TITLE SHEET, LOCATION SITE MAPS, ABBREVIATIONS AND INDEX OF DRAWINGS
T-1
FORT BUCHANAN, PUERTO RICO
REPLACE OLD ASBESTOS CEMENT
WATER PIPES-PHASE 3
A=945990.93
A=557178.16
ELEMENTARY SCH
NEW ANTILLES
A=34,796.45 SF
PRANG
A=945990.93
A=34,796.45 SF
PRANG
COURT NO. 2
x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x
STAND PIPE
VALVE
FIRE HYDRANT CAST IRON
ASBESTOS CEMENT
GALVANIZED IRON
WATER MAIN, SIZE
DUCTILE IRON
66" PRASA LINE
6" WATER PIPE
4" WATER PIPE
10" WATER PIPE
AND MATERIAL
16" WATER PIPE
LEGEND
EXISTING MAIN POTABLE WATER LAYOUT
EX-1
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
EXISTING CONDITION AREA 1
EX-2
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 3
EXISTING CONDITION AREA 2
EX-3
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 3
EXISTING CONDITION AREA 3
EX-4
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 3
EXISTING CONDITION AREA 4
EX-5
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 4
CROSSING OPEN CHANNEL DETAILS (XOC)
STEEL BEAM BRIDGE
HEAVY DUTY PIPE
SADDLE
CONCRETE
FOOTING
DUCTIL IRON PIPE
CONCRETE
PEDESTAL
DUCTIL IRON PIPE
TO MAIN PIPE
POLY VINYL
CHLORIDE PIPE
CREEK
WALL
45° DUCTIL IRON ELBOW
45° DUCTIL IRON ELBOW
N.T.S.
U BOLT WITH
NUTS & WASHES
45° FOOTING LOAD
DISTRIBUTION
FOR ANCHOR BOLTS SIZE
& LOCATION FOLLOW
MANUFACTURER
RECOMENDATIONS
STRESS
CONE
AIR RELEASE VALVE
EXISTING GRADE
GENERAL NOTES:
1. CONSTRUCTION PROJECT BOUNDARIES ARE LIMITED TO 25 FEET, EACH ,SIDE, OF THE TRENCH LINE.
2. ALL PIPE CONNECTIONS SHALL BE MECHANICAL JOINTS.
3. ALL CONCRETE STRUCTURES SHALL BE 3000 PSI AT 28 DAYS.
4. THE SAND BEDDING MATERIAL SHALL BE FREE OF STONE 0.25" OR GREATER.
5. THE REINFORCEMENT STEEL FOR ALL CONCRETE STRUCTURE SHALL BE "Fy = 60 KSI".
6. THE EXCAVATED MATERIAL AT THE ROAD SECTION SHALL BE DISPOSED OUT OF FORT BUCHANAN LIMITS, AND THE
USE OF CRUSHED STONE IS REQUIRED TO DO BACKFILL WORKS.
7. ALL PIPES SHALL BE PVC DR-14 UNLESS OTHERWISE INDICATED.
8. THE CONTRACTOR SHALL HAVE THE NECESSARY PRECAUTION TO NOT DISTURB THE ASBESTOS CEMENT PIPES TO
BE ABANDONED IN PLACE.
9. FOR EXISTING ASBESTOS CEMENT PIPES DIRECTLY AFFECTED BY THE INSTALLATION OF NEW PVC PIPES, CONTRACTOR SHALL REMOVE AND DISPOSE THE EXCESSIVE CONTAMINATED MATERIAL RESULTING FROM CUTS
AND TAPPING AT ITS OWN COST.
10. THE CONTRACTOR SHALL MAINTAIN THE VEHICULAR TRAFFIC FLOW DURING THIS PROJECT. IF IT IS NECESSARY, USE SAFETY BARRIERS, TRAFFIC SIGNS OR ANOTHER TRAFFIC EQUIPMENT TO ENSURE A VEHICULAR TRAFFIC
FLOW AT ALL TIME. CONTRACTOR SHALL COORDINATE WITH COR.
11. THE CONTRACTOR SHALL REQUEST AN EXCAVATION PERMIT BEFORE BEGIN THE EXCAVATION WORKS AT LEAST 30
DAYS IN ADVANCE. THIS EXCAVATION PERMIT HAVE THE APPROXIMATE LOCATION OF EXISTING UTILITIES.
12. THE CONTRACTOR SHALL BE ESPECIALLY CAREFUL AS NOT TO DAMAGE THE EXISTING UTILITIES INFRASTRUCTURE.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE DONE TO THE UNDERGROUND UTILITIES AND ANY
OTHER IN THE WORKING AREA.
13. THE CONTRACTOR SHALL CONSIDER THE USE OF UNDERGROUND DETECTOR DEVICE EQUIPMENT TO EXACTLY
LOCATE THE EXISTING UTILITY LINES.
14. CONTRACTOR SHALL PROVIDE NEW 0.75" DIAMETER COPPER PIPE CONNECTION, SERVICE SADDLE 4" X 0.75" &
FLARE CORP. 0.75" AND 0.75 '' NEW PRESSURE GAUGE LIQUID FILLED DEVICE WITH RANGE MEASUREMENT FROM 0
TO 100 psi AT 6 TO 10 BUILDINGS.
15. DOMESTIC CONNECTION FOR BUILDINGS SHALL BE REDUCED PROPERLY FROM 10 INCHES TO 4 INCHES PIPES AND
FROM 4 INCHES TO 2 INCHES PIPE. ALSO, A PROPER REDUCTION WILL BE NEEDED FROM 8 INCHES TO 6 INCHES PIPE.
16. ALL DOMESTIC CONNECTIONS NEED ISOLATION VALVES WITHIN 10 FT AWAY FROM THE FACILITY.
17. CONTRACTOR SHALL PROVIDE REQUIRED AIR RELEASE VALVES ACCORDING TO DESIGN. AT THE MINIMUM, DESIGN
MUST CONSIDER INSTALLATION OF AIR RELEASE VALVES AT HIGH POINTS.
18. CONTRACTOR SHALL PROVIDE THRUST BLOCK AT THE END POINT OF THE PIPING AND WERE PIPES CHANGE IN
DIRECTION.
19. CONTRACTOR SHALL IDENTIFY EXISTING UNDERGROUND UTILITIES LINES IMPACTING NEW WORK, NOT TO EXCEED
ONE WEEK AHEAD OF WORK SCHEDULE.
20. CONTRACTOR SHALL RESTORE THE SURFACE IMPACTED SUCH AS: GRASS, PAVEMENT, SIDEWALKS, AMONG
OTHERS IMMEDIATELY AFTER BACKFILL ACTIVITIES PROGRESS, BUT NOT LATER THAN 2 WEEKS.
21. FOR FIRE SUPPRESSION CONNECTIONS THE ISOLATION VALVE SHALL BE INSTALLED BEFORE THE EXISTING PIV.
22. CONTRACTOR SHALL CONSIDER INSTALL LIQUID PRESSURE GAUGES AT CROSSING OPEN CHANNELS AND BUILDING
INDICATED ON DRAWINGS.
23. WHEN DOMESTIC WATER CONNECTION ARE REQUIRED; CONTRACTOR SHALL PROVIDE AND INSTALL A BALL VALVE
AND UNIVERSAL UNION TO ISOLATE EXISTING OLD DOMESTIC PIPE FROM THE NEW PIPE CONNECTION.
PROPOSED POTABLE WATER SYSTEM (AREA 1)
SI-1
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
HEAVY DUTY PIPE
SADDLE
CONCRETE
FOOTING
DUCTIL IRON PIPE
CONCRETE
PEDESTAL
DUCTIL IRON PIPE
TO MAIN PIPE
POLY VINYL
CHLORIDE PIPE
CREEK
WALL
45° DUCTIL IRON ELBOW
45° DUCTIL IRON ELBOW
N.T.S.
U BOLT WITH
NUTS & WASHES
45° FOOTING LOAD
DISTRIBUTION
FOR ANCHOR BOLTS SIZE
& LOCATION FOLLOW
MANUFACTURER
RECOMENDATIONS
STRESS
CONE
AIR RELEASE VALVE
EXISTING GRADE
GENERAL NOTES:
1. CONSTRUCTION PROJECT BOUNDARIES ARE LIMITED TO 25 FEET, EACH ,SIDE, OF THE TRENCH LINE.
2. ALL PIPE CONNECTIONS SHALL BE MECHANICAL JOINTS.
3. ALL CONCRETE STRUCTURES SHALL BE 3000 PSI AT 28 DAYS.
4. THE SAND BEDDING MATERIAL SHALL BE FREE OF STONE 0.25" OR GREATER.
5. THE REINFORCEMENT STEEL FOR ALL CONCRETE STRUCTURE SHALL BE "Fy = 60 KSI".
6. THE EXCAVATED MATERIAL AT THE ROAD SECTION SHALL BE DISPOSED OUT OF FORT BUCHANAN LIMITS, AND THE
USE OF CRUSHED STONE IS REQUIRED TO DO BACKFILL WORKS.
7. ALL PIPES SHALL BE PVC DR-14 UNLESS OTHERWISE INDICATED.
8. THE CONTRACTOR SHALL HAVE THE NECESSARY PRECAUTION TO NOT DISTURB THE ASBESTOS CEMENT PIPES TO
BE ABANDONED IN PLACE.
9. FOR EXISTING ASBESTOS CEMENT PIPES DIRECTLY AFFECTED BY THE INSTALLATION OF NEW PVC PIPES, CONTRACTOR SHALL REMOVE AND DISPOSE THE EXCESSIVE CONTAMINATED MATERIAL RESULTING FROM CUTS
AND TAPPING AT ITS OWN COST.
10. THE CONTRACTOR SHALL MAINTAIN THE VEHICULAR TRAFFIC FLOW DURING THIS PROJECT. IF IT IS NECESSARY, USE SAFETY BARRIERS, TRAFFIC SIGNS OR ANOTHER TRAFFIC EQUIPMENT TO ENSURE A VEHICULAR TRAFFIC
FLOW AT ALL TIME. CONTRACTOR SHALL COORDINATE WITH COR.
11. THE CONTRACTOR SHALL REQUEST AN EXCAVATION PERMIT BEFORE BEGIN THE EXCAVATION WORKS AT LEAST 30
DAYS IN ADVANCE. THIS EXCAVATION PERMIT HAVE THE APPROXIMATE LOCATION OF EXISTING UTILITIES.
12. THE CONTRACTOR SHALL BE ESPECIALLY CAREFUL AS NOT TO DAMAGE THE EXISTING UTILITIES INFRASTRUCTURE.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE DONE TO THE UNDERGROUND UTILITIES AND ANY
OTHER IN THE WORKING AREA.
13. THE CONTRACTOR SHALL CONSIDER THE USE OF UNDERGROUND DETECTOR DEVICE EQUIPMENT TO EXACTLY
LOCATE THE EXISTING UTILITY LINES.
14. CONTRACTOR SHALL PROVIDE NEW 0.75" DIAMETER COPPER PIPE CONNECTION, SERVICE SADDLE 4" X 0.75" &
FLARE CORP. 0.75" AND 0.75 '' NEW PRESSURE GAUGE LIQUID FILLED DEVICE WITH RANGE MEASUREMENT FROM 0
TO 100 psi AT 6 TO 10 BUILDINGS.
15. DOMESTIC CONNECTION FOR BUILDINGS SHALL BE REDUCED PROPERLY FROM 10 INCHES TO 4 INCHES PIPES AND
FROM 4 INCHES TO 2 INCHES PIPE. ALSO, A PROPER REDUCTION WILL BE NEEDED FROM 8 INCHES TO 6 INCHES PIPE.
16. ALL DOMESTIC CONNECTIONS NEED ISOLATION VALVES WITHIN 10 FT AWAY FROM THE FACILITY.
17. CONTRACTOR SHALL PROVIDE REQUIRED AIR RELEASE VALVES ACCORDING TO DESIGN. AT THE MINIMUM, DESIGN
MUST CONSIDER INSTALLATION OF AIR RELEASE VALVES AT HIGH POINTS.
18. CONTRACTOR SHALL PROVIDE THRUST BLOCK AT THE END POINT OF THE PIPING AND WERE PIPES CHANGE IN
DIRECTION.
19. CONTRACTOR SHALL IDENTIFY EXISTING UNDERGROUND UTILITIES LINES IMPACTING NEW WORK, NOT TO EXCEED
ONE WEEK AHEAD OF WORK SCHEDULE.
20. CONTRACTOR SHALL RESTORE THE SURFACE IMPACTED SUCH AS: GRASS, PAVEMENT, SIDEWALKS, AMONG
OTHERS IMMEDIATELY AFTER BACKFILL ACTIVITIES PROGRESS, BUT NOT LATER THAN 2 WEEKS.
21. FOR FIRE SUPPRESSION CONNECTIONS THE ISOLATION VALVE SHALL BE INSTALLED BEFORE THE EXISTING PIV.
22. CONTRACTOR SHALL CONSIDER INSTALL LIQUID PRESSURE GAUGES AT CROSSING OPEN CHANNELS AND BUILDING
INDICATED ON DRAWINGS.
23. WHEN DOMESTIC WATER CONNECTION ARE REQUIRED; CONTRACTOR SHALL PROVIDE AND INSTALL A BALL VALVE
AND UNIVERSAL UNION TO ISOLATE EXISTING OLD DOMESTIC PIPE FROM THE NEW PIPE CONNECTION.
PROPOSED POTABLE WATER SYSTEM (AREA 2)
SI-2
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
DUCTIL IRON PIPE
TO MAIN PIPE
POLY VINYL
CHLORIDE PIPE
CROSSING OPEN CHANNEL DETAILS (XOC)
N.T.S.
GABION MATTRESS FOR
EMBANKMENT STABILITY
DUCTIL IRON PIPE
CHLORIDE PIPE
COMMISARY PARKING LOT PAVEMENT
AIR RELEASE VALVE
PROPOSED POTABLE WATER SYSTEM (AREA 3)
SI-3
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 3
GENERAL NOTES:
1. CONSTRUCTION PROJECT BOUNDARIES ARE LIMITED TO 25 FEET, EACH ,SIDE, OF THE TRENCH LINE.
2. ALL PIPE CONNECTIONS SHALL BE MECHANICAL JOINTS.
3. ALL CONCRETE STRUCTURES SHALL BE 3000 PSI AT 28 DAYS.
4. THE SAND BEDDING MATERIAL SHALL BE FREE OF STONE 0.25" OR GREATER.
5. THE REINFORCEMENT STEEL FOR ALL CONCRETE STRUCTURE SHALL BE "Fy = 60 KSI".
6. THE EXCAVATED MATERIAL AT THE ROAD SECTION SHALL BE DISPOSED OUT OF FORT BUCHANAN LIMITS, AND THE USE OF CRUSHED
STONE IS REQUIRED TO DO BACKFILL WORKS.
7. ALL PIPES SHALL BE PVC DR-14 UNLESS OTHERWISE INDICATED.
8. THE CONTRACTOR SHALL HAVE THE NECESSARY PRECAUTION TO NOT DISTURB THE ASBESTOS CEMENT PIPES TO BE ABANDONED IN
PLACE.
9. FOR EXISTING ASBESTOS CEMENT PIPES DIRECTLY AFFECTED BY THE INSTALLATION OF NEW PVC PIPES, CONTRACTOR SHALL
REMOVE AND DISPOSE THE EXCESSIVE CONTAMINATED MATERIAL RESULTING FROM CUTS AND TAPPING AT ITS OWN COST.
10. THE CONTRACTOR SHALL MAINTAIN THE VEHICULAR TRAFFIC FLOW DURING THIS PROJECT. IF IT IS NECESSARY, USE SAFETY
BARRIERS, TRAFFIC SIGNS OR ANOTHER TRAFFIC EQUIPMENT TO ENSURE A VEHICULAR TRAFFIC FLOW AT ALL TIME. CONTRACTOR
SHALL COORDINATE WITH COR.
11. THE CONTRACTOR SHALL REQUEST AN EXCAVATION PERMIT BEFORE BEGIN THE EXCAVATION WORKS AT LEAST 30 DAYS IN ADVANCE.
THIS EXCAVATION PERMIT HAVE THE APPROXIMATE LOCATION OF EXISTING UTILITIES.
12. THE CONTRACTOR SHALL BE ESPECIALLY CAREFUL AS NOT TO DAMAGE THE EXISTING UTILITIES INFRASTRUCTURE. THE CONTRACTOR
WILL BE RESPONSIBLE FOR ANY DAMAGE DONE TO THE UNDERGROUND UTILITIES AND ANY OTHER IN THE WORKING AREA.
13. THE CONTRACTOR SHALL CONSIDER THE USE OF UNDERGROUND DETECTOR DEVICE EQUIPMENT TO EXACTLY LOCATE THE EXISTING
UTILITY LINES.
14. CONTRACTOR SHALL PROVIDE NEW 0.75" DIAMETER COPPER PIPE CONNECTION, SERVICE SADDLE 4" X 0.75" & FLARE CORP. 0.75"
AND 0.75 '' NEW PRESSURE GAUGE LIQUID FILLED DEVICE WITH RANGE MEASUREMENT FROM 0 TO 100 psi AT 6 TO 10 BUILDINGS.
15. DOMESTIC CONNECTION FOR BUILDINGS SHALL BE REDUCED PROPERLY FROM 10 INCHES TO 4 INCHES PIPES AND FROM 4 INCHES TO 2
INCHES PIPE. ALSO, A PROPER REDUCTION WILL BE NEEDED FROM 8 INCHES TO 6 INCHES PIPE.
16. ALL DOMESTIC CONNECTIONS NEED ISOLATION VALVES WITHIN 10 FT AWAY FROM THE FACILITY.
17. CONTRACTOR SHALL PROVIDE REQUIRED AIR RELEASE VALVES ACCORDING TO DESIGN. AT THE MINIMUM, DESIGN MUST CONSIDER
INSTALLATION OF AIR RELEASE VALVES AT HIGH POINTS.
18. CONTRACTOR SHALL PROVIDE THRUST BLOCK AT THE END POINT OF THE PIPING AND WERE PIPES CHANGE IN DIRECTION.
19. CONTRACTOR SHALL IDENTIFY EXISTING UNDERGROUND UTILITIES LINES IMPACTING NEW WORK, NOT TO EXCEED ONE WEEK AHEAD
OF WORK SCHEDULE.
20. CONTRACTOR SHALL RESTORE THE SURFACE IMPACTED SUCH AS: GRASS, PAVEMENT, SIDEWALKS, AMONG OTHERS IMMEDIATELY
AFTER BACKFILL ACTIVITIES PROGRESS, BUT NOT LATER THAN 2 WEEKS.
21. FOR FIRE SUPPRESSION CONNECTIONS THE ISOLATION VALVE SHALL BE INSTALLED BEFORE THE EXISTING PIV.
22. CONTRACTOR SHALL CONSIDER INSTALL LIQUID PRESSURE GAUGES AT CROSSING OPEN CHANNELS AND BUILDING INDICATED ON
DRAWINGS.
23. WHEN DOMESTIC WATER CONNECTION ARE REQUIRED; CONTRACTOR SHALL PROVIDE AND INSTALL A BALL VALVE AND UNIVERSAL
UNION TO ISOLATE EXISTING OLD DOMESTIC PIPE FROM THE NEW PIPE CONNECTION.
24. EXISTING SUBMERSIBLE PUMP, PIPES AND THEIR ACCESSORIES SHALL BE REMOVED WHILE CONTRACTOR INSTALL THE NEW WATER
PIPES. CONTRACTOR SHALL DESIGN AND BUILD NEW CATCH BASIN TO COLLECT WATER FROM SURROUNDINGS. CONTRACTOR SHALL
INSTALL NEW SUBMERSIBLE PUMP, ELECTRICAL SYSTEM, PIPES AND THEIR ACCESSORIES FOR A PROPER FUNCTION.
HEAVY DUTY PIPE
SADDLE
CONCRETE
FOOTING
DUCTIL IRON PIPE
CONCRETE
PEDESTAL
DUCTIL IRON PIPE
TO MAIN PIPE
POLY VINYL
CHLORIDE PIPE
CREEK
WALL
45° DUCTIL IRON ELBOW
45° DUCTIL IRON ELBOW
N.T.S.
U BOLT WITH
NUTS & WASHES
45° FOOTING LOAD
DISTRIBUTION
FOR ANCHOR BOLTS SIZE
& LOCATION FOLLOW
MANUFACTURER
RECOMENDATIONS
STRESS
CONE
AIR RELEASE VALVE
EXISTING GRADE
PROPOSED POTABLE WATER SYSTEM (AREA 4)
SI-4
FORT BUCHANAN, PUERTO RICO
REPLACEMENT ASBESTOS CEMENT
WATER PIPES-PHASE 3
GENERAL NOTES:
1. CONSTRUCTION PROJECT BOUNDARIES ARE LIMITED TO 25 FEET, EACH ,SIDE, OF THE TRENCH LINE.
2. ALL PIPE CONNECTIONS SHALL BE MECHANICAL JOINTS.
3. ALL CONCRETE STRUCTURES SHALL BE 3000 PSI AT 28 DAYS.
4. THE SAND BEDDING MATERIAL SHALL BE FREE OF STONE 0.25" OR GREATER.
5. THE REINFORCEMENT STEEL FOR ALL CONCRETE STRUCTURE SHALL BE "Fy = 60 KSI".
6. THE EXCAVATED MATERIAL AT THE ROAD SECTION SHALL BE DISPOSED OUT OF FORT BUCHANAN LIMITS, AND
THE USE OF CRUSHED STONE IS REQUIRED TO DO BACKFILL WORKS.
7. ALL PIPES SHALL BE PVC DR-14 UNLESS OTHERWISE INDICATED.
8. THE CONTRACTOR SHALL HAVE THE NECESSARY PRECAUTION TO NOT DISTURB THE ASBESTOS CEMENT PIPES
TO BE ABANDONED IN PLACE.
9. FOR EXISTING ASBESTOS CEMENT PIPES DIRECTLY AFFECTED BY THE INSTALLATION OF NEW PVC PIPES, CONTRACTOR SHALL REMOVE AND DISPOSE THE EXCESSIVE CONTAMINATED MATERIAL RESULTING FROM CUTS
AND TAPPING AT ITS OWN COST.
10. THE CONTRACTOR SHALL MAINTAIN THE VEHICULAR TRAFFIC FLOW DURING THIS PROJECT. IF IT IS NECESSARY, USE SAFETY BARRIERS, TRAFFIC SIGNS OR ANOTHER TRAFFIC EQUIPMENT TO ENSURE A VEHICULAR TRAFFIC
FLOW AT ALL TIME. CONTRACTOR SHALL COORDINATE WITH COR.
11. THE CONTRACTOR SHALL REQUEST AN EXCAVATION PERMIT BEFORE BEGIN THE EXCAVATION WORKS AT LEAST
30 DAYS IN ADVANCE. THIS EXCAVATION PERMIT HAVE THE APPROXIMATE LOCATION OF EXISTING UTILITIES.
12. THE CONTRACTOR SHALL BE ESPECIALLY CAREFUL AS NOT TO DAMAGE THE EXISTING UTILITIES
INFRASTRUCTURE. THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE DONE TO THE UNDERGROUND
UTILITIES AND ANY OTHER IN THE WORKING AREA.
13. THE CONTRACTOR SHALL CONSIDER THE USE OF UNDERGROUND DETECTOR DEVICE EQUIPMENT TO EXACTLY
LOCATE THE EXISTING UTILITY LINES.
14. CONTRACTOR SHALL PROVIDE NEW 0.75" DIAMETER COPPER PIPE CONNECTION, SERVICE SADDLE 4" X 0.75" &
FLARE CORP. 0.75" AND 0.75 '' NEW PRESSURE GAUGE LIQUID FILLED DEVICE WITH RANGE MEASUREMENT FROM
0 TO 100 psi AT 6 TO 10 BUILDINGS.
15. DOMESTIC CONNECTION FOR BUILDINGS SHALL BE REDUCED PROPERLY FROM 10 INCHES TO 4 INCHES PIPES AND
FROM 4 INCHES TO 2 INCHES PIPE. ALSO, A PROPER REDUCTION WILL BE NEEDED FROM 8 INCHES TO 6 INCHES
PIPE.
16. ALL DOMESTIC CONNECTIONS NEED ISOLATION VALVES WITHIN 10 FT AWAY FROM THE FACILITY.
17. CONTRACTOR SHALL PROVIDE REQUIRED AIR RELEASE VALVES ACCORDING TO DESIGN. AT THE MINIMUM, DESIGN
MUST CONSIDER INSTALLATION OF AIR RELEASE VALVES AT HIGH POINTS.
18. CONTRACTOR SHALL PROVIDE THRUST BLOCK AT THE END POINT OF THE PIPING AND WERE PIPES CHANGE IN
DIRECTION.
19. CONTRACTOR SHALL IDENTIFY EXISTING UNDERGROUND UTILITIES LINES IMPACTING NEW WORK, NOT TO EXCEED
ONE WEEK AHEAD OF WORK SCHEDULE.
20. CONTRACTOR SHALL RESTORE THE SURFACE IMPACTED SUCH AS: GRASS, PAVEMENT, SIDEWALKS, AMONG
OTHERS IMMEDIATELY AFTER BACKFILL ACTIVITIES PROGRESS, BUT NOT LATER THAN 2 WEEKS.
21. FOR FIRE SUPPRESSION CONNECTIONS THE ISOLATION VALVE SHALL BE INSTALLED BEFORE THE EXISTING PIV.
22. CONTRACTOR SHALL CONSIDER INSTALL LIQUID PRESSURE GAUGES AT CROSSING OPEN CHANNELS AND
BUILDING INDICATED ON DRAWINGS.
23. WHEN DOMESTIC WATER CONNECTION ARE REQUIRED; CONTRACTOR SHALL PROVIDE AND INSTALL A BALL
VALVE AND UNIVERSAL UNION TO ISOLATE EXISTING OLD PIPE FROM THE NEW PIPE CONNECTION.
| Buchanan PH3 T-1 |
| Buchanan PH3 EX-1 |
| Buchanan PH3 EX-2 |
| Buchanan PH3 EX-3 |
| Buchanan PH3 EX-4 |
| Buchanan PH3 EX-5 |
| Buchanan PH3 SI-1 |
| Buchanan PH3 SI-2 |
| Buchanan PH3 SI-3 |
| Buchanan PH3 SI-4 |