AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

a. This amendment is issued for the follow ing:

(1) Provide response to questions submitted by contractor.

(2) Extend the solicitation closing date until 30 Aug 2018.

b. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912C318R0006

X 9B. DATED (SEE ITEM 11)

25-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Aug-2018

CODE

MICC - FT BUCHANAN

FT BUCHANAN

DIRECTORATE OF CONTRACTING

34 SOUTH GATE RD, STE 1104

FORT BUCHANAN PR 00934-4206

W912C3 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912C318R0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 24-Aug-2018 10:00 AM to 30-Aug-2018 10:00 AM.

(End of Summary of Changes)

The following items are applicable to this modification:

QUESTIONS AND ANSWERS

Solicitation #: W912C3-18-R-0006 Water Piping Replacement Phase

III

QUESTIONS AND ANSWERS:

1. Drawing Sheets 3, 4, 5, 6 do not show existing water piping lines, only valves, hydrants, and other items. Also, some components to not match with the master layout on sheet 2. Can drawings that show the water lines be provided?

Answer: Drawing of Existing Drawing Distribution was provided for references on Amendment 001 posted on FBO.gov on 10 Aug 2018. The information was obtained from a professional surveyor and military units.

2. Are other plans with existing utilities (other than water) available for review?

Answer: PDF versions drawings of existing utilities was provided on Amendment 001 posted on FBO.gov on 10 Aug 2018. The information was obtained from a professional surveyor and military units.

a. Cable TV

b. Street Lighting

c. Storm Sewer System

d. Electrical Distribution

e. Telephone System

f. Sanitary Sewer System

3. Drawing sheet 2 shows 2 existing water connections for what seems to be a parking lot with solar panels (Columbus Street). The new intended water distribution system on page 7 does not show any water connections to that area. Are water connections required for that area?

Answer: Yes, all existing facilities shall have water connections.

4. Drawing Sheet 7 of 10 does not indicate the size of the PRNG Building Connection.

Is the size of the connection available?

Answer: The size of the PRNG connection is not available. For concepts of the proposal estimate the contractor may consider an 8” connection.

5. Note 24 from drawing 9 of 10, establishes that: “Existing submersible pump, pipes and their accessories shall be removed while contractor install the new water pipes.

Contractor shall design and build new catch basin to collect water from surroundings.

Contractor shall install new submersible pump, electrical system, pipes and their accessories for a proper function.”

a. Please provide current pump specifications, past performance, and force line details. Also, please confirm that pump will be used to manage storm runoff.

Answer: Contractor shall consider to provide new submersible pump with same technical characteristics as the existing or similar. Contractor shall take into consideration the following:

1. Submersible pump of 3 inches diameters for discharge

2. Voltage: 230

3. Frequency: 60 Hz

4. Phase: Single

5. HP: A minimum of 3

The purpose of the pump is to mitigate the flooding issues in that particular area.

6. Section 1.8 Salvage Materials and Equipment requires the DB Contractor to provide a salvage plan, listing material and equipment to be salvaged, and their storage location.

It also establishes that: “The following Salvage Material has been identified by the government when pipe disconnections from existing lines are performed:

i. Mechanical Joint Elbows (long and short radius)

ii. Mechanical Joint Tee

iii. Mechanical Joint Curves (11.25 and 22.5 degrees)

iv. Mechanical Joint Coupled Joint Pip”

b. If the intent is to abandon existing lines, please clarify is this provision applies only to incidental encounters and/or possible connections. Please clarify the intent of this task or how is expected to be achieved.

Answer: This condition apply to either incidental encounters (pipes broken due to trench work) or point connections on Phase I and II but not limited to additional impacted areas. Contractor is responsible to establish a plan to achieve this task, however, the government will provide the approval/disapproval actions regarding the plan.

7. Please confirm that the valves shown on the distribution piping drawings are not the same as the isolation valves called on drawings General Notes #16 t at requires isolation valves within 10 Ft of the buildings.

Answer: Correct. All buildings/facilities shall have an isolation valve at a minimum distance of 10 feet away from the facility. The other valves corresponds to the main water distribution grid, fire hydrants, and fire suppression connections, among others.

8. On Solicitation page 52, Item 1.2.3.1.D it indicates that the government may provide non-potable water as needed. Will non-potable water be provided (from a source within the facility) for testing water piping and will the source of the water require that the water be loaded and transported by means of a water truck?

Answer: For pressure tests and housekeeping purposes, government will provide a non-potable located next to BLDG 161 (Water Spout). Contractor shall transport the non-potable water into a Water Truck Tank to the points where pressure tests will be conducted.

9. On solicitation page 71, Item 3.3.B.3 indicates that contractor shall consider use of well compacted excavated material over sand bedding and finish with top sol and sodding material.

a. Is there a specific requirement for top soil layer thickness and sodding type?

b. Please confirm that sand bedding is acceptable in lieu of gravel bedding.

c. Is there a minimum requirement for trenches depths or minimum top of conduit elevation?

d. Is there a minimum requirement for bedding coverage around the pipes?

Answer:

a. Designed of Record and contractors shall consider 2 inches of top soil.

Contractor shall consider the following sodding type: Zoysia

b. The sand bedding is acceptable.

c. The minimum requirement for trenches depths is 3.6 feet from bottom to ground surface. This will apply to pipes with diameters from 4 to 10 inches. However, the minimum requirement for trench depth regarding two inches is 2 feet.

d. The minimum requirement is 5 inches around the pipes.

10. On solicitation page 71, Item 3.3.E indicates that contractor shall leave abandoned in place existing piping that may contain asbestos and perform asbestos abatement only if incidental disturbance occurs and/or for water piping connections. Please confirm that the above- mentioned outlines the required scope.

Answer: Correct.

11. Please indicate if the contractor is required to perform asbestos and lead based paint testing to roads asphalt-concrete pavement (since it will be removed for piping trenches).

Answer: Contractor shall perform asbestos and lead based paint testing for all debris accumulated in designated and approved areas.

12. Please indicate if there are areas with soil contamination that may require testing for hazardous materials.

a. If there are areas with contaminated soils, please indicate where such conditions may exist or if the government will handle testing and disposal of any contaminated soils.

Answer: There are areas with potential of soil contamination in front of the buildings 539 and Wash Rack facility (across the street). Those areas has been identified by our Environmental Division already. The contractor is responsible to perform a test to determine whether hazardous or non-hazardous material. Also, is responsible to dispose the material in the approved landfill according to federal, state and local regulations.

13. As it relates to asphalt paving, please clarify the following:

a. Please indicate specific assumptions for asphalt paving thickness to be cut and removed- disposed.

b. Please indicate if there are specific requirements for the asphalt paving patching-repairs thickness.

c. Please indicate if unknown layers of concrete can be encountered and what shall be considered for cut, demo, disposal, etc. Is this work related cost under the CLIN Items 0010AA and 0010AB?

d. Shall the removed asphalt and concrete need to be disposed at a facility that recycles?

e. In order to comply with the Puerto Rico Department of Transportation Standards and Specifications for pavement please confirm that the Government will provide AADT (Annual Average Daily Traffic), expected design life and other parameters.

a. Please refers to section 3.3 (Civil Scope of Work), item A for additional information.

b. Contractor shall consider a new layer of asphalt with thickness of 2 inches.

c. Yes, there is a possibility to encounter concrete structures and slabs.

Contractor shall have past performance experience in how to conduct and perform saw cuts, demo, disposal, etc. The procedure established will depend on contractor analysis. The work description on CLIN 0010 is related to the cost provided in CLINS 0010AA and 0010AB for unforeseen conditions.

d. Due to lack of companies available and dedicate to recycling asphalt and concrete materials along the island, contractor shall considers to dispose those materials at municipal landfills.

e. This is a federal installation, so Puerto Rico Department of Transportation has no jurisdiction in here. No AADT is needed within Fort Buchanan boundaries.

14. On solicitation page 72, Item 3.4.2.b indicates that contractor shall provide pressure reducing valve stations. Without a design, this costly item would be difficult to estimate with accuracy. Please indicate if an allowance or a CLIN (unit price item) can be considered by the government for this item.

Answer: The government is anticipating the need of one pressure reducing valve stations however, it will depend on the design.

15. On solicitation page 72, Item 3.4.2.e indicates that contractor shall provide connection assemblies with isolation valves, by-pass valves, pressure regulators and backflow preventers (provisions that could be installed after a water meter). Also, all buildings shown on the solicitation plans have domestic water meters. On solicitation page 85, Item 1.2.7, it indicates that connections are to the existing water meters. Please clarify the intent of the connection requirements since the plans lead to indicate that the connections only would require an isolation valve within 10 Ft of the building or adjacent to the existing meters.

a. Can existing water meters be assumed to be functional and shall not be required to be replaced?

b. Page 204, Item 3.1.3.1 indicates that when there are no existing water meters, a new one shall be provided. Is a specification of the desired meters available and can it be provided?

c. Shall all the accessories indicated in the SOW need to be replaced / provided for all cases (existing and new meters)?

a. Contractors do not need to provide new water flow meters for facilities located within Phase III boundaries with the exception of the flow meters indicated at the Hotel Facilities.

b. Please refers to item a described above.

c. All the accessories indicated in the SOW shall be installed for all existing flow meters and the new flow meters in the hotel area.

16. Since the project is design-build, but the government has provided a set of drawings showing the intended scope.

a. Will water connections only be required for the buildings that show such connections on the bid plans?

Answer: Contractor shall confirm which existing facilities have domestic water, therefore, contractor is responsible to provide water connections for all facilities impacted within Phase III.

17. On solicitation page 73, Item 3.4.2.g indicates that contractor shall provide 6” fire hydrants, but the plans call for 4” water piping feeding the hydrants. Please clarify what size hydrants shall be considered as part of the unit cost.

Answer: The fire hydrants shall be 6 inches.

18. Please clarify that the Fire Suppression System connections are to be done onto the existing piping right before the entrance valve or PIV, and that the PIV shall not be replaced as part of the scope of the project.

Answer: Correct.

19. On solicitation page 74, Item 3.4.2.i indicates that contractor shall perform Fire Suppression Testing after piping connections are done. The codes and standards can be very broad, and each building Fire Suppression System can be different and be at different stages of its life cycle. Not having current status of the operational state of the systems makes this requirement difficult to assess.

a. If test are performed and they do not pass, what would be the contractor’s responsibility?

b. Please provide more specific requirements, or if the government will verify system operational status before and after the connections are performed.

a. Contractor is responsible to make the fire suppression connections. Contractor shall validate there is water running thru each system.

b. Contractor shall verify the operational status of each fire suppression before and after the connections are performed, but those validations must be coordinated in advance and in presence of the Fire Department and government.

20. On solicitation page 74, Item 3.4.2.j indicates that contractor shall consider a minimum 15 pressure gauge points. Drawings General Notes #4 indicates 6-10.

Please clarify the requirement.

Answer: Contractor shall consider a minimum 15 pressure gauge points. Revised drawings provided in Amendment 002.

21. On solicitation page 75, Item 3.4.2.r indicates that contractor shall provide a new submersible pump. Is a design criteria available for mechanical and electrical requirements?

1. Submersible pump of 3 inches diameters for discharge

2. Voltage: 230

3. Frequency: 60 Hz

4. Phase: Single

5. HP: A minimum of 3

22. On solicitation page 85, Item 1.2.6 indicates that contractor shall perform water connections after regular work hours. Please define the time that would be considered after regular work hours (after 4PM?).

Answer: From 4 pm to midnight. The mission of the building cannot be affected, therefore, the facility shall be ready to continue operations next working day without any interruption.

23. On solicitation page 86, Item 1.2.16 indicates that contractor shall backfill with selected material. Please indicate if there is a specific requirement related to the type of selected material (A-2-4, crush stone aggregate-Mogolla, etc.).

Answer: Contractor shall provide selective material (crush stone) on street crossings, while in grass areas, shall be using the same material excavated. However, if the existing material is saturated, the material will not be used for backfill. For this case, contractor shall provide selected backfill.

24. Please indicate if the vertical CLINS (unit priced items) require that air relief valve assemblies be considered / included.

Answer: Yes, however, in some cases, the air relief valves assemblies will depend on the design.

25. Please provide, if available, a sketch showing primary and secondary staging areas that would be available to the contractor.

Answer: Location is not available at this time. Coordination will be made after award.

26. Section 3.4.2.d of the Mechanical Scope requires the DB Contractor to provide "As Built" drawings indicating the specific location of the asbestos cement pipe abandoned in place. Please confirm if only the utilities found along the new trenches need to be identified in as-built plans since the rest (non-encountered) will be abandoned in place.

Answer: Correct. Only the asbestos cement pipes encountered within the trench path.

27. On Solicitation page 185, Section 3.27.1 and Plans General Notes #11 indicate that the contractor must submit an excavation permit (30 days in advance). Will one (1) Excavation Permit be required or multiple Excavation Permits be required based on project zones? If they are based on project zones, please provide a minimum number of excavation permits that must be submitted / procured?

Answer: The project does not require to divide the areas by zones. However, contractor shall considers to develop multiple excavations permits. The amount of excavations permits will depend on the propose working areas, but subject to government approval.

28. Please confirm that the project disturbance area exceeds 1.0 acre and if an

EPA General Construction Permit coverage will be required.

Answer: Correct, the area exceeds 1.0 acre and the EPA General Construction

Permit is required.

29. Permits and Construction Taxes: Please indicate if the project limits are in the Municipality of Guaynabo, the Municipality of Bayamón, or both. This is important to determine the payment of the required Construction Taxes (Patentes, Arbitrios)

Answer: The project limits are within Guaynabo and Bayamon Municipalities. Contractor shall determine the amount applicable of Permits and Construction Taxes for municipality.

30. Please confirm that Davis Bacon Wages or any prevailing wage determination does not apply to this project.

Answer: Davis Bacon Wages is not applicable.

31. Design Schedule: Sow Item 3.7 (Page 76) outlines design phases that amount to about 15 weeks (with design review periods). For the amount of design work (that includes extensive GPR, survey of existing conditions) required, please evaluate and confirm if more design time can be allocated / allowed.

Answer: The contractor must perform design and construction phases taking into consideration to not exceed the period performance, which is 540 days.

32. Proposal Due Date: Solicitation indicates that the proposal is due on August 24, 2018 (10:00 AM). Due to the complexity and extent of the scope, we hereby request that more time be provided. We suggest a few more weeks.

Answer: Government is contemplating an extension of the proposal due date until 30 Aug 2018.