AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Inform all potential offerors that the deadline for the submission of questions is 15 August 2018, 10 A.M. EST. Any questions received after this date and time may be answ ered at the discresion of the contracting off icer.
2. Provide questions and answ ers as of 10 Aug 18.
3. Provide the revised section C w ith all changes highlighted.
4. Add draw ing numbers 397-D730-01 LIGHTING PLAN-OUTBOARD PROFILE and 397-D730-02 LIGHTING PLAN to section J as attachments to the solicitation.
5. Add clauses listed in the summary of changes below .
All other terms and conditions shall remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 18
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Aug-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU18B0013
X 9B. DATED (SEE ITEM 11)
25-Jul-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Aug-2018
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BU18B0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0002 ATTACHMENTS
1. Drawing 397-D730-01 LIGHTING PLAN -OUTBOARD PROFILE
2. Drawing 397-D730-02 LIGHTING PLAN
3. Section C Revised 10 Aug 18
QUESTIONS AND ANSWERS 10 AUG
Questions and Answers W912BU18B0013 (As of 10 Aug 18)
Q1. Could Government please verify if the bid is due August 24th NLT 2:00 p.m. IAW block 9 of the SF 33 Form (and as posted on FBO) or if the due date is August 23rd IAW Section L?
A1. As of 7 August 2018, bids are due August 24th, 2:00 P.M. EST. Any updates to this time and date will be provided as an official amendment to the solicitation.
Q2. In Section C455 Deck Crane: What is the Billy Pugh product rescue basket? There are a few products that could be used for this, and the basket is needed to calculate the man-rated capacity for the crane. Also, is this to be used for harbor conditions?
A2. Billy Pugh Rescue Basket shall be OMB-1 or equal, rated for harbor conditions.
Q3. In Section C615: The original specs and current piping diagram show a single cylinder driving two rudders but the current specs (Section D) refers to 2 cylinders. Please confirm.
A3. The current piping diagram is correct, with a single cylinder driving two rudders.
Q4. In Section C615: The original specs and the current system diagram shows no steering from the engine room control stand but spec section F requires it.
A4. There should be steering controls from the Engine Room Control Stand as required in the specification.
Q5. In Section C615: Section F also requires two rudder angle indicators at each station but since the rudders are now mechanically synchronized by a tie bar, only one indicator per station is required. This section also requires pump running lights but these are normally included with the motor starter and not required in the engine control room for vessels under 50M in length. Please clarify.
A5. A single rudder angle indicator per station is acceptable. Pump running lights can be omitted in the engine room.
Q6. Could the Government please advise if there is a preferred method or specification reference for the Heated Walkway as referenced on the General Arrangement Drawing 826-B215-01 in
Zone 3D? Contractor does not see any reference to this in the solicitation and only sees reference to it on the drawing.
A6. Please disregard. No heated walkway is required on this vessel.
Q7. It has been confirmed by ABS that Load Line requirements only apply to vessels over 79’ in length and that operate outside the boundary line. Further, it is USCG’s policy to not permit the assignment of a Load Line to vessel under 79 feet in length, even if the owner requests it on a voluntary basis. Can the USACE please advise or kindly remove the Load Line requirement?
A7. Per correspondence with ABS, the contractor shall obtain a Statement of Voluntary
Compliance (SoVC) in the ABS plan review.
Q8. Contract Specification C420 Deck Fittings Part C states “Two (2) anchors similar to Fortress
FX-125” shall be used however, Contract Drawing 826-B599-01 calls out a Baldt 240 kg
Anchor. Can the USACE please confirm the type and quantity of anchors required?
A8. C420: Updated section C provides updated language, reflective of the following:
The anchors provided shall be one (1) Baldt 240kg stockless anchor or equal, with one (1)
Fortress FX-125 HHP or equal, backup anchor provided in a stowed location.
Q9. Contract Specification C420 Deck Fitting Part C states “20’ of ½” galvanized chain and
“300’ of ½” wire rope” is required for the Anchor; however, Contract Drawing 826-B599-01 calls for 340’ of 5/8” Wire Rope w/ 20’ of 5/8” Gr 1 chain. Can the USACE please confirm the type and length of rope and chain required?
A9. C420: Updated section C provides updated language, reflective of the following: The anchor line shall be 340' of 5/8" wire rope, with 20' of 5/8" grade 1 chain.
Q10. What is the operating temperature for the crane?
A10. The crane operating temperatures shall be in accordance with ASHRAE standards for New
York, New York.
Q11. Is drawing 397-D730-01 available?
A11. The drawing has been added as part of this amendment.
Q12. Can the Government please advise industry IAW Contract Clause C800 SPARE PARTS if
Contractor is to provide a drawing only for this requirement or is the Contractor to actually provide the list of spare parts? If the latter, please confirm if the Government has a NTE cost/CLIN for spare parts? Or, please confirm if Contractor is to provide a cost for these spare parts, what CLIN is Contractor supposed to include the cost of spare parts on in our response to the Government? C800 references packaging references to spare parts, but since spare parts can be dependent on Contractors choice of manufacturers, please advise the best way to establish price reasonableness on spare parts from the industry so evaluation of bids can be reviewed fairly.
A12. USACE is only requiring a drawing which will contain a complete inventory and list of spares as indicated in section C800. Section D01 and D02 apply to any spare parts the contractor tenders as required by the contract.
Q13. Sewage Tank; Page 26, C315, B states “all of the tanks shall be constructed of mild plate steel and mild structural steel.” Page 73, C667, D states “sewage tank shall be 200 gallon polyethylene tank.” Please clarify.
A13. The sewage tank shall be polyethylene in accordance with section C667.
Q14. Main Engine: Page 53, C605 C. The main engine is specified as having a brake horsepower of 670 (shaft horsepower approx. 645), but the propellers (C606) are specified for a shaft horsepower of 671 which will require a brake horsepower of about 700. Which is correct?
Please clarify.
A14. Section C606 has been updated to reflect 645 HP.
Q15. Insulation: Page 39-40, C436. The specification calls for fiberglass. To get a fire rating above A-0 we believe design will need to use Rockwool insulation. Please clarify.
A15. Section C436 allows the use of mineral wood to meet this requirement.
Q16. Reduction Gear: Page 54, C605, F. The main engine Reduction Gear calls for an internal shaft brake. This feature is not available on the ZF 2350 gear. This feature will require using a
ZF W3310 reverse gear. Please clarify.
A16. Section C605 has been updated to clarify this issue.
SECTION I - CONTRACT CLAUSES
The following have been added by reference:
52.222-3
52.222-4
52.223-6
52.228-2
52.229-3
52.232-1
52.232-9
52.232-13
52.232-23
52.232-25
52.233-1
52.249-2
52.249-8
The following have been added by full text:
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
(a) “Irrevocable letter of credit” (ILC), as used in this clause, means a written commitment by a federally insured financial institution to pay all or part of a stated amount of money, until the expiration date of the letter, upon presentation by the Government (the beneficiary) of a written demand therefor. Neither the financial institution nor the offeror/Contractor can revoke or condition the letter of credit.
(b) If the offeror intends to use an ILC in lieu of a bid bond, or to secure other types of bonds such as performance and payment bonds, the letter of credit and letter of confirmation formats in paragraphs (e) and (f) of this clause shall be used.
(c) The letter of credit shall be irrevocable, shall require presentation of no document other than a written demand and the ILC (including confirming letter, if any), shall be issued/confirmed by an acceptable federally insured financial institution as provided in paragraph (d) of this clause, and--
(1) If used as a bid guarantee, the ILC shall expire no earlier than 60 days after the close of the bid acceptance period;
(2) If used as an alternative to corporate or individual sureties as security for a performance or payment bond, the offeror/Contractor may submit an ILC with an initial expiration date estimated to cover the entire period for which financial security is required or may submit an ILC with an initial expiration date that is a minimum period of one year from the date of issuance. The ILC shall provide that, unless the issuer provides the beneficiary written notice of non-renewal at least 60 days in advance of the current expiration date, the ILC is automatically extended without amendment for one year from the expiration date, or any future expiration date, until the period of required coverage is completed and the Contracting Officer provides the financial institution with a written statement waiving the right to payment. The period of required coverage shall be:
(i) For contracts subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of--
(A) One year following the expected date of final payment;
(B) For performance bonds only, until completion of any warranty period; or
(C) For payment bonds only, until resolution of all claims filed against the payment bond during the one-year period following final payment.
(ii) For contracts not subject to the Miller Act, the later of--
(A) 90 days following final payment; or
(B) For performance bonds only, until completion of any warranty period.
(d)(1) Only federally insured financial institutions rated investment grade by a commercial rating service shall issue or confirm the ILC.
(2) Unless the financial institution issuing the ILC had letter of credit business of at least $25 million in the past year, ILCs over $5 million must be confirmed by another acceptable financial institution that had letter of credit business of at least $25 million in the past year.
(3) The Offeror/Contractor shall provide the Contracting Officer a credit rating that indicates the financial institutions have the required credit rating as of the date of issuance of the ILC.
(4) The current rating for a financial institution is available through any of the following rating services registered with the U.S. Securities and Exchange Commission (SEC) as a Nationally Recognized Statistical Rating
Organization (NRSRO). NRSRO's can be located at the Web site http://www.sec.gov/answers/nrsro.htm maintained by the SEC.
(e) The following format shall be used by the issuing financial institution to create an ILC:
[Issuing Financial Institution's Letterhead or Name and Address]
Issue Date _ ___
IRREVOCABLE LETTER OF CREDIT NO. ___
Account party's name ___ _
Account party's address ___ _
For Solicitation No. ___ _(for reference only)
TO: [ ___ U.S. Government agency]
[ ___ U.S. Government agency's address]
1. We hereby establish this irrevocable and transferable Letter of Credit in your favor for one or more drawings up to United States $ ___ . This Letter of Credit is payable at [issuing financial institution's and, if any, confirming financial institution's] office at [ ___ issuing financial institution's address and, if any, confirming financial institution's address] and expires with our close of business on ___ , or any automatically extended expiration date.
2. We hereby undertake to honor your or the transferee's sight draft(s) drawn on the issuing or, if any, the confirming financial institution, for all or any part of this credit if presented with this Letter of Credit and confirmation, if any, at the office specified in paragraph 1 of this Letter of Credit on or before the expiration date or http://www.sec.gov/answers/nrsro.htm any automatically extended expiration date.
3. [This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.] It is a condition of this Letter of Credit that it is deemed to be automatically extended without amendment for one year from the expiration date hereof, or any future expiration date, unless at least 60 days prior to any expiration date, we notify you or the transferee by registered mail, or other receipted means of delivery, that we elect not to consider this
Letter of Credit renewed for any such additional period. At the time we notify you, we also agree to notify the account party (and confirming financial institution, if any) by the same means of delivery.
4. This Letter of Credit is transferable. Transfers and assignments of proceeds are to be effected without charge to either the beneficiary or the transferee/assignee of proceeds. Such transfer or assignment shall be only at the written direction of the Government (the beneficiary) in a form satisfactory to the issuing financial institution and the confirming financial institution, if any.
5. This Letter of Credit is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No. ___ -- (Insert version in effect at the time of ILC issuance, e.g., ``Publication 600, 2006 edition'') and to the extent not inconsistent therewith, to the laws of
___ --[State of confirming financial institution, if any, otherwise State of issuing financial institution].
6. If this credit expires during an interruption of business of this financial institution as described in Article 17 of the
UCP, the financial institution specifically agrees to effect payment if this credit is drawn against within 30 days after the resumption of our business.
Sincerely, [ ___ Issuing financial institution]
(f) The following format shall be used by the financial institution to confirm an ILC:
___ [Confirming Financial Institution's Letterhead or Name and Address]
(Date) ___
Our Letter of Credit Advice Number ___
Beneficiary: ___ [U.S. Government agency]
Issuing Financial Institution: ___
Issuing Financial Institution's LC No.: ___
Gentlemen:
1. We hereby confirm the above indicated Letter of Credit, the original of which is attached, issued by ___ [name of issuing financial institution] for drawings of up to United States dollars ___ _/U.S. $ ___ and expiring with our close of business on ___ [the expiration date], or any automatically extended expiration date.
2. Draft(s) drawn under the Letter of Credit and this Confirmation are payable at our office located at ___ _.
3. We hereby undertake to honor sight draft(s) drawn under and presented with the Letter of Credit and this
Confirmation at our offices as specified herein.
4. [This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.] It is a condition of this confirmation that it be deemed automatically extended without amendment for one year from the expiration date hereof, or any automatically extended expiration date, unless:
(a) At least 60 days prior to any such expiration date, we shall notify the Contracting Officer, or the transferee and the issuing financial institution, by registered mail or other receipted means of delivery, that we elect not to consider this confirmation extended for any such additional period; or
(b) The issuing financial institution shall have exercised its right to notify you or the transferee, the account party, and ourselves, of its election not to extend the expiration date of the Letter of Credit.
5. This confirmation is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International
Chamber of Commerce Publication No. ___ -- (Insert version in effect at the time of ILC issuance, e.g., ``Publication 600, 2006 edition'') and to the extent not inconsistent therewith, to the laws of ___ --[State of confirming financial institution].
6. If this confirmation expires during an interruption of business of this financial institution as described in Article
17 of the UCP, we specifically agree to effect payment if this credit is drawn against within 30 days after the resumption of our business.
Sincerely, [Confirming financial institution]
(g) The following format shall be used by the Contracting Officer for a sight draft to draw on the Letter of Credit:
SIGHT DRAFT
[City, State]
(Date) ___
[Name and address of financial institution]
Pay to the order of ___ [Beneficiary Agency] ___ the sum of United States ___ This draft is drawn under
Irrevocable Letter of Credit No. ___
___ [Beneficiary Agency]
By: ___
(End of clause)
52.232-16 PROGRESS PAYMENTS (APR 2012)
The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:
(a) Computation of amounts. (1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under FAR 31.205-10 as an incurred cost for progress payment purposes.
(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors--
(i) In accordance with the terms and conditions of a subcontract or invoice; and
(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.
(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless--
(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and
(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).
(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:
(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.
(ii) Costs incurred by subcontractors or suppliers.
(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.
(iv) Payments made or amounts payable to subcontractors or suppliers, except for --
(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and
(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.
(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor
(ii) the value, for progress payment purposes, of the incomplete work. Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.
(6) The total amount of progress payments shall not exceed 80 percent of the total contract price.
(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs
(a)(4) or (a)(5) of this clause, the Contractor shall repay the amount of such excess to the Government on demand.
(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting Officer may make exceptions.
(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.
(b) Liquidation. Except as provided in the Termination for Convenience of the Government clause, all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The
Contractor shall repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.
(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:
(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs (f) and (g) of this clause).
(2) Performance of this contract is endangered by the Contractor's --
(i) Failure to make progress or
(ii) Unsatisfactory financial condition.
(3) Inventory allocated to this contract substantially exceeds reasonable requirements.
(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.
(5) The fair value of the undelivered work is less than the amount of unliquidated progress payments for that work.
(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph (b) of this clause, and that rate is less than the progress payment rate stated in subparagraph (a)(1) of this clause.
(d) Title.
(1) Title to the property described in this paragraph (d) shall vest in the Government. Vestiture shall be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture shall occur when the property is or should have been allocable or properly chargeable to this contract.
(2) "Property," as used in this clause, includes all of the below-described items acquired or produced by the
Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.
(i) Parts, materials, inventories, and work in process;
(ii) Special tooling and special test equipment to which the Government is to acquire title;
(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under paragraph (d) (2)(ii) of this clause; and
(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the
Government by other clauses of this contract.
(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.g., the termination clauses, shall determine the handling and disposition of the property.
(4) The Contractor may sell any scrap resulting from production under this contract without requesting the
Contracting Officer's approval, but the proceeds shall be credited against the costs of performance.
(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the
Contractor must obtain the Contracting Officer's advance approval of the action and the terms. The Contractor shall
(i) exclude the allocable costs of the property from the costs of contract performance, and (ii) repay to the
Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.
(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title shall vest in the Contractor for all property (or the proceeds thereof) not--
(i) Delivered to, and accepted by, the Government under this contract; or
(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the Government under this clause.
(7) The terms of this contract concerning liability for Government-furnished property shall not apply to property to which the Government acquired title solely under this clause.
(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor shall bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor shall repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is lost (see 45.101).
(f) Control of costs and property. The Contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.
(g) Reports, forms, and access to records. (1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the
Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.
(2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor's best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.
(3) Each Contractor request for progress payment shall:
(i) Be submitted on Standard Form 1443, Contractor's Request for Progress Payment, or the electronic equivalent as required by agency regulations, in accordance with the form instructions and the contract terms; and
(ii) Include any additional supporting documentation requested by the Contracting Officer.
(h) Special terms regarding default. If this contract is terminated under the Default clause, (i) the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments and (ii) title shall vest in the
Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the Default clause. The Government shall be liable for no payment except as provided by the Default clause.
(i) Reservations of rights.
(1) No payment or vesting of title under this clause shall --
(i) Excuse the Contractor from performance of obligations under this contract or
(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government's rights and remedies under this clause
(i) Shall not be exclusive but rather shall be in addition to any other rights and remedies provided by law or this contract and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(j) Financing payments to subcontractors. The financing payments to subcontractors mentioned in paragraphs (a)(1) and (a)(2) of this clause shall be all financing payments to subcontractors or divisions, if the following conditions are met:
(1) The amounts included are limited to--
(i) The unliquidated remainder of financing payments made; plus
(ii) Any unpaid subcontractor requests for financing payments.
(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery; or, if the subcontractor is a small business concern, 4 months.
(3) If the financing payments are in the form of progress payments, the terms of the subcontract or interdivisional order concerning progress payments--
(i) Are substantially similar to the terms of this clause for any subcontractor that is a large business concern, or this clause with its Alternate I for any subcontractor that is a small business concern;
(ii) Are at least as favorable to the Government as the terms of this clause;
(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;
(iv) Are in conformance with the requirements of FAR 32.504(e); and
(v) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if--
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments--
(i) Are substantially similar to the Performance-Based Payments clause at FAR 52.232-32 and meet the criteria for, and definition of, performance-based payments in FAR Part 32;
(ii) Are in conformance with the requirements of FAR 32.504(f); and
(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if--
(5) If the financing payments are in the form of commercial item financing payments, the terms of the subcontract or interdivisional order concerning payments--
(i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial item purchase that meets the definition and standards for acquisition of commercial items in FAR Parts 2 and 12;
(ii) Are in conformance with the requirements of FAR 32.504(g); and
(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if--
(6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern.
(7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the Government to the Contractor under this contract.
(8) If no unliquidated financing payments to the Contractor remain, but there are unliquidated financing payments that the Contractor has made to any subcontractor, the Contractor shall be subrogated to all the rights the
Government obtained through the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.
(9) To facilitate small business participation in subcontracting under this contract, the Contractor shall provide financing payments to small business concerns, in conformity with the standards for customary contract financing payments stated in Subpart 32.113. The Contractor shall not consider the need for such financing payments as a handicap or adverse factor in the award of subcontracts.
(k) Limitations on undefinitized contract actions. Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation shall apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and shall remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation shall be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions shall be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized. The amount of unliquidated progress payments for undefinitized contract actions shall not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract. Separate limits may be specified for separate actions.
(l) Due date. The designated payment office will make progress payments on the 30th day after the designated billing office receives a proper progress payment request. In the event that the Government requires an audit or other review of a specific progress payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date. Progress payments are considered contract financing and are not subject to the interest penalty provisions of the Prompt Payment Act.
(m) Progress payments under indefinite--delivery contracts. The Contractor shall account for and submit progress payment requests under individual orders as if the order constituted a separate contract, unless otherwise specified in this contract.
(End of clause)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
DOCUMENTS & ATTACHMENTS
J01 CONTRACT & REFERENCE DRAWINGS
The following drawings form a part of the design package. All drawings will be provided to the successful bidder in electronic file form. The below drawings shall be updated by the contractor during Phase I of the contract and submitted to ABS for regulatory review.
A. CONTRACT DRAWINGS
Drawing Number Title Revision
826-B105-01 HULL LINES B
826-B145-01 TONNAGE DIAGRAM B
826-B205-01 OUTBOARD PROFILE E
826-B215-01 GENERAL ARRANGEMENT I
826-B305-01 HULL SCANTLING PLAN F
826-B305-02 LONGITUDINAL STRUCTURE H
826-B309-01 TRANSVERSE HULL SECTIONS F
826-B315-02 DECKHOUSE SCANTLINGS E
826-B406-01 MDC STANDARD FLOATING PLANT PAINT
SCHEDULE -
826-B445-01 FIRE & SAFETY PLAN D
826-B599-01 ANCHOR SYSTEM DETAILS D
826-B601-01 PIPE MARKING GUIDE -
826-B605-02 SHAFTING & ASSEMBLY F
826-B615-01 STEERING ARRANGEMENT & DETAILS G
826-B620-01 BOW THRUSTER C
826-B630-01 FUEL OIL SYSTEM D
826-B640-01 ENGINE COOLING SYSTEM D
826-B650-01 ENGINE EXHAUST SYSTEM D
826-B660-01 BILGE SYSTEM PIPING C
826-B710-01 ELECTRICAL LOAD ANALYSIS -
826-B720-01 ELECTRICAL SYSTEM ONE-LINE
DIAGRAM (AC&DC) -
B. REFERENCE DRAWINGS
Drawing Number Title Revision
397-D317-01 MASTS 0
397-D320-01 POTABLE WATER TANK CONSTRUCTION 0
397-D420-01 DECK FITTINGS, BOAT DAVITS AND CHOCKS 0
397-D425-01 RAILINGS AND LADDERS 0
397-D660-01 BILGE SYSTEM PIPING 0
397-D665-01 POTABLE WATER SYSTEM 0
397-D667-01 SEWAGE AND SANITARY SYSTEM 0
397-B675-01 FIRE MAIN PIPING 0
397-D730-01 LIGHTING PLAN -OUTBOARD PROF 0
397-D730-02 LIGHTING PLAN 0
793-B725-01 CABLE SCHEDULE & VOLTAGE DROP (AC) 0
793-B725-02 CABLE SCHEDULE & VOLTAGE DROP (DC) 0
J02 NOT USED
J03 ENG 2454
J04 PERFORMANCE EVALUATION FOR SERVICE & SUPPLY CONTRACTS
In accordance with Federal Acquisition Regulation 42.15, this contract action is subject to the requirement for Contractor performance evaluation.
At a minimum, the performance evaluation shall be completed within 45 days of completion of each year’s performance. Additional (interim) evaluations may be prepared if any element listed is being performed unsatisfactorily.
The period of evaluation will begin on the date of acknowledgment of receipt of the Notice to Proceed and will run concurrent with the performance period of the resulting contract.
(End of Summary of Changes)