FORMERLY UTILIZED SITES REMEDIAL ACTION PROGRAM (FUSRAP)
Solicitation number
W912BU17R0002
Issued by

About this file

Attachment 4 - 17-R-0002 - PWS TO 2 (revised).pdf

View the file

Other files

File Type Posted
W912BU-17-R-0002_-_Amendment_0004.pdf PDF
O&M_Appendix_F__Benchscale_Treatability_Report.pdf PDF
FUSRAP_DuPont_-_Construction_Stormwater_Permit_061614.pdf PDF
FUSRAP_DuPont_-_Water_Allocation_permit_100114.pdf PDF
FUSRAP_-_Corp_Experience_Summary_Template.pdf PDF
Attachment_3_-_17-R-0002_-_PWS_TO_1_(revised).pdf PDF
W912BU-17-R-0002_-_Amendment_3.pdf PDF
O&M_Appendix_B_Hazleton_100gpm_WWTP_O&M_Manual_-BOOKMARKED.pdf PDF
DuPont_FUSRAP_Approved_Suppliers_list.pdf PDF
Attachment_6_-_17-R-0002-Bid_Schedule_(revised).pdf PDF
O&M_Appendix_E_Startup_Checklist,_Monitoring_and_Reporting_Forms.pdf PDF
FUSRAP_DuPont_-_NPDES_DSW_Permit_Equivalent_INITIAL_052914.pdf PDF
O&M_Appendix_G_Software_Logic_and_Loop_Control_Instructions.pdf PDF
CABRERA_2011a._Memorandum_USACE_Determination_of_Eligible_Contaminants_for_FUSRAP,_Investigation,_DuPont_Chambers_Works_FUSRAP_Site,_Deepwater,_NJ._June_2011..pdf PDF
O&M_Appendix_D_Discharge_Criteria_and_Associated_Permits.pdf PDF
FUSRAP_Non-Hazardous_Waste_Manifest_Report.pdf PDF
FUSRAP_DuPont_-_NPDES_DSW_MOD2_(DIOXIN).pdf PDF
FUSRAP_DuPont_-_NPDES_DSW_MOD1_(SALT_WATER_LIMS).pdf PDF
FUSRAP_Bidders_Site_Visit_Photos.pdf PDF
FUSRAP_DuPont_-_TWA_permit_17_July_2014.pdf PDF
O&M_Appendix_A_Vendor_Manuals_and_Product_Data_-_BOOKMARKED.pdf PDF
O&M_Appendix_C_P&ID_and_Design_Drawings.pdf PDF
FUSRAP_DuPont_-_FHA_Permit_081214.pdf PDF
W912BU-17-R-0002_-_Amendment_2.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
10.2.1_-_Bechtel_National_-_1985_Radiological_Survey_Report_(3-1985).pdf PDF
10.2.4c_-_2011c_-_BRA_-_Appendix_E.pdf PDF
10.2.8_-_ECC_-_CWTP_OM_Manual_B_Code.pdf PDF
10.2.13_-_2013_Record_of_Decision_-_DuPont_Chambers_Works_Sep_-2013.pdf PDF
10.2.6_-_2012b_-_Proposed_Plan_Nov_2012.pdf PDF
10.2.4_-_2011c_-_Baseline_Risk_Assessment.pdf PDF
10.2.4d_-_2011c_-_BRA_-_Appendix_H.pdf PDF
10.2.12_-_Statement_of_Guiding_Principles.pdf PDF
10.2.5c_-_2012_-_Combined_Sect_2.pdf PDF
10.2.9-_ECC_-_As-Left_Report.pdf PDF
W912BU-17-R-0002_-_Amendment_0001.pdf PDF
10.2.5d_-_2012_-_Combined_Sect_3_4_5.pdf PDF
10.2.4b_-_2011c_-_BRA_-_Appendix_A-D,_F,_G,_I-K.pdf PDF
10.2.5b_-_2012_-_Combined_Sect_1.pdf PDF
10.2.7_-_ECC_-_FUSRAP_UFP-QAPP_2014.pdf PDF
10.2.5_-_2012_-_Feasability_Study_Oct_2012.pdf PDF
Attachment_2_-_17-R-0002_-_Scope_of_Work_(Apendix_D).pdf PDF
Attachment_4_-_17-R-0002_-_PWS_TO_2.pdf PDF
Attachment_3_-_17-R-0002_-_PWS_TO_1.pdf PDF
Attachment_5_-_PPQ_from_UAI_15-1.pdf PDF
Attachment_6_-_17-R-0002_-_Bid_Schedule.pdf PDF
W912BU-17-R-0002_-_RFP.pdf PDF
Attachment_1_-_17-R-0002_-_Scope_of_Work.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C:\Users\e5ctcmwh\Desktop\FUSRAP\17-R-0002\Amendment 003\WIP\Attachment 4 - 17-R-0002 - PWS TO 2 (revised).docx1

FormerDuPontChambersWorksFUSRAP
RemedialAction
TaskOrder002

Performance Work Statement

Remediation Services

1.0 PROJECT OVERVIEW

The United States Army Corps of Engineers (USACE) is conducting the environmental restoration of the former DuPont Chambers Works Formerly Utilized Sites Remedial Action Program (FUSRAP) site. USACE is addressing radiological contamination at the site, resulting from past uranium refinement, scrap recycling and research performed for the Manhattan Engineer District (MED) and Atomic Energy Commission (AEC) in the early years of the nation’s atomic energy program. USACE is issuing this Performance Work Statement (PWS) under the requirements of the CERCLA of 1980, as amended, 42 United States Code (U.S.C.) § 9617(a), and the NCP, 40 CFR § 300.430(f)(2).

1.1 Background

The former DuPont Chambers Works site is an active chemical manufacturing facility, located in Salem County, New Jersey now run by Chemours. In the 1940s, E. I. du Pont de Nemours and Company performed work for the Federal Government in support of the nation’s early atomic energy program. The USACE is addressing residual radioactive contamination in specific areas of the property under the FUSRAP. The areas are collectively referred to as the DuPont FUSRAP site.

USACE identified the FUSRAP-eligible constituents of concern in site soils that were related to the uranium processing and research activities at the site and that could pose a risk to human health under an industrial land use scenario. Constituents of concern are uranium, thorium, and radium;

specifically Uranium-234 (234U), Uranium-235 (235U), Uranium-238 (238U), Thorium-230 (230Th), and Radium-226 (226Ra). The Remedial Action (RA) recommended in the Proposed Plan and selected in the Record of Decision, signed on September 12, 2013, only addresses these FUSRAP-

PWS TO 2 (revised).docx2 eligible constituents of concern and does not address other hazardous contaminants that may be present at the site.

1.2 Prior Remedial Action

A Remedial Action contract was awarded in 2013. The Contractor began performing work in 2014, with excavations commencing in the fall of 2014. In the winter of 2015 previously unidentified areas of contamination were found, nearly doubling the estimated volume of waste to be excavated under the contract (from 25,000 cubic yards (cy) to almost 45,000 cy). Of this volume, approximately 27,000 cy of soil (in situ) remains to be excavated and disposed offsite. Contract capacity and funding for the increased work was insufficient and the contract was ultimately terminated for the convenience of the Government.

During the execution of the remedial activities, several excavations were started in two separate Areas of Concern (AOCs) of the site currently controlled and fenced off by USACE. The first is AOC 6 of Operable Unit (OU) 3 and is located on the eastern portion of the Chemours facility; this area is also known as the eastern burial area. The second area consists of AOCs 1 and 2 of OU1 and is located in the northwest quadrant of the Chemours facility; this area is also referred to as F-corral. Two excavations in AOC-1 in F-corral and one excavation in AOC-6 currently remain open and contain ponded water; potentially contaminated soils along the excavation sidewalls are covered with plastic liner.

Also within the fenced area of F-corral are the existing site work trailers, the Waste Transfer Facility (WTF), and the construction water treatment plant (CWTP). The WTF consists of an elevated platform which can store about 1,000 cy of contaminated soils, is used for loading of contaminated soils into railcars, and is located directly adjacent to the rail spur. The CWTP was successfully used to treat groundwater from the excavations; this plant has been drained and shutdown and routine maintenance activities are being conducted to ensure viability of the plant for re-start. Additionally, some rental components were demobilized from the CWTP and will need to be replaced (as part of this task order).

As-left site conditions, including estimated remaining volumes for each AOC are detailed in the Contractor-prepared closure documents, including site figures prepared by the previous Contractor.

Additionally, RA radiological data is available to document all completed efforts .

2.0 SCOPE OF WORK:

The contractor shall provide qualified personnel to complete the major work items listed in this section as part of this task order. Note that this task order will be for work performed within one year from award. Follow-on task orders for additional years of work may be issued at a later date by the Government.

2.1 Detailed Scope

The scope of services includes but is not limited to, the following activities related to the RA at the DuPont FUSRAP site:

PWS TO 2 (revised).docx3

1. Excavation of contaminated soils with total uranium concentrations above the remediation goal of 65 picocuries/gram (pCi/g).

2. Physical separation and management of excavated material to minimize Class 7 radioactive materials and mixed waste. The mixed waste which includes both radiological and chemical constituents (note updated regulatory guidance) is more expensive to dispose of.

3. Loading excavated soil into rail cars at the WTF.

4. Transporation of individual rail cars within the project area for loading and staging.

Chemours rail services will transport the cars from the F corral location to the Chemours entrance.

5. Transportation of excavated soils by rail to an off-site licensed/permitted disposal facility.

6. Disposal of excavated soils at an off-site licensed/permitted disposal facility approved by the

USACE.

7. Backfilling and compaction of excavated areas with approved backfill.

8. Reactivation, operation and maintainance of the onsite construction water treatment plant

(CWTP); This includes mobilization to the site of any groundwater treatement plant units that were rented and demobilized by the previous Remedial Action Contractor.

9. Recovery of groundwater, some storm water, and non-aqueous phase liquids and treatment of recovered water in the CWTP.

10. Treatment of liquids at the CWTP to meet groundwater treatment permit levels. It is the Contractors responsibility to provide a CWTP that can adequately process contaminated surface or groundwater.

11. Testing and release of treated water treated in accordance with the site NJDEP discharge criteria into the Central Drainage Ditch.

12. Further delineation of radiologically contaminated areas.

13. Removal of substantial concrete foundations within excavation area.

14. Removal of partially intact chemical drums that are currently visible and others that are not yet known.

15. Possible removal of fully intact chemical drums (which may be encountered in the future).

16. Excavation work in level C.

17. Possible excavation work in level B.

18. Recovery of floating free-phase product in water-filled excavations to the extent necessary to complete the excavations.

19. Disposal of free-phase product which has been separated from water in the treatment plant.

20. Diversion of the Central Drainage Ditch is part of the upcoming work.

21. The Chemours facility has very antiquated infrastructure which will likely affect the upcoming excavation. Problems encountered in the past include;

a. Large Chemours clean water pipes leaking into excavations.

b. On-site Chemours building adjacent to WTF with an exterior wall leaning towards

WTF.

c. Cracks on retaining wall between RR tracks and WTF

d. Railroad track replacement.

22. Performance of a final status survey to verify that the completed RA meets the soil remediation goal in accordance with MARSSIM requirements;

23. Restoration of site to pre-existing conditions or as otherwise directed by USACE including:

a. Backfill and compaction of all excavations.

b. Note that three open excavations are present at the site, for these excavations, pre-existing shall be defined as their conditions prior to any excavation that has already

PWS TO 2 (revised).docx4 occurred.

24. Implementation of land use controls to limit potential onsite exposure to contaminants during

RA activities.

25. The contractor is responsible for backfilling the site with a Government-approved backfill material.

26. The contractor is responsible for compliance with all existing permit equivalents (found in task order #1).

27. Potential additional future work could include further excavation/delineation. The furthest extents of contamination will determine if potential additional work will be needed. That work could include items such as;

a. Demolition and construction of a small railroad bridge over the Central Drainage Ditch

b. Excavation under railroad tracks followed by replacement of Railroad tracks.

c. Excavation of contamination under active Chemours pipe racks

Note that the potential contamination under the railroad tracks and adjacent to the railroad bridge could cut off the WTF from the rail line requiring an alternate loading area

The scope of this work does not include addressing non-FUSRAP-related contamination that may be associated with past DuPont FUSRAP site chemical manufacturing operations unless it happens to be commingled with materials related to the FUSRAP remediation. Non-FUSRAP contaminants will be removed along with the eligible FUSRAP contaminants only to the extent necessary to successfully complete the FUSRAP response action. Comingling can be found in both soils and groundwater. Free-phase product has been found at the site in soil, groundwater and surface water which must be addressed as necessary. Free-phase product shall be only removed when it is within excavated soils, enters the CWTP, or is found floating on the surface water within excavations and must be removed to complete the excavation.

To assist in meeting the objectives of the PWS, the Government is providing the following documents:

Previous Contractor Documents

ECC 2016. As Left Report Remediation Services Formerly Utilized Sites Remedial Action Program at the DuPont Chambers Works Site Deepwater, New Jersey

As Built Drawings.

CWTP O&M Manual.

Final Status Survey Report.

3.0 WORK BREAKDOWN STRUCTURE

The Contractor shall conduct all activities in compliance with applicable federal, state, and local laws, regulations, and guidance. The Contractor shall comply with the provisions of this PWS and other Government provided documentation.

PWS TO 2 (revised).docx5

The work breakdown structure (WBS) and Work Authorization Documents (WAD) for this project is as follows:

WAD 1 General Conditions WAD 2 Excavation and Backfilling WAD 3 Waste Loading, Transportation and Disposal WAD 4 CWTP Operations and Maintenance WAD 5 Restoration WAD 6 Fixed Fee

Technical Direction letters will be utilized by the Government to authorize the Contractor to work on specific work elements of each WAD, or portions of WADs. The proposed value of any WAD cannot be exceeded without a contract modification. The Contractor shall notify USACE when 50% and 75% of the proposed value for each WAD has been expended. The contractor shall develop project-specific Standard Operating Procedures (SOP’s), which document the day-to-day cost management processes and procedures which will be followed for the administration of this cost reimbursable contract.

3.1 Project Schedule Constraints

Following are several time and schedule considerations to be made in maintaining the project schedule.These consist of Government-required project schedule obligations which the contractor shall adhere to as well as schedule obligations that the Government will adhere to.

1) On-site work days are assumed to be Monday through Friday, excepting Federal holidays, with a maximum of 10 hours per day; USACE anticipates up to a 12-month work year for this task order. The contractor may elect to work through the winter if desired, and if the contractor believes that this is more efficient and cost effective than shutting down and mothballing the site for three months. Note: working year round will also depend on USACE funding availability. This schedule may be modified with USACE Contracting Officer approval.

2) Contractor shall update the schedule as part of the PWS 1 scope.

3.2 General Conditions (WAD 1)

The Contractor shall provide project management support as necessary to perform the activities detailed in this PWS. The contractor must clearly separate project management costs and assign them to a task order. It is assumed that this WAD will provide the overall project management support for the entire task order #2 work. The Contractor shall provide technical and management support to meetings required to fulfill the objectives. The Contractor shall prepare minutes of the conference calls and meetings conducted for the duration of this project. The minutes for each meeting shall be prepared and posted to The file sharing website, initially in draft form for review and comment, and shall be finalized based on review comments received. Once approved, the final minutes shall be posted.

3.2.1 Project Kick-Off Meetings

There will be three kick-off meetings scheduled after award which will include the Pre-Construction Conference (about 2 hours), the QC/QA Understanding Meeting (2 hours), and the Pre-Work Safety Meeting (2 hours). Assume the meeting will be held at the DuPont FUSRAP site, in Deepwater, NJ.

PWS TO 2 (revised).docx6

Before making travel arrangements, the Contractor shall contact USACE so access arrangements can be made. The Contractor shall prepare and submit a letter containing meeting minutes to the USACE within 10 days after each site visit has been completed.

3.2.2 Document and Report Review

Following receipt of review comments on a deliverable, the Contractor shall prepare and submit draft responses to comments. After USACE approval of the draft responses to comments, the contractor shall submit the final submittal with all review comments addressed. Based on the agreements reached during the review conferences, the Contractor shall prepare and distribute the response to comments (RTCs).

The Contractor shall prepare and submit monthly progress reports to the Project Manager (PM) for the duration of the contract. The reports shall include details concerning the project management and fieldwork activities conducted, deliverables submitted, communications initiated and received, areas excavated, volume of soil excavated and disposed offsite, number rail cars on site, number rail cars shipped offsite, number of rail cars emptied at the disposal site, monthly demurrage fees (if any) summary of sample results, summary of CWTP operations (water treated) and any exceedances or other problems encountered, and other activities that were started, progressed, or completed, and meetings attended

The Contractor shall host a weekly progress meeting with USACE for the duration of the task order.

This will be done via conference call and/or on-site. The Contractor will prepare the weekly agenda, with input from USACE, host the meeting and prepare all necessary minutes as described above. The Contractor is responsible to maintain and distribute an open items list that identifies action items resulting from meetings and other communications, the party responsible for completing the action item, and the date the action item is due to be completed and the actual completion date.

The Contractor shall attend all meetings called by the Contract Officer’s Representative (COR) for the purpose of discussing status and issues related to this contract, examine the progress of work activities, and provide support and guidance.

The Contractor shall prepare meeting minutes and/or Memorandum for Record (MFR) of each meeting.

All such documentation shall be posted within seven (7) calendar days following each meeting or conference. All verbal conversations with entities outside USACE shall be documented in writing.

3.2.3 Project Brief to Chemours Management

The Contractor shall prepare for and assist USACE in hosting a project briefing for Chemours Management to discuss the DuPont FUSRAP project and its progress. The Contractor shall assume a four (4) hour meeting with three (3) professional staff in attendance at the meeting. The Contractor shall also assist USACE with preparation of presentation materials, to include the compilation of a project fact sheet. For bidding purposes, the Contractor shall assume one (1) Chemours management meeting to support.

PWS TO 2 (revised).docx7

3.2.4 Project Brief to Chemours Employees

The Contractor shall prepare for and assist USACE in hosting a project briefing for Chemours employees to discuss the DuPont FUSRAP project, its progress, and to address any employee concerns

– especially with regard to health and safety. The Contractor shall assume a two-hour meeting with three (3) professional staff in attendance at the meeting. For bidding purposes, the Contractor shall assume one annual meeting for this task order.

3.4 Implementation

The Contractor shall implement RA activities in accordance with the approved Work Plans, in order to meet the objectives of this PWS.

3.4.1 Excavation and Backfilling (WAD 2)

The Contractor shall implement the work at the DuPont FUSRAP site in accordance with the approved Work Plans and associated permits. The contractor shall be required to obtain excavation permits, work permits, and hot work permits from Chemours for the work required under this task order. Work cannot proceed until after permit approval by Chemours.Also, the contractor shall be required to perform all site operations in accordance with existing NJDEP permit equivalent requirements. All NJDEP permit equivalents will be obtained/updated as needed, and adminsistered under Task Order #1 (see section 2.5 Task Order #1).

Approximately 27,000 cubic yards of waste materials are anticipated to require excavation during completion of the RA activities under this contract. USACE anticipates that approximately 4,500 cubic yards of soil shall be excavated, and that approximately 4,500 cubic yards of clean soil shall be imported and used as backfill during this task order. Table 1 lists and provides volume estimates (for bidding purposes only) of waste quantities to be excavated by area.

Table 1: Waste Materials - Estimated Volumes

Area Remaining CY To Excavate (in situ yds)

SU#1 4687

SU#2 10496

SU#3 4878

SU#4

SU#5 4241

Road 160 Rail Spur 2527

TOTAL 26,989

3.4.2 Waste Loading, Transportation and Disposal (T&D) (WAD 3)

USACE anticipates that approximately 4,500 cubic yards of waste soil shall be loaded, transported, and disposed offsite during this task order. This is further divided into an expected 2,250 cubic yards of mixed (chemical and radiological) waste and 2,250 cubic yards of radiologic waste.

PWS TO 2 (revised).docx8

Transportation to the selected disposal facility will occur by rail-only. The Contractor will be required to, at a minimum, package waste shipments and load railcars. The contractor shall provide a unit price (per cy) for waste loading. The transportation subcontract will be awarded dependent upon the selected disposal facility(ies). The Contractor shall provide a price for disposal per cubic yard of both mixed waste and radiological waste based on competitive bidding. The proposed transportation subcontract need to include specific discussion of demurrage. Due to recent regulatory guidance, the Contractor should pay particular attention to 49 CFR § 173. The Contractor shall consider the most cost-effective transportation and disposal options.

The Contractor must clearly define the costs for demurrage including rail car demurrage. The Government believes demurrage can be avoided, however if the contractor plans on having demurrage fees as a part of their bidding strategy, these costs must be included in the contractor’s bid.

The Government intends to solicit T&D services concurrent with this solicitation against the Multiple Award Radiological Transportation and Disposal Services (MARTADS) contract in order assess and select the most cost effective pricing for T&D efforts at DuPont FUSRAP. If the T&D option is provided by the MARTADS, the contractor will be required to coordinate with a separate T&D contractor regarding waste shipments. For purposes of bidding the Contractor shall assume that T&D efforts are to be included in their proposal..

3.4.3 CWTP Operations and Maintenance (WAD 4)

The Contractor shall utilize the CWTP that currently exists on site for the duration of the field effort defined in this task order. Records of operation of the CWTP by the previous contractor showed that the volume of water treated under batch conditions was generally in the range of approximately 200,000 gallons per month, while volume under continuous treatment conditions was up to approximately 800,000 gallons per month. USACE expects that the CWTP will be operated, at least initially, under batch conditions, thus it is more likely that the contractor can expect to treat up to approximately 200,000 gallons per month.

The Contractor shall follow the USACE-approved O&M plan submitted in Task Order #1. Future modifications of the CWTP may be required to address additional contaminants which may be encountered during removal of waste. For purposes of bidding, it should be assumed that no additional contaminants will be encountered. Additional possible efforts specified in section 4.1 are possible such as excavation under an in-sevice pipe rack plus excavation under and possible replacement of a small rail bridge. For bidding purposes these items are not to be included.

The contractor shall be required to:

Perform startup of CWTP including mobilization of rental equipment that had previously been removed from the site, reassembly of all components, verification of operability of components including mechanical, electrical, computer, plumbing connections, etc.

Operate CWTP with proper personnel including oneoperator with NJDEP WWTP N-3-rated operator license, one operator with NJDEP WWTP N-2-rated operator license, plus any other required personnel such as electrician, plumber, mechanic, computer IT, etc.

Treat water from excavations and accumulated rainwater runoff to meet the site specific NJDEP treatment and discharge limits of the permit

PWS TO 2 (revised).docx9

Stock required chemicals and supplies Obtain required subcontracts Develop strategies for storing, treating, and discharging water in batch mode (initially), and possibly continuous mode later on.

Perform data collection and comply with storage and system documentation requirements

The CWTP requires licensed N3 operators to run the plant. The Contractor shall be responsible for all Operations and Maintenance of the CWTP and all infrastructure required to store and transport water to the CWTP. While the CWTP has had heat tracing and insulation installed, it is not entirely freeze proof, and the contractor may need to supplement this freeze proofing to the extent necessary. The It is the contractor’s responsibility to keep the CWTP and associated piping and tank in operation, if required, during the winter months. In the event that work is stopped and the CWTP is shut down for the 3-month winter period, freeze protection will not be required. Under this scenario, the CWTP tanks and lines will need to be drained.

3.4.4 Restoration (WAD 5)

The Contractor shall implement the Site Restoration Plan to return the site to previous conditions, or as otherwise directed by USACE. Restoration shall include compaction required for adequate resurfacing with no permanent water-filled depressions associated with subsurface settlement for a period of one year. Areas of the site where soil has been excavated (including the three currently open exavations) will be backfilled and compacted in controlled lifts with clean soil from a USACE-approved off-site source and returned to its present condition. All backfillmust meet New Jersey Insdustrial standards. The Contractor should assume that site restoration will be completed at the surface with six-inches of gravel. The only exception to this would be in the event that excavation occurs in a roadway, however this is not anticipated. The clean fill material shall be tested prior to placement to ensure it meets the above criteria.

3.5 Fixed Fee (WAD 6)

This award will be a cost plus fixed-fee service contract. The Contractor shall provide separate accounting for all fee-bearing activities.

4.0 DELIVERABLES

4.1 Document Requirements

The Contractor shall regularly update the The file sharing website initiated in Task Order #1 to allow the team to share information on the project. The The file sharing website will need to be updated on a weekly basis.

Anticipated deliverables are included in task order #1, however, other documents may be needed for this task order. Similar to the requirements for task order #1, all documents must be produced with at least Draft, Draft-Final, and Final versions and uploaded to the Contractor The file sharing site. All electronic versions will be in unlocked portable document file (pdf), and electronic working version

PWS TO 2 (revised).docx10 in appropriate Microsoft Office software (e.g. Excel where spreadsheets are used, Word for text, etc.).

Electronic deliverable plans and reports need to include all of the following:

1) full plans/reports in pdf format;

2) text only version in pdf format (include tables and figures only);

3) text only version in Word format;

4) include separate folders/files for each appendix; and

5) include tables containing calculations in xls format.

Note that pdf deliverables need to have a hyperlinked TOC.

Hard copies shall only be required at the discretion/direction of USACE. When hard copies are required, the documents shall be delivered to all reviewers by overnight delivery (addresses will be provided) as 8 1/2 by 11-inch bound copies. For the purposes of this PWS, the Contractor shall assume that each Final Plan/Report will require two (2) hard copies.

5.0 QUALITY

All Quality Management and Quality Control requirements are contained in the Base Contract SOW in sections 5.11.2.2 and 5.11.2.3 respectively.

6.0 GOVERNMENT PROPERTY

All materials gathered and developed in the performance of this work shall be the property of USACE.

The Contractor shall maintain a log of all property costing $100.00 or more that was acquired during the duration of this contract.

The Contractor shall not publicly release any data generated or reviewed under this contract without prior approval of the COR. Dissemination or public disclosure includes, but is not limited to, permitting access to such information by foreign nationals or by any other person or entity. It also includes the publication of technical or scientific papers. If approached by the news media, the Contractor shall refer them to the Contracting Officer (CO). Reports and data generated under this contract become the property of the Government and unauthorized distribution is specifically prohibited. Further information is located in the Contract Scope of Work in section 10.1.

7.0 GOVERNMENT RIGHTS

The USACE has unlimited rights to all documents/material produced under this contract. All documents and materials, produced under this contract shall be USACE owned and are the property of the USACE with all rights and privileges of ownership/copyright belonging exclusively to the Army.

These documents and materials cannot be used or sold by the Contractor without written permission from the Contracting Officer (KO). All materials supplied to the USACE shall be the sole property of the USACE and cannot be used for any other purpose.

PWS TO 2 (revised).docx11

The Government reserves the right to stop work under this contract for any violation of the Accident Prevention Plan/Site Safety and Health Plan () at no additional cost to the Government. The Contractor has the responsibility to stop work immediately if the work is considered to be a serious threat to the safety and/or health of workers, other personnel, or the environment. When work is stopped due to a hazard/threat to worker safety, health, or the environment, the situation and resolution must be documented and submitted to the KO. Once the Army verifies through the COR that the violation has been corrected, the Contractor shall be able to continue work. Work must be stopped when chemical and biological warfare agents are encountered.

8.0 SAFETY

The Contractor must follow safety procedures as specified in section 5.0 of the contract Scope of Work, and follow the approved site safety plans as specified in section 5.2.2.4 in the contract Scope of Work.

9.0 PERFORMANCE STANDARDS

The Contractor will be evaluated by the following;

Safety-the goal will be no lost time work accidents Efficiency of excavation, transportation and disposal-The primary performance standard will be for contaminated soil excavation, transportation and disposal. The Contractor will be judged on the cost per cubic yard of contaminated material removed from the site. If the USACE chooses to independently hire a contractor for transportation and/or disposal those aspects will not be included in the Contractor’s performance standards.

Schedule-The contractor will be evaluated on their adherence to the project schedule.

Cost Control-for this cost plus fixed fee task order, the contractor will be judged on their management and control of project costs.

Environmental Controls-The contractor will be evaluated on their performance of preventing spills and fugitive contaminated vapors or odors and compliance with NJDEP permits.

Management-The contractor’s management of the project will be evaluated as part of the performance evaluation at the end of the project.

10.0 PERIOD OF PERFORMANCE

The period of performance (PoP) to accomplish all the work elements outlined in this PWS is 365 calendar daysfrom the date of the award of this contract.

PWS TO 2 (revised).docx12

PWS TO 2 (revised).docx13

Appendix A

Bid Sheet for PWS 2

Number Cost per Total

WAD Item Unit of Units Unit Cost

1 General Conditions Total Total

2 Excavcation and on site waste handling CY

2 Backfilling of excavated areas CY

3 Waste Loading CY

3 Rail transportation of waste CY

3 Disposal of mixed waste CY

3 Disposal of radiologically only contaminated waste CY

4 Reactivation of CWTP Total

4 CWTP Operations and maintenance Month

6 Fixed Fee Percentage

PWS TO 2 (revised).docx14