W912BV-15-R-0068-0006_Amendment_6_Complete.pdf
PDF 6 MB Posted
- Attached to
- AIR CONTROL GROUP SQUADRON OPERATIONS TINKER AFB, OK Federal contract opportunity
- Solicitation number
- W912BV-15-R-0068
About this file
Amendment 0006 re changes to specs/dwgs.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912BV-15-R-0068_Amendment_7.pdf | ||
| Amendment_5_to_W912BV-15-R-0068_re_due_date.pdf | ||
| Amendment_4_to_W912BV-15-R-0068_complete.pdf | ||
| Site_Visit_Attendance_Sheets_10-27-15.pdf | ||
| W912BV-15-R-0068_Amendment_0003.pdf | ||
| W912BV-15-R-0068_Amendment_2_complete.pdf | ||
| AMENDMENT_0001.pdf | ||
| 15-R-0068_DRAWINGS.pdf | ||
| W912BV-15-R-0068_AFR_513_Squad_Ops_Bldg.pdf | ||
| 15-R-0068_Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
513th Air Group facilities building at Tinker Air Force Base, Oklahoma (100% small business set-aside).
This amendment publishes specification and draw ing changes: see the follow ing pages.
The proposal due date (13 November 2015) remains the same.
1. CONTRACT ID CODE PAGE OF PAGES
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Nov-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-15-R-0068
X 9B. DATED (SEE ITEM 11)
08-Oct-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Nov-2015
CODE
CONTRACTING DIV
USACE, TULSA 1645 S 101 E AVE
TULSA OK 74128-4609
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BV-15-R-0068
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
AMENDMENT 0006
AIR CONTROL GROUP SQUADRON OPERATIONS
TINKER AIR FORCE BASE, OKLAHOMA
1. The revised/appendices/pages listed below are hereby added to or revised and made a part of the solicitation.
Revised or added/deleted information can be located in the specifications by searching for an asterisk and amendment number (i.e., *AM6).
Table of Contents 00 22 11 01 45 01.00 10 08 33 24 09 90 00
2. Delete the following drawings and replace with the attached revised drawings:
CS102 Site Layout Plans – Bid Options A-201 Exterior Building Elevations A-202 Exterior Building Elevations A-601 Finish Schedule I-222 Second Floor Furniture Plan – Area “B”
FX001 Fire Suppression Notes, Legend and Abbreviations S-313 Foundation Sections and Details 4 of 4 S-414 Foundation Sections and Details 5 of 5
Air Control Group Squadron Operations Tinker AFB, Oklahoma
81432
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 11 00 SF1442 AND PRICING (CLIN) SCHEDULE
00 21 00 INSTRUCTIONS TO OFFERORS
00 22 11 PROPOSAL SUBMISSION REQUIREMENT, EVALUATION CRITERIA
AND BASIS OF AWARD
00 45 00 REPRESENTATIONS AND CERTIFICATONS
00 72 00 CONTRACT CLAUSES
00 73 00 SPECIAL CONTRACT REQUIREMENTS
00 73 46 WAGE DETERMINATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 04 00 COORDINATION, FIELD ENGINEERING, AND MEETINGS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00.10 10 DIGITAL SUBMITTAL PROCEDURES AND CORRESPONDENCE
01 33 29 SUSTAINABILITY REPORTING
01 35 26.00 10 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 45 01.00 10 USACE QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 02.00 10 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01 57 20.01 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00.00 10 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN
01 60 00.00 50 MATERIAL AND EQUIPMENT
01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 70 00.00 10 CONTRACT CLOSEOUT
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.00 40 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 19 OPEN WEB STEEL JOIST FRAMING
PROJECT TABLE OF CONTENTS Page 2
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING AND WATER PROOFING
07 18 00 TRAFFIC COATINGS
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 21 19 SPRAYED POLYURETHANE FOAM (SPF) INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 55 00 PROTECTED MEMBRANE ROOFING (PMR) AND PAVER SYSTEM
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 33 13 METAL ROLLING COUNTER DOORS
*AM6 08 33 24 OVERHEAD COILING GRILLES*
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 44 00 WINDOW, CURTAIN WALL AND GLAZED ASSEMBLIES
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 65 66 RESILIENT ATHLETIC FLOORING
09 68 00 CARPET
09 83 13 ACOUSTICAL WALL TREATMENT
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 10 00 VISUAL COMMUNICATIONS SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 14 02 INTERIOR SIGNAGE
PROJECT TABLE OF CONTENTS Page 3
10 21 13 TOILET COMPARTMENTS
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 24 13 ROLLER WINDOW SHADES
12 48 13.13 ENTRANCE FLOOR MATS
12 65 00 FIXED SEATING
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 PLUMBING PIPING INSULATION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS
23 09 23 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 31 13.00 40 METAL DUCTS
23 34 23.00 40 HVAC POWER VENTILATORS
23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 27 13.10 30 ELECTRIC METERS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 32 33 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
PROJECT TABLE OF CONTENTS Page 4
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 31 16 SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL
31 63 26 DRILLED CAISSONS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 GRADED-CRUSHED AGGREGATE BASE COURSE
32 11 29 LIME-MODIFIED SUBGRADE
32 12 10 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23.00 20 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 11 00 WATER DISTRIBUTION
33 24 13 GROUNDWATER MONITORING WELLS
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 51 15 NATURAL-GAS DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
AFR 513th Air Squadron Operations Facility Tinker AFB, OK
00 22 11 - 1
Section 00 22 11 - Proposal Submission Requirements, Evaluation Criteria, Basis of Award One-Step-Best Value, Design-Build (Single Award)
PROPOSAL INSTRUCTIONS
SECTION 00 22 11
PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA
1. 0 OVERVIEW
This is a competitive best-value solicitation for a construction contract for the AFR 513th Air Squadron Operations Facility located at Tinker Air Force Base, OK. The Government will evaluate proposals in accordance with the criteria described herein and award a firm fixed-price contract to the responsible firm whose proposal conforms to all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government.
If awarded the contract, the Offeror shall construct the project in accordance with the plans and specifications.
1.1 WHO CAN SUBMIT
1.1.1 Firms formally organized as construction contractors that have associated specifically for this project, consortia of firms or any other interested parties may submit proposals. Associations may be as joint ventures or as key team subcontractors.
1.1.2 Organization Conflicts of Interest (OCI) Disclosure: The Offeror shall provide a disclosure statement with its proposal which concisely describes all the relevant facts concerning the past or present organizational conflicts of interest relating to work on this project. In the same statement, and if applicable, the Offeror shall provide information to assure the Government that the conflicts of interest have been mitigated and/or neutralized to the maximum extent possible. If a conflict of interest is discovered after award of this contract, the Contracting Office will make a decision whether to terminate the contract.
1.2 PROPOSAL SUBMISSIONS AND THE TRADE-OFF PROCESS
The trade-off process permits trade-offs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Offerors submit their performance and capability information for review and consideration by the Government. Relative weights among technical factors are provided in the paragraph entitled “Proposal Contents And Related Evaluation Factors”. The Source Selection Evaluation Board (SSEB) reviews, evaluates, and rates the proposals against the source selection criteria in the RFP. A competitive range consisting of the most highly qualified technical Offerors will be established prior to discussions (if held).
The SSEB will review, evaluate and rate the project technical proposals against the source selection criteria in the RFP. Concurrently, the Government analyzes price proposals utilizing the techniques listed in FAR Part 15 and the government’s project cost estimate. Price will not be rated, but will be considered in making trade-offs to reach the final best value determination for award. The Source Selection Authority (SSA) compares proposals to one another and determines the best value for the government. The perceived benefits of the higher priced proposal must merit the additional cost, and the rationale for tradeoffs must be documented.
2.0 BASIS OF AWARD
Proposals must meet the criteria stated in the RFP to be eligible for award, to include responsiveness, technical acceptability and responsibility.
2.1 To determine which proposal represents the best overall value, the Government may compare proposals to one another. The Government intends to award a contract to the responsible Offeror whose proposal conforms
00 22 11 - 2 to the solicitation, is fair and reasonable, and offers the best overall value to the Government, considering the non-price factors described herein, and price. All evaluation factors, other than price, when combined, are considered slightly more important than price. Best value will be determined by a comparative assessment of proposals against all source selection criteria in this RFP and the prices offered. The intent of this solicitation is to obtain the best proposal within the funds available. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in FAR 15.001.
2.2 Award will be made to the Offeror whose proposal is determined to represent the best overall value to the Government based on the evaluated ratings. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. If other than the lowest priced offer, the offer must be sufficiently more advantageous than the lowest priced offer to justify the payment of additional amounts.
2.3 The Government intends to award a contract without discussions based on initial proposals received;
therefore, proposals shall contain the Offeror’s best terms from a cost and technical standpoint. The Government reserves the right to conduct discussions in accordance with FAR 52.215-1. If discussions are necessary, the Government will establish a competitive range of the most highly rated offerors. The Government reserves the right to address any pertinent issues in the proposals.
3.0 GENERAL INSTRUCTIONS
3.1 Requirement for Separate Price and Technical Proposals
3.1.1 Each Offeror must submit both a Price Proposal and a Technical Proposal. The Price Proposal and the Technical Proposal must be submitted as separate volumes. Ensure the file containing each separate volume is clearly marked to indicate its contents; and the identity of the offeror.
3.1.2 Both the Price Proposal and the Technical Proposal must be received by the closing date and time set for receipt of proposals.
3.1.3 No dollar amounts from the Price Proposal are to be included in the Technical Proposal.
3.1.4 All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal. Do not merely cross-reference similar material in the Price Proposal, or vice versa. Also, do not include links to websites in lieu of incorporating information into your proposal.
3.1.5 Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the proposal may be determined "unacceptable" and thus ineligible for award. Any questions related to specific terms and conditions should be resolved prior to submission of the offer.
3.2 Where to Submit. Offerors shall submit their proposal to the Contract Specialist and Contracting Officer in accordance with Section 00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS.
3.3 Submission Deadline. Proposals shall be received by the Tulsa District no later than the time and date specified in Block 10 of Standard Form 1442 or on amendment form SF30, as applicable.
3.4 General Submission Requirements
3.4.1 In order to effectively and equitably evaluate all proposals, the Contracting Officer must receive information containing sufficient detail to allow review and evaluation by the Government. Proposal clarity, organization, and cross-referencing are mandatory. Failures to submit and organize proposals as requested may adversely affect a proposal's evaluation. Offerors should provide sufficient detail and clearly define all items required in this section.
00 22 11 - 3
The Contracting Officer may remove any Offeror from further consideration during any phase of the procurement if the proposal fails to meet the submittal requirements of the RFP, or to reduce the competitive range for purposes of efficiency pursuant to FAR 15.306(c)(2).
3.4.2 Tabs. Proposal shall be organized and tabbed as shown in paragraph 5.0, PROPOSAL CONTENTS AND
RELATED EVALUATION FACTORS, SUBFACTORS AND ELEMENTS.
3.4.3 Printed Matter Submission Requirements:
3.4.3.1 Proposals shall be submitted in accordance with the following:
a. Proposals shall be submitted in book-marked original ADOBE PDF file format.
b. Technical and Price Proposals shall be separate PDF files.
c. Proposals shall be tabbed and labeled in a manner to afford easy identification from a Table of Contents.
d. Font size shall not be less than 10 point. Do not use condensed font.
e. Margins shall be 1-inch wide (minimum) but may include headers and footers.
f. Each page shall be identified with the appropriate page number centered at the bottom of the page, except for the cover sheet, which shall not be numbered. Page number format for the Table of Contents shall be “i, ii, iii….”
g. Sheet size of the proposal contents shall be 8-1/2 inches x 11 inches where sheets are prepared specifically for this proposal; however, if drawings, charts, or other graphics are submitted, sheets no larger than 11 inches x 17 inches and folded to 8-1/2 inches x 11 inches shall be used. Eleven-by-seventeen (11 x 17) inch sheets will be counted as two 8-1/2 inch x 11 inch sheets.
h. Proposals shall not exceed 70 pages, excluding the cover sheet, tabs and Table of Contents. The
Government will not review any information submitted in an appendix or attachment to the proposal. The Government will not evaluate any information beyond the page limitation prescribed.
i. The Offeror shall not submit verbatim sections of this solicitation as part of their proposal.
3.4.3.2 Cover Sheet and Table of Contents.
a. Proposals shall contain a cover sheet containing the information shown below in accordance with FAR
52.215-1 “Instructions to Offerors – Competitive Acquisitions”.
00 22 11 - 4
b. Table of Contents. Each file shall include a detailed Table of Contents.
3.4.3.3 Proposals that do not meet the requirements unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation, receiving no further consideration.
3.4.4 Electronic Format: Proposals shall be submitted to the Contract Specialist and Contracting Officer as instructed in Section 00 21 00 in original PDF format using Adobe Acrobat software. Do not scan or copy the documents into a PDF file as copies are not searchable. Sections of the proposal shall be linked to the Table of Contents in logical order through use of bookmarks. The Table of Contents shall be displayed automatically when the PDF file is opened.
3.4.5 Number of Copies: Submit one original of of the technical and one original of the price volume in electronic format. If the proposal size exceeds 10MB, the proposal must be sent via AMRDEC Safe Download: see Section 00 21 00.
3.4.6 Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision, e.g., Error, Omission, or Clarification, or amendment shall be included and be annotated for each revision. Proposal replacement pages shall be numbered, shall be clearly marked “REVISED”, and shall show the date of revision.
4.0 SPECIFIC INSTRUCTIONS FOR THE PROPOSAL
4.1 Electronic Proposal Format. The Offeror shall submit the complete proposal in electronic format with the entire proposal in .pdf format using Adobe Acrobat software to print to a .pdf file (or “save as .pdf”); do NOT scan the document(s) into a .pdf file. The text portion of the complete proposal shall be contained as a single .pdf file.
Sections of the proposal shall be bookmarked (linked to the index) in logical order.
4.2 Format and Contents of the Proposal and List of Tabs. The proposal will be appropriately labeled and organized using the tabs specified in the chart below.
4.3 Page Limitations. The following page limitations are established for each Factor/Subfactor/Element:
Factor 1 – PERFORMANCE CAPABILITY Subfactor 1 - Specialized Experience – Limited to 20 pages (1 page per project; maximum 5 forms per contactor/subcontractor) Subfactor 2 – Key Subcontractors – Limited to 5 forms plus one letter per subcontractor Subfactor 3 –Key Personnel – Limited to 1 page plus one letter per key person
PROPOSAL COVER SHEET FORMAT:
Solicitation Number: W912BV-15-R-0068
Title: Renovate AFR 513TH Air Squadron Operations Facility, Tinker AFB, OK
Name, address, email address(es), and telephone number(s) of Offeror.
Company CAGE code, DUNS number and Federal Taxpayer ID number (TIN).
Names, titles, telephone, and email addresses of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation.
Name, title, and signature of person authorized to sign the proposal.
NOTE: Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
00 22 11 - 5
Subfactor 4 – Organization & Technical Approach – Limited to 10 pages
Factor 2 – PROPOSED CONTRACT DURATION & PRELIMINARY SCHEDULE – No page limitation.
Factor 3 - PAST PERFORMANCE – No page limitation.
Factor 4 – QUALITY OF MATERIALS - FURNISHINGS – Limited to 10 pages Factor 5 – PRICE – No page limitation
5.0 PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS
1st Most Important Factor
2nd Most important factor – Equal to Factor 3
2ND Most important factor – Equal to Factor 2
4th Most important factor
6.0 VOLUME 1 - TAB A – ASSUMPTIONS:
Deviations and exceptions to the requirements contained in the RFP are not allowed. Any questions related to specific terms and conditions of the solicitation must be resolved prior to submission of the proposal. However, if assumptions are made, the Offeror shall list and describe in detail the assumption(s). If award is made without discussions, an exception or deviation to any portion of the RFP requirements may make the proposal ineligible for award. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the proposal may be deemed “unacceptable” and thus ineligible for award. See paragraph 15.3, “Definitions”.
6.1 Submission Requirements
The list of assumptions shall be located under Tab A of Volume 1 – Technical Proposal Information. All assumptions shall be fully supported with the Offeror’s rationale and shall fully explain the impact, if any, on the performance and specific requirement of the RFP. The Offeror shall clearly describe on the Proposal Cover Sheet
VOLUME 1 – TECHNICAL PROPOSAL FOR (SOLICITATION NO.), (PROJECT TITLE) – 3-RING BINDER TAB A Assumptions Not Rated but may affect other factors
VOLUME 1 – FACTOR 1 - PERFORMANCE CAPABILITY
TAB B SUBFACTOR 1 Specialized Experience 1st –Most important subfactor TAB C SUBFACTOR 2 Key Subcontractors 2nd – Most important subfactor TAB D SUBFACTOR 3 Key Personnel 3RD – Most important subfactor TAB E SUBFACTOR 4 Organization & Technical Approach 4th – Most important subfactor
VOLUME 1 – FACTOR 2 - TAB F – PROPOSED CONTRACT DURATION & PRELIMINARY
SCHEDULE
VOLUME 1 – FACTOR 3 – TAB G - PAST PERFORMANCE
VOLUME 1 – FACTOR 4 – TAB H – QUALITY OF MATERIALS - FURNISHINGS
VOLUME 2 – PRICE AND PRO-FORMA FOR (SOLICITATION NO.), (PROJECT TITLE) – SEALED ENVELOPE
TAB A FACTOR 5 Price (Standard Form 1442 or SF30 & CLIN Schedule) Not Rated
TAB B N/A Bid Bond Not Rated
TAB C N/A Self-Performed Work 15% minimum
TAB D N/A Required Pre-Award Information Not Rated
00 22 11 - 6 submitted with the Price Proposal any assumptions made concerning contractual and/or technical terms and include the monetary impact on the solicitation with the price proposal.
6.2 Evaluation Criteria
The list of assumptions will not be rated separately but will be used to determine if the Offeror understands the Statement of Work and the intent and may affect the rating of the other factors. It will also be used to compare the impact on the performance of the project.
7.1 VOLUME 1 - FACTOR 1 – PERFORMANCE CAPABILITY
7.2 Volume 1 – Tab B – Subfactor 1, Specialized Experience
7.2.1 Submission Requirements
Demonstrate the specialized experience of the Offeror and/or proposed team, including sub-contractors, on projects same/similar in size and complexity to that described in the solicitation for same/similar construction services. Emphasis shall be placed on construction projects of similar scope, complexity and functionality. Building is for an approximately 32,000 sf, two-story Air Control Group Squadron Operations facility. Building design includes an Operations Desk, ORC Ops Office, OSF Aviation Manager Office, Storage, Large 250 person Briefing Room (Auditorium), Building Manager’s Office, Mobility Storage, Mobility Office, Medical Office, Flight Medical Exam Room, 970th AACS Command Suite, Conference Rooms, Special Projects Office; Heritage Room, Mission Planning Flight Deck Room, Pilot’s/Navigator’s Workroom, Flight Engineer Workroom, Physical Training Room, 513th ACG Command Suite, 513th OSF Command Suite, CVZ Room, Public Affair’s Office, Career Adviser’s office, Male and Female Latrine/Shower/Locker Rooms, Laundry Room and Janitor’s Closet, Standards Evaluation Testing, Air Battle Management Work Room and required building support spaces. A secure area will be provided for the 970th Tactics Classified Work Area, 513th OSF/970th Classified Mission Planning & Battle Staff Work Area, 513th
Classified Work Area, 970th Tactics Unclassified Work Area, 513th OSF Intel Unclassified Work Area and an Unclassified Storage Room. The classified spaces will be classified as “open storage.” Other sensitive work areas are also included. If using subcontractors as part of the proposed team to demonstrate experience, describe the role they will play in this project and the percentage of work they will perform. Demonstrate successful management of multiple subcontractors and multiple project phases within an occupied and operational facility for all projects submitted.
The Contractor shall complete a minimum of three (3), but no more than five (5), “Experience Information” forms, attached at the end of this section (Attachment 1), in response to this factor. All blocks must be filled in and all data should be accurate, current, and complete. All projects submitted must be at least 50% complete and completed within the last 5 years. At least two (2) of the projects provided must be valued at over $10,000,000.
7.2.2 Evaluation Criteria
7.2.2.1 The Government will evaluate the extent of recent, related experience of the Offeror in regard to their role on this project. The Government may place greater importance on projects performed as a prime contractor than as a subcontractor, depending upon overall role and relevancy considerations. Federal Government project experience on military installations for similar construction will be given more consideration than non-Federal Government project experience. Offerors demonstrating experience with projects of similar size and complexity will be viewed more favorably by the Government. All projects must demonstrate successful management of multiple subcontractors and multiple project phases.
a. The Offeror must submit the requested information to demonstrate a record of recent, related experience in construction, for the project (which may include similar state or local government or private counterparts) included in this solicitation. Recent experience includes projects well underway (see above criteria) or those completed and turned over within 5 years of the proposal issue date for this RFP for construction
00 22 11 - 7 experience. Joint Venture partners should each demonstrate experience commensurate with their role on this project or how their experience qualifies them for their role on this project. If any of the information required is not included in the form (Attachment 1), then the Contractor will be considered non-responsive and evaluated as unacceptable.
b. The Government reserves the right to verify the experience record of cited projects or other recent projects by reviewing the Corps of Engineers Construction Contractor (or Architect-Engineer) Appraisal Support System (CCASS/ACASS), other DOD or Government appraisal systems or to interview owners or references. The Government may check any or all cited references to verify supplied information.
c. To receive credit for extent (amount) of experience, the Offeror shall demonstrate a history of recent, relevant experience. A firm will not receive credit under this factor for the relevant experience of key personnel proposed for this project.
d. The Government will consider extent of recent experience, degree of relationship of such experience to this project, demonstrated familiarity with applicable codes and local conditions. Some examples of relevancy to this project may include, but not be limited to:
1) Number, size, type work, complexity, location
2) Dates (well under way or completed no more than 5 years preceding date of Solicitation)
3) Firm's role and extent of work self-performed (brokering out all work and simply “placing the sidewalks” or similar minor work on a cited project are examples of less relevant experience).
7.2 Volume 1 - Tab C – Subfactor 2 – Key Subcontractors
7.2.1 Submission Requirements
Identify the potential Key Subcontractors chosen for mechanical, electrical and process controls installation, describing the extent of their involvement in the project. Submit no more than five Specialized Experience forms (Attachment 1) for each Key Subcontractor, using the same requirements as described in the Specialized Experience submission requirements in this RFP. Subcontractors shall be selected from the list of potential subcontractors. Any substitutions shall be approved by the Contracting Officer. All subcontractor personnel working on this project must be U.S. citizens or documented U.S. workers and must be able to provide proof of U.S.
citizenship or other authorized documentation (See Contract Clause 52.0000-4515 Security Contract Language for All Corps of Engineers’ Unclassified Contracts).
Provide letters of commitment for each of the Key Subcontractors (Attachment 4).
7.2.2 Evaluation Criteria
This subfactor is composed of two equal elements: Specialized Experience and Past Performance. The Government will evaluate the specialized experience and past performance of the Key Subcontractors for mechanical, electrical, and process controls installation using the same criteria as in the Specialized Experience evaluation for the prime contractor under Factor 1, Subfactor 1, above, in this RFP. After award, the Section 00 73 00 SCR entitled “Key Personnel, Subcontractors and Outside Consultants” will apply to the selection, which establishes the minimum quality standard. No substitution will be allowed without adequate reason and possible consideration to the Government.
7.3 Volume 1 - Tab D – Subfactor 3 - Key Personnel
7.3.1 Submission Requirements
00 22 11 - 8
The Offeror shall provide resume data for the following key personnel: Construction Project Manager, Quality Control Manager (CQC System Manager), Project Scheduler, Site Superintendent, and Site Safety and Health Oficer (SSHO) as applicable to this requirement. Résumé information to be provided shall be limited to no more than one
(1) page per person (Attachment 2), not counting the letter of intent, and shall include the following information as a minimum:
a. Name and title
b. Project assignment
c. Name of firm with which associated
d. Years experience in the role identified.
e. Years experience with this firm and with other firms
f. Education degree(s), year, specialization, if applicable
g. Active professional registration, year first registered, if applicable
h. Other experience and qualifications relevant to same/similar work required under this contract
The minimum experience requirements for the Construction Project Manager and on-site superintendent shall be in accordance with Section 01 45 01.00 10 USACE QUALITY CONTROL. Minimum experience requirements for other personnel shall be as required by Division 01 sections. No substitutions will be allowed without the approval of the Contracting Officer.
Provide letters of commitment for each of the key personnel (Attachment 3).
All contractor and subcontractor working on this project must be U.S. citizens or documented U.S. workers and must be able to provide proof of U.S. citizenship or other authorized documentation.
7.3.2 Evaluation Criteria
The Government will evaluate the required information to determine how well the Offeror identifies and demonstrates that its key personnel meet or exceed minimum qualifications necessary to perform construction.
Project Managers with professional certification to include Project Manager Professional (PMP) or equivalent are preferred. Project Schedulers shall have a minimum of 10 years of experience preparing schedules on projects with similar scope and complexity as this RFP; experience preparing schedules complying with the requirements of Section 01 32 01.00 10 PROJECT SCHEDULE is preferred. Offerors providing resumes for key personnel for this project that have experience in similar key positions on the projects shown under Specialized Experience will be viewed more favorably by the Government. Performance of key personnel proposed for this project may be taken into account when it comes to the attention of the Government. If alternates are proposed for key positions, the evaluation rating will consider the lesser qualified or experienced person, if there is a difference.
7.4 Volume 1 - Tab E -Subfactor 4 - Organization & Technical Approach
7.4.1 Submission Requirements
7.4.1.1 Provide information that describes the offeror’s organization and intended technical approach to executing the construction contract per the detailed requirements herein. Limit the information to 10 pages or less; clearly but concisely describe the organizational and technical approach to project management and execution.
7.4.1.2 Organization: Describe what firms, their resources and how their resources will be utilized, their roles and responsibilities and any contractual arrangements that have been established. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. A copy of the teaming or joint venture agreement(s) may be appended to the plan (not included in the page limitation).
Include a simple organizational chart (may be 11”x17” foldout, counted as one page), illustrating the organization, including the proposed quality control group(s). Present a matrix of responsibilities for each firm in executing the key work breakdown structure activities of the project, including construction activities for each major feature.
00 22 11 - 9
Identify the firms chosen for the project, if not to be self-performed. Describe the proposed management structure for the team, describing how the construction process will be managed and the authorities and the delegations of authority within the team. Include a key personnel organization chart that clearly depicts the key positions and the names of the personnel, their firm affiliations and their job locations, their job/position title within the organization. The key personnel organization chart shall be consistent with the corporate organization chart, with the matrix of responsibilities assigned to the firms, and with the list of key personnel to be provided under the Tab, “Key Personnel”.
7.4.1.3 Planning and Scheduling: Describe the time control capabilities and systems to be used to plan construction and how the schedule will be used to manage construction. Discuss internal procedures for handling delays to minimize time growth or ”schedule creep”.
7.4.1.4 Self-Performed Work: Generally describe the items the offeror will self-perform to comply with the requirements in Section 00 72 00 for self-performed work.
7.4.1.5 Quality Control: Describe the team’s quality control approach, corporate systems and capabilities to maintain quality control of the construction. Describe the proposed quality control organization, including the proposed staffing plan. Provide information on how you will handle internal and external requests for information, shop drawings, progress meetings, site visits, contract completion, closeout, as-built, and completion documentation. There is no need to submit a quality control plan as the successful offeror will provide that after award.
7.4.1.6 Safety Plan: Describe the team’s safety approach, corporate systems and capabilities to maintain safety requirements during construction. Describe the proposed safety organization, including the proposed staffing plan.
The intent is to provide enough detail to demonstrate the Offeror’s understanding of the project; however, it is not the intent for the Offeror to provide the amount of detail that will be required in the pre-work submittals contained in Division 01 of this RFP. Not included in 10 page limitation. Limit Safety Plan narrative to two pages.
7.4.2 Evaluation Criteria
7.4.2.1 The Government will evaluate the strengths, weaknesses and any deficiencies in the plan. The Government will evaluate the firm’s understanding of the requirements described in the Division 01 requirements and the plans and technical specifications of the Solicitation and the capability to execute the project. Some additional specific evaluation considerations are listed below. This list is not all-inclusive.
7.4.2.2 Organization. The Government will evaluate the clarity and strength of the overall organization and how well it is organized, structured and staffed to execute the entire scope of work. If applicable, joint venture participants’ contribution to the organization should be commensurate with their skills and background.
7.4.2.3 Planning and Scheduling. The Government will evaluate the Offeror’s scheduling capabilities to manage an integrated schedule.
7.4.2.4 Self-Performed Work. The Government will evaluate the Offeror’s proposal to ensure that the self-performed work complies with the requirements of Section 00 73 00 for self-performed work.
7.4.2.5 Quality Control. The Government will evaluate the Offeror’s capabilities and understanding of the contractually required quality control processes for construction. The Government will evaluate the adequacy of the staffing plan to cover all required tasks and responsibilities.
7.4.2.6 Safety Plan. The Government will evaluate the narrative for realism, logic, and understanding of the contractual requirements in regard to the safety plan.
8.0 VOLUME 1 - FACTOR 2 - TAB F - PROPOSED CONTRACT DURATION AND PRELIMINARY SCHEDULE
00 22 11 - 10
8.1 Submission Requirements
8.1.1 Proposed Contract Duration. The Offeror shall propose the contract duration in the appropriate location in the CLIN Schedule (Section 00 11 00), not to exceed the maximum contract duration specified in Section 00 73 00 SPECIAL CONTRACT REQUIREMENTS, SCR entitled “Commencement, Prosecution, and Completion of Work”.
8.1.2 Preliminary Schedule. Submit a preliminary summary level schedule for construction of the work required including any construction phasing. Schedules or diagrams may be provided separately in a size that is easily read, but shall be bound and clearly labeled as Tab F. The preliminary schedule will, after contract award, be replaced with a final schedule as required by Section 01 32 01.00 10 PROJECT SCHEDULE. The schedules shall be task oriented, indicating the number of calendar days, after notice to proceed, by which milestones are to be achieved.
Offeror may use a critical path or other method of his choice; however, schedules shall be graphically represented.
The proposed project schedule shall reflect the contract duration (additional consideration will be given for a schedule that is shorter than the contract duration period if it is shown to be achievable does not incur additional cost to the Government). Give attention to the following features:
a. Provide narrative describing long lead item equipment that must be ordered and show the required ordering date in the schedule.
b. Show construction phases and the overall construction phase for the project.
c. Show turnover of the project. Identify any proposed phased turnovers. The time to complete the project and turnover to the Government must consider the requirement for the Contractor’s CQC completion inspection and the subsequent joint Contractor-Government turnover inspection.
d. Show as-built submissions (See Section 01 70 00.00 10 CONTRACT CLOSEOUT).
e. Constraints: Offeror must demonstrate the capability and flexibility to plan and schedule the complete project to meet the proposed contract completion period. Clearly identify any constraints on the schedules presented (e.g., labor or material availability, permits, weather, etc.). Indicate the anticipated overall critical path on the schedule.
The intent is to provide enough detail to demonstrate the Offeror’s understanding of the project; however, it is not the intent for the Offeror to provide the amount of detail that will be required in the pre-work submittals contained in Division 01 of this RFP.
8.2 Evaluation Criteria
8.2.1 Proposed Contract Duration: This duration will become the contractually binding completion period if the Government accepts the proposal without discussions. The Government will evaluate the contract duration, as proposed by the Offeror in the Contract Line Item Schedule, not to exceed the maximum allowed duration of days specified in Section 00 73 00 SPECIAL CONTRACT REQUIREMENTS, “Commencement, Prosecution, and Completion of Work”. The Government will rate a proposed contract duration matching the maximum allowed contract duration as “satisfactory”. A proposed contract duration shorter than the maximum allowed duration will receive additional rating consideration, provided it is realistic and deemed to be achievable. An unreasonably condensed contract duration, which places additional cost or schedule risk on the Government will be considered a weakness.
Proposed contract duration that shortens the Government’s specified review times for shop drawings will not be considered. During the subsequent trade-off analysis, differences between proposed contract durations of at least three weeks (differences of 21 calendar days between proposals) will be considered an advantage to the government, with greater differences also considered, accordingly. No advantage will be considered between proposals for differences less than 21 calendar days. Offerors are warned the expenditure of appropriations to expedite the completion date of a military construction contract at additional costs to the Government will not be allowed. Offerors may not expedite the completion date of the construction contract through the use of overtime, 00 22 11 - 11 double shifts, larger crews and similar efforts unless such measures are required for normal construction efficiencies.
8.2.2 Preliminary Schedule. The Government will evaluate the preliminary schedule for construction. The length of the schedule must match the contract duration. If it is shorter, it offers no advantage to the Government because it is non-binding, only representing a preliminary planned schedule. A schedule shorter than the contract duration may indicate the Offeror is placing additional risk on the government for any delays between the scheduled completion date and the required contract duration. The Government will evaluate the schedule to assess the strength of understanding of the project scope, restrictions which must be considered in the schedule e.g., permitting, long lead items, etc. The Government will evaluate the strength of understanding of events associated with coordinating reviews, the Offeror’s capability to schedule the complete project within the proposed contract duration and the realism of the schedule.
9.0 VOLUME 1 - FACTOR 3 – TAB G - PAST PERFORMANCE
9.1 Submission Requirements
9.1.1 Past performance refers to the quality of recent project experience from the owner's perspective. The Past Performance Questionnaire (PPQ) included in the solicitation (Attachment 4) is provided for the Offeror or its team members to submit to the client for each project included in Factor 1 (Specialized Experience). Ensure correct phone numbers and email addresses are provided for the client’s point of contact. Completed Past Performance Questionnaires shall be submitted with your proposal. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires for inclusion in the proposals. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Do not request past performance questionnaires on projects that have final ACASS, CCASS, or CPARS evaluations. If a past performance questionnaire is received on a project where a final ACASS, CCASS, or CPARS evaluation exists, the ACASS, CCASS, or CPARS evaluation will serve as the official rating of record for evaluation purposes. Also include performance recognition documents received within the last 5 years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.
9.1.2 In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (ESRS), and any other known sources not provided by the Offeror.
9.1.3 Additional past performance examples may be submitted for consideration on any member of a Teaming Arrangement that will perform a major or critical aspect of the project. Projects cited shall be currently well underway (fully designed and at least 50% construction progress completed) or construction substantially completed within five (5) years preceding the date of this solicitation. If any firm has multiple functions or divisions, limit the project examples to those performed by the division, unit or team member submitting the offer. The Government may contact and interview the points of contact and reserves the right to interview other individuals acting for the listed reference, if the listed reference is not available. The proposed team members may also briefly provide information on problems encountered on identified contracts and the team member’s corrective action.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
9.2 Evaluation Criteria
00 22 11 - 12
9.2.1 The Government will perform a performance confidence assessment of the Offeror’s probability of successfully meeting the contract requirements, considering the degree of success of the team’s recent (well under way or turned over…