This is Amendment 0003 to Invitation for Bids (IFB) W912CH-26-B-A003, issued by the U.S. Army Corps of Engineers (USACE) on August 4, 2026, with an effective date of August 4, 2026. The amendment incorporates Section M.2 Contractor Responsibility and Eligibility for Award into the solicitation. All other terms and conditions of the IFB remain unchanged and in full force and effect.
The amendment modifies the evaluation and award criteria by adding comprehensive contractor responsibility requirements. Award will be made to the offeror submitting the lowest evaluated offer (price-only award basis) that meets all material requirements of the solicitation and satisfies FAR 9.104 responsibility criteria. The Government reserves the right to conduct preaward surveys and plant visits, request financial and technical background information, and determine an offeror non-responsible if requested data is not provided within 7 days or if the offeror refuses an onsite facility visit. The Government will evaluate bids based on unit prices for CLINs 0011 through 0016, calculate total price by summing all CLIN prices, assess price reasonableness, and evaluate for unbalanced pricing. Bidders must provide unit prices for all CLINs including First Article Testing (FAT) or risk bid rejection; no additional prices beyond those requested will be accepted. The solicitation includes sealed bidding procedures for award without discussions, equal low bid consideration per FAR 14.308, and single one-offer evaluation requirements per DFARS 252.215-7992.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification):
The purpose of Amendment 0003 to Invitation for Bids (IFB) W912CH-26-B-A003 is as follows:
1) To incorporate Section M.2. Contractor Responsibility and Eligibility for Award.
Please see the remaining pages of this amendment for additional details.
Note: Due to a contract-writing system error, Section J indicates that the attachments table has changed. However, no revisions have been made to this table. Bidders are instructed to disregard the Section J from/to changes identified herein.
All other terms and conditions of this IFB remain unchanged and in full force and effect.
Section J - List of Attachments
The attachments table has changed from:
Identifie r
Document Name
Document Description Reference Identifier
Date Line Item Page N umbers
Docum ent Type
Provide d Under Separat e Cover
A DD Form 1423
- Contract Data Requirements List
Contract Data Requirements List
(CDRL)
19 Dec
9000 6 Exhibit No
0001 Army Package 12986102
Technical Data Package (TDP) 16 Dec
Attach ment
No
0002 TACOM
OPSEC Plan (Provided at Award)
TACOM OPSEC Plan (Provided at Award)
01 Jul 2023 20 Attach ment
No
0003 Additional Guidelines for
CUI
Additional Guidelines for CUI 01 Aug
2 Attach ment
No
0004 First Article Waiver
First Article Waiver Worksheet 05 Mar 2014 3 Attach ment
No
W912CH26BA0030003
Worksheet
To:
Identifie r
Document Name
Document Description Reference Identifier
Date Line Item Page N umbers
Docum ent Type
Provide d Under Separat e Cover
A DD Form 1423
- Contract Data Requirements List
Contract Data Requirements List
(CDRL)
19 Dec
9000 6 Exhibit No
0001 Army Package 12986102
Technical Data Package (TDP) 16 Dec
Attach ment
No
0002 TACOM
OPSEC Plan (Provided at Award)
TACOM OPSEC Plan (Provided at Award)
01 Jul 2023 20 Attach ment
No
0003 Additional Guidelines for
CUI
Additional Guidelines for CUI 01 Aug
2 Attach ment
No
0004 First Article Waiver Worksheet
First Article Waiver Worksheet 05 Mar 2014 3 Attach ment
No
Section M - Evaluation Factors for Award
Miscellaneous text in this section has been modified to:
M.1. BASIS OF AWARD
(a) Overview. The Government will evaluate bids based on the unit prices identified in Section B for CLINs 0011 through 0016 and intends to award a single firm-fixed-price contract to the responsible Bidder with the lowest total price. The lowest total price will be determined as follows:
(1) CLIN Prices. The Government will verify the Bidder's CLIN prices by multiplying each year's proposed unit price by the estimated annual quantity. This is the first step in determining the lowest total price.
(2) Total Price. The Government will calculate the Bidder's total price by taking the sum of all its CLIN prices, as calculated in step 1. This is the final step in determining the lowest total price.
(3) If a Bidder fails to identify a unit price for all CLINs, including FAT, its bid may be rejected.
Further, the Government will not accept any additional prices identified in Section B or elsewhere in this IFB. If a Bidder submits additional prices, other than those requested, the bid may be rejected.
(b) Price Reasonableness. The Government will assess the reasonableness of the Bidder's proposed prices. A price is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business. The Government may make a determination of price reasonableness by any means allowable under RFO 15.404:
Cost and/or Price Analysis.
(c) Unbalanced Pricing. Unbalanced pricing exists when, despite an acceptable total price, the price of one or more contract line items or ranges is significantly over- or understated as determined by the application of cost and price analysis techniques. Offerors are cautioned that any bid determined to contain unbalanced pricing may be rejected or determined unacceptable for award. Please see RFO 15.404-6: Unbalanced Pricing for additional information.
(d) Award without Discussions. The Government will evaluate bids without discussions /negotiations and, therefore, the Bidder's initial bid shall contain its best terms. Further, the Government may reject any or all bids, accept other than the lowest bid, and/or waive informalities or minor irregularities in bids received. Please see RFO 52.214-10: Contract Award - Sealed Bidding for additional information.
(e) Equal Low Bids. A contract shall be awarded in the order of priority identified at RFO 14.308:
Award of Equal Low Bids when two or more low bids are equal in all respects. Therefore, the Bidder is required to complete and return the associated RFO 52.219-2: Equal Low Bids fill-in with its bid submission.
(f) Only One Bid. When only one bid is received, the requirements identified at RFO DFARS 252.215-7992: Only One Offer shall apply.
M.2. CONTRACTOR RESPONSIBILITY AND ELIGIBILITY FOR AWARD
(a) The Government will award a contract to the offeror that:
(1) submits the lowest evaluated offer if award is based on price only, or the offer that provides the best value to the Government if factors in addition to price are identified elsewhere in this solicitation,
(2) submits a bid or proposal that meets all the material requirements (including technical requirements of the specification, if applicable) of this solicitation, and
(3) meets all the responsibility criteria at FAR 9.104.
(b) To make sure that an offeror meets the responsibility criteria at FAR 9.104 the Government may:
(1) arrange a visit to the offeror's plant and perform a preaward survey;
(2) ask the offeror to provide financial, technical, production, or managerial background information.
(c) If the offeror does not provide the Government with the data requested within 7 days from the date the requested is received, or if the offeror refuses to have an onsite visit to the offeror's facility, the Government may determine the offeror to be non-responsible.
(d) If the Government visits the offeror's facility, please make sure that current certified financial statements and other data relevant to the bid or proposal available for Government personnel to review.
| IDCode: J |
| Page: 1 |
| Pages: 5 |
| AmendNo: 0003 |
| EffDate: 04 AUG 2026 |
| ReqNo: |
| ProjNo: |
| IssCode: W912CH |
| AdmCode: |
| IssuedBy: W6QK ACC- DTA |
KO DIRECTORATE OF CONTRACTING, 6501 EAST 11 MILE ROAD
WARREN, MI 48397-5000
UNITED STATES
STANLEY BIERNACKI, EMAIL: STANLEY.R.BIERNACKI.CIV@ARMY.MIL TELEPHONE: 571-588-9024 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912CH26BA003 |
| SolDate: 30 JUN 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: ELIZABETH LEVINE WELHOUSE |
| ContDate: |
| CODate: 04 AUG 2026 |
File details come from the government source that posted it. Updated .