This is a Pricing Schedule for rehabilitation services of Service Gate Stems. The schedule contains four Contract Line Items (CLINs): two basic items and two optional items. CLIN 0001 requires all parts, tools, labor, and equipment necessary to perform rehabilitation of Service Gate Stem #2 in accordance with the Performance Work Statement (PWS), priced as a lump-sum job. CLIN 0002 covers all remaining work including mobilization and demobilization, general clean-up, and incidental work not covered by CLIN 0001, also priced as a lump-sum job. CLIN 0003 (Option 01) and CLIN 0004 (Option 02) contain identical scopes for Service Gate Stem #5 rehabilitation and associated remaining work, respectively.

Key pricing and contractual terms require that prices must be entered for all individual items; total amounts submitted without individual item prices will be rejected. In case of variation between lump-sum prices and the total amount, the lump-sum prices will be considered the price submitted. If optional items 0003 and 0004 are awarded, a one-time addition of 180 days will be added to the contract duration, with the Government reserving the right to exercise options within 180 days after the Notice to Proceed. If optional items are exercised, gate hoist removal must occur sequentially, with the second hoist removable only after the first has been rehabilitated, tested, and commissioned.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICING SCHEDULE

ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT

BASIC ITEMS

All parts, tools, labor, and equipment necessary to perform rehabilitation of Service Gate Stem # 2 in accordance with the requirements and standards set forth in the Performance Work Statement (PWS).

Job

All remaining work. The work for this item shall include but not be limited to mobilization and demobilization;

general clean-up; and any other incidental and customarily performed work needed to complete work not covered by CLIN 0001.

OPTIONAL ITEMS

[Option 01]

All parts, tools, labor, and equipment necessary to perform rehabilitation of Service Gate Stem #5 in accordance with the requirements and standards set forth in the Performance Work Statement (PWS).

[Option 02]

All remaining work. The work for this item shall include but not be limited to mobilization and demobilization;

general clean-up; and any other incidental and customarily performed work needed to complete work not covered by CLIN 0003.

TOTAL AMOUNT (Basic Plus Option Items) $

NOTES:

1. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price submitted.

2. A one-time addition of 180 days will be added to the contract duration should Item 0003 & 0004 be awarded. The Government reserves the right to exercise the options within 180 days after the Notice to Proceed.

3. If optional items are exercised, gate hoist removal must occur one at a time; the second hoist can only be removed once the first has been rehabilitated, tested, and commissioned.