Spec_Amendment.pdf

PDF 705 KB Posted

Attached to
Tailrace Crane for RS Kerr Dam Federal contract opportunity
Solicitation number
W912BV18R0034
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

Full Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Tailrace Crane for RS Kerr Dam, newest first.
File Type Posted
Reference_Drawings.pdf PDF
W912BV18R0034_P00003.pdf PDF
W912BV18Q0034P00002.pdf PDF
W912BV18R0034P00001.pdf PDF
Attachment_3,_Drawings,_Tailrace_Crane.pdf PDF
AMRDEC_Instructions.pdf PDF
RSKerr_Tailrace_Crane_Specs_7-2-18.pdf PDF
AMRDEC_Instructions.pdf PDF
Drawings.pdf PDF
Attachment_4,_Additional_Drawings,_Tailrace_Crane.pdf PDF
CSS_Tailrace_Crane.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF CHANGES (SPECIFICATIONS AND DRAWINGS)

AMENDMENT 0003

RFP NO. W912BV18R0034

RS KERR POWERHOUSE NEW TAIL RACE CRANE

ROBERT S. KERR LOCK AND DAM 15, OKLAHOMA

Standard Form (SF) 30, Block 14 (continuation):

The proposal documents shall be revised as follows:

SPECIFICATIONS

Delete the previously issued Table of Contents and replace with the new Table of Contents attached hereto.

Delete the following list of previously issued sections and replace with the new sections attached hereto:

01 11 00

01 42 00

02 41 16.00 26

05 50 03.00 26

05 50 04.00 26

09 97 02.10 26

41 01 20.71 26

41 01 20.73 26

41 01 20.74 26

41 01 20.76 26.

Delete Section 01 22 00.00 10.

Add the following list of new sections attached hereto:

03 60 00.01 26

26 05 00.00 26.

DRAWINGS

Add, for information only, the 54 new Reference Sheets provided through

AMRDEC.

END OF SUMMARY OF CHANGES (SPECIFICATIONS AND DRAWINGS) – AMENDMENT 0003

TABLE OF CONTENTS SOLICITATION

NO. W912BV18R0034

RS KERR POWERHOUSE NEW TAILRACE CRANE

ROBERT S. KERR LOCK AND DAM 15, OKLAHOMA

OCTOBER 5, 2018

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 CONTRACTOR'S SITE OPERATIONS

01 11 00 SUMMARY OF WORK

01 32 16 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 46 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 – EXISTING CONDITIONS

02 41 16.00 26 REMOVE EXISTING CRANE

02 82 13 ASBESTOS ABATEMENT

02 83 13 LEAD IN CONSTRUCTION

DIVISION 03 – CONCRTE

03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND MINOR

EQUIPMENT FOUNDATIONS

DIVISION 05 – METALS

05 50 03.00 26 METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS

PROVISIONS

05 50 04.00 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED

ITEMS

DIVISION 09 – FINISHES

09 97 02.10 26 PAINTING: HYDRAULIC STRUCTURES

DIVISION 26 – ELECTRICAL

26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 01 20.71 26 NEW TAILRACE GANTRY CRANE DATA, TESTING AND TRAINING

41 01 20.73 26 TAILRACE GANTRY CRANE ELECTRICAL WORK

41 01 20.74 26 NEW TAILRACE GANTRY CRANE MECHANICAL AND STRUCTURAL WORK

41 01 20.76 26 NEW LIFTING BEAM

-- End of Table of Contents --

Revised By Amd 0003

TOC-1

RS Kerr Powerhouse New Tail Race Crane FY18 KERRTLRACECRAN18

SECTION 01 11 00 Page 1

Section Reissued by Amendment 0003

SECTION 01 11 00

SUMMARY OF WORK

08/11

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the other

Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes the removal and replacement of the existing draft tube gantry crane at Robert S. Kerr and incidental related work. The existing gantry crane has a rated capacity of 30-tons. The new crane will have a rated capacity of 40-tons. The work includes, but is not limited to;

removal and disposal of the existing 30-ton capacity gantry crane, design, fabrication, installation, and testing of the replacement 40-ton capacity gantry crane and lifting beam. There is an optional bid item for removing the rigid conductor existing electrification system.

1.2.2 Location

The work is located at the Robert S. Kerr Dam approximately five miles south of Sallisaw, Oklahoma on Oklahoma State Highway 59, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

The Powerhouse will be occupied during performance of work under this

Contract. The scheduled working hours of the Project staff at the Robert S.

Kerr Dam power plant are Mondays through Thursdays from 6:30 a.m. until

5:00 p.m. Fridays, Saturdays, Sundays, and Federal Holidays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours, unless otherwise specifically approved. Work outside of normal facility hours must be coordinated and approved by the Administrative Contracting Officer. Provide requests to work outside of normal facility hours to the Contracting Officer a minimum of 10 days prior to the proposed days of work outside of the normal schedule.

Before work is started, the Contractor shall arrange with the

Administrative Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to SECTION 00700 "FAR 52.236-9, Protection of Existing

Vegetation, Structures, Equipment, Utilities, and Improvements":

SECTION 01 11 00 Page 2

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 42 00 Page 1

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

11/14

1.1 REFERENCES

Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy

Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.

1.2 ORDERING INFORMATION

The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.

AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)

2025 M Street, NW, Suite 800

Washington, DC 20036

Ph: 202-367-1155

E-mail: info@americanbearings.org

Internet: http://www.americanbearings.org

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

38800 Country Club Drive

Farmington Hills, MI 48331-3439

Ph: 248-848-3700

Fax: 248-848-3701

E-mail: bkstore@concrete.org

Internet: http://www.concrete.org

AMERICAN GEAR MANUFACTURERS ASSOCIATION (AGMA)

1001 N. Fairfax Street, Suite 500

Alexandria, VA 22314-1587

Ph: 703-684-0211

Fax: 703-684-0242

E-mail: tech@agma.org

Internet: http://www.agma.org

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

One East Wacker Drive, Suite 700

Chicago, IL 60601-1802

Ph: 312-670-2400

Fax: 312-670-5403

Bookstore: 800-644-2400

E-mail: aisc@ware-pak.com

Internet: http://www.aisc.org mailto:info@americanbearings.org http://www.americanbearings.org/ mailto:bkstore@concrete.org http://www.concrete.org/ mailto:tech@agma.org http://www.agma.org/ mailto:aisc@ware-pak.com http://www.aisc.org/

SECTION 01 42 00 Page 2

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

1899 L Street, NW,11th Floor

Washington, DC 20036

Ph: 202-293-8020

Fax: 202-293-9287

E-mail: storemanager@ansi.org

Internet: http://www.ansi.org/

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

P.O. Box 28518

1711 Arlingate Lane

Columbus, OH 43228-0518

Ph: 800-222-2768; 614-274-6003

Fax: 614-274-6899

E-mail: tjones@asnt.org

Internet: http://www.asnt.org

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

1800 East Oakton Street

Des Plaines, IL 60018

Ph: 847-699-2929

Internet: http://www.asse.org

AMERICAN WELDING SOCIETY (AWS)

13301 NW 47 Ave

Miami, FL 33054

Ph: 888-WELDING, 305-824-1177, 305-826-6192

Fax: 305-826-6195

E-mail: customer.service@awspubs.com

Internet: http://www.aws.org

ASME INTERNATIONAL (ASME)

Two Park Avenue, M/S 10E

New York, NY 10016-5990

Ph: 800-843-2763

Fax: 973-882-1717

E-mail: customercare@asme.org

Internet: http://www.asme.org

ASSOCIATION FOR IRON AND STEEL TECHNOLOGY (AIST)

186 Thorn Hill Road

Warrendale, PA 15086-7528

Ph: 724-814-3000

Fax: 724-814-3001

E-Mail: memberservices@aist.org

Internet: http://www.aist.org/publications

ASTM INTERNATIONAL (ASTM)

100 Barr Harbor Drive, P.O. Box C700

West Conshohocken, PA 19428-2959

Ph: 877-909-2786

Internet: http://www.astm.org

CRANE MANUFACTURERS ASSOCIATION OF AMERICA (CMAA)

8720 Red Oak Boulevard, Suite 201

Charlotte, NC 28217-3992

Ph: 704-676-1190

Fax: 704-676-1199 mailto:storemanager@ansi.org http://www.ansi.org/ mailto:tjones@asnt.org http://www.asnt.org/ http://www.asse.org/ mailto:customer.service@awspubs.com http://www.aws.org/ mailto:customercare@asme.org http://www.asme.org/ mailto:memberservices@aist.org http://www.aist.org/publications http://www.astm.org/

SECTION 01 42 00 Page 3

Internet: http://www.mhi.org/cmaa

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

445 and 501 Hoes Lane

Piscataway, NJ 08854-4141

Ph: 732-981-0060 or 800-701-4333

Fax: 732-562-9667

E-mail: onlinesupport@ieee.org

Internet: http://www.ieee.org

INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)

3, rue de Varembe

P.O. Box 131

CH-1211 Geneva 20, Switzerland

Ph: 41-22-919-02-11

Fax: 41-22-919-03-00

Internet: http://www.iec.ch

INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)

1, ch. de la Voie-Creuse

Case Postale 56

CP 56 - CH-1211 Geneva 20

Switzerland

Ph: 41-22-749-01-11

Fax: 41-22-733-34-30

E-mail: central@iso.ch

Internet: http://www.iso.org

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

1300 North 17th Street, Suite 900

Arlington, VA 22209

Ph: 703-841-3200

Internet: http://www.nema.org/

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

1 Batterymarch Park

Quincy, MA 02169-7471

Ph: 617-770-3000

Fax: 617-770-0700

Internet: http://www.nfpa.org

RESEARCH COUNCIL ON STRUCTURAL CONNECTIONS (RCSC)

E-Mail: boltcouncil@gmail.com

Internet: http://www.boltcouncil.org

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

40 24th Street, 6th Floor

Pittsburgh, PA 15222

Ph: 412-281-2331

Fax: 412-281-9992

E-mail: info@sspc.org

Internet: http://www.sspc.org

U.S. ARMY CORPS OF ENGINEERS (USACE)

CRD-C DOCUMENTS available on Internet:

http://www.wbdg.org/ccb/browse_cat.php?c=68

Order Other Documents from:

USACE Publications Depot

Attn: CEHEC-IM-PD http://www.mhi.org/cmaa mailto:onlinesupport@ieee.org http://www.ieee.org/ http://www.iec.ch/ mailto:central@iso.ch http://www.iso.org/ http://www.nema.org/ http://www.nfpa.org/ mailto:boltcouncil@gmail.com http://www.boltcouncil.org/ mailto:info@sspc.org http://www.sspc.org/ http://www.wbdg.org/ccb/browse_cat.php?c=68

SECTION 01 42 00 Page 4

2803 52nd Avenue

Hyattsville, MD 20781-1102

Ph: 301-394-0081

Fax: 301-394-0084

E-mail: pubs-army@usace.army.mil

Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

General Services Administration

1275 First St. NE

Washington, DC 20417

Ph: 202-501-1231

Internet: http://www.gsaelibrary.gsa.gov/ElibMain/home.do

Obtain documents from:

Acquisition Streamlining and Standardization Information System

(ASSIST)

Internet: https://assist.dla.mil/online/start/; account registration required

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

8601 Adelphi Road

College Park, MD 20740-6001

Ph: 866-272-6272

Fax: 301-837-0483

Internet: http://www.archives.gov

Order documents from:

Superintendent of Documents

U.S.Government Printing Office (GPO)

710 North Capitol Street, NW

Washington, DC 20401

Ph: 202-512-1800

Fax: 202-512-2104

E-mail: contactcenter@gpo.gov

Internet: http://www.gpoaccess.gov

UNDERWRITERS LABORATORIES (UL)

2600 N.W. Lake Road

Camas, WA 98607-8542

Ph: 877-854-3577

E-mail: CEC.us@us.ul.com

Internet: http://www.ul.com/

UL Directories available through IHS at http://www.ihs.com

Not used

Not used mailto:pubs-army@usace.army.mil http://www.publications.usace.army.mil/ http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx http://www.gsaelibrary.gsa.gov/ElibMain/home.do http://www.archives.gov/ mailto:contactcenter@gpo.gov http://www.gpoaccess.gov/ mailto:CEC.us@us.ul.com http://www.ul.com/ http://www.ihs.com/

SECTION 02 41 16.00 26 Page 1

SECTION 02 41 16.00 26

REMOVE EXISTING CRANE

05/16

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A10.6 (1990; R 1998) Safety Requirements for

Demolition Operations

EM 385-1-1 (2014) Safety and Health Requirements

Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Removal Plan; G

On-Site Work Notification; G

Copies of Notifications

1.3 WORK DESCRIPTION

The work described in this section includes removal of the existing 30-ton gantry crane and the optional bid item for the removal of the power conductor system, currently located on the powerhouse tailrace deck at

Robert S. Kerr powerhouse.

1.3.1 Sequence of Construction

The existing gantry crane must be in operation the entire time the new crane is being erected and tested. The existing crane must be capable of traveling the full length of the rails except the erection areas for the new crane. Removal of the existing crane must not occur until after the new 40-ton capacity crane is fully operational, tested, and accepted by the

Government.

1.3.2 Remove Existing Crane

After the new crane is operational and accepted by the Government the

SECTION 02 41 16.00 26 Page 2 existing crane must be moved to the location indicated and disassembled.

Disassembly must occur during the dates specified in Clause 52.211-10.

Removal includes, but is not limited to, drive trucks, gantry structure, all electrical wiring and conduits, all mechanical equipment, machinery house, all hoists, and ropes. Rubbish and debris must be removed from

Government property daily (or stored in Contractor furnished receptacles), to avoid accumulation at the work site and prevent blocking of the roadway or debris or oil leaking into the river. Materials that cannot be removed daily may be temporarily stored on the project site in areas designated by the Administrative Contracting Officer. From there, pieces further reduced in size shall remain as large as practical to fit into trucks to transport to off-site disposal/recycling. All removed components become the property of the Contractor unless otherwise specified.

1.3.3 Remove Conductors and Supports (OPTIONAL BID ITEM)

The removal of the existing electrification bar system is a optional bid item. If this section is exercised by the Contracting Officer the power conductors and supports shall be removed in accordance with the requirements of this section, SECTION 05 50 04.00 26, METALS:

MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED ITEMS, and applicable

Regulatory and Safety Requirements.

1.3.4 Asbestos Removal

The removal of asbestos from the existing crane is considered a Class II operation. All brakes on the crane are assumed to contain asbestos.

Additionally, wiring throughout the crane may contain asbestos in the fabric insulation. Remove all asbestos-containing material (ACM) and dispose of and the asbestos work area must be completely cleaned. The

Contractor is responsible for the following asbestos abatement work items:

a. Pre-activity air testing to determine background levels of airborne asbestos and initial air monitoring to determine the level of friable asbestos created upon removal of ACM.

b. Removal and disposal of all asbestos containing material including asbestos on mechanical and electrical equipment shall be incidental to the work and no separate payment will be made. Handle and dispose of asbestos in accordance with SECTION 01 57 19 ENVIRONMENT PROTECTION and

SECTION 02 82 13 ASBESTOS ABATEMENT.

1.3.5 HANDLING OF LEAD

The gantry crane was painted with a lead based primer. All structural steel that is painted shall be considered to be contaminated with lead based paint and must be handled and disposed of in accordance with SECTION 01 57

19 ENVIRONMENT PROTECTION, and SECTION 02 83 13, LEAD IN CONSTRUCTION.

1.4 REGULATORY AND SAFETY REQUIREMENTS

Comply with federal, state, and local hauling and disposal regulations.

All solid waste from the removal of the existing crane, power conductors and poles will be disposed of in accordance with Section 01 57 19, ENVIRONMENT PROTECTION. In addition to the requirements of the "Contract

Clauses," conform to the safety requirements contained in ANSI A10.6.

Notify EPA as required, prior to asbestos removal.

SECTION 02 41 16.00 26 Page 3

1.5 ON-SITE WORK NOTIFICATION

Notify the Administrative Contracting Officer in writing 15 working days prior to demolition of the existing gantry crane.

1.6 COORDINATION

See SECTION 01 10 00, CONTRACTOR'S SITE OPERATIONS for requirements related to deck access impacts, and any or all coordination with the Government.

1.7 DUST AND DEBRIS CONTROL

Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding areas. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Contractor must protect river water from all debris created by activities related to the removal of the existing crane, power conductors and poles.

1.8 PROTECTION

1.8.1 Existing Conditions

Before beginning any removal work, survey the site and examine the drawings and specifications to determine the extent of the work. Take necessary precautions to avoid damage to existing and adjacent items to remain in place; any damaged items must be repaired or replaced as approved by the

Administrative Contracting Officer. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. The Contractor shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting or removal work performed under this contract.

1.8.2 Services and Utilities

Maintain existing utilities to stay in service and protect against damage during removal operations. Protect electrical and mechanical services and utilities. Where removal of existing utilities is specified or indicated, provide approved temporary covering of exposed areas.

1.8.3 Items to Remain in Place

Take necessary precautions to avoid damage to existing items to remain in place. Repair or replace damaged items as approved by the Administrative

Contracting Officer.

1.8.4 Protection of Personnel

Before, during and after the removal work the Contractor must continuously evaluate the condition of the structure being removed and take immediate action to protect all personnel working in and around the work site. No area, section, or component of columns or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove items or perform other work in the immediate area.

1.9 REMOVAL PLAN

The Removal Plan must include procedures and sequences for careful removal

SECTION 02 41 16.00 26 Page 4 and disposition of materials specified to be removed from site, a disconnection schedule of utility services, and a detailed description of methods and equipment to be used for each operation and of the sequence of operation. Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Removal Plan must be approved prior to mobilization to site. Indicate areas that may be weakened as a result of removal work and provide a plan for reinforcing these areas.

1.10 ENVIRONMENTAL PROTECTION

The work shall comply with the requirements of SECTION 01 57 19 ENVIRONMENT

PROTECTION.

1.11 USE OF EXPLOSIVES

Use of explosives will not be permitted.

PART 2 (Not Used)

3.1 EXISTING FACILITIES TO BE REMOVED

3.1.1 Existing Gantry Crane

Remove the existing gantry crane in a systematic manner from the top of the structure down to the tailrace deck. Remove structural framing members and lower to the deck by means of mobile crane, forklift, or other suitable methods as approved by the Administrative Contracting Officer. Overhead power lines at 161kV phase-to-phase span over the tailrace crane rails;

removal of the existing crane must adequate clearances per EM 385-1-1 with respect to these overhead power lines.

3.1.2 Existing Power Conductors and Supports (OPTIONAL BID ITEM)

The removal of the existing electrification bar system is a optional bid item. If exercised by the Contracting Officer the existing power conductors and supports shall be removed in a systematic manner. Remove conductors and support by suitable methods as approved by the Administrative

Contracting Officer. Overhead power lines at 161kV phase-to-phase span over the tailrace crane rails; removal of the existing crane must adequate clearances per EM 385-1-1 with respect to these overhead power lines.

Provide a removal plan as specified in SECTION 05 50 04.00 26, METALS:

MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED ITEMS.

3.1.3 Utilities and Related Equipment

Work that requires disconnection or interruption to utilities services must be coordinated through the Administrative Contracting Officer. Prior to start of work, utilities serving the removal work area will be shut off by the Government. The Contractor must follow all safe clearance lockout procedures as specified in SECTION 01 35 26 GOVERNMENT SAFETY REQUIREMENTS.

After the utilities are shut off and clearance is given, the

Contractor must disconnect and seal off utilities before proceeding with removal work.

3.1.4 Structural Steel

Dismantle structural steel at field connections and in a manner that will

SECTION 02 41 16.00 26 Page 5 prevent bending or damage. All structural steel shall become the

Contractor's property. All structural steel that is painted shall be considered to be contaminated with lead based paint and must be handled and disposed of in accordance with SECTION 01 57 19 ENVIRONMENT PROTECTION, and

SECTION 02 83 13, LEAD IN CONSTRUCTION. The contractor shall submit and have government approval of a lead compliance plan, in accordance with

02 83 13, before any demolition work is started.

3.1.5 Miscellaneous Metal

Scrap metal must become the Contractor's property. Contractor must dispose of scrap metal in accordance with local, state and federal regulations in addition to SECTION 01 57 19 ENVIRONMENT PROTECTION and must perform all notifications to subcontractors or disposal entities. Copies of notifications must be provided to the Contracting Officer. All miscellaneous metal that is painted must be considered to be contaminated with lead based paint and shall be handled and disposed of in accordance with SECTION 01 57 19 ENVIRONMENT PROTECTION, and SECTION 02 83 13, LEAD IN

CONSTRUCTION.

3.2 DISPOSITION OF MATERIAL

3.2.1 Title to Materials

Except for materials and equipment removed by the Government or set to remain in place as indicated on the contract drawings or as specified, all materials and equipment removed must become the property of the Contractor, removed from Government property, and disposed of in a legal manner. Title to materials resulting from removal work, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting

Officer of the Contractor's removal procedures, and authorization by the

Contracting Officer to begin removal work. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Material salvaged for the Contractor shall be stored as approved by the Contracting Officer and shall be removed from Government property. Materials and equipment shall not be viewed by prospective purchasers or sold on the project site.

3.2.2 Unsalvageable Material

Concrete and other noncombustible material must be disposed of in accordance with all applicable Federal, State, and local regulations. All unsalvageable materials that are painted must be considered to be contaminated with lead based paint and shall be handled and disposed of in accordance with SECTION 01 57 19 ENVIRONMENT PROTECTION, and SECTION

02 83 13, LEAD IN CONSTRUCTION.

3.3 CLEANUP

Debris and rubbish must be removed from the site. Debris must be removed and transported in a manner that prevents spillage on adjacent areas.

Apply local regulations regarding hauling and disposal. The Contractor must clean up site daily and whenever debris poses a safety hazard.

SECTION 03 60 00.01 26 Page 1

SECTION 03 60 00.01 26

CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES,

AND MINOR EQUIPMENT FOUNDATIONS

1.1 GENERAL INFORMATION

The work covered by this Section consists of furnishing all material, labor, and equipment, and performing all work for the removal of concrete from the powerhouse, the restoration of the concrete surfaces to the required lines and grades, and placement of equipment foundations in locations required. The Contractor is required to provide protection from concrete dust and water damage to existing and new equipment. Take effective measures to control gas, vapor, fumes, dust, slurry and mist during concrete removal operations. Accomplish work described in this

Section in accordance with and under limitations stated in Section

41 01 20.74 26.

1.2 REFERENCES

extent referenced. The publications are referenced to in the text by basic definition only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 318 (2014; Errata 1 2014) Building Code

Requirements for Structural Concrete and

Commentary

ASTM A1064/A1064M (2013) Standard Specification for

Carbon-Steel Wire and Welded Wire

Reinforcement, Plain and Deformed, for

Concrete

ASTM A615/A615M (2014) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete

Reinforcement

ASTM C1107/C1107M (2014) Standard Specification for Packaged

Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C882/C882M (2013a) Bond Strength of Epoxy-Resin

Systems Used with Concrete by Slant Shear

ASTM C928/C928M (2013) Packaged, Dry, Rapid-Hardening

Cementitious Materials for Concrete Repairs

ASTM C579 (2001; R 2006) Compressive Strength of

Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer

SECTION 03 60 00.01 26 Page 2

Concretes

ASTM C881/C881M (2013) Standard Specification for

Epoxy-Resin-Base Bonding Systems for

Concrete

ASTM C94/C94M (2014a) Standard Specification for

Ready-Mixed Concrete

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1926 Safety and Health Regulations for

Construction

1.3 SUBMITTALS

used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

Concrete Removal and Disposal Plan; G, HDC

Core Drilling Procedure; G, HDC

Concrete Imaging Report; G, HDC

Repair Procedure of Concrete Surfaces; G, HDC

1.4 CONCRETE REMOVAL LOCATIONS

Locations of concrete removal areas are shown on the drawings and as described as follows:

a. Core drill holes for stowage pins. Use core drill holes no larger than 6 inches in diameter unless otherwise shown on drawings. Locate core drill holes a minimum of 2 feet away from existing penetrations.

2.1 NON-SHRINK GROUT

Provide non-shrink grout which is inorganic, non-metallic, non-gas-liberating cement-based meeting all requirements of

ASTM C1107/C1107M; with a minimum 28-day compressive strength of 5,000 pounds per square inch (psi); and with no shrinkage (0.0 percent) and a maximum 2.0 percent expansion in the hardened state.

SECTION 03 60 00.01 26 Page 3

2.2 EPOXY ADHESIVE GROUT

Epoxy adhesive grout for use with post installed concrete anchors must be a high strength, two part epoxy adhesive meeting all requirements of

ASTM C881/C881M Type IV, Grade 2 and 3; have a minimum compressive strength of 12,000 psi per ASTM C579; and have a seven day cure bond strength of

1,800 psi per ASTM C882/C882M.

2.3 READY-MIX CONCRETE

Conform to ASTM C94/C94M for ready-mixed concrete. Provide a specified compressive strength f'c of 4,000 psi at 28 days (90 days if pozzolan is used); a maximum nominal size coarse aggregate of 3/4 inch, in accordance with ACI 318; an air content of between 4.5 and 7.5 percent; slump between

2 and 5 inches; a maximum water cement ratio of 0.50.

2.4 REINFORCING STEEL

Conform to the requirements of ASTM A615/A615M, Grade 60 for reinforcing steel bar. Conform to the requirements of ASTM A1064/A1064M for welded steel wire fabric. For details of reinforcement not shown, comply with the requirements of ACI 318, Chapters 7.7, 8.7, 9.7 and 25.

2.5 GROUT FOR UNCONFINED CONCRETE REPAIR

Provide commercially available prepackaged grout needing only the addition of water and pea gravel (depending on the size of the repair) and consisting of a commercial formulation suitable for the application proposed and meeting the requirements for ASTM C928/C928M. The use of metallic iron in the grout will not be acceptable.

3.1 GENERAL SAFETY

3.1.1 General

Accomplish all site work in compliance with EM 385-1-1, 29 CFR 1910 and

29 CFR 1926, as applicable.

3.1.2 Electrical Hazards

The work areas may be in proximity of energized electrical equipment.

Formally train and document safety training for all workers required to work in this area. Spray over onto live equipment is hazardous to workers and equipment and is not permitted. Provide Contracting Officer (CO) with signed safety training sheets documenting worker safety training prior to starting work.

3.2 GAS, VAPOR, FUME, DUST, SLURRY AND MIST CONTROL IN POWERHOUSE

Take all necessary measures to effect maximum control of all gases, vapors, fumes, dust, slurry and mists created by Contractor operations under this contract. To the maximum extent possible, remove all dust and dirt by vacuum cleaning and mopping, unless otherwise directed by the CO. The required dust and debris control measures include but are not limited to the following:

a. Provision of exhaust ducts which discharge outside the powerhouse

SECTION 03 60 00.01 26 Page 4 structure where mechanical ventilation is used. Comply with requirements of 29 CFR 1910.94 and 29 CFR 1926.57 for ventilation systems.

b. Controlled operation of power-driven tools.

c. Providing and removal of approved dust preventatives in areas that cannot be properly rendered free from excessive dusting by vacuum cleaning and mopping or other methods.

d. Vacuum cleaning and mopping (or other acceptable method) of spaces within the powerhouse where dust accumulates.

e. Only air, electrical, propane, or battery-driven equipment may be used inside the powerhouse.

f. Keep all doors closed when not in use.

g. Do not block doors for extended periods unless agreed upon in writing by the CO.

h. Methods to prevent exposure of employees to inhalation, ingestion, skin absorption, or contact with any material or substance at concentrations above those specified in 29 CFR 1910.1000, 29 CFR 1926.55 and 29 CFR 1926.58.

3.3 TEMPORARY BARRIER

Construct temporary barriers for the control of dust and debris as required by the CO. Submit the design of the barriers for approval, as part of the

Concrete Removal and Disposal Plan.

3.4 REMOVAL METHOD

3.4.1 General

Submit a written Concrete Removal and Disposal Plan showing equipment to be used, expected noise levels and duration. Submit concrete removal and disposal plan for approval within 60 calendar days after receiving Notice to Proceed. Do not commence any concrete removal without CO approval.

All concrete removed is the property of the Contractor and is required to be disposed of in accordance with applicable regulations. Remove concrete in a manner that will not fracture the surrounding concrete. Maintain a safety ground from the powerhouse ground system to the frame of the concrete cutting tool during cutting operations to avoid electrical shock hazards. Reinforced concrete removal is required to result in flush, level smooth surface at the lines and grades shown on the drawings. Take care not to damage reinforcing bar in the existing concrete. Explosive or chemical demolition will not be allowed. Provide adequate equipment to remove the pieces of concrete safely and without damage to the surrounding structure. Confine slurry or tailings generated from sawing or drilling operations to the immediate area, and dispose of by vacuuming and mopping.

Prevent damage to ground wires and electrical conduit. If during any cutting or core drilling activity copper tailings are produced, report such findings in writing to the Government Quality Assurance Representative

(GQAR). Implement additional dust control measures per paragraph GAS, VAPOR, FUME, DUST, SLURRY AND MIST CONTROL IN POWERHOUSE for work inside the powerhouse.

SECTION 03 60 00.01 26 Page 5

3.4.2 Recommended Procedure

Saw cutting, core-drilling, wire cutting or any combination thereof is the recommended method for the concrete removal to be done as part of this contract. In addition to cutting, chipping or grinding may be used to bring the concrete profile to the final finished grade. When the portion of concrete to be removed is of such a magnitude that it cannot be extracted in a single piece, perform additional cutting to allow the concrete to be removed in several convenient sized sections.

3.4.3 Core Drilling

Prior to core drilling, research the area to avoid and identify existing embedded reinforcing, ground wires, conduit, piping and raceways. Refer to reference drawings to assure drill patterns are likely to miss existing reinforcing, ground wires and conduit. Adjust the drill pattern to miss embedded obstructions. Securely ground all core drilling equipment during cutting operations to avoid electrical shock hazards. Submit Core Drilling

Procedure 60 days prior to commencement of core drilling work for approval;

submit together with Concrete Imaging Report. No core drilling is permitted without COR approval.

3.4.4 Chipping

When required, bring concrete removed by saw cutting, core drilling, or stitch drilling to the final required lines and grades by using lightweight chipping hammers, bush hammers, grinding or other approved means. Perform chipping operations such that the over breakage does not exceed 2 inches or extend below the existing grade.

3.4.5 Existing Concrete Strength

The existing concrete to be removed may be expected to range in strength from about 3,000 to over 6,000 psi. The nominal aggregate size of the concrete is unknown. Zones of honeycomb concrete may also be encountered during the drilling process.

3.4.6 Existing Embedded Items

Embedded items in the path of the concrete cutting or drilling operations may include, but are not limited to:

a. Reinforcing steel and minor embedded steel at various distances from the concrete faces.

b. Steel anchors and form tie backs used in placement of the existing concrete. The number and kind are unknown.

c. Electrical conduit.

d. Ground wires.

3.4.7 Research of Embedded Items and Concrete Imaging

Prior to concrete demolition, research the area to avoid and identify existing embedded reinforcing, ground wires, conduit, piping and raceways.

Refer to as-constructed reference drawings to assure drill patterns are likely to miss existing reinforcing, ground wires and conduit. Research of

SECTION 03 60 00.01 26 Page 6 the area must include concrete imaging techniques such as radiographic imaging, ground penetrating radar, or electromagnetic field detection.

Adjust drill pattern for coring and for anchor installation to miss embedded items and obstructions. Submit a Concrete Imaging Report for approval 60 days prior to commencement of core drilling work; submit with

Core Drilling Procedure, Saw Cutting Procedure, and Concrete Removal and

Disposal Plan. Include the following in the Concrete Imaging Report at a minimum:

a. Description of the findings.

b. Proposed penetration location and purpose of penetration.

c. Show the proposed concrete to be removed on a dimensioned concrete outline drawing of the area.

d. Photo or sketch showing:

(1) Embedded Items.

(2) Proposed penetration location.

(3) Dimensions.

3.4.8 Concrete Cutting Tolerances

a. Accurately locate the concrete cut through the existing concrete.

Locate wire or saw cuts within 1/8-inch of plan dimensions.

b. Accurately locate and drill the core drill holes through existing concrete. Minimize the drill wobble during the drilling operation to assure a true and straight hole meeting specified tolerances.

3.4.9 Quality Control

Establish and maintain a quality control system for the concrete cutting operation. Use a system sufficient to maintain tolerances such that the final concrete cutting conforms to the tolerances outlined in this section of the specifications. The Government reserves the right to inspect this control system to determine if the tolerances are being adhered to, and direct the Contractor to correct and repair any deviations from these tolerances.

3.4.10 Disposal Of Waste Water And Concrete Debris

Use a method in disposing of waste water employed in cutting, washing, and rinsing of concrete surfaces that does not stain, discolor, or affect exposed surfaces of the structure and does not allow waste water to enter the river or reservoir. As some Project drains lead to the river, do not dispose of waste water in Government drains. Disposewaste water as per the written Concrete Removal Plan. Do not allow debris to enter the river or reservoir and include methods to prevent this in the written Concrete

Removal Plan.

3.4.11 Repair Of Concrete Surfaces

Restore concrete surfaces to the required lines and grades shown using a

Government approved method. Submit Repair Procedure of Concrete Surfaces for approval 30 calendar days prior to performing repair. Do not commence repair work without an approved procedure. In the repair procedure, include detailed information on all materials and methods used.

a. If piping, conduit or ground wires are damaged during core drilling or concrete excavation, excavate a sufficient area of the concrete to allow the ground wire, conduit, or piping to be repaired by saw cutting

SECTION 03 60 00.01 26 Page 7 the perimeter of the area to a depth of 1-1/2 to 2 inches, and then complete the remaining excavation needed using hand tools or a bush hammer taking care to preserve embedded reinforcing steel intact.

Repair piping, conduit or ground wires per approved methods.

b. Removal of equipment must leave behind a smooth, level surface at the same grade as the surrounding concrete. Should equipment removal damage the concrete substrate or reveal irregularities that cannot practicably be ground smooth, outline the existing concrete by saw-cutting to prevent over-breakage and remove to a uniform depth of

0.5 to 1.5 inches taking care to avoid damage to embedded reinforcing bar and patch with grout suitable for unconfined concrete repair.

c. In all areas where concrete removal will leave transverse reinforcing steel exposed, coat the reinforcing and the local area around the bar with an approved epoxy coating unless otherwise indicated.

d. Repair any anchor holes made in concrete which are to be abandoned following completion of work with non-shrink grout.

e. Fill annualar space of holes greater than 1 inch in depth with non-shrink grout or with foam insulation and seal with fire rated material per paragraph FIRESTOPPING MATERIALS. Finished surface should be flush and installation remain intact through all reasonable normal usage of the area.

SECTION 05 50 03.00 26 Page 1

SECTION 05 50 03.00 26

METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS PROVISIONS

This SECTION covers general workmanship requirements, applicable to the fabrication and inspection of various items of metalwork and machine work.

These requirements are in addition to those contained in the specification sections covering the specific items of work or as shown.

ASME B4.1 (1967; R 2009) Preferred Limits and Fits for Cylindrical Parts

ASME B46.1 (2009) Surface Texture, Surface Roughness, Waviness and Lay

ASME BPVC SEC IX (2010) BPVC Section IX-Welding and Brazing

Qualifications

ASTM A 123/A 123M (2009) Standard Specification for Zinc

(Hot-Dip Galvanized) Coatings on Iron and

Steel Products

ASTM A 780/A 780M (2009) Standard Practice for Repair of

Damaged and Uncoated Areas of Hot-Dip

Galvanized Coatings

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

ANSI/ASNT CP-189 (2016) ASNT Standard for Qualification and

Certification of Nondestructive Testing

Personnel (ANSI/ASNT CP-105-2006)

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016)

Structural Welding Code - Steel

AWS QC1 (2007) Standard for AWS Certification of

Welding Inspectors

RESEARCH COUNCIL ON STRUCTURAL CONNECTIONS (RCSC)

RCSC S348 (2010) RCSC Specification for Structural

SECTION 05 50 03.00 26 Page 2

Joints Using ASTM A325 or A490 Bolts used, a designation following the "G" designation identifies the office

SD-05 Design Data

Welding Procedures; G HDC

Qualification of Welders and Welding Operators; G C

Certified Weld Inspector's Certification; G C

Inspection Agency Qualifications; G C

Welding Repair Plan; G HDC

Weld Inspection Reports; G HDC

1.4 INSPECTIONS AND TESTS

1.4.1 Inspections and Tests

Inspections and tests shall be performed in accordance with this SECTION and in conjunction with SECTION 01 45 QUALITY CONTROL to demonstrate that the fabrication and machine work are in conformity and in addition to the applicable inspection requirements elsewhere specified. A detailed plan shall be prepared as part of the CQC Plan to record all measurements, and other details that indicate the plans and specifications are met. These tests and inspections shall be performed at the Contractor's expense, certified, and available for review. Inspections and tests shall conform to the requirements of the particular sections of these specifications and plans for the respective items of work unless otherwise specified or authorized. The Government will notify the Contractor which inspections and tests shall be conducted in the presence of and witnessed by the

Administrative Contracting Officer. The Government shall be notified of the dates of the inspections and tests as required in SECTION 01 45 00

QUALITY CONTROL.

1.4.2 Structural Weldments

1.4.2.1 General

Inspection shall be made of each weldment to show that the completed unit meets all the details shown or specified. Records shall be kept of each inspection. The Government may independently inspect weldments. All weldments shall be made available for inspection by the Government at the

Government's request.

1.4.2.2 Non-destructive Inspection

When doubt exists as to the soundness of any weldment, such weldment shall be subjected to any form of non-destructive inspection as directed. This may include ultrasonic, magnaflux, dye penetrant, x-ray, gamma ray or any

SECTION 05 50 03.00 26 Page 3 other test that will thoroughly inspect the weldment in question. The cost of such inspection will be borne by the Government only if the weldment is determined to meet the specifications. The cost of the inspection for weldments found unsound shall be borne by the Contractor. Any unsound weldments will be rejected and shall be replaced and re-inspected at the

Contractor's expense.

1.4.2.3 Destructive Inspection

When doubt exists as to the soundness of any weldment that cannot be resolved by non-destructive inspection, coupons shall be taken for destructive inspection as directed. The cost of such inspection, repair, or replacement will be borne by the Government only if the weldment is determined to meet the specifications. The cost of the inspection for weldments found unsound shall be borne by the Contractor. Any unsound weldments will be cause for rejection and rejected weldments shall be repaired or replaced and re-inspected at the Contractor's expense.

PART 2 PRODUCTS (Not Used)

3.1 STRUCTURAL FABRICATION

3.1.1 General

Material must be straight before being laid off or worked. If straightening is necessary it shall be done by methods that will not impair the metal. Sharp kinks or bends shall be cause for rejection of the material. Material with welds will not be accepted except where welding is definitely specified, indicated on the drawings or otherwise approved.

Bends shall be made by dies, press brakes or bending rolls normally used in this type of fabrication. Where heating is required, precautions shall be taken to avoid overheating the metal and it shall be allowed to cool in a manner that will restore the original properties of the metal. Proposed flame cutting of material other than structural steel shall be subject to approval and shall be indicated on shop drawings. Shearing shall be accurate and all portions of the work shall be neatly finished. Corners shall be square and true unless otherwise shown. Re-entrant cuts shall be filleted to a minimum radius of 3/4-inch unless otherwise approved.

Finished members shall be free of twists, bends and open joints.

3.1.2 Dimensional Tolerances for Structural Work

Dimensions shall be measured by an approved calibrated steel tape of approximately the same temperature as the material being measured at the time of measurement. The overall dimensions of an assembled structural unit shall be within the tolerances shown or as specified in the particular section of THESE SPECIFICATIONS for the item of work. Where tolerances are not specified in other sections of these specifications or shown elsewhere, an allowable variation of 1/32-inch is permissible in the overall length of component members with both ends milled, and component members without milled ends shall not deviate from the dimensions shown by more than

1/16-inch for members 30 feet or less in length and by more than 1/8-inch for members over 30 feet in length.

SECTION 05 50 03.00 26 Page 4

3.1.3 Structural Steel Fabrication

Structural steel may be cut by mechanically guided or hand guided torches provided an accurate profile with a surface that is smooth and free from cracks and notches is obtained. Surfaces and edges to be welded shall be prepared in accordance with AWS D1.1/D1.1M. Where structural steel is not to be welded and is not exposed to view, grinding will not be required except as necessary to remove slag and sharp edges of mechanically guided or hand guided cuts. Hand or mechanically guided cuts which are to be exposed or visible shall be chipped, ground or machined to sound metal.

All exposed edges shall be ground to provide a radius, approximately

1/16-inch minimum.

3.2 WELDING

3.2.1 General

Unless otherwise authorized or specified, welding shall be by an electric arc welding process using a method which excludes the atmosphere from the molten metal. Welding for structural steel shall conform to AWS D1.1/D1.1M.

All mandatory appendices will be considered part of AWS D1.1/D1.1M and therefore apply. The nonmandatory appendices and commentary will be used as guides and supplementary information unless otherwise specified for the interpretation and application of AWS D1.1/D1.1M. Welding shall conform to procedures in ASME BPVC SEC IX for welding of stainless steel, non-ferrous metals, and dissimilar metals.

3.2.2 Filler Metal

a. The electrode, wire, wire flux or electrode-flux combination and grade of weld metal shall conform to the appropriate AWS specification for the base metal or metals and welding process being used or shall be as shown where a specific choice of AWS specification allowables is required. Only low-hydrogen electrodes shall be used for shielded metal-arc welding. The AWS designation of the electrodes to be used shall be included in the schedule of welding procedure to be furnished. The filler metal shall meet the requirements of

AWS D1.1/D1.1M, Annex T - Filler Metal Strength Properties.

b. For welding base metals not specifically covered by AWS D1.1/D1.1M, all deposited weld metal, unless otherwise specified or authorized, shall have yield points and ultimate tensile strengths not less than those specified for the respective base metals welded and shall have an elongation, in two (2) inches, of at least 95 percent of the value specified for the base metal. Where stress-relief heat treatment is specified, elongation shall be measured after stress relieving.

Chemical composition shall be compatible with that of the base metal.

3.2.3 Qualification Of Welders And Welding Operators

Qualification of Welders and Welding Operators shall be submitted. Welding operators, welders, and tack welders shall be qualified for the particular type of work to be done. Qualification shall be in accordance with

AWS D1.1/D1.1M. The welders and welding operators so qualified shall be certified and approved by name prior to any welding being performed by that individual. The qualifications shall be submitted on Form M-4 or M-5, Annex M of AWS D1.1/D1.1M, or equal. Prior qualification may be accepted provided the welder has performed satisfactory work in accordance with

AWS D1.1/D1.1M within the preceding six (6) months. A continuity log

SECTION 05 50 03.00 26 Page 5 showing the welder has been engaged in the welding process shall be submitted along with welder qualification records. The welder or welding operator shall be required to repeat the qualifying tests when, in the opinion of the Contracting Officer, their work indicates a reasonable doubt as to their proficiency. Certification shall be submitted for those passing the test and upon approval, they shall be considered qualified.

Those not passing shall be disqualified until passing. All expenses in connection with qualification or re-qualification shall be borne by the

Contractor.

3.2.4…