W912BU18B0013_Amendment_0001.pdf
PDF 302 KB Posted
- Attached to
- Liberty and Ellis Island Vessel 3101
- Solicitation number
- W912BU18B0013
About this file
Amendment 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_W912BU18B0013_SF_1409.pdf | ||
| Amendment_0005.pdf | ||
| Amendment_0004.pdf | ||
| 793-D780-01_ALARM_MONITORING_CONTROL_SYSTEM_OVERVIEW.pdf | ||
| 3101_Section_H_Updated_17_Aug_2018.DOCX | DOCX document | |
| Amendment_0003.pdf | ||
| W912BU18B0013_As_Amended_Through_Amendment_0003.pdf | ||
| 3101_Section_C_Updated_17_Aug_2018.docx | DOCX document | |
| 3101_Section_C_Updated_8-10-2018.docx | DOCX document | |
| 397-D730-02_LIGHTING_PLAN.pdf | ||
| Amendment_0002.pdf | ||
| 397-D730-01_LIGHTING_PLAN_-OUTBOARD_PROF.pdf | ||
| 826-B445-01_RD_Fire_&_Safety_Plan.pdf | ||
| 793-D725-01_CABLE_SCHEDULE_VOLTAGE_DROP_AC.pdf | ||
| Contract_Drawings.7z | 7Z file | |
| Reference_Drawings.7z | 7Z file | |
| W912BU18B0013.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Include Section E that w as inadvertently left out of the solicitation.
2. Update FAR Clause 52.211-8 under Section F, Item Number 0001AA should be 180 calendar days and update Delivery Information accordingly.
All other terms and conditions remains the same.
Bidder must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended). FAILURE TO ACKNOWLEDGE
AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR PROPOSAL.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 28
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Jul-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU18B0013
X 9B. DATED (SEE ITEM 11)
25-Jul-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Jul-2018
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BU18B0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION E - INSPECTION AND ACCEPTANCE
The following have been added by full text:
INSPECTION AND ACCEPTANCE
Section E – Inspection and Acceptance
E01 INSPECTION
The Contract will be managed by the Marine Design Center (MDC) of the U.S. Army Corps of Engineers
(USACE) and is subject to inspection by its appointed representatives to ensure strict compliance with the terms of the Contract. No Government Representative, except the Contracting Officer, is authorized to change any provision of the specifications, nor shall the presence or absence of a Government Representative relieve the Contractor from any requirements of the Contract.
When steel construction commences, the Contractor shall coordinate with ABS to ensure the frequency of onsite inspections are not less than once every two weeks.
The Contractor shall provide Safe for Workers labels, in accordance with the OSHA regulations stated in
29 CFR 1915.11-12, for all confined and enclosed spaces prior to permitting entrance for work or inspection. This procedure shall be reflected in the Contractor’s Safety Plan. See Contract Section H, Clause H07.
Entry shall not be permitted to any confined or enclosed space that does not have a current Safe for Workers label.
E02 LAUNCHING
The Contractor shall be responsible for the satisfactory launching of the vessel at the time and date selected and mutually agreed upon by the Contractor and the COR.
The Contractor shall provide a written notice to the COR 7 calendar days prior to the launching. Prior to launching, all painting below the main deck (interior and exterior) must be completed. The hull interior and exterior surfaces shall be thoroughly inspected by an authorized Government representative to verify compliance with the requirements of the specification. The vessel shall not be launched until the hull painting has been approved by the
COR. The Contractor shall schedule 3 days between hull inspection and launch to allow any new paint on the hull interior and exterior to cure properly.
The condition of the vessel shall be recorded at the time of launch. This shall include the levels of all tanks, draft and freeboard readings at the port and starboard forward, midship, and aft locations, a list of shipyard equipment on board, an estimate percent of the vessel complete, and the time and date of the launch.
After launching, all tanks and voids shall be inspected for damage and leaks, and their conditions shall be recorded.
E03 QUALITY CONTROL AND INSPECTION
A. GENERAL
After Notice To Proceed with Phase I “PLANNING, ENGINEERING AND SCHEDULING” the Contractor shall develop a Contractor Quality Control (CQC) and Inspection Program for the work required in this Contract. This program shall contain two sub-programs which will provide for review and quality control of the “Engineering and
Scheduling” submittals and regular inspection and testing of the construction work in progress and the preparation and maintenance of documentation and records.
The first sub-program, (CQC of the engineering phase), must be submitted within 14 calendar days after the
Notice To Proceed with the Phase I “PLANNING, ENGINEERING AND SCHEDULING” phase of the Contract.
The second sub-program, (CQC of the construction phase), must be submitted and accepted in the
“PLANNING, ENGINEERING AND SCHEDULING” phase of the Contract. The Notice To Proceed with Phase II
“CONSTRUCTION, TESTING AND DELIVERY”, will not be issued until this document is accepted.
The documentation and records of sub-program 1 shall:
Define the review and correction process for all “Planning, Engineering and Scheduling” phase submittals with particular attention given to the Final Design Drawings.
The documentation and records of sub-program 2 shall:
Define Contractor tests and inspections to be accomplished for each work item of the Contract.
Such tests and inspections shall be keyed to the appropriate paragraph of each clause.
Be commensurate with the complexity of the work in the specification and adequate to assure the
Contractor that the product or subproduct offered conforms to the requirements of the Contract.
Be available to the Government Representative at all times and contain recorded data of all
Contractor conducted inspections and tests conducted to date. All Quality Control reports, including those of subcontractors and regulatory agencies will be maintained and included in the Test Report of Contract Clause E05.
List by name and title, the Contractor’s representatives who are authorized to witness or perform and sign for each test and inspection.
The following are the minimum requirements for data to be recorded:
Type of inspection or test (e.g., visual, mechanical, liquid penetrant, radiographic), accept/reject criteria, and a statement as to whether the inspection was satisfactory or unsatisfactory.
Number and type of deficiencies of material or workmanship found in the product or subproduct inspected and corrective action taken to correct the deficiencies and, for repetitive deficiencies, to preclude recurrence.
Date and signature of the Authorized Contractor Representative who witnessed or performed the test or inspection.
Responsible authorized personnel shall inspect the work in progress and all completed work, conduct necessary tests and record the data required. An Authorized Contractor Representative shall sign the records attesting to the validity of the information.
Contractor certified inspection is an integral part of all work, therefore the COR will consider the entire
Contract incomplete if Contractor documentation and records signed by the Contractor’s Authorized Representative are not complete.
B. SUBCONTRACTORS
Work subcontracted and/or performed away from the shipyard is covered by this inspection system. The prime Contractor cannot delegate the authority to witness or perform, and sign for tests and inspections conducted away from the shipyard, without approval of the COR.
If the subcontractor has an established Quality Control program with designated organization and personnel, the prime Contractor may designate an appropriate individual in that organization as his authorized representative.
Such designation shall clearly indicate that the individual is an employee of a subcontractor and his appointment shall be subject to the approval of the COR.
C. TESTING
When any workmanship, material, or apparatus fails to pass any test or inspection, it shall be fully retested only after all known faults have been eliminated. Where directed by the COR, such failed material or apparatus shall be completely removed from the work and renewed. Any defects in workmanship or material shall be remedied by the Contractor at no additional cost to the Government, except where work was performed on material furnished by the Government.
D. ABS ONSITE INSPECTION
When steel construction commences, the Contractor shall coordinate with ABS to ensure the frequency of onsite inspections are not less than once every two weeks. The Contractor shall provide a schedule for the ABS Onsite
Inspections. The schedule shall include the scheduled inspection date(s), actual inspection date(s), and signature blocks for the ABS Inspector and Contractor, and notes for what inspection(s) were conducted. This report shall be kept current and upon request be made available to the COR.
E04 FACILITIES FOR PERSONNEL
While it is not intended that the Marine Design Center will have a Resident Engineer’s Office, the Contractor shall provide office space at the construction site for use by a Marine Design Center staff of three people.
The space shall be convenient to the work site and consist of two desks, three chairs, three lockers, one commercial telephone, and access to the Contractor’s telephone system. The commercial telephone shall have speaker-phone capability. The Contractor shall also provide WiFi internet access for Government mobile devices and laptops.
The space shall be air conditioned, heated, ventilated, well maintained and well secured, and be convenient to toilet and shower facilities. The space shall be suitable for both male and female staff.
Government Representatives attending the construction may bring with them communication equipment, cameras, and various items of test equipment. The Contractor shall permit unencumbered ingress and egress to and from the shipyard and vessel with such equipment.
Upon request, the Government representative shall have the unrestricted use of a facsimile machine, photocopier, word processing equipment, paper, supplies, etc.
The Contractor shall furnish an up-to-date set of drawings for exclusive use of USACE personnel while in the shipyard.
In addition, the Contractor shall also furnish two parking spaces within the shipyard, in safe locations and accessible to the assigned office space.
E05 TRIALS, TESTS AND DEMONSTRATIONS
A. GENERAL REQUIREMENTS
1. Levels of Testing
The Contractor shall perform tests on all equipment, machinery, and systems; individually, and integrated as a whole. The tests shall be performed as necessary to demonstrate satisfactory compliance with the Specification requirements contained in Section C, “DESCRIPTION/SPECIFICATION/WORK
STATEMENT,” of this Contract.
The Contractor shall perform four levels of testing as follows:
Level 1 Pre-Trial Tests
Level 2 Builder’s Dock Trials
Level 3 Dock Trials
Level 4 Open Water Trials
Level 5 Final Acceptance Demonstrations
All demonstrations, tests, and trials shall be performed as specified herein and as specified in Section
C of the Contract. The Contractor shall furnish all labor, materials, tools, and test equipment as necessary and perform the testing, trials, and demonstrations specified.
It is expected that the Contractor shall complete the prior level of testing before moving on to subsequent levels.
2. Consumables and Operating Fluids
The Contractor shall furnish all fuel oil, hydraulic oil, lubricating oil, gear oil, engine anti-freeze, treatment chemicals, degreasing agents, gases, potable water and any other consumables required to perform the tests and demonstrations, and as required in Contract Section C.
3. Test Documentation
The Contractor shall prepare an Agenda and Test Memoranda of the required tests and trials for the vessel in accordance with the requirements set forth herein. Two copies of the Agenda and Test Memoranda shall be submitted to the COR for review and approval 60 days prior to the scheduled testing (see Contract
Section H, Clause H02).
a. Test Agenda
For the vessel, the Contractor shall prepare a Test Agenda for Level 3 and Level 4 Tests and Trials. The Agenda shall be a complete, detailed schedule of all tests, trials and demonstrations specified in this clause. The Test Agenda shall be arranged by day, not date, and shall list the specific tests, trials, and demonstrations, and the sequence in which these will be performed.
b. Test Memoranda
For the vessel, the Contractor shall prepare Test Memoranda for all systems and equipment tested under the Levels 1, 2, 3, 4 and 5 test and trial requirements of this clause.
The test memoranda shall describe the actual test procedures and data to be recorded. The procedures shall be in accordance with the “start-up” procedures for the equipment, as delineated in the operating manuals furnished for the equipment by the manufacturer. The Contractor shall incorporate demonstrations of all applicable controls, instruments, and alarms, into each system’s
Builder’s Dock Trials, Dock Trials, Open Water Trials, and Final Acceptance Demonstrations sections of the Test Memoranda. Data recorded in time intervals shall be tabular so that data trends can be easily recognized.
Each test memorandum shall:
List the major equipment
Include a space for nameplate data, make, model and serial number of equipment, etc.
List the characteristics of equipment (i.e. impeller size, motor size horsepower and amperage, flow capacity, line pull capacity, cfm, etc.)
Reference the manufacturer’s manual(s) used to format the test procedure
Describe instrumentation for each test
Describe the test procedure
List the Pass/Fail limits
List the expected results
Include a space for the actual results
Include a space for the ambient conditions
Include signature blocks for Contractor Representative, ABS and Government
Representative witness signatures, times and dates
Include a space for writing comments
The Test Memoranda shall be typed on 8½-inch by 11-inch sheets of paper, single side, in three-ring notebook, with dividers for each section. Each page shall include the Marine Design
Center project number (3101) and hull number (826) at the top. An electronic copy of the Test
Memoranda shall also be provided to the Government.
The memoranda shall be arranged by system and equipment, with each level of testing for a specific system or piece of equipment recorded under the respective heading.
The memoranda shall be arranged by system and level of testing similar to the following outline:
X. System (or equipment)
a. Pre-Trial Tests
b. Builder’s Dock Trials
c. Dock Trials
d. Open Water Trials
e. Final Acceptance Demonstrations
4. Test Reports
Completion of system or vessel testing shall be reported to the COR in the following manner:
Within two days of the completion of any tests, a copy of the memorandum for that specific test shall be available for review at the request of the COR.
Upon completion of any level of testing, the COR shall be notified that the specific level of testing has been completed. At his discretion, the COR may request to review the test memoranda for that level of testing.
With completion of subsequent levels of testing, all test memoranda shall be filled-in, and placed in the Test Report. Results of all vendors’ tests shall be filled with the applicable test section. The Test Report, with all prior test results, must be current at all times, and shall be available for review at the request of the COR at any time.
The Test Report shall be reviewed and approved by both the Contractor and the COR at the conclusion of each level of testing. Review and approval of the Test Report by the Contractor and the COR is a precondition of moving to the next level of testing.
Within 10 calendar days following the successful completion of Final Acceptance
Demonstrations (Level 5), the Contractor shall submit the Final Acceptance Demonstrations report to the COR for review.
The final version of the Test Report, including results of the previous four levels of the tests and trials, shall be bound in three ring binders and two copies shall be submitted within 30 calendar days following successful completion of the Level 5 demonstrations, and prior to Final
Payment. A scanned version of the final Test Report shall be provided to the Government. The
Test Report shall be in .pdf file format.
5. Deficiencies
The COR will compile a list of deficiencies which will be given to the Contractor. All deficiencies shall be corrected. Final Acceptance of the vessel will be made following remedy of all deficiencies.
The successful completion of all tests, trials, demonstrations and remedied deficiencies, shall be determined by the COR.
B. PRE-TRIAL TESTS (LEVEL 1)
The Pre-trial tests are designed to ensure proper construction, and installation of all equipment, piping, and electrical systems, tanks, and exterior and interior bulkheads. Pre-trial tests shall be performed during the course of construction and prior to the beginning of Level 2 testing (Builder’s Dock Trials).
The COR shall be notified at least 24 hours in advance of any such testing and may, at his discretion, send a
Government representative to witness any or all tests. The Contractor shall coordinate with ABS to ensure that they are present for all tests required to be witnessed for class.
Documentation of all pre-test inspection shall be in accordance with the requirements of Contract Clause E03
(Quality Control and Inspection). All deficiencies, including cracks, leaks, grounds detected in new circuits, or poor workmanship shall be corrected prior to commencement of the Builder’s Dock Trials. Pre-trial tests shall include the following:
1. Hull
All tanks and watertight bulkheads shall be tested in accordance with ABS Rules.
Verify there are an adequate number of lifting eyes for machinery and equipment removal provided and installed throughout the hull. Load test lifting eyes. Verify safe working load markings on lifting eyes.
2. Superstructure
All weathertight exterior bulkheads shall be hose tested for tightness prior to coating. All weathertight doors, windows, manholes, and hatches shall be hose tested for tightness.
3. Machinery Systems
The testing requirements set forth herein include system flushing procedures which shall be performed to demonstrate system cleanliness and integrity.
a. Compressed Air
Upon completion of installation, the piping of the compressed air system shall be hydrostatically tested in accordance with the ASME code. The system shall be inspected for leaks at the welds, fittings, etc. Upon completion of the hydrostatic test, the entire system shall be blown dry with air. The Contractor shall take proper precautions to protect any controls, equipment connections, the whistle, and the air tool stations.
b. Piping Systems
Hydrostatically test all piping systems (except CO2 piping) for leaks at 1-1/2 times working pressure for a period of not less than 10 minutes per test. Each system shall be inspected for leaks at the welds, fittings, hoses, etc. Upon completion of a system’s hydrostatic testing, the system shall be thoroughly flushed with its respective fluid.
c. CO2 Piping
Upon completion of the CO2 piping and prior to the cylinders being connected to the system, the piping shall be pressure tested with CO2 or another inert gas. Testing of the piping shall be in accordance with the requirements outlined by USCG in 46 CFR, subchapter H, subpart 76.15, paragraph 76.15-15.
d. Exhaust Systems
Blank off and test the flanges, welds, and gaskets of each exhaust system using compressed air and soap bubbles. The main engine exhausts and the diesel generator exhausts shall all be checked in this manner.
e. HVAC
Blow out with compressed air all installed ductwork. Operationally test each supply and exhaust fan, along with the ducting to ensure the absence of leaks, adequate support, and acceptable vibration levels.
f. Potable Water
In addition to hydrostatically testing the system in accordance with (b) above, the
Contractor shall clean, chlorinate, and flush all system tanks and piping.
4. Electrical Cabling
Insulation resistance readings of all installed power and lighting cable shall be taken using a 500 volt megger, and shall be in accordance with IEEE Standard 45, Section 34. The measured cable insulation resistance must meet or exceed the minimum values outlined in the referenced IEEE publication. Also, measure the voltage drop of the longest receptacle circuit. A complete record of all readings shall be kept to assure that all circuits and equipments have been checked.
C. BUILDER’S DOCK TRIALS (LEVEL 2)
Builder’s Dock Trials are a preliminary “run-through” of all required Dock Trials (Level 3) by the Contractor.
The intent of this testing is to provide both the Contractor and the COR reasonable assurance that all equipment and systems have been thoroughly prepared and are ready for formal testing in Dock Trials (Level 3).
For the vessel, Builder’s Dock Trials shall be conducted at the Contractor’s facility listed in Section B of the
Contract. The COR shall be notified, in writing, at least 3 working days prior to the scheduled commencement date of Builder’s Trials. The Test Report must be current prior to commencing Builder’s Dock Trials.
The trials shall be of sufficient scope and duration to assure that all machinery and equipment is operable and all systems are complete. The trials need not be carried out to the same degree as the Level 3 testing.
D. DOCK TRIALS (LEVEL 3)
1. General
Dock Trials are the operability tests the Contractor must perform in the presence of the Government
Representative to demonstrate the proper installation, operation, control, and performance of all equipment, machinery, and systems installed as part of this Contract. Specific dock trials and demonstrations are defined in paragraph E.
In addition, each test or demonstration shall include control, instrumentation and alarm operation as applicable.
Prior to the start of Dock Trials, all construction and installations must be complete (except for final cleaning and touch-up painting), and all Level 1 and Level 2 testing must be successfully completed and documented. Please note that there are specific test items and system cleaning that shall be completed prior to the vessel’s launch. The Test Report shall be current through the two levels of testing.
The Commencement of Dock Trials shall not be sooner than one full working day after completion of Builder’s Dock Trials. The COR shall be notified immediately of any condition which would delay the conduct of Dock Trials.
The COR shall be notified in writing 10 working days in advance of the date set for testing of the vessel. Results of the Level 2 Testing shall be transmitted to the COR at least one day prior to the start of the Dock Trials if Level 2 Testing was not attended by a Government Representative.
All testing and trials shall be conducted in the presence of a Government representative and vendor representatives for the following equipment:
Main Diesel Engines
Diesel Generator Sets
Variable Speed Motor Drives (if applicable)
Main Switchgear
Control, Monitoring & Alarm System(s)
HVAC
Deck Crane
Fire Detection, Alarm & Extinguishing System
The cost to have vendor representatives on-site during testing shall be the responsibility of the
Contractor.
The tests shall be conducted in accordance with the Agenda.
The Contractor shall indicate on the test memoranda which tests will be performed using the diesel generators and which tests will be performed using the shore power.
The success of all tests and the existence of any deficiencies shall be determined by the COR.
Deficiencies discovered during the Dock Trials shall be remedied prior to start of Open Water Trials (Level
4).
2. Safety Requirements
During dock trials and thereafter, the atmosphere in spaces being prepared for, and preserved by, paints and tank coatings dissolved in highly volatile, toxic, and flammable solvents (29 CFR 1915.35(b)), shall be tested frequently and shall be in accordance with the U.S. Occupational Safety and health Agency
Standards regulations stated in CFR 1915.31-36.
Within 24 hours of final inspection, and before any representative of the U.S. Government boards the vessel for such duties, each compartment or space to be inspected shall be certified “SAFE FOR
WORKERS” by the National Fire Protection Associations (NFPA) certified Marine Chemist. This means that in the compartment or space so designated:
The oxygen content of the atmosphere is at least 19.5 percent and below 22 percent by volume;
The concentration of flammable vapors is below 10 percent of the lower explosive limit
(LEL);
Toxic materials in the atmosphere are within permissible concentrations;
Any residues or materials associated with any work in the space shall not produce uncontrolled release of toxic materials under existing atmospheric conditions while maintained as directed on the Marine Chemist’s certificate.
The Contractor shall notify the Government when this certificate has been issued. The vessel will not be inspected and accepted by the Government without an NFPA Marine Chemist certificate for each hull compartment designated “SAFE FOR WORKERS.”
E. SPECIFIC DOCK TRIALS AND DEMONSTRATIONS (LEVEL 3)
1. Coating System, Floor Coverings, Sheathing, Joinery & Ceilings
The hull coating system shall be inspected and approved prior to the vessel’s launch. Please refer to Contract Section C, Clause C406, for specific details.
Verify all anodes are installed properly.
Verify all floor covering systems are installed in accordance with manufacturer’s recommendation and the satisfaction of the COR. Where required, provide a letter approving the system from the system manufacturer.
Verify all sheathing, joinery, and ceilings are installed to the satisfaction of the COR. Verify access panels are provided where necessary.
2. Hull & Vessel Markings
Prior to the vessel’s launch, the hull markings shall be visually inspected for continuous welding and placement. The location of each hull marking shall be verified to ensure it is correct (i.e. draft marks measured from the bottom of the hull). Verify the spelling of the hull markings on the forward bulwark and across the transom.
Verify padeye markings, including safe working load limits.
Verify the name boards are spelled correctly and installed.
Verify the stack insignias are provided and properly installed and secured to the stacks.
Verify all nameplates, notices, signage, labels, tags, pipe markings and electrical markings are installed per Contract Section C, Clause C460, Clause C601, and Clause C702.
Verify the fire control plans are correct and installed per Contract Section C, Clause C679.
3. Vessel Launch
The condition of the vessel shall be recorded at the time of launch. This shall include the levels of all tanks, draft readings at Port/Starboard forward and aft locations, a list of shipyard equipment on board, an estimate percent of the vessel complete, and the time of launch.
After launching, all tanks and voids shall be inspected for damage and leaks.
4. Inclining Experiment
In accordance with Contract Section C, Clause C115.B, a stability test on the vessel shall be performed to determine the basic stability parameters. The inclining experiment shall accurately determine the As-Built lightship weight and the coordinates of the center of gravity for the completed vessel in three directions.
Upon completion of all work, with the vessel in the lightship condition, the Contractor shall assist in conducting an inclining test. The inclining test shall be carried out in accordance with ASTM F 1321-14.
The Government will provide the requirements, incline weight data, pendulum lengths, etc., to the
Contractor. The Government, in conjunction with the Contractor, will prepare the incline test procedure.
The Government will direct the incline procedure, record the data and prepare the report.
The Contractor shall coordinate with the regulatory bodies, including submitting the procedure and results, and scheduling the experiment with the necessary witnesses.
The Contractor shall be responsible for providing all inclining weights, pendulum setup, support equipment, and personnel. The Contractor shall erect a minimum of 3 pendulums for the inclining experiment.
5. Hull & Tanks
The Contractor shall show that each hull compartment is dry and free from leakage. The hull compartment paint shall be complete, intact and fully cured.
For the integral and independent tanks, all liquid level sight gauges, magnetic level indicators, petcocks, sampling valves, and drains shall be demonstrated and verified.
Verify all deck plates and grating are provided, properly isolated and secured. Verify access panels in the deck plates are provided where necessary.
6. Superstructure
Use a pressure hose to visually check for leaks and demonstrate weather tightness of all doors, windows, hatches, manholes, pilothouse top penetrations, and bulkheads.
Verify all grating are provided, properly isolated and secured.
7. Doors, Windows, Hatches & Manholes
Demonstrate that each hatch and manhole is functioning by opening and removing (for non-hinged hatches) and replacing/closing it and securing it in place. The required markings on the escape hatch and voids shall be confirmed. If applicable, confirm chain is provided and installed for removable hatches.
Demonstrate the each door (joiner, watertight, fume tight, weathertight) is functional by opening, closing, securing in opened and closed positions, and locking/unlocking (where applicable). Watertight doors shall be cleaned and greased. The watertight door shall be adjusted to close and dog with minimal effort.
Demonstrate that each sliding window is functioning by opening, closing and securing it. The
Contractor shall also demonstrate that each window shade and/or curtain is installed and functioning properly.
Where applicable, the tinting/frosting on required windows shall be verified.
8. Deck Fittings & Fendering
Demonstrate that all deck fittings have been properly installed and verify continuous welding and installation of all support structure.
Load test each deck tiedown to its rated safe working load.
Verify bulwark gate functionality.
Verify all fendering is provided and properly installed.
9. Vertical & Inclined Ladders
Demonstrate that all vertical ladders have been installed and are functional.
Demonstrate that all inclined ladders have been installed and are functional.
Demonstrate the removal process for vertical and inclined ladders, where applicable. Ladders do not have to be removed for testing.
10. Fixed Fire Extinguishing (CO2) System
Demonstrate the proper operation of the installed CO2 system. Tests shall be performed in accordance with NFPA12, with the exception of the full discharge requirement, to demonstrate proper operation of the trip devices, nozzles, audible alarms, visual alarms, and the automatic shutdown of the ventilation system fans. These tests may be done concurrently with the required ABS tests of the system.
The ABS representative and a Government representative must be present to witness the tests. A representative of the CO2 system shall be present during the test and trials of the CO2 system.
Proper operation of each CO2 system shall be demonstrated by discharging a test cylinder through the respective system. The system supplier, in accordance with his test procedures, shall conduct each test.
The demonstration shall include:
Operation of local activation system.
Operation of all remote pull stations.
Operation of the audible alarms in the engine room.
Verify 30 second discharge delay.
Automatic shutdown of the engine room supply and exhaust ventilation fans.
Automatic closure of the louvers of the supply and exhaust ventilation fans for the engine room.
Automatic shutdown of HVAC and ventilation systems on the vessel, see Contract Section
C, Clause C685.
Verify required signage, including warnings and instructions are posted.
Note: The Government representative and ABS inspector must be present to witness both the Level
1 hydrostatic piping test and the operational test described here. All tests shall be performed to the satisfaction of the ABS Inspector, responsible for issuing a Statement of Fact for the CO2 system. As such, these tests may be performed prior to the commencement of Dock Trials.
11. Main Engines
For each main engine, demonstrate the following in the presence of an authorized manufacturer’s representative:
Cold starting. The cold starting testing shall demonstrate the minimum number of starts required by ABS for the engine.
Starting and stopping of each engine from all control panels.
Operation of all emergency stops. Resetting at the local engine panel.
All engine controls and instrumentation.
Operation of all engine alarms from all control panels. Ensure the proper operation of all alarm test circuits for each main engine.
Automatic shutdown for engine overspeed.
Operation of engine jacket water heaters.
12. Diesel Generator Sets
For each diesel generator set, demonstrate the following in the presence of an authorized manufacturer’s representative:
Cold starting. The cold starting testing shall demonstrate the minimum number of starts required by ABS for the engine.
Stability of operation.
Starting and stopping of the generator from all control panels.
Operation of all emergency stops.
All engine controls and instrumentation.
Operation of all engine alarms from all control panels. Ensure the proper operation of all alarm test circuits.
Operation of automatic shutdowns.
Operation of the jacket water heaters.
Operation of the combustion air cleaners, including checking and cleaning the filters.
13. Load Bank Testing
Each diesel generator set shall be load bank tested. Operate each generator set at 1/4, 1/2, 3/4 and full loads in 15 minute intervals, 100% rated load (with the use of a load bank) for 2 hours, and 110% rated load (with the use of a load bank) for 2 hours. All engine and generator parameters shall be recorded at 5 minute intervals for the partial and full load periods, and at 15 minute intervals for the 100% and 110% load period.
14. Main Engine Cooling System
Demonstrate that proper cooling water flow takes place during the operation of each main engine.
Inspect each system for leaks. Check the engine jacket water temperature gauges (locally and at all remote panels), the jacket water cooler circuit inlet and outlet temperatures, and the after cooler circuit inlet and outlet temperatures of the box coolers.
Verify seachest construction and demonstrate ability to remove box coolers while afloat.
Verify box cooler functionality at zero knots.
15. Diesel Generator Cooling System
Demonstrate that proper cooling water flow takes place during the operation of each diesel generator set engine. Inspect each system for leaks. Check the engine jacket water temperature gauge readings and temperatures at all inlets and outlets. All cooling system testing shall be at 110% load.
16. Engine & Generator Exhaust System
Demonstrate the operation of each main engine and diesel generator exhaust systems. Inspect each system for leaks and verify the backpressure on each system.
17. Steering System
Before leaving the dock for Open Water Trials, demonstrate the operation of the steering rudders from hard over to port to hard over to starboard, and intermediate positions to simulate normal operation.
Record the time to shift from Hard over to Hard over. Inspect the system for leaks.
Demonstrate the operation of the rudder angle indicators.
Demonstrate the operation of the non-follow-up/jog lever for the steering rudders.
Demonstrate the operation of all hydraulic pumps.
Demonstrate the operation of the visual and audible alarms for loss of hydraulic pressure, low oil level in the reservoir, and high temperature alarm.
Check the system filter and inspect the fluid.
18. Bow Thruster
Demonstrate the operation of the bow thruster in both directions.
19. Anchor & Anchor Winch
Verify installation and operation of anchor slide.
Verify that the proper amount of chain and nylon rope is supplied with the anchor.
Verify anchor deployment and retrieval.
18. Fuel Oil System
Ensure proper flow to and from the main engines and the diesel generator engines during operation.
Check the fuel filters on each main engine and generator set.
Demonstrate the ability of the fuel off-vessel station. Connect a hose to the pump-off connection and demonstrate proper operation.
Demonstrate the operation of the remote, emergency shut-off valves.
Demonstrate the ability/operation of all liquid level gauges, electronic level systems, audible and visual alarms, pump start-stop controls, indicator lights, and emergency shut-downs/stops. Verify and calibrate the electronic tank leveling system.
Verify fuel transfer and fill hoses are provided, outfitted and marked in accordance with Contract
Section C, Clause C630.
The Contractor shall be responsible for maintaining the fuel oil tank filled and for delivering the vessel with the fuel oil tank filled to capacity.
18. Service Oil Systems
Demonstrate the ability of the lube oil transfer pump to transfer oil from the tanks to the engine room reel stations. Each station shall demonstrate the ability to fill the main engines and generators with the respective oils. Check the system for leaks. Demonstrate operation of the transfer pumps.
Demonstrate the ability/operation of all liquid level gauges, audible and visual alarms, indicator lights, and pump start-stop controls.
The Contractor is responsible for filling the lube oil tank and for delivering the vessel with the lube oil tank full.
19. Waste Oil System
Demonstrate the ability of the waste oil pump to transfer waste oil from the main engines and generators in the Engine Room to the portable waste oil container. Demonstrate all waste oil hose connections and check for leaks.
lights, and pump start-stop controls.
20. Bilge System
Demonstrate the operation of the bilge system using the bilge pump by taking suction of water from each compartment bilge suction and discharging the water overboard. Record the discharge pressure for the pump(s). Record the time to take suction from all compartments. The bilge pump(s) shall satisfy the ABS bilge pump flow capacity as stated in ABS Rules for Building and Classing Steel Vessels for Service on
Rivers and Intracoastal Waterways (4-3-3/3.5.4 Bilge Pump Capacity). Demonstrate the operation of the bilge pump.
Demonstrate the ability of all manifold valves to operate properly in the open and closed positions and readily turn between those positions. Verify manifold instruction plates and other required signage is provided and installed.
Demonstrate the ability/operation of the bilge level sensors in each compartment outfitted with the equipment. Demonstrate the ability/operation of the audible and visual alarms for the bilge system.
Demonstrate the ability/operation of all pump start-stop controls and indicator lights.
21. Potable Water
Demonstrate that there is adequate flow of cold water to each respective fixture (sinks, toilets, etc.), and that there is adequate flow of hot water to the sinks.
Demonstrate the operation of each potable water pressure set pump to cut-in at a set pressure and cut-off at a set pressure by allowing flow to continue from a fixture. Record the pressures.
Extract sufficient water effluent samples and have them tested by a qualified facility to demonstrate that the water meets the EPA regulations of Title 40, Chapter 1, Part 141 – “National Interim Primary
Drinking Water Regulations.”
Measure the chlorine level in the potable water tank using a standard test kit.
Check all system filters and ensure they are function.
Demonstrate the ability/operation of the electronic level system and displays. Verify and calibrate the electronic tank leveling system.
lights, and the pump start-stop controls.
Verify all potable water hoses and connections are in accordance with Contract Section C, Clause
C665.
The Contractor is responsible for maintaining the potable water tank filled and for delivering the vessel with the potable water tank full.
22. Sewage and Sanitary System
Flush toilet several times to demonstrate the ability of the system.
Demonstrate the operation of all HVAC drains and sink drains.
Demonstrate the ability of the transfer pump to pump from the raw sewage tank to the pump-off station.
lights, and pump start-stop controls
24. Firemain System
Demonstrate the starting capability of the bilge/fire pump from the local station and all remote stations.
Demonstrate the operation of all fire stations, hoses and nozzles.
Demonstrate the ability of the fire pump to provide the required water flow in accordance with 46
CFR 27.301(a) sizing requirements. Record the pump discharge pressure. Using a pitot tube, measure the pressure at each nozzle. Several combinations of stations shall be demonstrated.
25. Fire Detection & Alarm System
Demonstrate the operation of the fire detection system. The testing and trials shall demonstrate:
The activation of the alarms from each smoke detector and heat sensor.
The activation of alarms from each CO detector.
The automatic shutdown of the HVAC System and any ventilation fans and louvers in accordance with Contract Section C, Clause C678.
The activation of all audible and visual alarms, including operation of the red indicating light on the pilothouse top.
Operation of the back-up power supply and the system battery charger.
A representative of the alarm system shall be present during the test and trials of the fire detection and alarm system.
26. Life Saving & Fire Safety Equipment
Verify that all Lifesaving (Contract Section C, Clause C445) and Fire Safety Equipment (Contract
Section C, Clause C679) required by their respective contract clauses have been installed and each is fully functional. Ensure that each portable fire extinguisher is charged to the correct operational pressure, properly mounted and is USCG approved. Ensure that the waterlights on the life rings are functional.
Ensure that the alarmed AED is functional and verify service plan.
27. HVAC
Demonstrate the satisfactory operation of each compartment’s ventilation system, air conditioning system, and heating system. This includes ensuring proper airflow for engine function and achieving required temperatures in each respective space.
28. Compressed Air System
Testing of the vessel’s compressed air systems shall be carried out as outlined below. Air receiver certificates shall be provided prior to testing.
a. Ship’s Service System
Demonstrate the charging of the air receiver from atmospheric to the system design pressure. Record the amount of time required to charge the receiver.
Demonstrate the ability of the compressor to cut-in at a set pressure and cut-out at a set pressure.
Verify the operation of the hour meter for the compressor.
Demonstrate airflow to all air tool stations and reels.
Demonstrate the operability of all reducing stations, relief valves and receiver drain valves.
Demonstrate the operation of the air horn from the ship’s service air.
29. Camera System
Demonstrate the operation and proper field of vision of each camera. Demonstrate monitor operations and functions.
Demonstrate the operation of the system power supply.
30. Alarm Systems
Demonstrate the operation of each alarm system:
General Alarm System
Bilge Alarm System
Watertight Door Indicators and Alarms
Misc. Alarms
Each station of an alarm system shall be tested for operation showing all of the activation locations, and silencing of the visual and audible alarms of the system at all readout/panel locations.
Demonstrate the operation of the battery charger for the General Alarm System.
Demonstrate the operation of the system power supply.
31. Main Deck Crane
Demonstrate satisfactory operation of the deck crane. The crane shall be load tested in accordance with the manufacturer’s requirements.
A representative of the crane supplier shall be present during the tests and trials of the crane.
32. Rescue Skiff and Davit
Verify the rescue skiff cradle is properly constructed and fits the shape of the hull. Verify adequate padding is provided on the cradle. Verify adequate tie-down straps are provided and functional. Demonstrate the tie-downs.
Demonstrate satisfactory operation of the davit.
Demonstrate the lifting sling is properly designed for the skiff’s center of gravity.
Demonstrate the operation of the davit to swing the rescue skiff out of its storage cradle and lower the boat into the water off of the transom. Demonstrate the operation of the davit to raise the rescue skiff from the transom and place it onto its storage cradle.
Demonstrate satisfactory operation of the rescue skiff and outboard motor for a minimum of 30 minutes. During this time the rescue skiff shall be put through various turning maneuvers and all of the features and systems tested.
33. Miscellaneous Equipment
Demonstrate the all outfitting and equipment required in Contract Section C, Clause C437 is provided. Where applicable, demonstrate the operation of appliances and equipment listed in the referenced clause. The test memo shall list all items, including manufacturer make and model for miscellaneous equipment testing.
34. Pilothouse Window Wipers, Defrosters, and Washing System
The Contractor shall demonstrate that each window wiper is functioning at all speeds. The sweep of the wiper shall be confirmed. The wiper contact against the window shall be adjusted until the tension is acceptable to the COR.
The Contractor shall demonstrate that all defrosters are functioning.
Demonstrate the operation of the window washing system. Verify adequate flow and coverage on the required windows. Demonstrate filling the reservoir(s).
The Contractor is responsible for maintaining the washing fluid and for delivering the vessel with the washing fluid full.
35. Communication Equipment
Demonstrate the operation of the system for each piece of communication equipment.
36. Navigation Equipment
Demonstrate all navigation equipment is installed, functioning and integrated properly.
Demonstrate the operation of all halyards.
37. AC Electrical System
a. General
In order to demonstrate the operation of the electrical system as integrated system, the
Contractor shall perform approximately ½ of the Level 3 machinery tests using the diesel generator(s). The remaining ½ of the Level 3 machinery tests shall performed using shore power supplied through one of the vessel's shore power receptacle. It is the Contractor's option as to which tests shall be powered from shore power and which tests shall be powered by the diesel generator(s).
b. Main Switchboard
Demonstrate the operation of all circuit breakers and all equipment in the main switchboard. For the generator breakers and the shore power breaker, safely demonstrate all mechanical and electrical interlocks.
Demonstrate the ability of the generators to be paralleled and all of the following features of the switchboard:
Automatic synchronizer
Auto-manual synchronizer selector switch
Generator power available lights
Voltage regulator control rheostat
Speed control rheostat
Voltmeters and selector switches
Ammeters and selector switches
Frequency meter and selector switch
Wattmeter
Multifunctional amp, volt, and watt transducers.
Space heaters
Test Switch
For shore power operation, demonstrate the ability of the switchboard to monitor the following:
Shore power available light
Voltmeter
Ammeter
Frequency meter
Phase sequence/loss system
Demonstrate the ground detection features in the switchboard for:
480 volt AC system – lights, ammeter, and test switch.
208Y/120 volt system – lights, ammeter and test switch.
c. Distribution Panels
Demonstrate the operation of all AC circuit breakers in the distribution panel boards.
d. Motors and Controllers
Demonstrate the operation of each motor controller.
Demonstrate the low-voltage release (LVR) for the following motor controllers:
Bilge/Fire Pump
Steering System Hydraulics
38. DC Electrical…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.