD) and USACE policy for the duration of the Contract.

The Contractor shall perform all necessary environmental remediation work as required to meet the requirements of this SOW. The SOW is being conducted under the Resource Conservation and Recovery Act (RCRA) with regulatory coordination through the Kansas Department of Health and the Environment (KDHE) Bureau of Environmental Remediation (BER) and the United States Environmental Protection Agency (EPA) Region VII.

The documentation provided in Attachment 1 represents the most recent and appropriate documentation available for the tasks identified in this SOW. Documents include the following:

Attachment 1a - Final Remedial Action Report, 1200 Area, 2011 Attachment 1b - Final Corrective Measures Implementation Report, 1200 Area Settling Lagoons/Effluent

Ditches and Pond 3 Corrective Measures Design/SLERA Investigations and Removal Action, 2013 Attachment 1c - Draft Pre-Design Investigation Work Summary, Building 1206, 2018 Attachment 1d - Building 1206 Construction Drawings (various years)

The objectives of the 1200 Area work are to:

Excavate hexavalent chromium contaminated overburden soil from underneath Building 1206 (Figure 3) Dispose of contaminated soil and concrete off-site Backfill to pre-existing grades with clean off-site borrow, restore concrete slab, and restore foundation stabilization elements

1.1. Site Description

The former KSAAP is located in Labette County, Kansas, approximately 20 miles north of the Oklahoma state line and 30 miles west of the Missouri state line, near the town of Parsons (Figure 1). The 1200 Area (formerly the Casing Rework Area) refers to approximately 49 acres in the south-central portion of KSAAP (Figure 2).

Chromium contamination at the site resulted from casing rework of 105-millimeter cartridges, which started in Building 1206 in 1953. Part of this rework process involved cleaning the casings with a chromic acid solution, the first such reported use of this chemical in the 1200 Area. At present, the site is mostly grasslands with five brick and block buildings, a system of engineered drainage ditches, a system of stem lines, and a storm water retention pond at the southeastern end of the site (Pond #1).

Two earthen-type, unlined lagoons, southern settling lagoon (SSL) and northern settling lagoon (NSL) located within the 1200 Area were used for settling and storage of wastewater containing chromic acid solution and rinse water, respectively, generated from casing reworking. Discovery of the former settling lagoons, which were filled in and abandoned after casing rework operations ceased, occurred during implementation of the Soils Corrective Measures, after the 2004 Resource Conservation and Recovery Act (RCRA) Facility Assessment and 2005 RCRA Facility Investigation.

Wastewater was reportedly discharged directly into the SSL without treatment. Water from the SSL did not drain off-site, but instead either evaporated or was allowed to infiltrate into the ground. Detergent used in the casing rework process was discharged to a ditch located between the two lagoons to a point where it entered a drainage ditch on the west side of the lagoons. The rinse water was conveyed via a third ditch to the NSL, then treated with

W912DQ18R3010

sodium met bisulfite prior to entry into a 30-minute retention pond and finally treated with lime prior to discharge into a ditch on the west side of the lagoons. The drainage ditch west of the lagoons conveyed the detergent and treated rinse water to Pond #3 located to the southwest of the 1200 Area.

In 2007, USACE performed a Remedial Action which included excavation and off-site disposal of soil contaminated with hexavalent chromium and polychlorinated biphenyls. In November 2011 USACE began the Corrective Measures Implementation (CMI) which consisted of investigation trenches and subsequent excavation of 100 by 250 feet of SSL material down to the top of the weathered limestone. The depth of excavation ranged from approximately 5 to 6 feet below ground surface (bgs).

1.2. Cleanup Criteria

The soil clean-up criteria for KSAAP are for non-residential use and are presented in the Final Corrective Measures Decision (CMD) (EPA, 2006). Hexavalent chromium is expected to be the only contaminant exceeding the clean-up criteria underneath Building 1206. Therefore, hexavalent chromium results from confirmation sampling performed as part of the soil removal will be compared to the clean-up criteria of 64 milligrams per kilogram and additional soil removal shall be performed as needed.

2. KEY PERSONNEL

Project Manager: The Project Manager (PM) shall be competent, experienced and knowledgeable in the field of hazardous and toxic waste cleanup, environmental laws and regulations, and the type of activities in the SOW. The PM is responsible to assure the goals of the Contract are attained in a manner consistent with the Contractor's approved Accident Prevention Plan (APP), Contractor Quality Control Plan (CQCP) and all State, Federal and local laws and regulations. The PM will coordinate with the Certified Industrial Hygienist (CIH) and the Site Safety and Health Officer (SSHO) to assure that all activities are performed in a safe manner. The PM shall be employed by the Contractor and be the primary point of contact.

Field Supervisor: The Field Supervisor is responsible to ensure compliance with the requirements identified in the SOW and the CQCP. The Field Supervisor, or their designated representative, shall be physically present at the project site whenever work is in progress. Their responsibilities shall include:

Inspection of materials and equipment received on-site to assure compliance with contract requirements Inspection of all field activities Supervision of Quality Control (QC) testing as required by the contract documents Completing daily QC reports

Sampling, Analysis, and Chemical Quality Management: The Contractor chemical quality control coordinator (CQCC) shall have a degree in chemistry or a related field with a minimum of 16 semester hours in chemistry and 4 years of experience in chemical contamination cleanup work. The CQCC shall be responsible for the QC of sampling, sample handling including sample custody, field testing, coordinating the QC of the laboratory, and assuring the required submittals are on time and of high quality.

Certified Industrial Hygienist: The Contractor shall utilize the services of an experienced CIH to implement and oversee the Safety and Health Program and to develop, implement and sign the APP and any addenda. Any changes to the established Safety and Health Program or APP shall be at the direction and approval of the CIH, with concurrence of the Contracting Officer (KO). The CIH will not necessarily be required to be on-site during removal action activities but shall be readily available for consultation when required. The minimum qualifications of the CIH shall include:

Certified by the American Board of Industrial Hygiene A minimum of 5 year working experience in the chemical or hazardous waste disposal industry Demonstrable expertise in air monitoring techniques and in development of personal protective equipment programs for working in potentially toxic atmospheres Working knowledge of applicable Federal, State, and local occupational safety and health regulations

Site Safety and Health Officer: The Contractor shall utilize a trained and experienced (minimum 1 year) SSHO to assist and represent the CIH in the implementation and enforcement of the approved APP. A SSHO shall be assigned during work activities on a full-time basis and shall be either a Contractor employee or a subcontractor who reports to the Contractor and the CIH in matters pertaining to site safety and health. The SSHO shall have the on-site responsibility and authority to modify or halt work, or remove personnel from the site if working conditions which may affect on-site/off-site safety and health change. The SSHO shall be the main contact for any on-site emergency situation. Except in an emergency, the SSHO may modify the approved APP only after consultation and concurrence of the CIH and the KO.

Professional Engineer: The Contractor shall utilize the services of an experienced Professional Engineer to design and oversee the stabilization, excavation, and restoration efforts within Bldg. 1206. The Professional Engineer will not necessarily be required to be on-site during all construction activities but shall be readily available for consultation when required. The Professional Engineer shall perform a site inspection prior to submittal of the Work Plan and at least one additional site inspection during construction and restoration activities. The Professional Engineer will be required to certify/stamp the Foundation/Wall Stabilization Plan and Floor/Foundation Restoration Plan to document it will adequately restore the building to pre-construction condition. The minimum qualifications of the Professional Engineer shall include:

Certified in the state of Kansas as a Professional Engineer A minimum of 5 years of related experience as a Structural or Civil Professional Engineer

Personnel may perform dual roles if the proposed personnel satisfies the requirements for both roles. No personnel will be permitted to perform more than two roles at the site concurrently.

3.0 CONTRACTREQUIREMENTS

3.1 Period of Performance and Commencement of Work

The period of performance for the contract is two years from the date of contract award. The period of performance for the execution of the tasks listed below in the SOW is dependent on the agreed to schedule submitted with the proposal. The Contractor must receive approval from the USACE COR on all site-specific plans (outlined below) before initiating any on-site activity. The time stated for completion shall include acceptance of all demobilization and site restoration activities as defined in this SOW.

3.2 Notice of Completion of Contract

The Contractor shall notify the KO upon completion of the Contract. The Contractor shall give advance notice of the date the work will be fully completed and ready for final inspection.

3.3 Inspections

USACE technical experts will independently review all work to ensure compliance with all applicable requirements.

USACE will have a representative on site during all intrusive activities. Corrective action must be certified and approved by the USACE COR consistent with the contract.

3.4 Government Rights

USACE has unlimited rights to all documents and data produced under this contract. All documents and data, to include the source codes of any software produced under this contract, shall be USACE-owned with all rights and privileges of ownership and copyright belonging exclusively to USACE. These documents and materials cannot be used or sold by the Contractor without written permission from USACE. All materials supplied to USACE shall be the sole property of USACE and cannot be used for any other purpose. This right does not nullify any other USACE rights under the applicable Data Rights clause(s).

3.5 Stop Work Authority

All Contractor and USACE personnel have the authority and responsibility to stop work immediately if the work is considered to be a serious threat to safety and health of field or other personnel or to the environment. When work is stopped due to a hazard/threat to worker safety, health or the environment, the situation and resolution shall be documented and submitted to the KO within 48 hours. Work shall be stopped if chemical warfare agents or ordinance are discovered and the KO notified immediately. In addition, the KO has the authority to stop work temporarily on a project following one working day written notification to the Contractor. Stop work notices can be issued due to nonconformance to project specifications or lack of performance by the Contractor. Contractor shall notify the KO immediately of any differing site conditions (see FAR Clause 52.236-2, Differing Site Conditions).

3.6 Environmental Responsibility Considerations

The Government shall retain the responsibility for any assessed natural resource damages that are attributed to the historic releases of hazardous substances (prior to Contract with Contractor) and any unavoidable natural resource damage that occurred due to the remedial work and incidental to the reasonable implementation of the corrective measures. The Contractor shall be responsible for any and all natural resource injuries and associated Natural Resource Damage claims brought as a result of its action, inaction, or negligence (e.g. release of hazardous substance or unreasonable disturbance of natural resources as a result of construction activities).

Response claims, property damage, and personal injury claims brought due to contamination and hazardous substance releases that have occurred historically (prior to Contract with the Contractor) and are not due to Contractor remediation activities or negligence are excluded from Contractor responsibility. The Contractor shall be responsible for and indemnify USACE for:

Response cost claims for any environmental remediation services the Contractor has assumed responsibility for under this SOW All costs associated with correction of a failure occurring during the remedial action to the extent such failure was caused by the willful or negligent acts or omissions of the Contractor in the course of performing environmental services

All personal injury or property damage claims to the extent caused by the acts or omissions of the Contractor in the course of performing the services

All natural resource damages pursuant to 42 U.S.C Section 9607 (a)(4)(C), to the extent that such damages were caused or contributed to by the actions of the Contractor or its successors in interest

All costs associated with or arising from any negligent acts or omissions or willful misconduct of the Contractor in the course of performing the environmental services or implementing remedial actions

3.7 Restrictions

The Contractor is cautioned to take no guidance during the course of the work from any other source except the KO or the Contracting Officer’s Representative (COR).

3.8 Limits of Work

The Contractor shall limit work to within the boundary of the 1200 Area as shown on Figure 4 and demarcated by the existing security fencing. The Contractor shall not work beyond the 1200 Area fence line without prior approval from the KO.

3.9 Working Hours

The Contractor shall adhere to any installation, county or municipal ordinances when performing on‐site, physical work. In general, work shall be performed between the hours of 7:30 AM and 5:00 PM, Monday through Friday. Work outside regular working hours requires KO approval.

Make application 7 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. If working during periods of darkness, the different parts of the work shall be lighted in a manner approved by the KO. Lighting shall be in accordance with USACE Engineering Manual (EM) 385‐1‐1.

3.10 Regulatory Requirements

The Contractor shall identify applicable Federal, State and Local laws, regulations, and agreements and perform its work in accordance with them. The Contractor shall ensure that all activities performed by its personnel, subcontractors and suppliers are executed in accordance with Federal, State and Local laws, regulations, and agreements. Any incident of noncompliance noted by the Contractor shall immediately be brought to the attention of the KO, the USACE PM, and BRAC by telephoning and then by written notice. Nothing in this Contract shall relieve the Contractor of its responsibility of compliance with all applicable environmental laws and regulations. The Contractor shall be responsible for obtaining all permits, licenses, approvals, and/or certificates necessary to accomplish the work specified. Any clearances needed for locating utilities or other work, shall be obtained by the Contractor with the assistance of the KSAAP point of contact, prior to initiation of any drilling or excavating operations. The Contractor shall coordinate with the KO and KSAAP prior to performing any work and comply with any site-specific time and procedural requirements described in the permits obtained.

3.11 Laboratory Requirements

The Contractor shall ensure that all subcontract laboratories performing analyses in support of this procurement have an established and documented laboratory quality system that conforms to ISO/IEC 17025:2005 as implemented by the DOD Quality Systems Manual for Environmental Laboratories (latest version) as determined by maintaining DOD Environmental Laboratory Accreditation Program (ELAP) accreditation during the period of contract performance.

Laboratories must possess any required state certification and be accredited for the DOD ELAP by a DOD approved accrediting body which is ISO/IEC 17011:2004 compliant. As an element of the DOD ELAP, all laboratories must demonstrate the ability to generate acceptable results from the analysis of proficiency-testing sample(s), subject to availability, using each applicable method in the specified matrix. The Contractor shall ensure the laboratory makes appropriate documentation available to the KO.

Soil and concrete laboratories performing third party testing shall be currently certified as an approved testing laboratory by USACE.

3.12 Quality Control

Contractor Quality Control (CQC) is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the CQC System Manager for each definable feature of the construction work as follows:

Preparatory Phase: This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field.

Maintain and make available in the field for use by Government personnel until final acceptance of the work.

Review of the contract drawings.

Check to assure that all materials and/or equipment have been tested, submitted, and approved.

Review of provisions that have been made to provide required control inspection and testing.

Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

Review of the appropriate activity hazard analysis to assure safety requirements are met.

Discussion of procedures for controlling quality of the work including repetitive deficiencies.

Document construction tolerances and workmanship standards for that feature of work.

Check to ensure that the portion of the plan for the work to be performed has been accepted by the KO.

Discussion of the initial control phase.

Include a meeting conducted by the CQC System Manager and attended by the superintendent, Government, Quality Assurance personnel, other CQC personnel (as applicable), and the foreman responsible for the definable feature.

Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report.

Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

Initial Phase: This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing.

Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Resolve all differences.

Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report.

Indicate the exact location of initial phase for future reference and comparison with follow-up phases.

The initial phase should be repeated for each new crew to work on-site or any time acceptable specified quality standards are not being met.

Follow-up Phase:

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements until completion of the particular feature of work. Record the checks in the CQC documentation.

Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

Additional Preparatory and Initial Phases: Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

Documentation: Maintain current records providing factual evidence that required QC activities or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:

Contractor/subcontractor and their area of responsibility.

Operating plant/equipment with hours worked, idle, or down for repair.

Work performed each day, giving location, description, and by whom. When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

Test or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, or Follow-up). List of deficiencies noted, along with corrective action.

Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

Submittals and deliverables reviewed, with contract reference, by whom, and action taken.

Offsite surveillance activities, including actions taken.

Job safety evaluations stating what was checked, results and instructions or corrective actions.

Instructions given/received and conflicts in plans or specifications.

Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract.

Furnish the original and one copy of these records in report form to the Government daily within 24 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.

3.13 Notification of Noncompliance

The KO will notify the Contractor of any detected noncompliance with the foregoing requirements: Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the KO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

3.14 Submittals

All final submittals provided to the Government by the Contractor shall be certified by an engineer or other required technical staff member registered in the state in which the site is located. With the following exception, the Contractor shall provide a draft version, comment responses, a draft final version, comment responses and a final version of all work plan and report submittals: the CQCP and APP will only be reviewed by USACE. The COR will provide consolidated Army (i.e. USACE and BRAC) comments on draft documents to the Contractor within thirty (30) business days. Draft versions will be reviewed by USACE and BRAC only. Draft final versions will be back-checked by USACE and BRAC prior to submittal to EPA and KDHE. All other submittals, such as progress reports, etc. shall only include final versions; however, USACE reserves the right to provide comments for errors or omissions and request a revised draft. Each version of all submittals shall be provided in electronic format and hard copy in quantities listed in Table 1. In addition, one copy of all final reports shall be submitted to the Parsons Library KSAAP Administrative Record.

At the completion of the project, the Contractor shall provide a complete set of project records including all correspondence, memorandums, e-mails, trip reports, sampling plans, test results, submittals, waste disposal documents, photographs, and any other records or documents generated as a result of the project. All electronic deliverables shall be in a format compatible with USACE software: All text documents shall be furnished in either MS Word (.doc) or Adobe Acrobat (.pdf). Maps, graphics, and photographs generated for work plans and reports shall be provided in .pdf, .jpg, and GIS or Microstation formats.

4 PROJECT TASKS

Administratively, the work effort involved will be separated into various tasks. Initially, the following tasks shall be the basis for developing a cost, as well as cost tracking during project execution. The Contractor may be required to track costs on a more detailed subtask list for project control. The Bid Schedule is Attachment 2.

4.2 Bid Item 1- General Conditions

This work includes all of the items required by the SOW that is not explicitly covered under other bid items.

Examples of this are the Contractor’s cost for insurance, fees, permits, and other similar expenses directly related to the work; project-dedicated supervisory staff and equipment; meetings; compliance with specified regulatory requirements; pre-construction and construction period planning, project schedule updates, periodic submittals, reporting, and administration; Contractor quality control; field preparation and tasks not included under the other bid items; environmental protection and spill control; project photographs and videotaping; weather monitoring; weekly inspection during shutdown periods (if necessary); and installing and maintaining temporary facilities.

The Contractor is responsible for complying with all federal, state, and local safety and environmental regulations.

All hazardous wastes and contaminated material discovered or generated through the execution of this project will be disposed of in accordance with all applicable federal, state, and local laws and regulations.

No office facilities, electrical connections, water connections, or phone services will be provided by the government.

A suitable area will be provided to allow the Contractor to set up temporary trailers and to support equipment storage if required. Figure 4 shows suggested staging areas that are flat and gravel covered; however, the contractor may use other areas within the project work limits as approved by the COR.

Contractors entering the Great Plains Industrial Park will be required to check into the front gate upon arrival.

All subcontractors will follow the same procedure. The Contractor shall alert the front gate of any subcontractors who will be arriving at the facility to include waste haulers, equipment deliveries, etc. No badging of Contractors or subcontractors is required.

Building 1206 Entrance Building 1206 has one roll-up door located in the northwest corner of the building, and one roll-up door in the south wall that can be used to access the building and bring equipment into the building. There are two large roll-up doors in the north-northeast portion of the building, but they are inaccessible from the exterior of the building. See Figure 4A— Building Access.

A Stormwater Pollution Prevention Plan is required per Bid Item 2. The Notice of Intent (NOI) for Authorization to Discharge Stormwater Runoff from Construction Activities application will be obtained by the Contractor through the KDHE Bureau of Water.

Building Stability during Construction: To ensure the overall stability and structural integrity of the existing building during construction, the Contractor will be responsible for design of the temporary excavation shoring, sheeting and foundation underpinning as required to meet the safety and submittal requirements of EM 385-1-1. A Building Stabilization Plan is required per Bid Item 2, all labor associated with development of the work plan shall be included in Bid Item 2. The Engineer will provide periodic inspection of excavations and soil/groundwater conditions throughout construction. The Contractor shall be responsible for providing detailed pre-construction photographs to document the condition of the existing building, including surfaces finishes, cracks, or other structural blemishes that might be misconstrued as damage caused by earthwork operations. Labor associated with site visits, pre-construction documentation, and inspections by the Professional Engineer shall be included under General Conditions.

Dust Control: The Contractor shall control dust generated from excavation of contaminated soils and contaminated concrete. Dust control methods and procedures shall be outlined in the Excavation and Material Handling Plan required under Bid Item 2. The use of water for dust control should be avoided if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.

Pre and Post Construction Inspection and Videotape: Prior to the start of work and at the completion of work, the Contractor shall document the condition of the site and haul routes used to transport contaminated soil to offsite disposal facilities and import clean backfill material and equipment. This documentation shall consist of a written memorandum and high definition video of these features at a resolution of 1080P. Particular attention shall be given to documenting the condition of building 1206, the road leading into the site and other local roads used to transport material. No video documentation is required of State or Interstate highways.

Contractor Manpower Reporting: The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report contractor manpower information (including subcontractor manpower information) required for this contract. The contractor shall submit all the information required in the format specified at the following web address:

https://armycmra.dmdc.osd.mil/Login.aspx

The Contractors shall fill in the required information on the website, fields are shown below:

KO

COR

Contract number, including task and delivery order number Beginning and ending dates covered by reporting period Contractor name, address, phone number, e-mail address, identity of contractor employee entering data Estimated direct labor hours (including sub-contractors) Estimated direct labor dollars paid this reporting period (including sub-contractors) Total payments (including sub-contractors) Predominant Federal Service Code (FSC) reflecting services provided by contractor (and separate predominant

FSC for each sub-contractor if different) Estimated data collection cost Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the

Army Requiring Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information)

Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardization nomenclature provided on website)

Presence of deployment or contingency contract language

Number of contractor and sub-contractor employees deployed in theater this reporting period (by country)

As part of its submission, the Contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will not exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. If contract performance is completed before 30 September, the data can be entered upon contract completion rather than waiting for the end of the fiscal year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a contractor’s systems to the secure web site without the need for separate data entries for each required data element at the web site. The specific formats for the XML direct transfer may be downloaded from the web site.

Assumptions (Attachment 3):

Assume Level C personal protective equipment (PPE) will be required during all intrusive indoor work.

4.3 Bid Item 2 – Work Plans

Contractor Quality Control Plan (CQCP): The Contractor shall prepare a project-specific CQCP that will be submitted prior to any other deliverables. The purpose of the CQCP is to describe the quality control procedures that will be implemented to ensure field work is completed and documented in accordance with project objectives and applicable requirements and standards. This CQCP shall identify the key project elements, required end products, critical stages of product development, acceptability criteria, quality control check lists or forms to be used for each field work activity, corrective action processes, and a quality control organization with the names of individuals, qualifications of those individuals, responsibilities, and chains of authorities. The CQCP will describe internal quality control reporting procedures and those for quality control reporting to the Government. The CQCP shall include forms and checklists that shall be used to document quality control for all activities.

The plan shall include as a minimum:

The quality control organization.

Number and qualifications of personnel to be used for quality control.

Authority and responsibilities of quality control personnel.

Methods to be used for quality control including subcontractor's work.

Types of instructions to be scheduled and performed, including:

Preparatory Initial Follow-up

Test methods, including the specified test methods in the delivery order SOW, and if applicable, the name of qualified testing laboratory to be used.

Method of documenting and reporting quality control operations, inspections, and testing.

A copy of a letter of direction to the Contractor's representative responsible for quality control, outlining his duties and responsibilities, and signed by a responsible officer of the firm.

Identification of the Contractor’s Quality Control Manager. The QC Manager shall have completed the USACE

Construction Quality Management for Contractor’s course and provide proof of course certification.

Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors.

A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines.

The CQCP is to be delivered to the KO and COR within 60 calendar days after receiving the notice to proceed (NTP). In addition, three copies of a comprehensive written CQCP shall be submitted to the KO and COR within 5 working days when changes are made thereafter. After acceptance of the CQCP the Contractor must obtain the KO’s acceptance in writing of any proposed change to their QC system/plan.

Work Plan: The Contractor shall prepare a Soils Corrective Measures Implementation (CMI) work plan for Building 1206. The work plan consists of multiple documents which outline the Contractor’s strategy and requirements for performing the activities outlined in this SOW and provide the approach for collecting the necessary data. All draft work plan documents shall be submitted within 60 calendar days after NTP. The minimum work plan components are as follows:

1. Work Plan

Introduction/Purpose: Provide summary description of the project.

Project Management: Describe the construction management approach including levels of authority and responsibility and lines of communication. Include an organization chart.

Project Schedule: The Contractor shall prepare, submit, and update a critical path method project schedule for review at the Pre-Construction Conference and subsequent progress meetings. The project schedule shall be prepared using computer software that produces legible, easily updated critical path schedules. The critical path schedule shall be in the form of a bar chart with project title and a separate horizontal bar for each work activity or operation. The chronological order of the start of each major operation or segment of work shall determine the vertical location of its bar on the chart. Milestones marking the scheduled completion date for all critical tasks, including submission of the CMI Report, shall be included on the schedule.

Excavation and Material Handling Plan: Provide a detailed discussion of the excavation approach, technical methods, analytical analyses, screening criteria, and activity sequencing, including figures showing excavation, removal of the overhead steel pillars/overhead trolley system, embedded rail system, staging, temporary facility locations and flow of traffic, as well as methods for preventing the creation or spreading of dust and debris during activities. Provide the clean-up criteria to be used and a discussion of confirmation sampling requirements and analyses to be performed. Include a discussion on site restoration and requirements.

Storm Water Pollution Prevention Plan (SWPPP): The Contractor shall develop a SWPPP. The plan shall include proposed equipment, materials, and means and methods to prevent the spread of contamination by runoff of site water or materials.

Structural Safety Plan: During demolition, continuing inspections by a Competent Person (CP) shall detect hazards resulting from weakened or deteriorated floors, walls, or loosened material. No employee shall be permitted to work where such hazards exist until they are corrected by shoring, bracing, or other means. The frequency of inspections will be identified in the Structural Safety Plan.

The Contractor may remove the deteriorated wall. The wooden part of the wall and the brick above shall be removed to the steel rafters. The Contractor shall also remove the loose brick on each side of the opening to create a clean, clear opening. If ACM is identified it should be properly identified and disposed of. This opening will be inspected by USACE Construction Representatives. These plans should be proposed under the Structural Safety Plan with Professional Engineer’s certification. Costs for this should be included under Task 3.

Waste Handling and Management Plan: The Contractor shall develop a waste handling plan. The plan shall include proposed equipment and material, product data, sampling and testing requirements, means and methods to conduct handling and disposal of all wastes including, personal protective equipment, municipal waste, soil, and water.

Building Stabilization Plan and Floor Slab Removal and Restoration Plan: The Contractor shall develop a Building Stabilization Plan that proposes stabilization of the foundation and south wall. The Contractor shall develop a Floor Slab Removal and Restoration Plan for the cut portion of the floor and any foundation stabilization elements required to safely excavate the contaminated soils beneath Building 1206. The temporary excavation plans and calculations shall be stamped by a licensed Civil or Geotechnical Engineer with a minimum of five (5) years of related experience. The Contractor shall specify all quality control material testing requirements to be performed. The Contractor shall be responsible for repair of damage caused by construction operations to restore the structural condition of the building before construction. The Contractor shall deconstruct all temporary shoring, sheeting, and foundation underpinning. Repair drawings and calculations stamped by a licensed Civil or Geotechnical Engineer shall be submitted for approval.

2. UFP-QAPP

The QAPP shall be prepared in accordance with the UFP-QAPP (2012) information found at https://www.epa.gov/fedfac/assuring-quality-federal-cleanups. The UFP-QAPP shall describe procedures for field sampling; sample submittal for analysis; field chemical parameter measurement; data documentation; data assessment and reporting requirements. The Contractor shall state in the UFP-QAPP the methods intended for use to accomplish the chemical QC items to assure accurate, precise, representative, complete, legally defensible and comparable data. It will also describe all chemical parameter measurements for the soil matrices for the removal action. The Contractor shall propose laboratories that meet the requirements of Section 3.11.

A table shall be provided that identifies the number of samples, including any QC and quality assurance (QA) samples, extraction and analytical methods, screening criteria, precision, accuracy, representativeness, comparability, completeness, and sensitivity for analytical determinations. The UFP-QAPP will give a description with full detail for all personnel who will perform all onsite activities required for project Data Quality Objectives.

Contractor shall describe how analytical data and results will be evaluated, documented, and managed. Refer to Section 6.3 regarding Staged Electronic Data Delivery (SEDD) requirements.

3. Accident Prevention Plan

The Contractor shall prepare a site-specific APP based on EM 385-1-1 01.A.11 and Appendix A with appropriate Appendix A, Section 9 plans and attachments including a Site Safety and Health Plan (SSHP) (Section 28). The Contractor will be aware that their corporate safety and health standard operating procedures may not meet the site-specific requirements of EM 385-1-1, e.g., drilling safety (Section 18.H), fall protection (Section 21.C), , site-specific health plans (HAZWOPER, Section 33), excavation (Section 25.A) to name some of the common ones (and there are others). The Contractor is responsible for complying with the entirety of the EM 385-1-1 (e.g., Section 1 has general policy/plan requirements); and should have a qualified/competent person (See Appendix A) to develop, implement, and oversee the APP (the site health manager is a Certified Industrial Hygienist [CIH] per Section 33).

All work shall comply with 29 Code of Federal Regulations (CFR) 1910.120 and USACE Safety and Health Requirements Manual, EM 385-1-1 (November 2014 edition) to include errata and changes (See http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf).

The CIH shall assist in preparing, reviewing, and will approve the Accident Prevention Plan. The CIH shall verify Level C PPE is adequate to ensure worker safety during intrusive activities.

4.4 Bid Item 3 - Mobilization and Site Preparation

Mobilization: The Contractor shall be responsible for all labor, materials, and equipment necessary to transport to and from the site all personnel and equipment and setup and teardown of any temporary facilities. This also includes obtaining subsurface and/or overhead utility clearances required to start work. Demobilization costs are included under Bid Item 9.

All costs required to prepare Bldg. 1206 for excavation work and all staging areas shall be included in this Bid Item.

Staging areas for excavated soil and concrete shall be set up as needed to prevent the spread of contamination;

however, direct loading is allowed and encouraged. The Contractor is strongly encouraged to minimize the footprint of all staging areas to the maximum extent possible by direct loading or other means. Any staging area holding contaminated material shall be protected from cross contamination; if protection is not taken the Contractor shall be responsible for sampling the area to prove cross-contamination did not occur. The Contractor should assume clearing of five feet tall grass in any area proposed for soil stockpiling, etc.

It should be noted that in preparing the southeast wall for excavation Contractors may come into contact with ACM. It is the responsibility of the Contractor to properly identify, sample and dispose of the ACM, if present.

Sufficient erosion and sediment controls shall be installed to ensure that the nearby tributary is not impacted by soil or sediment originating from the site. All costs associated with establishing and maintaining site erosion controls shall be included in this task. Cover of non-contaminated soil or imported fill is not required. Cover of contaminated soil or concrete piles will be required. Covering with plastic is effective but labor intensive process, therefore the Contractor is encouraged to evaluate alternative solutions to using plastic to minimize stockpile management costs.

Work shall include all labor, materials, and equipment associated for establishing excavation material and equipment staging areas, installing sediment and runoff controls, installing temporary haulage roads if needed, and performing any required vegetation and debris removal required.

Remove overhead steel pillars/overhead trolley system (Figure 5), the material will be left on-site, the landowner will provide a nearby location within the 1200 Area

Remove embedded rail system, the material will be disposed off-site by the Contractor.

4.5 Bid Item 4– Floor Slab Removal

The Contractor shall remove the concrete slab and underlying gravel sub-base, as well as any curbs or trenches necessary to access the contaminated soil in accordance with the Floor Slab Removal and Restoration Plan submitted under Bid Item 2 – Work Plans. The concrete slab is documented in historical drawings to be 6 inches thick in most areas, however some variability should be anticipated based on placement of footings, interior slab supports, columns, and curbs or trenches. Refer to Table 4-4 in Att. 1c for approximate concrete thicknesses.

Rebar appears to be present in at least a portion of the concrete. Rebar should be assumed, at a minimum, in the concrete under and around the railroad lines and curbs. Tie-in dowels may be present at foundation columns.

As-built drawings of the Building 1206 foundation and floor plan are included in Attachment 1.

The Contractor shall define the extent of concrete and sub-base removal and propose methods for removing the concrete slab with minimal impact to the surrounding structure. Saw-cutting and hydraulic hammering are examples of acceptable methods for removal of the concrete slab. Concrete and sub-base may not be recycled for use on-site, disposal requirements and costs are included under Bid Item 6.

Remove concrete slab overlying the excavation area, approximately 3,100 square feet (Table 4) All excavated concrete and sub-base will be hauled off-site for disposal, approximately 120 bank cubic yards

4.6 Bid Item 5-Sub Slab Soil Removal

The soil exceedances for hexavalent chromium are shown on Figure 3. Figure 5 shows the estimated extent of contamination based on those soil exceedances. The estimated soil removal volume is shown in Table 4. The Contractor shall define the lateral and vertical excavation extent based on existing documentation (Attachment 1) and propose methods to remove all soil contamination in exceedance of 64 mg/kg. Attachment 1c contains the current draft version of the Pre-Design Investigation performed at Building 1206, additional information on the extent of contamination is presented in Figure 4-7, Figure 4-9, and the boring logs within Appendix B of the report.

The…