RSKerr_Tailrace_Crane_Specs_7-2-18.pdf

PDF 2 MB Posted

Attached to
Tailrace Crane for RS Kerr Dam Federal contract opportunity
Solicitation number
W912BV18R0034
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Tailrace Crane for RS Kerr Dam, newest first.
File Type Posted
Spec_Amendment.pdf PDF
Reference_Drawings.pdf PDF
W912BV18R0034_P00003.pdf PDF
W912BV18Q0034P00002.pdf PDF
W912BV18R0034P00001.pdf PDF
Attachment_3,_Drawings,_Tailrace_Crane.pdf PDF
AMRDEC_Instructions.pdf PDF
AMRDEC_Instructions.pdf PDF
Drawings.pdf PDF
Attachment_4,_Additional_Drawings,_Tailrace_Crane.pdf PDF
CSS_Tailrace_Crane.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912BV18R0034

US Army Corps of Engineers Tulsa District Arkansas River Watershed Robert S. Kerr Lock and Dam 15, Oklahoma

RS Kerr Powerhouse New Tail Race Crane

Specifications

July 2, 2018

JVS

TABLE OF CONTENTS

SOLICITATION NO. W912BV18R0034

RS KERR POWERHOUSE NEW TAILRACE CRANE

ROBERT S. KERR LOCK AND DAM 15, OKLAHOMA

APRIL 25, 2018

TOC-1

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 CONTRACTOR'S SITE OPERATIONS

01 11 00 SUMMARY OF WORK

01 32 16 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 46 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 – EXISTING CONDITIONS

02 41 16.00 26 REMOVE EXISTING CRANE

02 82 13 ASBESTOS ABATEMENT

02 83 13 LEAD IN CONSTRUCTION

DIVISION 05 – METALS

05 50 03.00 26 METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS

PROVISIONS

05 50 04.00 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED

ITEMS

DIVISION 09 – FINISHES

09 97 02.10 26 PAINTING: HYDRAULIC STRUCTURES

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 01 20.71 26 NEW TAILRACE GANTRY CRANE DATA, TESTING AND TRAINING

41 01 20.73 26 TAILRACE GANTRY CRANE ELECTRICAL WORK

41 01 20.74 26 NEW TAILRACE GANTRY CRANE MECHANICAL AND STRUCTURAL WORK

41 01 20.76 26 NEW LIFTING BEAM

-- End of Table of Contents --

RS Kerr Powerhouse New Tail Race Crane FY18 KERRTLRACECRAN18

SECTION 01 10 00

CONTRACTOR'S SITE OPERATIONS

PART 1 GENERAL

1.1 GENERAL INFORMATION

This section covers the general requirements applicable to specific Contractor's operations for work performed on site.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2009) Manual of Uniform Traffic Control Devices

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction site plan; G Project Manager/Contractor's Agent Qualifications; G Contractor’s Superintendent Qualifications; G

Qualifications and identification of Contractor’s superintendent, a minimum of 30 calendar days prior to the start of site work

SD-09 Manufacturer's Field Reports

Weekly Coordination Meeting Minutes

Minutes of weekly coordination meetings within 3 working days of the meeting

Contractor Security Program; G

Contractor Security Program, a minimum of 30 calendar days prior to the start of site work

SECTION 01 10 00 Page 1

Gas, Vapor, Fume, Dust, and Mist Control Program; G

Gas, Vapor, Fume, Dust and Mist Control Program, a minimum of 30 calendar days prior to the start of site work.

1.4 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), access and haul routes, avenues of ingress/egress to the fenced area(s) and details of the fence installation. Indicate if the use of a supplemental or other staging area is desired. Show locations of construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

1.5 CONTRACTOR SECURITY PROGRAM

In accordance with the DoD Information Assurance Certification and Accreditation Process (DIACAP), all contractors and their employees, and all subcontractors and subcontractor's employees requiring admittance to Tulsa District (SWT) Power Houses shall have a current Joint Personnel Adjudication System (JPAS) background check verified through SWT Emergency Management/Security office before they are allowed to enter the power plant building or structures. A maximum of 10 contractor employees will be authorized to obtain and hold no escort required status at any one time during the contract. The Contractor's Project Manager, Engineer, Contractor Quality Control (CQC) System Manager, Site Safety and Health Officer (SSHO), Superintendent, and subcontractor foremen are required to obtain the JPAS background check prior to mobilization to the construction site. A minimum of 120 days is required for SWT to process the JPAS background check once all required information is received.

All contractors and their employees, and all subcontractors and subcontractor's employees requiring escorted admittance to SWT powerhouses shall have a current (within 90 days of submission) completed local law enforcement background check submitted to the Contracting Officer and powerhouse Superintendent/Lake Manager no less than 5 working days prior to the needed day of entry and approved by the Government before they are allowed to enter the power plant building or structures. The contractor shall be responsible for all escort duties. Non-escort required employees shall escort escort-required employees and shall maintain visual contact with escort required employees at all time inside power plant buildings or structures.

All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the powerhouse any employee the Contracting Officer deems, incompetent, careless, disruptive, or otherwise objectionable.

All no-escort-required background checks must be conducted through the Personnel Security Investigation Portal (PSIP) submitted through the SWT Emergency Management/Security office. A minimum of 120 days is required for SWT to process the PSIP background check once all required information is received.

The JPAS and PSIP checks will be performed at no additional cost to the contractor/subcontractor.

SECTION 01 10 00 Page 2

All escort-required background checks must be conducted by a law enforcement agency* (i.e., Sheriff's Office, etc) within the state in which the person resides. Any costs associated to obtain the law enforcement background checks shall be the responsibility of the contractor/subcontractor/individual. Individuals will be allowed to enter SWT buildings and structures at the Denison power house as required to perform work under this contract as long as they are properly escorted and do not have any disqualifying factors. Background check disqualifying factors include: Any felony conviction; a misdemeanor conviction within the previous five years for a crime of violence, drug use/possession, or theft. If an individual does not have a disqualifying factor but has a misdemeanor conviction then those individuals will be evaluated or considered on a case by case basis. The contractor or subcontractor of the individual who has been approved to enter the Powerhouses shall coordinate all access with either the Lake Manager, Power Plant Superintendent, or on-site USACE representatives.

*Background checks for Oklahoma can be obtained through the following URL:

http://www.ok.gov/osbi/Criminal_History/index.html

Other States:

www.gallantbackgroundchecks.com

To be eligible to perform under this contract, contract employees shall meet the requirements listed above for background checks as well as the requirements listed below, to the satisfaction of the Contracting Officer:

Foreign workers shall be lawfully admitted to the United States (U. S.)

and have documentation (authorization to work in the U.S.) from U.S.

Citizenship and Immigration Services (USCIS). Foreign Nationals working on contracts shall be approved through the USACE Foreign Disclosure Officer prior to work.

No person presently under sentence of imprisonment will be allowed to work on a Government facility.

The Contractor shall ensure each employee is issued and displays at all times a proper identification badge. The badge shall be unique for each employee and include at a minimum the following:

CONTRACTOR

Name of Employee Employee Photo Name of Company

The Contractor shall keep an updated personnel/badge roster and ensure badges are turned in immediately when an employee is no longer required or otherwise allowed on the job site. Updated roster will be provided to the Government Quality Assurance Representative (GQAR) weekly.

1.6 WORK AREAS AND ACCESS

1.6.1 Access Roads, General

No new access roads are required. Any damage to existing roadways, project grounds, or Government property used for access purposes shall be repaired and the surface shall be restored to its pre-contract condition.

SECTION 01 10 00 Page 3

The Contractor shall comply with all requirements of state and county authorities for use of existing roadways, such as traffic regulations, load limits, etc. Public and project roads shall not be obstructed by Contractor's operations.

The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas, or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic, appropriate barricades and signs shall be provided, placed, and maintained by the Contractor. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night. Anchor signs and barricades as necessary to prevent displacement by winds.

1.6.2 Access and Use of Work Areas By Other Contractors

The Contractor will not have exclusive use of the work areas included in this contract. Other (third party) contractors with separate Government contracts may require access to and be working in the same space as the contractors and subcontractors working on this contract. Contractors and subcontractors will be required to make accommodations for the third party contractors.

1.6.3 Access By Government Personnel

Clear access shall be maintained for Government personnel and equipment through all work areas.

1.6.4 Contractor's Staging/Storage Areas and Employee Access

The Contractor's staging/storage area shall be as directed by the COR.

This area will be exposed to the weather. All packaging, crates, and parts for installation must be crated to be waterproof. The job-site office may be in the staging area. The project areas off-limits to Contractor personnel will also be designated by the GQAR. Salespersons or personnel seeking employment will not be permitted inside fenced security areas or the powerhouse. Signs containing instructions for personnel seeking the Contractor shall be erected outside the powerhouse security fence. The content and location of the signs shall be approved by the GQAR prior to erection of signs.

1.6.5 Access to Work Areas

Access shall be through existing gates and doors. Access into the powerhouse will only be by the powerhouse door at the loading platform area and will only be available during designated work hours.

1.6.6 Public Use Fishing Area Access

Safe public access to existing public use fishing areas shall be maintained at all times. The Contractor shall take actions as directed by the GQAR to insure public safety (related to Contractor vehicles and activities) is maintained.

1.7 VEHICLES

Parking of private vehicles shall be restricted to areas as directed by the COR. All Contractor's vehicles shall display identification of such size

SECTION 01 10 00 Page 4 and color to allow Government personnel to identify the vehicle.

1.8 SANITATION FACILITIES

The Contractor’s employees may only use the designated restrooms. Failure of the Contractor's personnel to keep Government restrooms neat and orderly will result in denial of further use. Sanitation facilities furnished by the Contractor shall be in accordance with EM 385-1-1, and shall be located outside the powerhouse at locations directed by the GQAR. The Contractor shall provide freeze protection during the winter months as required to prevent spillage and unsanitary conditions.

1.9 UTILITIES

1.9.1 Government Furnished Utilities

All utilities that are required for use in performance of the work under this contract shall be Contractor-furnished except the following, which shall be as directed by the GQAR:

a. Electricity

Electric power in the area for each unit may be obtained from the following existing sources at draft tube deck.

(1) 2 each 120-volt, 1 phase, 20-ampere (maximum) circuits

(2) 1 each 480-volt, 3-phase, 70-ampere (maximum) circuit

The Contractor shall be responsible for conditioning the power as necessary and providing conductors, transformers, etc. from existing service locations if required.

1.9.2 Temporary Utility Connections

All utilities provided by the Government will be at no cost. Care shall be exercised in conserving all Government-furnished utilities. Extension cords shall be Contractor-furnished. All temporary utility connections shall be subject to approval of the GQAR. The location of all power lines and all temporary connections for electricity shall be coordinated with the GQAR. All temporary circuits and devices for conditioning the power shall be provided, connected, maintained, and removed by the Contractor prior to final acceptance. Ground fault protection for all circuits shall be Contractor-furnished.

1.9.3 Telephone

The Contractor shall be responsible for having the local telephone company furnish all telephone service needed on the job site. All connections, hardware, and service charges for telephone service shall be the responsibility and expense of the Contractor. The Project telephone system will not be available to the Contractor. Reliable cellular phone service may not be available in the area. The Contractor shall be responsible for determining if cell phones will work.

1.10 CARE OF DRAINS

Existing powerhouse and area drains shall not be used for disposal of any solid or liquid materials other than clear water. Drains obstructed by the

SECTION 01 10 00 Page 5

Contractor shall be cleaned immediately by the Contractor. All costs incurred in the cleaning and clearing of plugged drains shall be borne by the Contractor. The Contractor is advised cleaning and clearing of plugged drains may be a very significant cost.

1.9 SAFE CLEARANCE PROCEDURES

A Safe Clearance System, as stated in EM 385-1-1 and amended by the RS Kerr Project personnel, is used by project personnel to insure continuity of service and safety to personnel and equipment. Any work performed which requires taking project operating equipment out of service shall be done only after a formal clearance is obtained by the Contractor with 48-hour minimum notice. Clearance shall not be violated by Contractor personnel.

Any violation of Safe Clearance Procedures will be grounds for the Government to require the Contractor to remove the offender(s) immediately for the duration of the contract. A copy of the Tulsa District/Robert S.

Kerr Safe Clearance Procedure will be supplied to the Contractor upon request, SWT OM 385-1-31-A and SWT OM 385-1-31-B are included in this document starting on pages 317 and 329 respectively.

1.11 DAILY CLEANUP AND DISPOSAL

In conjunction with Section 01 57 19 Temporary Environmental Controls, work areas shall be kept neat at all times. All debris resulting from the work shall be collected, removed, and disposed off-site at least twice per week or more often as directed by the GQAR. The Government's trash cans, dump boxes, other containers, and refuse service shall not be used. Liquid waste shall not be disposed of in powerhouse drains.

1.12 STORAGE OF EQUIPMENT AND MATERIALS

Indoor storage of equipment and materials will not be provided by the Government. Outdoor storage of equipment and materials will be permitted only in designated staging areas awings and as directed by the GQAR. All equipment and materials proposed for temporary storage areas within the Government allocated staging areas shall be coordinated with and approved by the GQAR. A minimum distance of three feet shall be maintained between the Contractor's stored items and the existing powerhouse equipment to allow access at all times. Do not block visibility and access to wall mounted fire extinguishers. Do not block stairway access.

1.13 CONTRACTOR'S EQUIPMENT AND MATERIAL

1.13.1 General

The planned method of transportation and operation of Contractor heavy equipment to be used in the performance of this contract shall be coordinated with and approved by the GQAR. This shall include the type, size, and loading of equipment and the proposed transportation routes and work areas to be used on the project. Operation of heavy equipment adjacent to existing structures shall not overload the capacity of the structure.

1.13.2 Movement of Equipment and Material by the Contractor

The Contractor shall provide all cranes, rigging, lifts, operators, and other necessary items to load, unload, and move equipment or material as required to pursue and complete the work whether owned by the Government or by the Contractor, unless specifically stated otherwise. This includes but is not limited to providing an air, electrical, or battery operated

SECTION 01 10 00 Page 6 fork lift and portable crane for loading, handling, and moving materials and equipment which are not accessible by the powerhouse cranes. Rail access and barge unloading facilities do not exist.

1.13.3 Area Lighting

The Contractor shall provide all lighting necessary to perform the work and provide a safe work environment.

1.14 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS

The GQAR shall be informed immediately of any damaged equipment or other conditions involving additional work in which the Contractor believes he has no responsibility. The failure or abnormality shall not be disturbed until witnessed by the GQAR. Any damage or abnormal conditions not reported as specified above but discovered at a later date, shall be corrected at the Contractor’s expense.

1.15 PROTECTION OF MATERIAL AND WORK

Materials, supplies, tools, equipment, and Government property (including all tools, equipment, and special devices supplied by the Contractor and to be turned over to the Government at the end of the contract) shall be protected and preserved in accordance with manufacturer’s recommendations.

If material, equipment, supplies, and work performed are not adequately protected, such property may be protected by the Government and the cost thereof will be charged to the Contractor or deducted from payment due.

The Government and the Contractor shall survey and verify the existing conditions and damage to existing facilities prior to the start of the work. The Contractor is responsible for the removal of all stains and residues, and the repair of damage to structures and equipment caused by construction activities. All existing Government property and powerhouse equipment shall be protected from damage at all times.

1.16 GAS, VAPOR, FUME, DUST, AND MIST CONTROL INSIDE AND OUTSIDE POWERHOUSE

All necessary measures shall be taken to effect control of all gases, vapors, fumes, dusts, and mists created by Contractor activities under this contract. All dust and dirt shall be removed by wet vacuuming or wet sweeping unless otherwise approved by the GQAR. The Contractor shall submit a Gas, Vapor, Fume, Dust, and Mist Control Program to the Government. The required control program shall include the following:

a. Provision of exhaust where mechanical ventilation is used.

Ventilation systems shall comply with requirements of 29 CFR 1910.94 and 29 CFR 1926.57. Utmost care shall be taken for control of existing asbestos and lead contaminants. See Sections 01 35 26, 01 57 19, 02 82 13, and 02 83 13.

b. Controlled operation of power-driven tools.

c. Furnishing and removing of approved dust preventatives in areas which cannot be properly rendered free from excessive dusting by vacuum cleaning or other methods.

d. Vacuum cleaning (or other method approved by GQAR) of spaces within the powerhouse where dust accumulates.

e. Methods to prevent exposure of employees to inhalation, SECTION 01 10 00 Page 7 ingestion, skin absorption, or contact with any material or substance at concentrations above those specified in 29 CFR 1910.1000, 29 CFR

1926.55 and .58.

f. Dust, mists, and fumes outside the powerhouse shall be controlled to prevent entry through doors, air handling systems, and air intakes.

1.17 DRAWINGS AND MANUALS

Existing drawings and manuals required for the work will be available for viewing, during normal project day shift working hours, from 7:00 a.m. to 3:30 p.m. Monday through Friday. Drawings and manuals shall not be removed from the office.

1.18 PROJECT MANAGER, SUPERINTENDENT AND PERSONNEL

1.18.1 Project Manager/Contractor's Agent Qualifications

The Contractor shall employee a Project Manager for this contract who shall be have full authority to negotiate and sign all contract modifications.

The Project Manager shall have a minimum of 2 years experience in project management of the replacement or refurbishment of overhead gantry cranes of 25 tons or greater capacity. A verifying contact, name, and phone number shall be provided for at least two such facilities. The Project Manager shall possess a 4-year bachelor's degree from an accredited university in either engineering or construction management. The Project Manager's qualifications, experience, a verifying contact, name and phone number, shall be submitted not less than 30 days prior to start of any work. The Project Manager shall be fluent in the spoken and written English language. The Contractor shall keep a competent authorized designee, fully authorized to act for him in his absence, and to receive such orders as may be given for the proper continuance of the work. Written notice to do any work, to alter any work, or to cease work which the Contractor is obligated to do, or concerning any imperfections in work or any material furnished, when given to the project manager in charge of the work shall be considered as notice to the Contractor. The Project Manager shall not serve as the SSHO or CQC System Manager. The Project Manager may serve as both the Project Manager and Superintendent if meeting all all contract requirements for both positions and if duties for both positions are satisfactorily performed.

1.18.2 Contractor’s Superintendent Qualifications

The superintendent shall have a a minimum of 3 years experience in gantry cranes of 25 tons or greater capacity. The Superintendent shall be present at the site at all times during work and shall be responsible for providing complete and correct direction of all construction activities, the initial starting, and all subsequent operation of the equipment until tests are completed. The superintendent shall be responsible for following the project's Safe Clearance Procedure. The superintendent shall initiate instructions for all actions necessary for the proper inspection, handling, assembly, and testing of the equipment. The superintendent shall keep a daily record of all work accomplished and all measurements taken during construction activities and shall provide copies on request or on completion of installation of the equipment associated with one generating unit. The superintendent, in conjunction with the CQC System Manager, shall keep all as-built drawings current and provide copies upon completion of the work as directed in Section 01 78 00. The superintendent shall report immediately in writing to the Contracting Officer any work not in

SECTION 01 10 00 Page 8 accordance with the manufacturer's recommendation or any special conditions which may result in completion of work not meeting the requirements of the contract. The superintendent shall be fluent in the spoken and written English language. The Superintendent's qualifications, experience, a verifying contact, name and phone number, shall be submitted not less than 30 days prior to start of site work.

1.18.3 On-Site Engineer

A Commissioning Engineer from the crane manufacturer shall be onsite during final setup and all testing. The Commissioning Engineer shall possess a four year bachelor's degree in engineering from an accredited university.

The Commissioning Engineer's qualifications, experience, a verifying contact, name, and phone number shall be submitted not less than 30 days prior to the start of the commissioning. The commissioning engineer shall perform no other duties onsite.

1.18.4 General Requirements for Contractor's Personnel

The Contractor shall prepare and revise (whenever organizational changes occur) a project organization chart with employee names and defining their work relationships. The Contractor shall maintain a complete organizational chart of all positions that will be working on the project.

All personnel employed by the Contractor shall be fully qualified in their respective fields to render the services necessary. The Contractor’s organizational plan shall be maintained in the CQC Plan and submitted as directed by the GQAR. If non-English fluent workers are employed on the project, the Contractor shall have a bi-lingual member on the team.

1.19 USE OF EXISTING TAILRACE (DRAFT TUBE) CRANE

1.19.1 General

The Contractor shall cooperate with the Government in the use of the existing tailrace (draft tube) crane for scheduled and emergency project maintenance. The Government shall have priority use of the crane in emergency conditions. The draft tube crane shall remain in service until the new draft tube crane has been installed and successfully tested. No other Government cranes or lifting devices will be available for use by the Contractor.

1.19.2 Operators and Riggers

1.19.2.1 General

The Contractor shall provide riggers for the duration of the on-site work.

1.19.2.2 Contractor Riggers

Qualified riggers shall be furnished for lifting and in attaching loads to the crane. An affidavit stating the riggers qualifications shall be furnished upon request by the GQAR. The affidavit shall include a complete record of all related experience and be signed by the rigger and the Contractor. Riggers' knowledge of hand signals shall be checked by the Government.

1.19.3 Lifting Devices and Special Handling Equipment

The Government will furnish no lifting devices. All lifting devices and

SECTION 01 10 00 Page 9 special handing equipment shall be provided by the Contractor and shall be turned over to the Government upon completion of the contract. All lifting devices shall rated for at least 125% of the load. Slings shall be new and furnished by the Contractor.

1.20 TEMPORARY FACILITIES

Temporary facilities provided during construction shall be removed prior to final payment.

1.21 PROTECTION AND RESTORATION OF EXISTING FACILITIES

All existing facilities shall be protected, whether or not shown on the drawings. Upon completion of the work, all existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.

1.22 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

The Government will limit interference with the Contractor's work to a reasonable extent and the Government and Contractor shall coordinate as necessary.

1.23 SCAFFOLDING

The Contractor shall furnish and install all necessary scaffolding.

Approved antislip surface material shall be installed on scaffolding platforms. Scaffolding shall comply in every respect with EM 385-1-1. Any scaffolding, ladder, stairway, or other access methods which is not covered or in compliance with EM 385-1-1 shall be submitted by the Contractor for written approval by the Contracting Officer GQAR prior to use.

1.24 NOISE CONTROL

Noise control and noise levels shall conform to requirements set forth in the appropriate regulations, including EM 385-1-1, Section 05.C, 29 CFR 1910.95, 29 CFR 1926.52 and .101. The most stringent requirement shall govern.

1.25 FIRE CONTROL

All fire fighting equipment, supplies, and personnel shall be supplied by the Contractor in accordance with EM 385-1-1, Section 09, 29 CFR 1910 SUBPART L and 29 CFR 1926 SUBPART F. The Contractor shall provide properly rated fire lockers for storage of flammable materials.

1.26 BARRICADES AND DANGER, DETOUR, AND WARNING SIGNS

1.26.1 Barricades and Danger and Detour signs

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, and detour and other signs; provide a sufficient number of watchmen; and take all necessary precautions for the protection of the work and the safety of the public.

Powerhouse galleries, floors, project roads, etc. partially obstructed or closed to traffic shall be protected by effective barricades. Obstructions

SECTION 01 10 00 Page 10 shall be continuously illuminated day and night. Suitable warning signs shall be properly illuminated day and night. The signs, signals, and barricades shall comply with EM 385-1-1 SECTION 08, 29 CFR 1910.145 and 29

CFR 1926 SUBPART G.

1.26.2 Warning Signs

Warning signs shall be erected 500 feet in advance of any place on the project where operations interfere with the full, normal use of a road by traffic. Warning signs shall conform to the standards established in Part IV of the MUTCD.

1.27 PROJECT SECURITY AND SITE WORKING HOURS

1.27.1 Security

The security of the Contractor's property and items furnished under this contract are the Contractor’s responsibility, until installed, tested, and accepted, whether stored inside or outside the powerhouse and/or security areas.

1.27.2 Government Project Personnel Working Hours

The scheduled working hours of the Government project personnel are Monday through Thursday 6:00 a.m. to 4:30 p.m. Federal holidays, Saturdays and Sundays are non-work days. Project personnel support required by the Contractor may be scheduled other than Project staff working hours but must be coordinated with and approved by the Government at least 24 hours before the support is required.

1.27.3 Contractor's Working Hours

The Contractor's work schedule shall not exceed one shift, five (5) days per week, ten (10) hours per day and shall be coordinated with the Contracting Officer. All federal holidays and Sunday's shall be non-work days. Notification of any proposed changes to the work schedule shall be submitted to the Contracting Officer for approval.

1.28 WEEKLY COORDINATION MEETINGS

Once each week, a coordination meeting shall be held between the Contractor and the Government. This meeting will be used to discuss the Contractor’s proposed schedule, actual progress in the last week, and work planned in the up coming week. A meeting time and place shall be mutually agreed upon. The Contractor shall submit Weekly Coordination Meeting Minutes within three working days, to the GQAR.

1.29 PERMITS AND RESPONSIBILITIES

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence, and shall take proper safety and health precautions to protect the work, the workers, the public, and property of others. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any work which may have been

SECTION 01 10 00 Page 11 accepted under the contract.

1.30 TOOLS AND MISCELLANEOUS EQUIPMENT AVAILABLE FOR CONTRACTOR’S USE

1.30.1 General

Government tools and equipment in the powerhouse are not available for use. The Contractor shall provide all tools.

1.30.2 Contractor Furnished Tools

Any special tool, item of equipment, or lifting/handling device or devices required for the work which is not furnished by the Government shall be furnished by the Contractor. Any special tool, lifting device, or item of equipment utilized by the Contractor for this work which may be needed for maintenance activities (including equipment disassembly & re-assembly) shall remain the property of the Government. Special tools are defined as non-standard or unique tools necessary to perform disassembly or re-assembly of the newly installed equipment.

1.30.3 Damage to Tools

Any Government or Contractor furnished tool, item of equipment, and lifting device (which will be left at the site) damaged during the performance of this work shall be repaired or replaced.

1.30.4 Protective Coatings

Protective coatings, including Cosmoline grease, shall be removed from the above applicable items prior to use. Upon completion of the work to be performed under this contract, all protective coatings, including painted surfaces, shall be returned to a satisfactory condition suitable for long-term storage.

1.31 GENERATING UNIT AVAILABILITY AND ACCESS

Generating units will be in service during this contract. Should the contractor need the overhead lines to be de-energized during installation of the new crane or removal of the existing crane, the Contractor shall provide the Government 30 days advanced notice before de-energizing the overhead lines is necessary. The Government will arrange for the unit outages. An attempt will be made to make the unit available on the dates the Contractor desires and in accordance with the Contractor’s repair schedule. The order of unit outage shall be coordinated with the GQAR.

The first day of unit availability shall not be a weekend day. Unit overlap in work activities may be permitted at the discretion of the Government if conditions (such as a period of low water, low generation need, etc.) allow.

1.32 DISPOSAL AND SALVAGE OF EQUIPMENT AND MATERIALS

1.32.1 Disposition of Material and Equipment

Title to all materials and equipment to be disposed of, excepting salvage items, is vested in the Contractor upon receipt of signed contract and such materials and equipment are designated scrap only as directed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed. The Contractor may retain these items in usable form and take possession of them providing that there is no

SECTION 01 10 00 Page 12 subsequent cost or inconvenience to the Government. The Government does not guarantee that these items are complete or in working order, and the Contractor shall assume responsibility for any damages caused by their use immediately upon taking possession of them. Scrap materials shall be removed from the Government's property within 90 days of removal.

Materials and equipment shall not be sold on the site. Disposal of hazardous wastes shall be in accordance with other sections of these specifications.

1.32.2 Salvage

The Contractor shall dispose off Government property all materials and equipment removed from the project.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

-- End of Section --

SECTION 01 10 00 Page 13

SECTION 01 11 00

SUMMARY OF WORK

08/11

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the other Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes the removal and replacement of the existing draft tube gantry crane at Robert S. Kerr and incidental related work. The existing gantry crane has a rated capacity of 30-tons. The new crane will have a rated capacity of 40-tons. The work includes, but is not limited to;

removal and disposal of the existing 30-ton capacity gantry crane, design, fabrication, installation, and testing of the replacement 40-ton capacity gantry crane and lifting beam. There is an optional bid item for removing the rigid conductor existing electrification system.

1.2.2 Location

The work is located at the Robert S. Kerr Dam approximately five miles south of Sallisaw, Oklahoma on Oklahoma State Highway 59, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

The Powerhouse will be occupied during performance of work under this Contract. The scheduled working hours of the Project staff at the Robert S.

Kerr Dam power plant are Mondays through Thursdays from 6:30 a.m. until 5:00 p.m. Fridays, Saturdays, Sundays, and Federal Holidays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours, unless otherwise specifically approved. Work outside of normal facility hours must be coordinated and approved by the Administrative Contracting Officer. Provide requests to work outside of normal facility hours to the Contracting Officer a minimum of 10 days prior to the proposed days of work outside of the normal schedule.

Before work is started, the Contractor shall arrange with the Administrative Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain. Repair or

SECTION 01 11 00 Page 1 replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 2

SECTION 01 32 16

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Construction Schedule; G

SD-07 Certificates

Monthly Updates

1.2 ACCEPTANCE

Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Network Analysis Schedule (NAS).

The acceptance of a Baseline Construction Schedule is a condition precedent to:

a. The Contractor starting work on the demolition or construction stage(s) of the contract.

b. Processing Contractor's invoice(s) for construction activities/items of work.

c. Review of any schedule updates.

Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).

1.3 SCHEDULE FORMAT

1.3.1 Network Analysis Schedule (NAS)

Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6 or Microsoft Project 2010. Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule. Build the schedule as follows:

a. The Project Schedule must show submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, SECTION 01 32 16 Page 1 inspection, testing, and closeout activities. Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.

b. With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended; each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.

c. Each activity must be assigned its appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.

d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.

Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".

1.3.1.1 Primavera P6 Settings and Parameters

Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.

a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.

b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:

(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.

(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.

c. Project Level, Dates Tab:

(1) Set "Must Finish By" date to "Contract Completion Date".

d. Project Level, Defaults Tab:

(1) Duration Type: Set to "Fixed Duration & Units".

(2) Percent Complete Type: Set to "Physical".

(3) Activity Type: Set to "Task Dependent".

(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.

SECTION 01 32 16 Page 2

Alternative calendars may be used with Contracting Officer approval.

e. Project Level, Calculations Tab:

(1) Activity percent complete based on activity steps: Must be Checked.

(2) Reset Remaining Duration and Units to Original: Must be Checked.

(3) Subtract Actual from At Completion: Must be Checked.

(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.

(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.

f. Project Level, Settings Tab:

(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".

g. No on-site construction activity may have durations in excess of 20 working days.

1.3.1.2 Microsoft Project 2010 Settings and Parameters

The Network must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 20 working days.

1.3.1.3 Cost Loading Microsoft Project 2010 Schedules

Assign material, labor and equipment costs to their respective Construction Activities. Material and equipment costs for which payment will be requested in advance of installation must be assigned to their respective procurement activity (i.e. the material/equipment on-site activity).

Evenly disperse overhead and profit to each activity over the duration of the project. Cost loading must total to 100 percent of the value of the contract.

a. Submit an Earned Value Report with each schedule update showing activity budget, cost percent complete, earned amount and cost to complete as directed by the Contracting Officer.

b. With each schedule submission, provide a Schedule Variance control (SVC) diagram showing:

(1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates.

(2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.

1.3.2 Schedule Submittals and Procedures

Submit Network Analysis Schedules (NAS) and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.

SECTION 01 32 16 Page 3

1.4 SCHEDULE MONTHLY UPDATES

Update the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.

a. Narrative Report: Provide with schedule updates. Identify and justify;

(1) Progress made in each area of the project

(2) Critical Path

(3) Date/time constraint(s), other than those required by the contract

(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path

(5) Status of Contract Completion Date and interim milestones;

(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);

(7) Description of current and future schedule problem areas.

Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.

1.5 CONTRACT MODIFICATION

Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.

a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party, describe how it originated, and how it impacts the schedule. The schedule submission must consist of three native files:

(1) Fragnet used to define the scope of the changed condition

(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.

(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is determined.

SECTION 01 32 16 Page 4

b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after the data date of schedule update used.

c. All TIAs must include any mitigation, and must determine the apportionment of the overall delay assignable to each individual delay. The associated narrative must clearly describe the findings in a chronological listing beginning with the earliest delay event.

(1) Identify types of delays as follows:

(a) Excusable Delay: Force-Majeure (e.g. weather) - Contractor may receive time extension, but time will not be compensable.

(b) Inexcusable Delay: Contractor Responsibility - Contractor will not receive time extension.

(c) Compensable Delay: Government Responsibility - Contractor may receive compensable time extension.

(2) If a combination of any of the delay types outlined above occurs, it is considered a Concurrent Delay, which will require an analysis of the facts to determine compensability and entitlement to any time extension under the applicable contract clauses.

d. Submit Data disks containing the narrative and native schedule files.

e. Unless the Contracting Officer requests otherwise, only add conformed contract modifications into the Project NAS.

1.6 3-WEEK LOOK AHEAD SCHEDULE

Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.

Key the work plans to activity numbers when a NAS is required and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, and review during the weekly CQC Coordination or Production Meeting.

1.7 CORRESPONDENCE AND TEST REPORTS:

All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.

1.8 ADDITIONAL SCHEDULING REQUIREMENTS

Any references to additional scheduling requirements, including systems to

SECTION 01 32 16 Page 5 be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to all requirements of…