Performance Work Statement AMD0001.pdf
PDF 221 KB Posted
- Attached to
- Cherry Creek Dam (CO) Rehab Gate Stems
- Solicitation number
- W9128F26QA016
About this file
This is a Performance Work Statement (PWS) for the rehabilitation of Service Gate Stems No. 2 and No. 5 at Cherry Creek Dam in Aurora, Colorado, issued by the US Army Corps of Engineers under Solicitation No. W9128F26QA016. The contract is a firm-fixed-price, performance-based service contract with a 180-calendar-day period of performance after award, with a one-time extension available if contract options are exercised. The scope encompasses comprehensive refurbishment of hydraulic gate cylinder rods and associated components, including cleaning and re-chroming gate stems at the contractor's off-site facility, honing cylinder interior walls, replacing oil and water packing, glands, studs, nuts, gaskets, bonnet components, and installing new scraper-style wipers. The contractor must also conduct inspections, prepare detailed reports with photographs documenting existing conditions, and furnish required submittals including Activity Hazard Analysis, Abbreviated Accident Prevention Plan, Work Plan, product data, inspection reports, as-builts, and final reports. Operating hours are 7:00 AM to 5:30 PM, Monday through Friday, excluding federal holidays.
The Government will furnish the tower handrail fall-protection system, 7.5-ton overhead crane, tool transport box, spanner wrench, 10-ton auxiliary rigging beam, scale, and 110V power. The contractor must furnish all other supplies, equipment, and services, including labor, materials, specialized tools, and utilities such as water, restroom facilities, and oil capture systems. The contractor is responsible for all mobilization and demobilization costs, coordination of Lock-Out/Tag-Out activities, fall protection equipment, oil and hydraulic fluid management, and system testing and recommissioning. Key requirements include a pre-work meeting with site inspection, compliance with USACE safety standards (EM 385-1-1), Antiterrorism Level I training for all personnel, E-Verify employment eligibility verification, physical security protocols, and a one-year warranty on all hydraulic gate stem rehabilitation work. Award will be based on past performance and experience (significantly weighted over price), with quoters required to demonstrate at least two similar projects completed within the past seven years, followed by price evaluation and contract options consideration. Payment is made upon completion and government acceptance of all services and processed invoices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CD00100-PWS 2026- Page 1 of 19
Performance Work Statement
(PWS)
Contract No. xx Solicitation No. W9128F26QA016
Rehab Gate Stems No. 2 & 5
Cherry Creek Dam, CO March 2026
US Army Corps of Engineers
CD00100-PWS 2026- Page 2 of 19
This page was intentionally left blank for duplex printing.
CD00100-PWS 2026- Page 3 of 19
Contents
1. General Information
1.1 Background
1.2 Scope of Work
1.3 Period of Performance
1.4 Contractor Personnel
1.5 Quality Control
1.6 Quality Assurance
1.7 Hours of Operation
1.8 Pre-Work Meeting
1.9 Submittals
1.10 Standards and Regulations
1.11 Physical Security
1.12 Antiterrorism/Operation Security Requirements
1.13 Payment
2. Definitions
2.1 Acceptable Level of Performance (ALP)
2.2 Contracting Officer’s Representative (COR)
2.3 Performance-Based Contract (FAR 2.101)
2.4 Performance Requirements Summary (PRS)
3. Government Furnished Items and Services
3.1 Services, Facilities and Equipment
3.2 Utilities
4. Contractor Furnished Items and Responsibilities
4.1 General
5. Specific Tasks
6. Performance Requirements Summary
7. Quotes Best Value Evaluation
CD00100-PWS 2026- Page 4 of 19
1. General Information
The Cherry Creek Dam and Reservoir Project, located in Arapahoe County, Colorado, southeast of Denver, forms a key component of the comprehensive flood control plan for the South Platte River Basin, which spans Colorado, Wyoming, and Nebraska. Designed to mitigate flooding and manage regional water resources, the project integrates several major structural and operational features. The dam itself is a rolled earth-fill structure extending approximately 14,300 feet in length. A spillway, carved through a ridge that defines the reservoir’s right rim, provides a controlled path for excess water during high-flow events. The outlet works, situated in the right abutment, include an intake tower, a triple-barrel concrete conduit, and a stilling basin that safely dissipates energy before the flow reenters Cherry Creek via the discharge channel.
The intake tower serves as the central control point for water regulation. It contains five rectangular water passages, each equipped with a 6-foot by 9-foot slide gate used to precisely manage discharge levels. The deck atop the tower is enclosed within a reinforced concrete superstructure that houses critical operational and maintenance equipment, including a diesel standby generator, a 15-ton overhead crane with a 7½-ton auxiliary electric chain hoist, and various recording instruments for system monitoring.
Within the intake tower are the service gate hoists, low-flow bypass valve controls, position readouts, and power units necessary for adjusting water releases. A steel stairway connects the lower hoist room to the upper operating deck, enabling safe movement between levels for maintenance personnel. Together, these engineered systems ensure Cherry Creek Dam operates efficiently and reliably, providing essential flood protection, water management, and regional safety benefits.
1.1 Background
Following a previous incident involving the failure of the water packing gland on Service Gate Stem No.
1, a service contract was issued to replace the packing material and perform associated repairs. The scope of that contract included hydraulic hoist stem scoring repair, re-chroming, installation of a new wiper seal, and correction of a hoist brake leak. During contract modification, additional repair work was also completed on Gate Stems No. 3 and No. 4.
After successful completion of these rehabilitation efforts, the Tri-Lakes Project Office has decided to initiate a similar comprehensive rehabilitation service contract for Service Gate Stems No. 2 and No. 5.
This proactive measure is intended to ensure the continued safe and reliable operation of the intake service gates.
1.2 Scope of Work
This contract encompasses the rehabilitation of Service Gate Stems No. 2 (Base Bid), and No. 5 (Bid Option) located at Cherry Creek Dam in Aurora, Colorado. The subsequent sections and Attachment A (Annotated As built) delineate the detailed scope of work to be executed following the disassembly of each hydraulic cylinder in accordance with the terms of this service contract.
• Refurbish the cylinder rods (gate stems) and automatic gate hanger cylinder rods by cleaning, removing heavy mineral buildup and pitting, polishing, measuring, and re-chroming *[Am0001](gate hanger cylinders only) [Am0001]** at the contractor’s off-site facility.
• Lightly hone the inner wall of the cylinder to remove minor scoring and obtain smooth surface.
• Clean and inspect the piston rings and prepare an inspection report (the inspection report shall be prepared, including photographs of the cleaned items and documentation of their overall condition. If any conditions require repair or replacement, the report shall clearly specify the necessary work and
CD00100-PWS 2026- Page 5 of 19 include all associated costs.).
• Replace oil packing, glands, studs, and nuts in the automatic gate hanger assembly.
• Replace oil packing and glands in the main hydraulic cylinder.
• Replace water packing in the main hydraulic cylinder.
• Replace gate bonnet studs and nuts (replace bonnet gasket if present or replace bonnet seal).
• Replace all hydraulic cylinder gaskets.
• Machine a groove in the existing water packing seat and install new scraper style wiper (replace studs and nuts).
• Replace cap screws (total 28 ea.) on the gate lower stem nut access cover.
It shall be noted that the work specified herein may require the Contractor to mobilize and/or demobilize multiple times over the course of the contract. In certain instances, removal and replacement of ancillary items may be necessary, even if such requirements are not explicitly identified in the Statement of Work (SOW). Furthermore, any action described within the SOW may be adjusted, modified, or omitted based on actual site conditions, with prior authorization from the U.S. Army Corps of Engineers (USACE).
The Contractor is advised that the automatic gate hanger cylinder head may contain lead-based paint. The Contractor shall take all necessary precautions to protect workers from exposure to lead-based paint particulates while performing work on or around this item. All debris generated from such work shall be collected and disposed of in strict compliance with all applicable federal, state, and local regulations.
The Government will not exercise supervision or control over the service providers hired by the Contractor in performing the services described herein. Such service providers shall be accountable exclusively to the Contractor, who in turn remains responsible to the Government. This is a firm-fixed-price, performance-based service contract in which the Government defines and measures desired outcomes, while the Contractor retains discretion over the methods employed to achieve these outcomes.
Prior to commencing any work, the Contractor shall meet with representatives of the Government and the USACE Tri-Lakes Project Office to review all aspects of the contract. This meeting shall include a walk-through inspection of the work site. The purpose of this inspection is to protect both the Contractor and USACE from disputes regarding the condition of equipment or property, and to document any existing damage or signs of use. Notes and/or photographs shall be taken of all relevant equipment or areas, and an inspection report shall be prepared. This report must be signed by representatives from both USACE and the Contractor before work begins. Upon completion of these steps, the Contractor shall be authorized to proceed with the work.
1.3 Period of Performance
The period of performance shall be 180 calendar days after award. A one-time extension will be added to the contract duration if the contract options are exercised.
1.4 Contractor Personnel
1.4.1 General
The contractor shall perform all work under this contract using his or her own qualified employees on the contractor’s own payroll except as provided in Paragraph 1.4.2 Subcontracting.
1.4.2 Subcontracting
CD00100-PWS 2026- Page 6 of 19
The contractor shall not subcontract any work without written approval of the Contracting Officer.
Compliance with the provisions of this contract by subcontractors shall be the responsibility of the contractor.
1.5 Quality Control
1.5.1 The contractor shall designate, in writing, an employee who shall serve as the contact for matters involving quality and performance or nonperformance of the required work stated in this PWS. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to ensure that the required work is performed in accordance with the standards contained herein. The contractor shall furnish the above written designation to the USACE Contracting Officer or Contracting Officer’s Representative (COR) no later than the first day of work. The contractor shall include the name(s), address(s), and telephone number(s) of the responsible individual(s).
1.5.2 The Contracting Officer reserves the right to disapprove any individual whom she/he considers incompetent to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the contractor.
1.6 Quality Assurance
The government will use the methods stated in this PWS to ensure that the Contractor is performing the services required by this PWS in an acceptable manner. The Government may use Quality Assurance Evaluators (QAE(s)) to provide assistance with the quality assurance methods.
1.6.1 The government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government shall perform inspections in a manner that will not delay the work.
1.6.2 If any of the services do not conform to contract requirements, the government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.
1.6.3 Upon verification of a validated customer complaint or corrective action report, the Contracting Officer or COR will notify the contractor that they are required to re-perform specific services within 14 calendar days of the verification.
1.6.4 The government may take action, if the contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The government may (1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the government that related to the performance of such service or (2) terminate the contract in whole or in part.
1.6.5 The contractor is responsible to replace/repair any damage to government property due to negligence, at his or her own cost. The government may take action, if the contractor fails to replace/repair any damage to government property. The government may (1) by contract, or otherwise, replace/repair damaged government property and charge to the contractor any cost incurred by the government to replace/repair any damage.
CD00100-PWS 2026- Page 7 of 19
1.7 Hours of Operation
The contractor is responsible for conducting business, between the hours of 7:00am - 5:30pm Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.8 Pre-Work Meeting
Prior to commencing any activities, the contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work requirements, scheduling, submittal process, review of the Activity Hazard Analysis (AHA), and Abbreviated Accident Prevention Plan (AAP). At least one (1) week prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.
1.9 Submittals
Prior to commencement of services, the Contractor shall submit the following documents to the COR for review and approval. Government approval is required for submittals with a "G" classification.
SD-01 Preconstruction Submittals Preconstruction submittals that are required prior to or commencing with the start of work shall be submitted within 30 calendar days of contract award unless specified elsewhere in the PWS.
• Activity Hazard Analysis (AHA); G-AO
• Abbreviated Accident Prevention Plan (APP) ; G-AO
• Identification of Contractor Employees & Vehicles; G-AO
• Proof of Insurance for Contractors and Subcontractors; G-AO
• Technical scope of work (Work Plan) with USACE-verified ordered steps; G-AO
SD-03 Product Data Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work. Samples of warranty language.
• Gate Stem (cylinder rod) Rehabilitation Plan; G-DO
-Submittal shall include methods for *[Am0001] clean and repair of main cylinder rods, and clean, repair, and re-chrome of [Am0001]**automatic gate hanger cylinder rods. The plan shall also identify honing methods for cylinder interior wall. Include location of contractor offsite facility where the work will be performed.
• Oil and Water Packing, Glands, and Seats; G-DO
-Submittal shall include product data for listed items and water packing seat grooving method to install new scraper seal wiper.
CD00100-PWS 2026- Page 8 of 19
• Gaskets; G- DO
• Scraper Seal (Bar) Wiper; G- DO
• Bolts, Screws, Nuts, And Washers; G- DO
• Warranty; G-AO
SD-09 Report Documentation of the measurement and verification actions taken by contractor at the job site or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing agency.
• Inspection Report; G-AO
-The report shall include photos and descriptions documenting the existing conditions of the items subject to replacement and refurbishment (cylinder rod and wall). All ancillary items not listed in the paragraph 1.2 but are necessary to be repaired must be clearly identified and recorded in this document. In such case, the report shall clearly indicate the anticipated level of work, schedule, and itemized cost.
SD-11 Closeout Submittals
• As-builts; G-AO
-Contractor may utilize the bridging drawings however all as-built conditions must be recorded after completion of the contract work. The final as-builts shall be submitted no later than 2 weeks after completion of on-site work.
• Final Report; G-AO
-In conjunction with as-builts, the final report including photos of all refurbished and replaced components shall be prepared and submitted no later than 4 weeks after completion of on-site work.
1.9.1 Submittal Procedures
a. SUBMITTALS. During the performance of this contract, the Contractor will be required to submit to the Contracting Officer for approval, review, or for information only certain descriptive literature, data, fabrication drawings, shop drawings, diagrams, test reports, samples, certificates, etc., as identified below.
The required submittals will be submitted in the number of copies and directed to the address as shown below.
b. SUBMITTAL FORM. The attached submittal form (ENG Form 4025) will be used for transmitting the submittals. This form may be reproduced by the Contractor and shall be properly executed by filling out all the heading blank spaces and identifying each item submitted. Special care should be taken to ensure proper listing of the specification paragraph and/or sheet number of the contract drawing pertinent to the data submitted for each item.
CD00100-PWS 2026- Page 9 of 19
c. ACTION REQUIRED. If the submittal is for information only or for review, work will continue unless the Contracting Officer notifies the Contractor that the submittal fails to indicate that the material, method, test, etc., conforms to the specification. If the submittals require approval, such submittal must be submitted to and approved by the Contracting Officer prior to performance by the Contractor.
d. MEANING OF APPROVALS. The submittal returned to the Contractor shall be marked as noted on the back of ENG Form 4025. The approval of the submittal by the Contracting Officer shall not be construed as a complete check, but will indicate only that the general method of prosecution and detailing is satisfactory. Approval will not release the Contractor of the responsibility for any error which may exist as the Contractor is responsible for satisfactory prosecution and detailing of all the work.
e. WHEN NOT APPROVED. The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and the number of copies as specified in the initial submittal.
f. WITHHOLDING OF PAYMENT. Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
g. SENDING OF SUBMITTALS. The Contracting Officer may request submittals in addition to those listed when deemed necessary to adequately describe the work covered in the respective sections or drawings. Prior to submittal, all items shall be checked and approved by the Contractor and each respective transmittal form (ENG 4025) shall be stamped, initialed, and dated by the Contractor certifying that the accompanying submittal complies with the contract requirements.
h. “G-DO” Submittals. For submittals identified herein as “G-DO” the Contractor shall submit all contract submittals to the COR either via email or by mail to the following address:
US Army Corps of Engineers, Tri-Lakes Project Office, 9307 South Wadsworth Blvd, Littleton, CO 80128-6901.
i. “G-AO” and “FIO” Submittals. For submittals identified herein as “G-AO” the Contractor shall submit one (1) digital copy (pdf format). All “G-AO” Government Approved submittals are noted as “G- AO” in the technical specifications and shall be sent to the Tri-Lakes Project Office. Submittals not requiring Government approval have no notation and are “For Information Only” and shall be submitted to the Tri-Lakes Project Office.
1.10 Standards and Regulations.
The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations. Applicable regulations include, but are not limited to the following:
1.10.1 Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and Regulations Governing Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316.
(https://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2- 316.pdf?ver=2013-08-22-104526-670)
CD00100-PWS 2026- Page 10 of 19
1.10.2 Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated March 2024.
(https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015%20March%202024.pdf)
1.10.3 Occupational Safety and Health Standards (29 CFR 1910);
1.10.4 Activity Hazard Analysis (AHA)- The contractor shall prepare the AHA in accordance with Paragraph 1-6 or 2-6 of the EM 385-1-1.
1.10.5 Abbreviated Accident Prevention Plan (APP) - EM 385-1-1 in its entirety may be too complex for the type of work performed under these contracts; contractors may reference Appendix A, for abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a Competent Person (CP) to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.
1.11 Physical Security
1.11.1 The contractor shall be responsible for safeguarding all government facilities, property, and materials provided for contractor use. The contractor shall secure all government facilities, property, and materials. Specific security conditions may change based on threats to national defense and based on the risk of specific facilities to these threats. The contractor shall always abide by these changing conditions, as applicable.
1.11.2 The contractor shall ensure all keys issued by the government are not lost, stolen, duplicated, or used by unauthorized persons.
1.11.3 The Contractor shall immediately report to the COR any occurrences of lost or stolen keys.
1.11.4 In the event keys, other than master keys are lost or stolen, the contractor may be required, upon written direction of the COR, to re-key or replace the affected lock or locks without cost to the government. The government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the payment due the contractor. If a master key is lost or stolen, the government may need to replace all locks and keys for that system. The government will deduct the total cost to replace the locks and keys from the contractor’s invoice.
1.11.5 The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor’s employees. The contractor shall not facilitate access of secured areas to persons other than contractor personnel or subcontractors engaged in performance of contract work requirements.
1.12 Antiterrorism/Operation Security Requirements
1.12.1 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA
CD00100-PWS 2026- Page 11 of 19 representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed;
the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this
1.12.2 Antiterrorism (AT) Level I Training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at: https://jko.jten.mil (website subject to change).
1.12.3 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.
1.12.4 Suspicious Activity Reporting training (e.g., iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
1.12.5 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
CD00100-PWS 2026- Page 12 of 19
1.13 Payment
1.13.1 The government will make payment upon completion of all services, after the government has inspected and accepted the services, and the government has reviewed, approved, and processed the contractor’s invoice. The contractor shall submit the invoice to the COR or any other person that the COR has designated to receive the invoice.
1.13.2 The contractor must provide the contractor’s name, address, contract number, period of services completed (i.e., for the month of January or for the period of performance of January 1 through February 23), CLIN number and specific quantities of work performed (i.e., 1 Month, 40 days, 100 acres, etc.), and total requested, for an invoice to be considered proper. The contractor shall submit the invoice by the fifth (5th) of the month for services completed the previous month or submit the invoice upon completion of all services, in accordance with the period of performance stated in the CLIN.
1.14 Warranty
1.14.1 The contractor shall warrant all hydraulic gate stem rehabilitation work, including materials and workmanship, for a minimum period of one (1) year from the date of final acceptance by the Government.
During the warranty period, the contractor shall, at no additional cost to the Government, promptly repair or replace any defective components or work that fails to perform as specified due to faulty materials, improper installation, or workmanship. The warranty shall include all labor, equipment, and materials necessary to correct deficiencies and restore the hydraulic gate stem system to full operational condition.
2. Definitions
The following definitions and descriptions apply wherever the word(s) or phrase(s) is/are stated in this
PWS:
2.1 Acceptable Level of Performance (ALP)
The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot considered satisfactory on the average. The allowable leeway or variance from a standard before the government will reject the specific service.
2.2 Contracting Officer’s Representative (COR)
means an individual designated as authorized in writing by the Contracting Officer to perform specific technical or administrative functions.
2.3 Performance-Based Contract (FAR 2.101)
Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.
2.4 Performance Requirements Summary (PRS)
The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.
CD00100-PWS 2026- Page 13 of 19
3. Government Furnished Items and Services
3.1 Services, Facilities and Equipment
The Government will provide the tower upper-level handrail fall-protection system, the 7.5-Ton Tower Crane, tool transport box, spanner wrench, and 10-ton auxiliary rigging beam and scale. The Government will operate or supervise the raising and lowering of Gates #2 or #5 and will assist the Contractor in adding blocking under Gate #2 or #5 to allow leakage flow. One gate shall be worked on at a time.
3.2 Utilities
The Government will supply existing tower 110V power for the Contractor’s use. The Contractor is responsible for understanding and adhering to the limitations of the existing power facilities and will be liable for repairing any power-related accidents or outages resulting from their activities. The Contractor must also provide all additional utilities and services required for the project, including, but not limited to, water, restroom facilities, and used oil capture or clean-up systems. Furthermore, the Contractor shall instruct all employees in appropriate utilities conservation practices.
4. Contractor Furnished Items and Responsibilities
4.1 General
The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract that are not listed under Section 3 of this PWS.
5. Specific Tasks
5.1 Before beginning any work, the Contractor shall meet with personnel from the USACE Tri-Lakes Project Office to review all elements of this contract, including a walkthrough inspection of the work site.
This inspection is intended to protect both the Contractor and USACE from potential disputes regarding equipment damage or misuse. During the inspection, notes and/or photographs shall be taken to document the condition of any equipment in the area that shows existing damage or signs of prior use.
Representatives from both USACE and the Contractor shall sign the inspection report. Once the inspection is complete, the Contractor may proceed with the work. The tasks described in this document are provided for general guidance only. The Contractor is fully responsible for developing the work plan, implementing all safety procedures, and coordinating Lock Out Tag Out (LOTO) activities with Tri- Lakes Project personnel..
5.2 USACE personnel will train the Contractor in the operation of the gate cylinders as necessary to perform required work herein.
5.3 On the upper tower level, remove gate well covers, cover support beams and install the USACE handrail system on the upper operating level.
5.3.1 The Contractor shall strictly adhere to the USACE-approved fall protection plan when working around open gate wells. Contractor must provide all necessary fall protection equipment.
5.3.2 Use of the 7.5-ton overhead bridge crane to remove the gate well covers after installing the handrail system.
CD00100-PWS 2026- Page 14 of 19
5.4 Inspect the 7.5-ton overhead bridge crane and prepare it to lift the cylinder from its mounting. The larger 15-ton crane cannot access the cylinder center line and shall not be used.
5.5 Transport Contractor-furnished and installed wood cribbing blocks to the lower level using the USACE-furnished tool transport box attached to the 7.5-ton crane. These blocks will be used as safety blocking to support the cylinder assembly on its bonnet face after lifting.
5.6 Using the tool transport box, transport to the lower level needed tools and a clean oil drum and / or 5 gallons buckets to contain removed oil. Assume approximately 300 gallons of oil to be drained from each cylinder.
5.7 USACE personnel will place an emergency gate in upstream gate slot so work can be completed on subject service gate stems (# 2 or #5 one at a time). Contractor will need to place Lock-Out/Tag-Out protection on subject service gate (#2 or #5).
5.8 Prepare for wet tunnel access up to the emergency gates. An air monitoring device, portable ventilation fan, and radio communications shall be in use during all personnel access of the wet tunnel, which is a non-permit confined space (a competent person shall be present outside of the outlet works tunnel). The Contractor shall anticipate that there will be some water in the tunnel from leakage at the emergency gate so shall place adequate minor blocking under the subject service gate when it is in the closed/down position so water does not back up behind the Service Gate. After the wet tunnel is secure, transport the USACE-furnished spanner wrench and any other required tools to the wet tunnel to remove the lower leaf nut recess cover plate and the lower alloy leaf nut. The Contractor shall expect that some or all of the recess cover cap screws will be “frozen” in place, causing difficulty in removing the access cover plate, and shall replace all of these screws with new flat socket cap screws.
5.9 Attach rigging to the stem extension at the top of the cylinder using the USACE-furnished threaded eye bolt while the gate is still in the lowered position.
5.10 Using the hydraulic system, completely raise the hydraulic cylinder stem. This will push the top stem extension shaft out of the service gate and top out the piston. Note: The control valves at the operating floor are spring return to open centers.
5.11 Once retracted, close the 1-1/2” ball valves in the hydraulic supply and return lines near the wall.
5.12 Oil in the cylinder does not need to be removed for weight, but there are no isolation valves at the cylinder and the hydraulic hoses connected to the cylinder are not long enough to allow the cylinder to be raised with the hoses still connected. With the gate stem fully raised, oil shall be drained from the cylinder by removing the cap or air vent at the very bottom of the lower pipe connection. As the oil is being removed it shall be collected and placed into clean containers. (There is approximately 300 gallons of oil in the cylinder when in the raised position.) No attempt shall be made to disconnect the hoist hydraulic hoses until the crane has been attached to the upper stem extension, the gate stem is in the fully raised position and the oil has been removed from the cylinder. The crane should be connected before draining oil, as the automatic gate hanger assembly (brake) may not adequately hold the stem. The Contractor shall be responsible for the loss or spill of oil. If oil is spilled the Contractor shall clean all concrete surfaces and items covered with a solvent solution. The Contractor must mitigate any oil leakage out into the stilling basin and into Cherry Creek after consultation and approval of USACE.
5.13 With the hoist connected to the stem extension, the stem fully retracted and the oil removed from the cylinder, the upper hydraulic hose shall be disconnected from the cylinder and the lower hydraulic hose shall be disconnected from the hydraulic piping, adjacent to the isolation valve. The free end of the lower
CD00100-PWS 2026- Page 15 of 19 hydraulic hose shall be connected to the cylinder upper hose connection. The free end of the upper hydraulic hose shall be connected to the lower hydraulic piping. This will cause the cylinder and the piping to be “looped” preventing leakage of oil from both the piping system and the cylinder.
5.14 With the crane still connected to the stem extension, relax the pull from the crane (approximately 10 inches.) Remove three (3) brass studs equally spaced around the upper flange of the cylinder / cylinder head assembly. Install three (3) Contractor furnished 1-7/8” lifting eyebolts which are capable of lifting the required load. Contractor furnished rigging and / or slings shall be installed between the newly installed lifting eyebolts and the central clevis, making sure that the rigging does not interfere with the cylinder head. The crane should now be set up to lift the cylinder and bonnet cover assembly from the cylinder upper flange, and the gate stem and piston assembly from the stem extension.
5.15 Remove the forty-two (42) 1-5/8” diameter bonnet cover nuts from the studs taking care not to damage the gasket and seal, if there is one, between the bonnet and the bonnet seat plate. The gasket, studs and nuts shall be replaced with new when reinstalling the bonnet.
5.16 Using the 7.5-ton crane, raise the entire cylinder assembly approximately 6 feet or until the bottom of the stem is above the bonnet seating plate.
5.17 Crib up to each end of the bonnet and lower the hoist down to rest on the cribbing. For safety, crib up as the hoist is rising. Contractor shall furnish and transport all cribbing. Lifted assembly shall at all times remain attached and “snugged” to the 7.5-ton crane, even when the hoist is cribbed.
5.18 Cover the opening in the floor with plywood and / or tarps for safety and to keep from dropping parts or tools into the gate well. Any items dropped shall be retrieved by the Contractor. The opening and gate well are considered confined spaces.
5.19 The Contractor shall record existing conditions of the gate stem (cylinder rod). Once inspected and recoded, the gate stem shall be properly crated and shipped to the contractor’s off-site facility where the gate stem is to be refurbished.
5.20 The upper gate leaf nut and spacer can now be removed. MARK OR MEASURE THE POSITION OF THE LEAF NUT IN RELATION TO THE END OF THE GATE STEM. Record the information.
5.21 Inspect integrity of the water packing seat. Replace water packing and oil packing. Cut a groove in the water packing seat and install new scraper seal type wiper. When being re-installed, the water packing seat shall be installed using six (6) new stainless steel (in lieu of existing brass) studs and nuts.
5.22 Raise the entire assembly slightly to allow for the removal of cribbing and the temporary cover over the gate slot. Lower the entire assembly showing care to align the bolt holes of the bonnet and the bonnet seat plate to facilitate the bolting of the bonnet back into place and to align the gate stem such that it is not damaged during the lowering operation.
5.23 Install contractor furnished new bonnet cover nuts and studs taking care not to damage the gasket between the bonnet and the bonnet seat plate, if there is one.
5.24 Remove the twenty (20) 1-3/4” diameter studs and nuts holding the bonnet to the cylinder. Lift the cylinder/head assembly using care to continue to align the stem during the lift. Raise the assembly to the point that the threads in the stem for the lower leaf nut move past the water packing gland such that there is room to remove the water packing gland and install the new gland. Replace cylinder gaskets with new.
Replace the oil packing gland, oil packing seat, and the oil packing.
CD00100-PWS 2026- Page 16 of 19
5.25 Install the new water packing gland and new oil packing gland using the four (4) existing brass 7/8” studs.
5.26 Lower the cylinder/head assembly using care to align the gate stem such that the brass gland is not damaged. Align the bolt holes between the cylinder and the bonnet cover and reattach the cylinder/head assembly to the bonnet cover using the twenty (20) 1-3/4” diameter stud bolts. Raise the cylinder and bonnet to reinstall the upper leaf nut and spacer.
5.27 Prior to lowering and reseating the cylinder assembly the Contractor and USACE personnel shall inspect all work on the cylinder, the bonnet gasket or seals, and the condition of the top of the service gate.
5.28 If satisfactory, the hoist can be lowered, reseating the bonnet, and reinserting the gate stem into the service gate. Provide 2 beads of water-proof sealant or suitable watertight gasket between the bonnet cover and the bonnet seating plate. The bonnet nuts shall be reinstalled and torqued evenly and all connection to the cylinder can be restored. USACE personnel shall be present until the bonnet is seated.
5.29 The Contractor shall again travel up the tunnel to reinstall the gate leaf nut and cover plate. All cover plate brass hardware shall be replaced by the Contractor with new hardware.
5.30 The Contractor shall be responsible for refilling with oil and bleeding the air out of the hydraulic system to the satisfaction of USACE. Air vent valves are available on the piping at appropriate locations.
Old oil may be reused, or it can be recycled, and new oil added. New or used oil must be filtered thru a 5-micron filter prior to being added to the system. Hydraulic oil shall be Chevron Rykon Premium Oil ISO 32 or equivalent.
5.31 With a USACE representative present, test the operation of the gate and cylinder while bleeding any air from the system.
5.32 Upon satisfactory completion of the project, all work areas shall be thoroughly cleaned and restored to their previous state. Access hatches shall be reinstalled. The Contractor shall lightly brush touch up the paint on any disturbed coating areas on the cylinder that were disturbed under this contract only. The silver colored paint is aluminum-based enamel and any other areas shall be alkyd-based enamel. Color shall match the existing.
CD00100-PWS 2026- Page 17 of 19
6. Performance Requirements Summary
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
Rehabilitate intake structure service gate stems # 2 (base bid) and # 5(bid option) as specified and illustrated in this
PWS.
The contractor shall provide all parts, labor, and equipment necessary for service gate stems # 2 and # 5 rehabilitation work specified in this PWS. Work shall include replacement of ancillary parts including but are not limited to packing, packing glands, hardware, gaskets, etc. specified in this
PWS.
Zero Deviation from Standard
100% Inspection by the COR.
PRS # 2.
Submittals including- Pre-construction submittals, Product data, Reports, and Close-out Submittals
The contractor shall provide all submittals listed in the section 1.9 in accordance with Submittal procedures in the section 1.9.1
Zero Deviation from Standard
100% Review / Approval by Tri lakes Office and/or District Office.
7. Quotes Best Value Evaluation
All documentation which has been properly submitted will be evaluated. Proposals will be evaluated based on the factors to select the responsible offeror whose proposal is most advantageous quotes and to the Government. Quotes will be evaluated using the following factors:
7.1 Factor 1- Past Performance and Experience: The quoter shall provide a minimum of two references of work on similar project(s) for a government agency or a non-government firm completed within the past seven (7) years. Contractor shall demonstrate successful past performance in repairing or rehabilitating hydraulic hoist cylinders and hydraulic power units. Experience consists of projects completed as a prime contractor or joint venture contractor that have the capabilities to perform this work. These references need to be equal to or similar in scope and size of this solicitation. The contractor shall provide dates and information to demonstrate how comparable they are to this requirement in size and complexity. The
CD00100-PWS 2026- Page 18 of 19 contractor shall include points of contact, titles, telephone numbers, and email addresses (if available) for all references.
The quoter shall submit past performance information for each project submitted for this factor. DO NOT provide Past Performance references for projects other than those submitted for this factor.
For evaluation purposes, “similar” is defined as regularly engaged in the rehab or repair of hydraulic cylinder gate hoists, gate stems and maintenance of hydraulic power units. This factor is designed to verify the experience of the offeror having been regularly engaged in the rehab of such systems. Project submittal information should clearly illustrate experience in hydraulic cylinders and gate stems rehab and testing. If more than two projects are submitted, only the first two listed in the proposal will be evaluated. Each project cited should have been completed within seven (7) years from the date that the quote for this project is due. Only those projects for which the offeror was the prime or joint venture contractor shall be submitted. The government preference is that project examples submitted be of completed projects (i.e. construction complete).
Each project summary must include the following for each project: a description of the project, scope, location, firms on the team that constructed the project, construction contract award amount, final construction cost and completion date. Narratives of each project should include a brief project overview and its relevance to this project, and identify the name, address, telephone, e-mail, and fax number of the customer and a knowledgeable non-customer who can verify the experience cited.
Additionally, past performance may be based on the Contracting’s Officer’s knowledge of and previous experience with similar contracts and any information contained in the Contractor Performance Assessment Reporting System (CPARS), contained at https://www.cpars.gov/cparsweb/home.
The quoter will receive a rating of exceptional for past performance that demonstrates successful completion of similar referenced projects and where the additional information retrieved from CPARS and from the Contracting Officer is favorable. The quoter will receive a rating of satisfactory for past performance that has at least one reference that demonstrates successful completion of similar projects and the information from CPARS, and the Contracting Officer is favorable. The quoter will receive a rating of unsatisfactory for past performance that does not demonstrate any successfully completed similar reference projects and where the additional information from CPARS and the Contracting Officer is not favorable.
Past performance and experience are significantly more important than price. However, should two or more bidders be equal in the government’s past performance and experience evaluation, price shall be used to break the tie.
7.2 Factor 2-Price: Quote shall be inclusive of all costs that might be incurred during this agreement such as, but not limited to, mobilization, labor, materials, equipment rental fees, licenses and insurance. The Contractor shall provide bid prices for all line items on the bid sheet.
7.3 Factor 3-Contract Options: The Government will evaluate quotes for award purposes by adding the total price for all bid option(s) to the total price for the basic requirement. The Government may determine that a quote is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
For the purpose of the award of the contract, the Government intends to evaluate the option to extend services, provided under FAR 52.217-8, as follows:
CD00100-PWS 2026- Page 19 of 19
The evaluation will consider the possibility that the option can be exercised at any time and can be exercised in increments of one to six months, but for no more than a total of six months during the life of the contract.
The evaluation will assume that the prices for any option exercised under FAR 52.217-8 will be at the same rates as those in effect under the contract. The evaluation will therefore assume that the addition of the price or prices of any possible extension or extensions under FAR 52.217-8 to the total price for the basic requirement and the total price for the priced options has the same effect on the total price of all quotations relative to each other, and will not affect the ranking of proposals based on price, unless, after reviewing the quotes, the Government determines that there is a…