Solicitation No. W912BV18R0022

US Army Corps of Engineers Tulsa District Red River Watershed Lake Texoma, Texas

Install Transformer, Bus, and Switchgear

Specifications

June 22, 2018

TABLE OF CONTENTS SOLICITATION

NO. W912BV18R0022

INSTALL TRANSFORMER, BUS, AND SWITCHGEAR

LAKE TEXOMA, TEXAS

JUNE 22, 2018

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00.00 40 SUMMARY OF WORK

01 22 00.00 26 MEASUREMENT AND PAYMENT

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 46 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 58 00 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE (O&M) DATA

DIVISION 02 - EXISTING CONDITIONS

2 83 20.00 25 LEAD BASE PAINT (LBP) ABATEMENT, REMOVAL AND DISPOSAL

DIVISION 03 - CONCRETE

3 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND

EQUIPMENT FOUNDATIONS

DIVISION 05 - METALS

05 50 03.00 26 METALWORK FABRICATION, MACHINE WORK, AND

MISCELLANEOUS PROVISIONS

05 50 04.00 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP

FABRICATED ITEMS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL

EQUIPMENT

DIVISION 26 - ELECTRICAL

26 05 00.00 26 GENERAL ELECTRICAL

26 05 13.00 26 MEDIUM-VOLTAGE CABLE

26 05 19.00 26 INSULATED WIRE AND CABLE (2000 Volts and Below)

26 08 01.00 26 SYSTEMS TESTING AND COMMISSIONING

26 13 13.00 26 METAL-CLAD SWITCHGEAR

26 24 19.00 26 MOTOR CONTROL CENTERS

26 25 00.00 26 BUS STRUCTURES

-- End of Project Table of Contents --

TOC-1

DOCUMENT 00 41 10 Page 1

SECTION 00 41 10

PRICING SCHEDULE

ITEM

DESCRIPTION

ESTIMATED

QUANTITY

UNIT

UNIT

PRICE

AMOUNT

BASE BID

0001 Remove Transformer Bank 1 1 Job XXXX $ (3 single Phase GSU Transformers)

0002 Remove Transformer Bank 2 1 Job XXXX $

(3 single Phase GSU Transformers)

0003 Remove Existing Single 1 Job XXXX $ phase spare GSU Transformer

0004 Remove and Dispose of 40,000 Gal. $ $ Transformer Insulating Oil

0005 Remove Existing Unit 1 1 Job XXXX $ 15 kV Switchgear

0006 Remove Existing Unit 2 1 Job XXXX $

15 kV Switchgear

0007 Furnish New 15 KV 1 Job XXXX $ Unit 1 Switchgear (SJ1)

0008 Furnish New 15 KV 1 Job XXXX $

Unit 2 Switchgear(SJ2)

0009 Install New 15 kV Main 1 Job XXXX $ Unit 1 Switchgear (SJ1)

0010 Install New 15 kV Main 1 Job XXXX $

Unit 2 Switchgear (SJ2)

0011 Remove Existing Unit 1 1 Job XXXX $ Isolated Phase Bus

0012 Remove Existing Unit 2 1 Job XXXX $

Isolated Phase Bus

0013 Furnish and Install New 1 Job XXXX $ Unit 1 Metal Enclosed Bus

0014 Furnish and Install New 1 Job XXXX $

Unit 2 Metal Enclosed Bus

0015 Furnish New Relay 2 Each $ $ Panels for Main Board (Transformers 1 and 2)

DOCUMENT 00 41 10 Page 2

0016 Furnish And Install New 1 Job XXXX $ Motor Control Centers (CQT1 and CQT2)

0017 Make external Connections 2 Each $ $ to New GSU Transformers

0018 Modify Transformer Pedestals 2 Each $ $

0019 Remove Existing Deluge Piping 2 Each $ $

0020 Clean insulating oil tanks 1 Job XXXX $

0021 Disposal of Transformer Bushings containing PCBs 1 Job XXXX $

TOTAL BASE $

OPTION

0022 Asbestos Abatement 120 Hours $ $ to include sampling, disposal, and record keeping

TOTAL OPTIONAL ITEMS $

TOTAL $

Option may be exercised, at the option of the Government, at the time of contract award up to 1 calendar year after the date of contract award.

-- End of Document -

SECTION 01 11 00.00 40 Page 1

SECTION 01 11 00.00 40

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY OF WORK

The work to be performed under this contract consists of providing the labor, equipment, and materials to remove the existing single phase GSU transformers, the 15 kV switchgear for units 1 and 2, the iso-phase bus between the generator and the transformers, make connections to the new three phase gas insulated transformers, install new segregated phase bus, install new non-segregated phase bus, install new 15 kV switchgear, provide new controls and relaying, furnishing new control room switchboard panels, furnish and install new motor control centers, and all the necessary auxiliary and ancillary equipment and systems required necessary to install the equipment at the Denison Powerhouse to make it fully operational. The new GSU power transformers are to be furnished by others with the external connections to be made under this contract as summarized below and as required in specifications and drawings.

The work includes electrical work and related work including, but not limited to, the following:

a. Remove and dispose of seven (7) single phase GSU transformers (2 three phase transformer banks and 1 spare) including oil, piping, cabling and conduit, equipment no longer to be used and the disconnection from the overhead transmission line.

b. Remove and dispose of the two 15 kV switchgear lineups (unit 1 and unit 2) including the cable and conduit no longer to be used.

c. Remove and dispose of the existing iso-phase bus for units 1 and 2 to include the sections from the generator to the switchgear and from the switchgear to the six GSU transformers.

d. Remove insulating oil from the existing "clean" and "dirty" insulating oil storage tanks and clean the tanks.

e. Remove the existing oil filled transformer nitrogen piping, fire suppression deluge piping, oil piping systems, and their support structures.

f. Design, manufacturer, test and deliver FOB Denison Powerhouse two new switchgear assemblies with all breakers and auxiliary equipment.

g. Design, manufacturer, test and deliver FOB Denison new segregated bus for connection between the generator main leads and the new 15 kV switchgear and non-segregated bus for connection of the new switchgear to the new GSU transformers.

h. Connect the power and control cables and conduits to the new Gas Insulated Transformers T1 and T2 on Denison Powerhouse tailrace deck (transformers are to be furnished and placed in location by others).

Connect the cable from the new high voltage transformer bushings to the

SECTION 01 11 00.00 40 Page 2 overhead transmission lines.

i. Modify the existing transformer pedestal. Design and install new transformer foundation to allow the transformer supplier to place the transformers in the final location. After the transformer is placed in its final location, weld and provide touchup paint.

i. Remove existing surge arresters and brackets and provide and install new mounting brackets and new surge arresters on the high voltage side of the new transformers.

j. Install, level, and test new 15 kV switchgear for units 1 (SJ1) and 2 (SJ2) including all cable and conduit connections to make the equipment fully operational both locally and remotely as well as connection of the 15 kV cable connections to the existing excitation system transformers and the existing station service transformer.

k. Install, adjust, level, and test new segregated phase bus from the new 15 kV switchgear to the existing generator main leads including the modification of the generator main leads to connect the new bus at the generator main floor to make it fully operational.

l. Install, adjust, level, and test new non-segregated phase bus from the new 15 kV switchgear to the new GSU transformers (provided by others) and connect to the low voltage bushings to make it fully operational.

m. Furnish, install, and test the new 480 VAC-120/208 VAC Power center.

n. Furnish, install, and test two new motor control centers to supply power to powerhouse auxiliary systems to include programming internally mounted PLC.

o. Furnish and install new grounding conductors to new equipment.

p. Layout, manufacturer, wire, test and deliver FOB Denison two new control room main board rear panels for replacement of the the existing transformer relay panels with new digital transformer relays. Panels to be installed by others based on Contractor provided installation wiring drawings.

q. Install all new wire, cables and raceway required to connect the new equipment and make it fully operational including remote operation, alarm and indication. Cables going to control room to be installed by Contractor but terminated on control room end by others.

r. Furnish and install all new raceways as required to install the new equipment including supports.

s. Furnish as-constructed drawings.

t. Furnish the services of manufacturer erecting engineers to supervise, direct the installation, and test the switchgear, bus, and motor control centers.

u. Perform field acceptance testing and commissioning in coordination with the GSU transformer field engineer for the new transformer. GSU transformer field engineer services to be furnished under GSU transformer supply contract.

SECTION 01 11 00.00 40 Page 3

V. Replace the neutral current transformers on each of the main unit generators.

w. As a an option provide industrial hygienist to perform asbestos survey and test suspected materials.

x. As an option, test, remove, and dispose of asbestos containing materials including all containment, packaging, and disposal costs.

Work shall be performed under the direction of a Certified Industrial Hygienist (CIH). The CIH shall be onsite as needed.

1.2 ATTACHMENTS

See photographs in "Attachments" at the end of this section for information only to assist in identifying and clarifying areas of work. These photographs are not intended to define the scope of the work.

Specifications and drawings shall take precedence over any conflict with these photographs.

1.3 SPECIFICATIONS AND DRAWINGS

Technical specifications in Divisions 01-48 listed in the Table of Contents cover the detailed requirements for the equipment and services listed in the schedule. The drawings listed on INDEX OF DRAWINGS, SHEET G-002 accompany this specification and are part thereof.

1.4 CHANGES IN SPECIFICATIONS AND DRAWINGS

The Government reserves the right to revise or amend the specifications and/or drawings prior to the date set for opening bids. Copies of such amendments will be furnished to all prospective bidders. If the revisions and amendments require material changes in quantities or prices bid, or both, the date set for bid opening may be extended to enable bidders the opportunity to revise their bids. The amendment will include an announcement of the new date for opening bids.

1.5 DEFINITIONS

a. Wherever in the specifications, or upon the drawings, the words "directed", "required", "ordered", "designated", "prescribed", or words of like import are used, it shall be understood that the "direction", "requirement", "order", "designation", or "prescription" of the Contracting Officer is intended, and similarly the words "approved", "acceptable", "satisfactory", or words of like import shall mean "approved by" or "acceptable to" or "satisfactory to" the Contracting Officer unless otherwise expressly stated.

b. Where "as shown", "as indicated", "as detailed", or words of like import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean "provided complete in place", that is, "furnished and installed". (FAR 52.236.21(b) and (c)).

c. Wherever in these specifications or upon the drawings, the words "Contracting Officer" (CO) or "Contracting Officer's Representative" (COR) are used, it shall be understood to also mean "Government" unless otherwise expressly stated.

SECTION 01 11 00.00 40 Page 4

d. Wherever in these specifications the acronym "GQAR" is used, it shall be understood to mean "Government Quality Assurance Representative", unless otherwise expressly stated.

e. Wherever in these specifications the work "weekend(s)" is used, it shall be understood to mean "Saturday, Sunday, and Federal Holidays", unless otherwise expressly stated.

f. Whenever in these specifications the word "Project" is used, it shall be understood to mean Denison Powerhouse.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

Attachments

FOR REFERENCE ONLY

The attached photos are for information only to assist in identifying areas of work and are not intended to define the scope of the work.

Specifications and drawings shall overule any conflict with the photos.

Existing Surge Arrester

Deluge piping to be removed

Existing fencing and gate. May be temporarily removed and replaced as necessary to perform work. Posts are mechanical anchored and not embedded in concrete

Existing oil piping

Existing transformers to be removed. 6 plus 1 spare.

EL. 545 - View of Transformers from parking lot

PPT low voltage cable Cable tray

15 KV cable tray for PPT primary cables and station service transformer primary cables.

Cables to be replaced. Ground cable to be added

Cable tray for control cables to be extended for new cables to enter new switchgear

Unit 1 Switchgear to be replaced

Existing Unit 1 Excitation System Power Potential transformer (PPT)

Access way to cable gallery

EL 528 Front view of Unit 1 switchgear (52G1 and 52S1)

Bus to be removed I/ \

Existing control cables to be replaced

PPT low voltage cable tray PPT low voltage cables to remain

Maintain distance from new Switchgear to existing power potential transformer no less than 3 ft.

15KV cable tray

Control cable tray to be extended to new switchgear to run new cables directly into switchgear

The existing concrete is rough chipped out at bottom edge. The existing concrete on floor and wall at edge shall be cut as required to ensure new switchgear maintains a minimum of 3 ft of clearance between equipment on right side.

Typical for both unit 1 and unit 2

EL 528 Front View Unit 1 Switchgear

Unit 1 Power Potential Transformer (PPT)

Main cable trays extending to below the Terminal Room

Unit 1 PPT low voltage PPT cable tray. Cables and tray to remain

Unit 2 control cable tray

Unit 2 Low voltage PPT cable tray

Unit 2 15 KV

Control cable Tray for Unit 1 switchgear to be extended into new switchgear

15 KV cable tray for unit 1

Aisle way into cable gallery under transformer deck

Unit 2 PPT

EL 528 Looking from Unit 1 switchgear to unit 2

Existing switchgear control cable to be removed

Iso Phase bus to be removed

Control cable to be extended into new

Location of existing transition from iso phase bus to generator main lead bus.

New bus to be extended to generator floor above

Main control cable trays which extend to room below Terminal Room

15 KV cables to station service transformer to be replaced

15 KV cable to PPT to be replaced

750 KVA Station Service Transformer

Unit 1 switchgear to be replaced

Unit 1 Power potential transformer (PPT)

Access door to cable gallery below transformer deck

EL 528 Looking from access door south to station service bay, Unit 1 on right

Existing Asbestos trays

Approximate location of deck penetration for Deluge piping to be used to run new power and control cables to new transformers

Iso Phase bus to

Approximate location of new Motor Control Centers CQ-T1 and CQ-T2

Insulating oil piping be removed

Existing spare nitrogen system to be removed

Space for cable trays and raceways

Typical nitrogen system piping to be removed from tanks to transformers

Location of new Power Center

CR-B1

15 KV cables to be removed

Transformer T1 Nitrogen system to be removed replaced

Gallery gutter. New unit 1 and unit 2 switchgear to be moved upstream toward generator so it does not span the gutter

EL 528 Cable Gallery - Rear view of Unit 1 switchgear looking south toward Station Service bay

Approximate location of new power center CR-B1

Bus to be removed

Typical nitrogen \piping to be removed from tanks to transformers

Cable tray and raceway to be removed

Cables to

Iso phase bus to be removed Access way to turbine room

Transformer T1 Nitrogen system to be removed.

EL 528 Cable gallery review view of unit 1 switchgear

Iso phase bus to be removed

Typical nitrogen piping to each transformer to be removed

Deluge piping to be modified for control and power cables to new transofmres

Insulating oil piping

Space available for installing raceways

15 KV cable and raceway

Typical control/power cable drops from each

Unit 2 switchgear

Transformer T2 Nitrogen system to be removed

Access way to turbine room

Asbestos trays removed

EL 528 cable gallery- Looking north from unit 1 to unit 2 i

Unit 2 PPT Low voltage cables to remain

Unit 2 PPT 15 KV cables to

PPT low

PPT 15 KV

.) J. J

Control cables and cable trays.

Cables to be removed and cable tray to be extended to run cable into new switchgear voltage cable tray

HIGH VOLTAGE

13800 vous

HIG!i VOLTAlGE

13800 vous

111111"''' 11 11111 11111 ii , ,,,,, Will

@!ltd*•)

J HIGH VOLTAGE

ClE!i 13800 VOlTS

Unit 2 Power Potential

EL 528 Front view of unit 2 switchgear

PPT low voltage cable tray

PPT 15 KV

cable to be replaced

Cable tray to be extended

15 KV cable tray to new switchgear The new switchgear to be moved upstream to be flush with cable gallery wall in rear. Distance from new Switchgear to existing power potential transformer to be no less than 3 ft.

PPT Low voltage cable to remain

Unit 2 Power Potential

EL 528 Front view of unit 2 switchgear

Space for new cable tray and raceways

Typical routing of Nitrogen system piping to transformers

Approximate location of deluge piping penetration of the transformer deck

Transformer T2 Iso Phase

Nitrogen piping to be removed from tanks to transformers

Transformer T2 Nitrogen system to

15 KV cable and raceway to be removed

EL 528 Cable Gallery Rear view of Unit 2 Switchgear

Unit 2 15 KV cables and raceway to be removed

Transformer T2 nitrogen

EL 528 Rear view of Unit 2 switchgear

Space available for new cable tray and conduits

Typical nitrogen pipng to

Iso Phase bus to be removed

Stairway down Asbestos cable tray

Spare transformer nitrogen

Approximate location of new motor control centers CQ-T1 and CQ-T2

Gallery Gutter

EL 528 Cable gallery View from Station Service Bay toward Unit 1-2

Ceiling deck joint drainage hoses.

New CQ-T1 and CQ-T2 to be place between deck joints

Typical nitrogen system piping to be removed from tank to transformer

Iso phase bus

Typical nitrogen system piping to be removed from tanks to transformers

Spare Transformer nitrogen system to be removed

Transformer T1 nitrogen

Stairway Down

Gallery Gutter

Space available for installation of the new Motor Control Centers CQ-T1 and CQ-T2. Mount away from wall out of gutter. Mount between the ceiling deck joints

EL 528 Cable Gallery- Approximate location of new Motor control centers

= =J =

I d

GI .. .. + - •

\ Existing breaker to be connected to supply the new motor control center CQ-T1

..ili5:1115:1111 :::ill I ::1111 ::::1111 :::111 lll l:::lll l::!lll::illl • 1115111511 atll5 -

4 •

' \ ' ",J' - ,u r· - \ 1111 :::111 1:::111 1:::111 1::

\ Jl:::fliS:l IS::IJJ

:;:111 1::111::111::1111

• - t m..a... [(· !:[3 !

DO NOT TOUCH

E l::Sllle:lll::lllS::

:::111::111:::111:::1111 • lll::!llll ::S!== •••;;;

- SWITCHES

I Existing breaker to be connected to supply the new motor control center CQ-T2

:::111:::1111 :::111 1::111

·····:::1 :::;111::: • ::111 1::1111 ::1111 ::111 1 111 1111 1551115511155 -

EL 528 Station Service 480 volt switchgear. Supply to new Motor control centers

Iso phase bus to be replaced iso phase bus/generator main lead bus transition housing

EL 528 Iso Phase bus transition compartment. Looking up from floor of el 528

Insulating barrier at floor of generator air housing.

New bus to be installed above this location and new insulating barrier to be provided

Generator Bus to be modified to connect to new non-segregated bus at approximatedly el 545

Iso phase bus - generator bus transition housing with cover removed

Coupling capacitors to be emoved and turned over to the Government

Iso Phase bus to be removed

Ceiling of EL 528 - View looking up to generator main leads from floor of elevation 528

Existing generator main leads.

To be modified to connect to new non-segregated bus.

Bus to be terminated in this location

The new non-segregated bus to be terminated above EL 545.

Modify the existing generator main bus to terminate to the bus

Existing insulating barrier to be replace to accommodate the new non-segregated bus

EL 545 Generator Main leads at air housing door

Generator main lead bus to be modify .

to connect to the new non-segregated bus. .

New Bus to terminate above the floor inside generator housing

Existing insulating barrier in floor of generator air housing

EL 545 Generator Main Leads. Looking toward floor

Main generator leads exiting generator

Location of terminals for new non-segregated bus

Existing insulating barrier floor

EL 545 Generator Main lead Bus with air housing door open

I

EL 545 Generator Neutral Bus and current transformers

Generator Neutral Current transformers.

Replace with different turns ratio

Three neutral current transformers to be replaced. Located inside generator air housing

EL 545 Generator neutral current transformers inside air housing

15 KV cable tray

15 KV cables to

750 KVA station service transformer

Two spare 15 KV breakers to be removed

EL 528 Turbine floor looking from unit 1 toward Station service bay mounting area for arrester discharge counters

Bus penetration through transformer pedestal, typ.

space between transformer rails and bus penetration

EL 545 - Powerhouse downstream wall

EL 545 - Transformer rail and spare transformer area

Existing transfer cart

EL 545 - Transformer rail and existing transfer cart replace surge arresters

If required due to layout changes, provide new drop from tension wire to arrester

Existing brackets and supports

EL 545 Deck - Existing Surge Arresters

Oil piping typical

Contractor may use the existing transfer cart. The Government makes no claims to its fitness for transferring transformers; Contractor is responsible to verify and analyze capacity for use.

EL 545 - Existing transformer transfer cart

Denison Install Transformer, Bus, and Switchgear FY18 DENISONTRNINST18

SECTION 01 22 00.00 26 Page 1

SECTION 01 22 00.00 26

MEASUREMENT AND PAYMENT

1.1 GENERAL INFORMATION

The payment for work described in the following paragraphs shall constitute full compensation for work required under the cited Bid Items, and such work shall include all items incidental to completion of the required work, whether specifically mentioned in these specifications or not. In the event any work is required by the specifications sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to and included in the contract prices and payments for the items listed in the price schedule. The word "provided" shall be understood to mean "furnished and installed" when used in this section or elsewhere in the technical sections.

1.2 MEASUREMENT

Items measured as a "Job" will be measured for payment as a lump sum in the locations indicated. This measurement includes all incidental work and materials such as fittings, fasteners, and electrical materials that are necessary to make a complete installation. Unless the payment item paragraph makes a specific exception of any item, incidental items will not be measured under any other item even though there is another listing for the work or material.

1.3 PAYMENT

1.3.1 Base Bid

Item 0001 Remove Transformer Bank 1 (3 single Phase GSU Transformers)

Payment to Disconnect the external electrical and mechanical connections, drain oil, handle residual oil, and remove and dispose of the existing three single phase transformers from the Denison Project will be paid for under Item 0001 "Remove Transformer Bank 1 (3 single Phase GSU Transformers)" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, material, and labor required to disconnect, remove from the site and dispose of the existing three single phase oil filled transformers at the Denison Project for transformer Bank 1.

Item 0002 Remove Transformer Bank 2 (3 single Phase GSU Transformers) three single phase transformers from the Denison Project will be paid for under Item 0002 "Remove Transformer Bank 2 (3 single Phase GSU Transformers)" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, material, and labor required to disconnect, remove from the site and dispose of the existing three single phase oil filled transformers at the Denison Project for transformer Bank 2.

SECTION 01 22 00.00 26 Page 2

Item 0003 Remove Existing Single Phase Spare GSU Transformer spare single phase GSU transformer from the Denison Project will be paid for under Item 0003 "Remove Existing Single Phase GSU Transformer" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor required to disconnect, remove from site and dispose of the existing single phase spare transformer at the Denison Project.

Item 0004 Remove and Dispose of Transformer Insulating Oil

Payment to Remove and Dispose of Transformer Insulating Oil will be paid for under Item 0004 "Remove and Dispose of Transformer Insulating Oil".

Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor to remove the oil from the insulating oil tanks in the powerhouse and to and transport the oil to approved disposal facilities, to include acceptance of disposal manifest. Quantity of oil listed is estimated and measurement will be per gallon.

Item 0005 Remove Existing Unit 1 15 kV Switchgear

Payment to Remove the Existing 15 kV Main Unit Switchgear for Unit 1 will be paid for under Item 0005 "Remove Existing Unit 1 15 kV Switchgear" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor to disconnect cable, raceways and bus and remove the switchgear, including all unused raceways, and wire and cable.

Item 0006 Remove Existing Unit 2 15 kV Switchgear

Payment to Remove the Existing 15 kV Main Unit Switchgear for Unit 2 will be paid for under Item 0006 "Remove Existing Unit 2 15 kV Switchgear" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor to disconnect cable, raceways and bus and remove the switchgear, including all unused raceways, and wire and cable.

Item 0007 Furnish New 15 KV Unit 1 Switchgear (SJ1)

Payment to furnish new main unit 15 kV switchgear for unit 1 will be paid for under Item 0007 "Furnish New 15 KV Unit 1 Switchgear (SJ1)" as a lump sum. Price and payment shall constitute full compensation for the design, manufacturer, factory testing and delivery FOB Denison Powerhouse a complete switchgear assembly for SJ1 including all required breakers, instrument transformers, and auxiliary equipment.

Item 0008 Furnish New 15 KV Unit 2 Switchgear (SJ2)

Payment to furnish new main unit 15 kV switchgear for unit 2 will be paid for under Item 0008 "Furnish New 15 KV Unit 2 Switchgear (SJ2)" as a lump sum. Price and payment shall constitute full compensation for the design, manufacturer, factory testing and delivery FOB Denison Powerhouse a complete switchgear assembly for SJ2 including all required breakers, instrument transformers, and auxiliary equipment.

Item 0009 Install New 15 kV Main Unit 1 Switchgear (SJ1)

SECTION 01 22 00.00 26 Page 3

Payment to install the Contractor furnished new main unit 15 kV switchgear for unit 1 will be paid for under Item 0009 "Install New 15 kV Main Unit 1 Switchgear (SJ1)" as a lump sum. Price and payment shall constitute full compensation for the setting of the new equipment, installing raceways, wire and cable, field testing to make a fully operational new switchgear assembly for unit 1.

Item 0010 Install New 15 kV Main Unit 2 Switchgear (SJ2)

Payment to install the Contractor furnished new main unit 15 kV switchgear for unit 2 will be paid for under Item 0010 "Install New 15 kV Main Unit 2 Switchgear (SJ2)" as a lump sum. Price and payment shall constitute full compensation for the setting of the new equipment, installing raceways, wire and cable, field testing to make a fully operational new switchgear assembly for unit 2.

Item 0011 Remove Existing Unit 1 Isolated Phase Bus

Payment to Remove the existing 15kV isolated Phase Bus for Unit 1 will be paid for under Item 0011 "Remove Existing Unit 1 Isolated Phase Bus" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor to remove this equipment, including all bracket and fasteners, for unit 1. Payment shall also include removal and disposal cost for lead based paint.

Item 0012 Remove Existing Unit 2 Isolated Phase Bus

Payment to Remove the existing 15kV isolated Phase Bus for Unit 2 will be paid for under Item 0012 "Remove Existing Unit 2 Isolated Phase Bus" as a lump sum. Price and payment shall constitute full compensation for the furnishing of all equipment, materials, and labor to remove this equipment, including all brackets and fasteners for unit 2. Payment shall also include removal and disposal cost for lead based paint.

Item 0013 Furnish and Install New Unit 1 Metal Enclosed Bus

Payment to furnish and install new 3000 A 15 kV Segregated Phase Bus and Non-Segregated bus for unit 1 will be paid for under Item 0013 "Furnish and Install Unit 1 Metal Enclosed Bus" as a lump sum. Price and payment shall constitute full compensation furnishing all equipment,labor, and materials to design, manufacturer, factory test, deliver FOB Denison powerhouse, install the bus including all parts for mounting and leveling the equipment, installing grounding conductors, field testing to make a complete assembly for the segregated bus between the generator and the switchgear and the non-segregated bus between the switchgear and the transformer for unit 1 including modification of the generator main lead bus and neutral CT replacement.

Item 0014 Furnish and Install New Unit 2 Metal Enclosed Bus

Payment to furnish and install new 3000 A 15 kV Segregated Phase Bus and Non-Segregated bus for unit 2 will be paid for under Item 0014 "Furnish and Install New Unit 2 Metal Enclosed Bus" as a lump sum. Price and payment shall constitute full compensation furnishing all equipment, labor, and materials to design, manufacturer, factory test, deliver FOB Denison powerhouse, install the bus including all parts for mounting and leveling the equipment, installing grounding conductors, field testing to make a complete assembly for the segregated bus between the generator and the

SECTION 01 22 00.00 26 Page 4 switchgear and the non-segregated bus between the switchgear and the transformer for unit 2 including modification of the generator main lead bus and neutral CT replacement..

Item 0015 Furnish New Relay Panels for Main Board Transformers 1 and 2

Payment to furnish new relay panels to replace the existing transformer protective relays on the main board in the control room will be paid for under Item 0015 "Furnish New Relay Panels for Main Board Transformers 1 and 2". Price and payment shall constitute full compensation for the design, manufacturer, factory testing and delivery FOB Denison Powerhouse complete relay panels to be installed by others. Measurement will be per panel.

Item 0016 Furnish And Install New Motor Control Centers (CQT1 and CQT2)

Payment to furnish and install new motor control centers CQT1, CQT2 and CR-B1 will be paid under Item 0016 "Furnish And Install New Motor Control Centers (CQT1 and CQT2)" as a lump sum. Price and payment shall constitute full compensation for the design, manufacturer, factory testing, delivery FOB Denison Powerhouse, installation, (including wire and cable), and field testing to provide a completely functional equipment for CQT1, CQT2 and

CR-B1.

Item 0017 Make External Connections to New GSU transformers

Payment to install all raceways and wire and cable to connect the new transformers to the new and existing equipment for Transformer T1 and T2 will be paid under Item 0017 "Make External Connections to New GSU transformers". Price and payment shall constitute full compensation for the installing all conduit systems and cabling from the new transformers to the new and existing equipment, install new surge arresters with brackets to make a complete operational system. Connection of the metal enclosed bus shall be made under the line item for installing the bus. Measurement will be made per transformer.

Item 0018 Modify Transformer Pedestals

Payment to remove the existing rails and grout on the existing pedestals and modifying the pedestals to accept the new transformers will be paid under Item 0018 "Modify Transformer Pedestals". Price and payment shall constitute full compensation for the work as required by the drawings and specifications. Measurement will be made per transformer.

Item 0019 Remove Existing Deluge Piping

Payment to remove the existing deluge and nitrogen piping Unit 1 and 2 will be paid for under Item 0019 "Remove Existing Deluge, oil and Nitrogen piping systems for transformers 1 and 2". Price and payment shall constitute full compensation for the furnishing of all equipment and labor to remove this equipment, including all brackets, and nitrogen bottles fittings. Measurement will be made per transformer bank.

Item 0020 Clean Insulating Tanks

Payment to clean the existing dirty and clean insulating oil tanks will paid under Item 0020 "Clean Insulating Tanks" as a lump sum. Price and payment shall constitute full compensation for the cleaning of the tanks and the removal of all materials used to clean the tanks.

SECTION 01 22 00.00 26 Page 5

Item 0021 Disposal of Transformer Bushings containing PCBs

Payment to package, remove and dispose of PCB containing transformer bushings will be paid under under Item 0021 "Disposal of Transformer Bushings containing PCBs" as a lump sum. Price and payment shall constitute full compensation for packaging, transportation to disposal facility and disposal of the bushings containing PCBs. Full payment will not provided until manifest indicating disposal has been received. Chain of custody manifests shall be provided if bushings have been offloaded prior to arrival to final disposal site.

1.3.2 Option

Item 0022 Asbestos Abatement Work

Payment to perform all asbestos abatement work will be paid under under Item 0022 "Asbestos Abatement to include sampling, disposal, and record keeping" per hour. The furnishing of material, labor, and equipment to perform asbestos abatement work is set forth in the contract specifications and will be paid at an all inclusive hourly rate. Rate shall include all costs for sampling, disposal, and record keeping under the direction of a

CIH.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 32 01 Page 1

SECTION 01 32 01

PROJECT SCHEDULE

02/15

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of two years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01 Page 2

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6 that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

SECTION 01 32 01 Page 3

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings/Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met. In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals

(individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O&M manuals.

SECTION 01 32 01 Page 4

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Performance Verification testing.

i. Other systems testing, if required.

j. Contractor's pre-final inspection.

k. Correction of punch list from Contractor's pre-final inspection.

l. Government's pre-final inspection.

m. Correction of punch list from Government's pre-final inspection.

n. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the RMS web site:

(http://rmsdocumentation.com)

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

SECTION 01 32 01 Page 5

Field Activity Code Length Description

*Some systems require activity code fields.

the specific software field requirements.

that FEATURE OF WORK values be placed in several The notation shown is for Primavera P6. Refer to guidelines with respect to the FEATURE OF WORK

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item

SECTION 01 32 01 Page 6

Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.

An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float

SECTION 01 32 01 Page 7 calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop seasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the

SECTION 01 32 01 Page 8

Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.