This is a request for information from the U.S. Army Corps of Engineers regarding the rehabilitation of four turbine and generator units at the Robert S. Kerr Powerhouse in Oklahoma. The project requires refurbishing the existing turbine runners and rewinding the corresponding generators, including disassembly and replacement of internal components, and rehabilitation of other parts as specified. The goal of the RFI is to provide industry an opportunity to review the specifications and drawings, and provide feedback on existing and emerging technologies that could support the project related to turbine and generator rehabilitation. Responses are requested to assist in developing acquisition strategies and performance specifications, though no contract will be awarded based on responses. Proprietary information will be protected from unauthorized disclosure.

W912BV19R0042 RS Kerr Powerhouse Turbine and Generator Rehabilitation - Draft Solicitation and Specifications

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912BV19R0042

US Army Corps of Engineers Tulsa District Arkansas River Watershed Robert S. Kerr Lock & Dam 15, Oklahoma

Powerhouse Turbine/Generator Rehabilitation

Industry Review Specifications

June 12, 2019

RSL

FY19

PROJECT TABLE OF CONTENTS Page 1

TABLE OF CONTENTS

INDUSTRY REVIEW FOR SOLICITATION NO. W912BV19R0042

POWERHOUSE TURBINE/GENERATOR REHABILITATION

ROBERT S. KERR LOCK & DAM 15, OKLAHOMA

JUNE 12, 2019

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

00 22 11 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND

BASIS OF AWARD

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 GENERAL CONDITIONS

00 73 00 SUPPLEMENTARY CONDITIONS

00 73 46 WAGE DETERMINATION

DIVISION 01 – GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00.00 26 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 PROJECT SITE SECURITY

01 45 00 QUALITY CONTROL

01 46 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 83 13 LEAD REMEDIATION

DIVISION 03 - CONCRETE

03 31 26.10 28 SELF-CONSOLIDATING CONCRETE

03 50 00.00 26 DISCHARGE RING LINER CONCRETE WORK

03 60 00.00 26 CONCRETE DEMOLITION

DIVISION 05 - METALS

05 05 23.20 26 WELDING

05 05 33.20 26 NON-DESTRUCTIVE TESTING

05 14 00.13 26 WELDING STRUCTURAL ALUMINUM

05 50 03.20 26 METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS

PROVISIONS

05 50 14.00 26 TURBINE MAINTENANCE PLATFORM

PROJECT TABLE OF CONTENTS Page 2

TABLE OF CONTENTS

INDUSTRY REVIEW FOR SOLICITATION NO. W912BV19R0042

POWERHOUSE TURBINE/GENERATOR REHABILITATION

ROBERT S. KERR LOCK & DAM 15, OKLAHOMA

JUNE 12, 2019

DIVISION 09 - FINISHES

09 97 02.23 26 PAINTING: HYDRAULIC STRUCTURES

DIVISION 22 - PLUMBING

22 00 00.00 26 MECHANICAL EQUIPMENT AND PIPING

22 00 00.12 26 DELIVERY OF NEW TURBINE OIL

DIVISION 26 - ELECTRICAL

26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 19.00 26 INSULATED WIRE AND CABLE

DIVISION 48 - ELECTRICAL POWER GENERATION

48 06 15.12 26 NEW TURBINE OIL

48 13 13.00 26 HYDRAULIC TURBINE MODEL TESTING

48 13 13.01 26 HYDRAULIC TURBINE

48 13 13.02 26 DISASSEMBLY AND REASSEMBLY OF HYDRAULIC TURBINE-GENERATOR

UNITS

48 13 13.03 26 GENERATOR THRUST BEARING HIGH PRESSURE LIFT PUMP SYSTEM

48 13 13.04 26 EXISTING TURBINE COMPONENT, REFURBISHMENT AND REPLACEMENT

48 13 13.06 26 GENERATOR THRUST BEARING INSPECTION AND REFURBISHMENT

48 13 13.07 26 GUIDE BEARING INSPECTION & REFURBISHMENT

48 13 13.08 26 DISCHARGE RING PARTIAL REPLACEMENT AND GENERAL CAVITATION

AND CRACK REPAIR

48 13 13.10 26 FLUSHING AND CLEANING OF TURBINE OIL SYSTEM AND SEQUENCE

OF OIL-RELATED WORK

48 13 13.11 26 MISCELLANEOUS PARTS, MATERIALS, AND SERVICES

48 13 13.24 26 GENERATOR BRAKE SYSTEM REFURBISHMENT

48 13 16.00 26 REWIND OF HYDRAULIC-TURBINE DRIVEN GENERATORS

48 13 16.02 26 MACHINE CONDITION MONITORING OF HYDRAULIC TURBINE

GENERATOR UNIT

48 13 16.20 26 ROTOR SPIDER ANALYSIS AND REFURBISHMENT

48 70 01.00 26 NERC COMPLIANCE FOR HYDROGENERATORS

-- End of Project Table of Contents --

ROBERT S. KERR POWERHOUSE TURBINE AND GENERATOR REHABILITATION

This is a competitive solicitation for the rehabilitation of Turbine Generating Units 1 through 4 at Robert S. Kerr Pow erhouse, to include the rehabilitation of the existing runner and the rew ind of its correspnding generator. The contracting off icer intends to aw ard a f irm-fixed price contract under the best value continuum using the tradeoff process in accordance w ith FAR 15.101-1 to the responsible offeror w hose proposal the source selection authority determines conforms to teh solicitation, is fair and reasonable, and offers the best overall value to the Government, considering non-price factors described in the solicitation, and price.

This acquisition iis solicited as an UNRESTRICTED procurement.

The NAICS code for this project is 237990, Other Heavy and Civil Engineering Construction. The size standard is $36.5M.

In accordance w ith DFARS 236.204, the construction cost magnitude for this project is $100,000,000 to $125,000,000.

JULIE S HILL 918.669.7699

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

20-Jun-2019

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________2100 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

W912BV

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

918-669-7436FAX:TEL: TEL: FAX:

W912BV19R0042 59

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

PROPOSAL SCHEDULE

SOLICITATION NO. W912BV19R0042

KERR POWERHOUSE GENERATOR/TURBINE REHABILITATION

3/27/2019 Item No. Description Est. Qty. UOM Unit Price Amount

0001-0049 SITE WORK AND STRUCTURAL

Disassemble Hydraulic Turbine/Generator Unit and Inspect Components 4 EA $ $

Reassemble Generating Unit with New Runner and Components. 4 EA $ $

Design and Furnish Center Hole Jacking System 1 Job $ $

Operational Testing After Reassembly of Generating Unit 4 EA $ $

0005 Painting 4 EA $ $

On-site Lead Based Paint Removal and Disposal 4 EA $ $

Furnish New Draft Tube Platform 2 EA $ $

Disposal of Turbine Lubrication Oil First 6,000 Gallons

6,000 Gal $ $

Disposal of Turbine Lubrication Oil Over 6,000 Gallons (Optional)

2,000 Gal $ $

Flushing and Cleaning of Governor and Turbine Oil Systems

4 EA $ $

Supply New Turbine Lubrication Oil

6,000 Gal $ $

Supply Additional Turbine Lubrication Oil (Optional)

2,000 Gal $ $

0100-0199 MECHANICAL WORK

Design, Manufacture, Test and Deliver 49,300 hp Kaplan Runner Assembly Prototype

1 EA $ $

0101 Perform Basic Model Test 1 Job $ $

0102 Furnish Turbine Model 1 Job $ $

Manufacture, Test and Deliver 49,300 hp Kaplan Runner Assembly Remaining 3

3 EA $ $

Clean, Inspect, and Ship Main Shaft to Contractor's Shop

4 EA $ $

Machine Main Shaft, Oil Slinger, and Turbine Shaft Sleeve 4 EA $ $

Inspect, Ship, and Refurbish Upper Generator Guide Bearing Pads 4 EA $ $

0107 Inspect and Refurbish Lower Generator Guide Bearing Pads 4 EA $ $

Inspect Turbine Guide Bearing Housing (Inner Head Cover)

4 EA $ $

Inspect , Ship, and Refurbish Turbine Guide Bearing 4 EA $ $

Inspect, Ship, and Refurbish Spare Upper Generator Guide Bearing Pads 4 EA $ $

Inspect, Ship, and Refurbish Spare Lower Generator Guide Bearing Pads 4 EA $ $

Inspect, Ship, and Refurbish Spare Turbine Guide Bearing 4 EA $ $

Generator Thrust Bearing Phase 1 Inspection 4 EA $ $

0114 Generator Thrust Bearing Phase 2 Inspection (Optional) 4 EA $ $

Inspect, Ship, and Refurbishment of Thrust Bearing Shoes 4 EA $ $

Furnish One New Set of Thrust Bearing Shoes 1 Job $ $

0117 Inspect Generator Shaft 4 Job $ $

Ship Generator Shaft and Thrust Bearing Runner to Contractor's Shop (Optional) 4 Job $ $

Resurface Thrust Bearing Collar (Optional) 4 Job $ $

Resurface Thrust Bearing Runner on Generator Shaft (Optional) 4 Job $ $

Refurbishment of Thrust Bearing Runner (Optional) 1 EA $ $

Inspect and Refurbish Air Valve Assembly 4 EA $ $

Refurbish Wicket Gate Servomotors 8 EA $ $

Chrome Plate Gate Servo Piston Rod (Optional) 8 EA $ $

Furnish New Wicket Gates (Set) 4 EA $ $

Wicket Gate Operating Mechanism Refurbishment 4 EA $ $

Furnish Spare Set of Shear Pins, Spare Set of Wicket Gate Stem Packing, Spare Set of Wicket Gate Packing 1 Job $ $

0128 Stay Ring Inspection 4 EA $ $

Machine Outer Headcover Flange in Shop (Optional) 4 EA $ $

Furnish New Headcover Facing Plates (Optional) 4 Set $ $

Machining of Headcover Facing Plates 4 EA $ $

Machining of Stay Ring Mounting Flange and Surfaces

4 EA $ $

Inner Headcover Inspection and Refurbishment 4 EA $ $

Provide New Bottom Ring Facing Plates 4 Sets $ $

Machining of Bottom Ring Facing Plates 4 EA $ $

Operating Ring Inspection and Refurbishment 4 EA $ $

Line Bore Wicket Gate Stem Bushing Housings 4 EA $ $

Provide New Packing Box, Gland and Lantern 4 EA $ $

0139 Furnish Shaft Sleeve 4 EA $ $

Furnish Mandrel and Clamps for Shaft Sleeve (Optional) 1 Job $ $

Provide and install Discharge Ring Liner 4 EA $ $

0142 Cavitation Spot Repair 200 Cubic Inches

Cubic Inches $ $

Inspect and Refurbish Oil Head, Units 2-4 3 Job $ $

Inspect and Refurbish Oil Head, Unit 1 1 Job $ $

Furnish New Oil Head Bushings 4 Job $ $

Replace Turbine Guide Bearing Oil System 4 Job $ $

0147 Replace Spiral Case Valve 4 EA $ $

Replace Raw Water Piping Appurtenances 4 Job $ $

Replace Headcover Drainage Pumps 4 EA $ $

Furnish New Spare Generator Air Coolers 1 Job $ $

Provide and Install New Thrust Bearing Oil System 4 EA $ $

Braking System Refurbishment 4 EA $ $

Brake Ring Refurbishment (Optional) 4 EA $ $

Replace Check and Gate Valves 4 EA $ $

Spider Strengthening Inspection and Analysis 4 EA $ $

Weld Strengthening of Rotor Spider Est.2,300

Cubic Inches $

Structural Plate Stiffeners for Spider stengthening Est. 12,000 Lbs. $ $

Turbine Oil Purification System 1 Job $ $

Design, Provide, and Install New Automatic/Manual Gate Lock 4 EA $ $

Refurbish Turbine Lower Guide Bearing Lubrication System 4 EA $ $

Replace Turbine Oil Transfer Pump and Motor 1 Job $ $

0200-0211 ELECTRICAL WORK

Furnish Complete Set Of Stator Coils Including Supplies and Accessories For A Complete New Winding Including Factory Testing

4 EA $ $

Furnish For Accelerated Life Test and Have Tested Prototype Coils Identical To Coils Supplied In Item 0200 1 Job $ $

Furnish For Thermal Cycle Test and Have Tested Prototype Coils Identical To Coils Supplied In Item 0200 1 Job $ $

Furnish Generator Spare Parts

1 Job $ $ 0204 Truing Collector Rings 4 EA $ $

(Option) Perform Minor Stator Iron Repair 800 HRS $ $

(Option) Furnish and Install New Stator Core 4 EA $ $

Install and Test New Stator Winding 4 EA $ $

Furnish and Install New Generator Terminal Box 4 EA $ $

0209 Perform Special Field Tests 1 Job $ $

Furnish and Install Complete New Machine Condition Monitoring System 4 EA $ $

Furnish and Install New Generator Heaters Per Unit 4 EA $ $

0300-0312 OPTIONAL LABOR

Miscellaneous Welding (Optional) 320 LBS $ $

0301 Machinist Hire (Optional) 320 HRS $ $

0302 Electrician Hire (Optional) 320 HRS $ $ 0303 Painter Hire (Optional) 200 HRS $ $

Other Skilled Craftsmen Hire (Optional) 320 HRS $ $

General Laborer Hire (Optional) 320 HRS $ $

Liquid Penetrant Method (Optional) 160 HRS $ $

Magnetic Particle Method (Optional) 160 HRS $ $

0308 Ultrasonic Method (Optional) 160 HRS $ $

Radiographic Method (Shop Only) (Optional) 30 HRS $ $

Thermal Spraying (Optional)

100 HRS $ $

Miscellaneous Parts and Materials (Optional) 1 Job NTE 200,000.00$

0312 Asbestos Coordination 4 EA $ $

BASE ITEMS

AS NEEDED ITEMS

ESTIMATED ITEM

NOT TO EXCEED

The Government may require the delivery of the item(s) identified in the Price Schedule as an "(Optional)" item. The quantities for these items may be increased or decreased or the item(s) may not be used at all, at the discretion of the Government. The unit price or amount of an optional item will remain unchanged whether the quantities are increased or decreased. The Government may exercise an option by written notice to the Contractor commencing from the date of contract award through the date the contract is closed, unless otherwise specified herein. If an optional item is exercised, the contract completion date will not be extended, however, with mutual agreement, the schedule of work may be modified. Where appropriate, the above may be supplemented by applicable provisions of Part 17, Subpart 17.2, "Options", and FAR 52.211-18 "Variation in Estimated Quantities" of the Federal Acquisition Regulations (FAR).

The quantity for Item's marked EST is estimated and may be increased or decreased at the discretion of the Government.

Items not identified in the Price Schedule as an "(Optional)" item are considered base items. Base items are those required for the refurbishment of the four (4) Kaplan type turbine generating unit.

The quantity for Item's marked NTE is the maximum allowed by the Government for that Item without modification to the contract.

W912BV19R0042

Section 00 21 16 - Instructions to Proposers

INSTRUCTIONS, CONDITIONS & NOT

INSTRUCTIONS, CONDITIONS & NOTICES TO OFFERORS

1.0 GENERAL REQUIREMENTS

1.1 Intent: This is a competitive solicitation for a firm, fixed-price Design-Bid-Build construction contract to be awarded using the Trade-Off, Best Value selection process. The intent of this solicitation is to issue a single Contract for the Turbine-Generator project located at the R.S. Kerr Power Plant. The contract is being awarded in support of the U.S. Army Corps of Engineers, Tulsa District (SWT) hydropower mission. The Government will evaluate the proposals in accordance with the criteria described herein, and award a firm fixed price contract to the responsible offeror, whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government.

Interested firms or joint venture entities (referred to as “offerors” or “proposers”) submit specified performance capability proposals, demonstrating their capability to successfully execute the design-bid-build construction contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described in Section 00 22 11, PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND BASIS OF AWARD to choose the best value proposal for award.

1.2 Project Description: The requirements of this contract are to provide all equipment, labor, materials, and work required to refurbish Robert S. Kerr turbine generating Units 1 through 4 at the R.S Kerr Power Plant located in Sallisaw, Sequoyah County, Oklahoma. The existing turbines are five bladed Kaplan type units manufactured by Allis Chalmers. They were designed for a maximum output of 46,000 hp but have been operated at 35,000 hp to accommodate the existing generator nameplate of 28,947 KVA at a power factor of 0.95. The units have been generator limited over their life. The rehabilitation of each turbine generator unit shall include the rehabilitation of the existing runner and the rewind of its corresponding generator. This work will require the disassembly of the runner hub and replacement and refurbishment of internal components, rewind of the generator, and replacement or rehabilitation of other components as required in the specifications. The Contractor shall also be required to rehabilitate Units 1 through 4 by replacement of the generator stator winding. The new stator winding shall be rated at 42,000 KVA at a power factor of 0.9 with a temperature rise limited to 75 degrees C above a 40 degree C ambient temperature. Replacements of Units 1 through 4 generator stator cores will be included as an option to be exercised on an as needed basis. The field winding will be inspected, tested, and cleaned. Specifically, the proposed plan of work involves the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following work in strict accordance with the detailed requirements of the contract.

1.3 Government Security Requirements: The offeror(s) must ensure that ALL mail sent to the Tulsa District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the item or it will be REJECTED by the US Army Corps of Engineers mail room facility.

1.4 Copies of Solicitation Documents and Amendments: Copies of the solicitation and amendments are available on the INTERNET ONLY. All solicitation documents will be posted to the Federal Business Opportunities (FBO) website at: http://www.fbo.gov.

Solicitation number: W912BV19R0042

It shall be the contractor’s responsibility to check the websites for any amendments. The offeror shall submit all requested information specified in this solicitation in the proposal. There will be no public opening of the proposals received as a result of this solicitation.

1.5 Offeror’s Questions and Comments: If an offeror believes that any element of the RFP is unclear or inconsistent, the offeror is encouraged to submit an inquiry to the Bidders Inquiry System identifying their concern.

Questions and/or comments relative to the document should be submitted via Bidders Inquiry at:

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=HomePagePublic. Instructions for registering in the ProjNet Bidder Inquiry system are available on the above web site.

The Bidder Inquiry Key for this project is: 5IZY45-QFCU2V.

Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

Note: All questions and/or comments should be entered in Bidder’s Inquiry no later than 14 calendar days prior to the proposal deadline, so they may be given consideration or action taken prior to receipt of offers.

1.6 Pre-Proposal Site Visit: The Government intends to hold a pre-proposal conference for this solicitation.

The date, location, and time will be announced by amendment to the solicitation. Once announced each offeror must submit in writing, via email, the firm’s name, address, point of contact, telephone number, email address and number of personnel planning to attend no later than 48 hours prior to the conference to:

POC: Jay Surman Email: Jay.V.Surman@usace.army.mil Telephone: (918) 669-7020

All interested offerors are urged to attend. During this conference, the requirements set forth in the solicitation will be reviewed and discussed, with part of the conference to include a question and answer period.

1.7 Requirements to Attend the Site Visit: Only registered persons will be permitted to attend the site visit. In addition to the below information, please also provide your name of firm, firm’s CAGE and/or DUNS number, and name and position title of primary point-of-contact and their telephone number and email address. Only two persons from each business entity will be permitted to attend.

U.S. Citizens: To register, U.S. citizens interested in attending the site visit must submit a Tulsa District (SWT) Security Access Form to the Point of Contract (POC), Contract Specialist Bruce Hayes, by email to bruce.e.hayes@usace.army.mil no later than two (2) days prior to the site visit. If submitting the form in less than two days, the person may not receive approval for participation. Notification of approval or denial will be provided prior to the date of the site visit. The form is available as a pdf attachment on www.fbo.gov with this solicitation and is titled as Pre-Proposal Site Visit Form.

Foreign Nationals (FNs): FNs wishing to attend the site visit shall submit a completed SWT FN Security Form and legible color copies of two of the following documents: Passport (unexpired or expired), Certificate of U.S.

Citizenship (INS Form N-560 04 N-561), Certificate of Naturalization (INS Form N 550 or N-570), unexpired foreign Passport with I-551 stamp or attached INS Form I-94 indicating unexpired employment authorization, an Alien Registration Receipt Card with photo (INS Form I-151 or I-551), unexpired Temporary Resident Card (INS Form I-688), unexpired Employment Authorization Card (INS Form I-688A), unexpired Reentry Permit (INS Form I-327), unexpired Refugee Travel Document (INS- Form I571), or unexpired Employment Authorization Documentation issued by the INS which contains a photograph (INS Form I-688B) to the SWT POC. These documents must be submitted two (2) weeks prior to the site visit. Exceptions will be considered on a case by case basis but will be limited. The form is available at:

http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx.

1.8 Accuracy in Proposals: Proposals must set forth full, accurate, and complete information as required by this RFP (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

2.0 PROPOSAL SUMITTALS AND FORMAT

2.1 Proposals shall be sent via the AMRDEC Safe website: https://safe.amrdec.army.mil/safe/ before the time and date specified in the solicitation (Standard Form 1442). Enter the following email addresses for recipients of the AMRDEC download:

Julie.S.Hill@usace.army.mil Brian.C.Hutchison@usace.army.mil

Should AMRDEC not be available, proposals may be submitted on CD/DVD and delivered (postal or delivery service) to:

USACE Tulsa District Attn: Julie S. (Shay) Hill, Contract Specialist:

Floor 09 2488 East 81st Street Tulsa OK 74137-4290

2.2 See Sections 00 22 11 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA.

3.0 ADDITIONAL INFORMATION

3.1 This is a competitive acquisition. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

3.2 Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

3.3 Debriefings. The Contracting Officer will promptly notify offerors of any decision to exclude them from competition if a competitive range is determined, whereupon they may request and receive a debriefing in accordance with FAR 15.505. The Contracting Officer will notify unsuccessful offerors of the source selection decision in accordance with FAR 15.506. Upon such notification, unsuccessful offerors may request and receive a debriefing. Offerors desiring debriefing must make their request in accordance with the requirements of FAR 15.505 or 15.506, as applicable. All debriefings will be provided officially in writing.

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm-fixed price contract resulting from this solicitation.

(End of provision)

52.223-22 PUBLIC DISCLOSURE OF GREENHOUSE GAS EMISSIONS AND REDUCTION GOALS--

REPRESENTATION (DEC 2016)

(a) This representation shall be completed if the Offeror received $7.5 million or more in Federal contract awards in the prior Federal fiscal year. The representation is optional if the Offeror received less than $7.5 million in Federal contract awards in the prior Federal fiscal year.

(b) Representation. [Offeror is to check applicable blocks in paragraphs (b)(1) and (2).]

(1) The Offeror (itself or through its immediate owner or highest-level owner) [ ___ ] does, [ ___ ] does not publicly disclose greenhouse gas emissions, i.e., make available on a publicly accessible Web site the results of a greenhouse gas inventory, performed in accordance with an accounting standard with publicly available and consistently applied criteria, such as the Greenhouse Gas Protocol Corporate Standard.

(2) The Offeror (itself or through its immediate owner or highest-level owner) [ ___ ] does, [ ___ ] does not publicly disclose a quantitative greenhouse gas emissions reduction goal, i.e., make available on a publicly available Web site a target to reduce absolute emissions or emissions intensity by a specific quantity or percentage.

(3) A publicly accessible Web site includes the Offeror's own Web site or a recognized, third-party greenhouse gas emissions reporting program.

(c) If the Offeror checked ``does'' in paragraphs (b)(1) or (b)(2) of this provision, respectively, the Offeror shall provide the publicly accessible Web site(s) where greenhouse gas emissions and/or reduction goals are reported:

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Contracting Officer, CECT-SWT-E, 2488 E. 81st Street, Tulsa OK 74137,

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.acq.osd.mil/dpap/dars/dfarspgi/current/

Section 00 22 16 - Supplementary Instructions to Proposers

PROPOSAL SUBMISSION REQUIRMENT

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND BASIS OF AWARD

1.0 OVERVIEW

1.1 This is an unrestricted competitive solicitation for a firm, fixed-price Design-Bid-Build construction contract to be awarded using the Trade-Off, Best Value selection process. This Request for Proposal (RFP) is to refurbish Robert S. Kerr turbine generating Units 1 through 4 at the R.S Kerr Power Plant located in Sallisaw, Sequoyah County, Oklahoma. The solicitation criteria shall rely upon industry standards, as much as possible and firms must meet all project requirements.

1.2 Offerors will submit proposals including technical, non-technical, and a price proposal. The Government will evaluate initial proposals in accordance with the criteria described in this Section. Award of a firm fixed-price contract will be made to the responsible offeror whose proposal conforms with all the terms and conditions of the solicitation and represents the overall best value to the Government, considering the evaluation factors, below. The final evaluation rating used for comparison, selection, and award will reflect the ratings received during proposal evaluation. Cost and price information will not be rated but will be evaluated in accordance with FAR Part 15.4.

When combined, all non-price factors are considered significantly more important than price.

1.2.1 The proposal must describe the capability of the offeror to perform the work and understanding of the requirements contained in the Statement of Work, and set forth full, accurate, and complete information required by the RFP. The proposal should be prepared simply and economically and be legible, clear and coherent.

1.2.2 This is not a sealed bid procurement process. Issuance of this Request for Proposal does not constitute an award commitment on the part of the Government. Contract award is subject to funds availability.

1.2.3 Proposal Submissions and the Trade-Off Process. This process permits tradeoffs among price and non-price factors and allows the Government to accept other than the lowest priced proposal. Proposals must demonstrate performance and capability information for review and consideration by the Government. Relative weights among past performance and technical factors are provided, below. The Source Selection Evaluation Board (SSEB) reviews, evaluates, and rates the proposals against the source selection criteria in the RFP. If discussions are held, a competitive range consisting of the most highly qualified firms will be established, first. Concurrently, the Government analyzes price proposals. Price will not be rated, but will be a factor in making the final best value determination for award.

2.0 GENERAL INSTRUCTIONS

2.1 Who May Submit: Any legally organized business firm formally organized as entities, construction contractors that have associated specifically for this project, consortia of small business firms or any other interested parties may submit proposals. Associations may be as joint ventures or as key team subcontractors.

2.2 Specific instructions for Joint Ventures (JV) and Partnerships.

2.2.1 JV or Partnerships shall be registered in the System for Acquisition Management (www.SAM.gov) as a JV or Partnership.

2.2.2 JV or Partnerships shall provide a copy of the Joint Venture or Partnership Agreement.

2.2.3 JV or Partnerships shall provide a detailed statement outlining the following in terms of percentages, where appropriate:

2.2.3.1 The relationship of the JV or partnership parties in terms of business ownership, capital contribution, and profit sharing.

2.2.3.2 The management approach of the JV or partnership in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the JV or partnership and perform the duties necessary to complete the work.

2.2.3.3 The structure of the JV or partnership and decision-making responsibilities of the JV or partnership parties in terms of who will control the manner and method of performance of the work.

2.2.3.4 The bonding responsibilities of the JV or partnership parties.

2.2.3.5 Identification of key personnel having authority to legally bind the JV or partnership to subcontracts and state who will provide or contract for the labor and materials for the JV or partnership.

2.2.3.6 Identification of party maintaining the JV or partnership bank accounts for the payment of all expenses and deposits of all receipts, keep the books and records, and pay applicable taxes for the JV or partnership.

2.2.3.7 Identification of party furnishing the facilities, such as office supplies and telephone service.

2.2.3.8 Identification of party having overall control of the JV or partnership.

2.2.4 JV or partnerships shall identify in other sections of the proposal, where appropriate, whether key personnel are employees of the individual JV or partnership parties (and identify the party) or hired as employees of the JV or partnership.

2.2.5 If one of the JV or partnership parties possesses experience and/or past performance as a Federal Government contractor or as a Corps of Engineers contractor, that experience and/or past performance will be included as the experience and/or past performance of the JV or partnership.

2.3 Where to Submit: Submit proposals to USACE Tulsa District as instructed in Section 00 21 00

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS.

2.4 Submission Deadline. Proposals shall be received by the Tulsa District no later than the time and date specified in Block 10 of Standard Form 1442 or as amended in a Standard Form 30.

2.5 General Submission Requirements

2.5.1 Page Limitations. Proposals are limited to the number of pages shown below.

VOLUME I

Factor/Subfactor Description Page Limit

Factor 1 Turbine and Generator Company Experience 30 pages

Factor 2 Past Performance 5 pages*

Factor 3 Turbine Replacement 31 pages

Subfactor 1 Turbine Efficiency 5 pages

Subfactor 2 Technical Approach 20 pages**

Subfactor 3 Cavitation Requirements 1 page

Subfactor 4 Stator Winding Losses, Manufacturing & Installation 5 pages

Subfactor 5 Schedule N/A

Factor 4 Small Business Participation Plan N/A

VOLUME II

Factor 5 Price and Pro Forma N/A

Proposal Cover Sheet

Signed Cover Letter

Price Proposal - section 00 11 00

Bid Guarantee

JV Agreement (if applicable)

Financial Capability & Pre-Award Information

Small Business Subcontracting Plan (if applicable)

*excluding PPQs **including drawings

2.5.2 The proposal shall contain a detailed table of contents for each volume organized as shown in paragraph

3.0. A cover sheet identifying the firm(s) (name, address, point of contact), project description, and solicitation number shall be provided with each volume, followed by a table of contents. Improper proposal formats will unnecessarily delay the evaluation process and may be rejected after the initial evaluation without receiving any further consideration. The Government will not evaluate any information beyond the page limitations noted.

2.5.3 In order to effectively and equitably evaluate all proposals, proposals must include sufficient detail to allow review by the Government. Proposal clarity, organization, and cross-referencing are mandatory. Failures to submit and organize proposals as requested may adversely affect a proposal's evaluation. Provide sufficient detail and clearly define all items required in this section.

2.5.4 The Contracting Officer may remove any proposal from further consideration during any phase of the procurement if the proposal fails to meet the submittal requirements of the RFP, or to reduce the competitive range for purposes of efficiency pursuant to FAR 15.306(c)(2).

2.6 Proposal Submissions

2.6.1 Proposals shall be submitted in electronic format and contain the information in original PDF files that are accurately bookmarked. Electronic proposals shall be submitted via AMRDEC Safe Download (https://safe.amrdec.army.mil/safe/), see Section 00 21 00. Proposals shall be labeled in a manner to afford easy identification from a Table of Contents. Font size shall not be less than 10 point. Do not use condensed font. Each page shall be sequentially and consecutively identified with the appropriate page number centered at the bottom of each page. The Government will not review any information submitted in an appendix or attachment to the proposal.

Do not submit verbatim sections of this solicitation as part of the proposal. Proposals that do not meet these requirements may be subject to rejection.

2.6.2 Electronic Format: The offeror shall provide the complete proposal via AMRDEC Safe Download. The electronic files for each volume shall contain the respective portion of the proposal in PDF format using Adobe Acrobat software; do not scan the documents into a PDF file except the bid bond may be scanned. The text portion of each volume of the proposal shall be contained as a single PDF file. Sections of the proposal shall be linked to the index in logical order through use of bookmarks.

2.6.3 Number of Copies: Submit one copy of all electronic files via AMRDEC Safe Download, see Section 00 21 00.

2.6.4 Proposal revisions, if requested, shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision, e.g., Error, Omission, Clarification, or amendment shall be included and be annotated for each revision. Proposal replacement pages shall be numbered, shall be clearly marked “REVISED” show the date of revision.

3.0 PROPOSAL AND RELATED EVALUATION FACTORS

VOLUME I

Factor/Subfactor Location Description Relative Importance

Factor 1 Tab A Turbine and Generator Company Experience Most Important Factor

Factor 2 Tab B Past Performance 2nd Most Important Factor

Factor 3 Tab C Turbine Replacement 3rd Most Important Factor Subfactor 1 Tab C1 Turbine Efficiency Most Important Subfactor Subfactor 2 Tab C2 Technical Approach 2nd Most Important Subfactor Subfactor 3 Tab C3 Cavitation Requirements 3rd Most Important Subfactor

Subfactor 4 Tab C4 Stator Winding Losses, Manufacturing & Installation 4th Most Important Subfactor

Subfactor 5 Tab C5 Schedule 5th Most Important Subfactor

Factor 4 Tab D Small Business Participation Plan 4th Most Important Factor

VOLUME II

Factor 5 Price and Pro Forma 5th Most Important Factor

Tab A Proposal Cover Sheet

Tab B Signed Cover Letter

Tab C Price Proposal - section 00 11 00

Tab D Bid Guarantee

Tab E JV Agreement (if applicable)

Tab F Financial Capability & Pre-Award Information

Tab G Small Business Subcontracting Plan (if applicable)

4.0 STANDARD FORM 1442 AND PROPSAL DATA SHEET

4.1 Submit the SF-1442, completed and signed by the firm’s authorized representative. Include the completed proposal data sheet (See Attachment 1, provided at the end of this Section).

5.0 VOLUME 1, FACTOR 1 – TURBINE AND GENERATOR COMPANY EXPERIENCE

5.1 Submission

5.1.1. Provide, in detail, the experience of your organization or proposed team in contracts of similar type and complexity, including a list (no greater than 5, but no less than three) of 280” or greater Kaplan turbine projects relevant to the proposed contract which your organization or proposed team has completed within the last 15 years, or which is currently under contract and more than 50% complete. Identify the experience that company design personnel have with Kaplan turbine design and evaluating hydro turbine design conditions similar to those found at R.S. Kerr Power Plant.

Provide, in detail, the experience of your organization or proposed team in contacts of similar type and complexity, including a list (no greater than 5, but no less than three) separate generator stator projects relevant to the proposed contract which your organization or proposed team has completed within the last ten (10) years, or which is currently under contract and more than 50% complete. Identify the experience that company design personnel have in addressing design conditions similar to those found at R.S. Kerr Power Plant.

Provide, in detail, the experience of your organization or proposed team in contacts of similar type and complexity, including a list (no greater than 5, but no less than three) stator winding and stator core replacement contracts held within the last five (5) years. The projects selected should represent work similar to that proposed, whereby they have designed, manufactured, installed and tested a complete winding and at least a portion of stator core for a large hydroelectric generator. Project examples should be completed (or are 50% complete at the time of this offer), have the same or similar insulation system as the proposed to be supplied under this solicitation, be of separate design and/or location (i.e., not three contracts in one powerhouse). Project examples shall identify the firms providing this experience and their relationship to the offeror during said project, e.g. prime contractor (same as offeror), subcontractor, material supplier, not associated with the offeror, etc.

5.1.2 Within the narrative of the Project Detail Sheet, the offerors shall identify themselves as regularly engaged in the design, manufacture, and installation of Kaplan turbine runners for hydroelectric generators of 30 – 60 MW within the past 15 years. The offerors shall identify themselves as regularly engaged in the design, manufacture, installation and repair of stator coils and stator core laminations for hydroelectric generators of 30-60 MVA for a period of time of 5 years or greater.

5.1.3 The projects selected should represent work similar to that proposed for the R.S. Kerr Power Plant. Project examples shall identify the firms providing this experience and their relationship to the offeror during said project, e.g. prime contractor (same as offeror), subcontractor, material supplier, not associated with the Offeror, etc.

5.1.4 For each identified project, fill in attached Project Detail Sheet, included as Attachment 1. The Offeror will present no more than 5 examples for turbine experience, no more than 5 examples for generator experience, and no more than 5 examples for stator winding and core replacement experience for this Factor.

5.2 Evaluation

The offeror will be evaluated on the recency, relevancy (type and size), and complexity of the projects submitted as compared to the requirements for the R.S. Kerr Power Plant. The offeror shall provide the Project Detail Sheet as required for the submission. The projects selected should represent work similar to that proposed for the R.S. Kerr Power Plant. Project examples shall identify the firms providing this experience and their relationship to the offeror during said project, e.g. prime contractor (same as offeror), subcontractor, material supplier, not associated with the offeror, etc. A proposal demonstrating extensive detailed experience for the organization and/or proposed team in contracts of similar type, complexity, and size relevant to the requirements of the solicitation will be evaluated more favorably.

6.0 VOLUME 1, FACTOR 2 – PAST PERFORMANCE

6.1 Submission

The offerors shall address past performance for ALL projects submitted for Factor 1. The offeror may also include a narrative addressing past performance. As a minimum, the offeror shall provide questionnaires for the past performance of projects for which there is no CPARS rating available. The offeror will provide a “Past Performance Evaluation Questionnaire” to the point of contact and/or the person that represents the client’s opinion of the offeror’s past performance for each of the three projects listed. Submit all Past Performance Questionnaires on Form PPQ-0 (“PPQ”), a copy of which is included at the end of this section. USACE requests the offeror’s client complete and sign the PPQ before submitting directly back to the offeror. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s) with the statement PPQ NOT RETURNED at the top of the first page of the PPQ.

Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. All questionnaires are due by the proposal due date. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, identified in Section 00 21 00. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. PPQs should be resubmitted. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror. The Government may not contact all of the identified client references / points of contact. This assessment is based on the offeror’s record of relevant and recent past performance information that pertains to the construction services outlined in the solicitation requirements. If the firm is divided into severable segments (e.g., division, group, or unit) the Government will evaluate only the past performance of those segments of the firm(s) that will actually perform the work.

Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance and assigned a performance confidence rating of “neutral.”

6.2 Evaluation

6.2.1. Government will view past performance information on projects similar in nature, size, scope, complexity and dollar value as relevant past performance. Government will evaluate the actual performance ratings determining how well the contractor did work associated with the past performance reports on previous or current projects.

Should there be no relevant past performance ratings, the Government will give a rating of not relevant.

6.2.2 Government will evaluate responses from customers in example projects identified by the offeror and from Past Performance Evaluation Questionnaires received or extrapolated from other available Government sources and Civil Sources if available.

6.2.3 Government will make an assessment of the offeror’s past performance in providing services or construction consistent with the scope and complexity of the Government’s requirement. While the Government will consider past performance information from other sources, the burden of demonstrating satisfactory past performance rests with the offeror. The Government will use past performance information provided in the offeror’s proposal and information obtained from other sources including but not limited to those sources identified in Section 00 22 11 of the solicitation. Should the Government have personal information relative to interaction with the contractor on relevant projects, this past performance information will be acceptable for evaluation if properly document by memorandum for record or PPQ.

6.2.4 Any significant achievement, problem, or lack of relevant data in any element of the work can become an important consideration in the source selection process. Offerors are encouraged to include all relevant past efforts, including demonstrated corrective actions in their proposal.