This is an Abstract of Offers for a construction solicitation issued by the US Army Corps of Engineers, Contracting Division (CENWO-CT) for road maintenance services at Oahe Dam in Omaha, Nebraska. The solicitation number is W9128F26BA019, issued July 13, 2026, with offers opened July 9, 2026. One amendment was issued to the solicitation. Morris Inc (UEI: CHWKANT8L8N3) submitted the only bid received, with bid security required at 20 percent of the bid amount.
The contract covers a four-year period including a base year (2026-2027), two full contract years (2027-2028 and 2028-2029), and an optional 8-month period. The work encompasses twelve major categories of road maintenance: earthwork, aggregate materials, concrete work, crack sealing, asphalt seal and fog coats, hot mix asphalt, asphalt pothole repair, pavement markings, seed and sodding, cold milling bituminous pavements, geotextile fabric, and storm drainage utilities. The Independent Government Estimate (IGE) totals $3,343,181.18 across all periods, while Morris Inc's bid totals $4,015,350.00. The contractor's pricing shows significant markups over the IGE, particularly in asphalt surface treatment ($9.75 per square yard versus $3.43 IGE), hot mix asphalt paving ($190-193 per ton versus $201.59 IGE), and concrete work items. Unit prices escalate progressively across each contract year to account for anticipated cost increases.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised Bid Schedule in Excel Format.xlsx | XLSX spreadsheet | |
| Amd 0001 for W9128F26BA019 Road Maintenence IDCC at Oahe SD.pdf | ||
| 00 10 00 - Bid Schedule-Revised 6July2026.docx | DOCX document | |
| Bid Schedule in Excel Format.xlsx | XLSX spreadsheet | |
| DB Wage Det SD20260001 1.30.2026.pdf | ||
| W9128F26BA019 Road Maintenance IDCC at Oahe SD.pdf | ||
| 00 10 00-Bid Schedule.docx | DOCX document | |
| Specifications W9128F26BA019 OA IDCC Road Maintenance 2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED
13-Jul-26 9-Jul-26
I CERTIFY THAT I HAVE OPENED, READ AND
AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE
C. REASONABLE CONTRACT
Item No Description QTY UNIT UNIT PRICE (YEAR 1) Amount
UNIT PRICE (YEAR
1) Amount
1 Earthwork * (31 00 00) 0001a 100-499 CY 100 CY $27.64 $2,764.00 40.00$ 4,000.00$ 0001b Over 500 CY 500 CY $16.56 $8,280.00 30.00$ 15,000.00$
2 Aggregate Material (32 11 23) 0002a Gravel Surfacing (Stockpiled) 1,000 TON $35.89 $35,890.00 35.00$ 35,000.00$ 0002b Aggregate Base Course (Stockpiled) 1,000 TON $35.89 $35,890.00 35.00$ 35,000.00$ 0002c Fine Aggregate (Stockpiled) 1,000 TON $40.00 $40,000.00 55.00$ 55,000.00$ 0002d Gravel Surfacing (Supplied-In-Place) 1,000 TON $41.46 $41,460.00 55.00$ 55,000.00$ 0002e Aggregate Base Course (Supplied-In-Place)1,000 TON $46.99 $46,990.00 55.00$ 55,000.00$ 0002f Fine Aggregate (Supplied-In-Place) 1,000 TON $40.00 $40,000.00 65.00$ 65,000.00$ 0002g Crushing Asphalt Mix Material 500 TON $18.31 $9,155.00 13.85$ 6,925.00$
3 Concrete Work (32 16 13) 0003a Pavement 4” thick 800 SQ FT $7.36 $5,888.00 15.00$ 12,000.00$ 0003b Pavement 6” thick 800 SQ FT $10.16 $8,128.00 17.50$ 14,000.00$ 0003c Pavement 8” thick 800 SQ FT $12.64 $10,112.00 20.00$ 16,000.00$ 0003d Straight Curb 100 FT $58.27 $5,827.00 90.00$ 9,000.00$ 0003e Curb & Gutter (Cast) 100 FT $58.27 $5,827.00 90.00$ 9,000.00$ 0003f Curb & Gutter (Slip Form) 1,000 FT $23.41 $23,410.00 70.00$ 70,000.00$ 0003g Rebar (#3 or #4) 100 LB $3.06 $306.00 4.50$ 450.00$
4 Crack Sealing (32 01 17.16) 0004a Asphalt 20,000 FT $4.77 $95,400.00 3.50$ 70,000.00$ 0004b Concrete 500 FT $8.31 $4,155.00 4.50$ 2,250.00$
NAME AND TITLE OF CERTIFYING OFFICIAL
Nadine L. Catania - Contracting Officer
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F26BA019
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE
(Check A, B or C AND COMPLETE D, E AND F)
5. PROJECT TITLE
OMAHA, NE 68102-1618
1616 CAPITOL AVENUE
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
9. OFFERS
TO THIS SOLICITATION
SIGNATURE
A. OFFEROR
Morris Inc
UEI: CHWKANT8L8N3
Oahe Dam Road Maintenance IDCC
IGE
A. HIRED LABOR
Bid Security 20% of BID
C. AMENDMENTS ACKNOWLEDGED: 1
6. NUMBER OF AMENDMENTS ISSUED : 1
B. REASONABLE CONTRACT
(Without Profit)
(Including Profit)
BID SCHEDULE BASE YEAR (2026-2027)
5 Asphalt Seal & Fog Coats (31 12 36.13) 0005a Asphalt Surface Treatment 10,000 SQ YD $3.43 $34,300.00 9.75$ 97,500.00$ 0005b Flush Seal 10,000 SQ YD $2.49 $24,900.00 2.50$ 25,000.00$ 0005c Fog Seal 10,000 SQ YD $1.94 $19,400.00 2.50$ 25,000.00$
6 Hot Mix Asphalt (32 12 16) 0006a Pave Gravel Surface 400 TON $201.59 $80,636.00 190.00$ 76,000.00$ 0006b Overlay Paved Surface 400 TON $201.59 $80,636.00 190.00$ 76,000.00$
7 Asphalt Pothole Repair (32 12 16) 0007a Asphalt Patch ≤ 2” depth 400 SQ FT $3.49 $1,396.00 12.50$ 5,000.00$ 0007b Asphalt Patch 2” ≥ 4” depth 400 SQ FT $4.68 $1,872.00 17.50$ 7,000.00$
8 Pavement Markings (32 17 24.00 10) 0008a Shoulder Striping 10,000 FT $1.26 $12,600.00 2.50$ 25,000.00$ 0008b Centerline Striping 5,000 FT $1.26 $6,300.00 2.50$ 12,500.00$ 0008c Parking Area Striping 300 FT $3.83 $1,149.00 7.50$ 2,250.00$ 0008d Stop Line Striping (12”) 20 FT $10.19 $203.80 75.00$ 1,500.00$ 0008e Handicap & Misc. Symbols 2 EA $130.98 $261.96 1,000.00$ 2,000.00$
9 Seed & Sodding (32 92 19) 0009a Seeding 300 SQ YD $0.89 $267.00 3.00$ 900.00$ 0009b Sodding 300 SQ YD $21.07 $6,321.00 6.50$ 1,950.00$ 0009c Erosion Blanket 300 SQ YD $4.48 $1,344.00 3.00$ 900.00$
10 Cold Milling Bituminous Pavements (32 01 16.17) 0010a Asphalt Milling (≤2”) 2,500 SQ YD $7.24 $18,100.00 7.50$ 18,750.00$ 0010b Asphalt Milling (>2”- 4”) 2,500 SQ YD $9.05 $22,625.00 10.00$ 25,000.00$ 0010c Full Depth Reclamation 2,500 SQ YD $10.98 $27,450.00 12.50$ 31,250.00$
11 Geotextile Fabric (31 05 19) 0011a Supplied in Place 100 SQ YD $3.84 $384.00 5.00$ 500.00$
12 Storm Drainage Utilities (33 40 00) 0012a 18” CMP Culvert (0’-5’ Depth) 30 FT $101.06 $3,031.80 150.00$ 4,500.00$ 0012b 18” CMP Culvert (5’-10’ Depth) 30 FT $127.68 $3,830.40 175.00$ 5,250.00$ 0012c 24” CMP Culvert (0’-5’ Depth) 30 FT $113.23 $3,396.90 175.00$ 5,250.00$ 0012d 24” CMP Culvert (5’-10’ Depth) 30 FT $139.85 $4,195.50 200.00$ 6,000.00$ 0012e 18” CMP Culvert Flared End 2 EA $1,076 $2,151.98 2,000.00$ 4,000.00$ 0012f 24” CMP Culvert Flared End 2 EA $1,384 $2,768.38 2,500.00$ 5,000.00$
IGE TOTAL $779,002.72 BID TOTAL 992,625.00$
00013 Earthwork * (31 00 00)
BID SCHEDULE YEAR 2 (2027-2028)
00013a 100-499 CY 100 CY $28.54 $2,854.00 40.00$ 4,000.00$
00013b Over 500 CY 500 CY $17.00 $8,500.00 30.00$ 15,000.00$
00014 Aggregate Material (32 11 23) 00014a Gravel Surfacing (Stockpiled) 1,000 TON $37.88 $37,880.00 36.00$ 36,000.00$
00014b Aggregate Base Course (Stockpiled) 1,000 TON $37.88 $37,880.00 36.00$ 36,000.00$ 00014c Fine Aggregate (Stockpiled) 1,000 TON $35.46 $35,460.00 56.00$ 56,000.00$ 00014d Gravel Surfacing (Supplied-In-Place) 1,000 TON $43.66 $43,660.00 56.00$ 56,000.00$ 00014e Aggregate Base Course (Supplied-In-Place)1,000 TON $49.41 $49,410.00 56.00$ 56,000.00$ 00014f Fine Aggregate (Supplied-In-Place) 1,000 TON $42.09 $42,090.00 66.00$ 66,000.00$ 00014g Crushing Asphalt Mix Material 500 TON $19.33 $9,665.00 14.00$ 7,000.00$
00015 Concrete Work (32 16 13) 00015a Pavement 4” thick 800 SQ FT $7.77 $6,216.00 15.25$ 12,200.00$ 00015b Pavement 6” thick 800 SQ FT $10.73 $8,584.00 17.75$ 14,200.00$ 00015c Pavement 8” thick 800 SQ FT $13.34 $10,672.00 20.25$ 16,200.00$ 00015d Straight Curb 100 FT $61.52 $6,152.00 90.00$ 9,000.00$ 00015e Curb & Gutter (Cast) 100 FT $61.52 $6,152.00 90.00$ 9,000.00$ 00015f Curb & Gutter (Slip Form) 1,000 FT $24.66 $24,660.00 70.00$ 70,000.00$ 00015g Rebar (#3 or #4) 100 LB $3.23 $323.00 4.50$ 450.00$
00016 Crack Sealing (32 01 17.16) 00016a Asphalt 20,000 FT $5.01 $100,200.00 3.50$ 70,000.00$ 00016b Concrete 500 FT $8.78 $4,390.00 4.50$ 2,250.00$
00017 Asphalt Seal & Fog Coats (31 12 36.13) 00017a Asphalt Surface Treatment 10,000 SQ YD $3.61 $36,100.00 9.75$ 97,500.00$ 00017b Flush Seal 10,000 SQ YD $2.62 $26,200.00 2.50$ 25,000.00$ 00017c Fog Seal 10,000 SQ YD $2.01 $20,100.00 2.50$ 25,000.00$
00018 Hot Mix Asphalt (32 12 16) 00018a Pave Gravel Surface 400 TON $212.10 $84,840.00 191.00$ 76,400.00$ 00018b Overlay Paved Surface 400 TON $212.10 $84,840.00 191.00$ 76,400.00$
00019 Asphalt Pothole Repair (32 12 16) 00019a Asphalt Patch ≤ 2” depth 400 SQ FT $3.66 $1,464.00 12.50$ 5,000.00$ 00019b Asphalt Patch 2” ≥ 4” depth 400 SQ FT $4.92 $1,968.00 17.50$ 7,000.00$
00020 Pavement Markings (32 17 24.00 10) 00020a Shoulder Striping 10,000 FT $1.33 $13,300.00 2.50$ 25,000.00$ 00020b Centerline Striping 5,000 FT $1.33 $6,650.00 2.50$ 12,500.00$ 00020c Parking Area Striping 300 FT $4.03 $1,209.00 7.50$ 2,250.00$ 00020d Stop Line Striping (12”) 20 FT $10.66 $213.20 75.00$ 1,500.00$ 00020e Handicap & Misc. Symbols 2 EA $138.32 $276.64 1,000.00$ 2,000.00$
00021 Seed & Sodding (32 92 19)
00021a Seeding 300 SQ YD $0.92 $276.00 3.00$ 900.00$ 00021b Sodding 300 SQ YD $22.23 $6,669.00 6.50$ 1,950.00$ 00021c Erosion Blanket 300 SQ YD $4.72 $1,416.00 3.00$ 900.00$
00022 Cold Milling Bituminous Pavements (32 01 16.17) 00022a Asphalt Milling (≤2”) 2,500 SQ YD $7.49 $18,725.00 7.50$ 18,750.00$ 00022b Asphalt Milling (>2”- 4”) 2,500 SQ YD $9.36 $23,400.00 10.00$ 25,000.00$ 00022c Full Depth Reclamation 2,500 SQ YD $11.35 $28,375.00 12.50$ 31,250.00$
00023 Geotextile Fabric (31 05 19) 00023a Supplied in Place 100 SQ YD $4.04 $404.00 5.00$ 500.00$
00024 Storm Drainage Utilities (33 40 00) 00024a 18” CMP Culvert (0’-5’ Depth) 30 FT $106.20 $3,186.00 150.00$ 4,500.00$ 00024b 18” CMP Culvert (5’-10’ Depth) 30 FT $133.69 $4,010.70 175.00$ 5,250.00$ 00024c 24” CMP Culvert (0’-5’ Depth) 30 FT $119.02 $3,570.60 175.00$ 5,250.00$ 00024d 24” CMP Culvert (5’-10’ Depth) 30 FT $146.51 $4,395.30 200.00$ 6,000.00$ 00024e 18” CMP Culvert Flared End 2 EA $1,134 $2,268.00 2,000.00$ 4,000.00$ 00024f 24” CMP Culvert Flared End 2 EA $1,457 $2,914.00 2,500.00$ 5,000.00$
IGE TOTAL $811,518.44 BID TOTAL 1,000,100.00$
00025 Earthwork * (31 00 00) 00025a 100-499 CY 100 CY $30.19 $3,019.00 40.00$ 4,000.00$ 00025b Over 500 CY 500 CY $17.98 $8,990.00 30.00$ 15,000.00$
00026 Aggregate Material (32 11 23) 00026a Gravel Surfacing (Stockpiled) 1,000 TON $40.04 $40,040.00 37.00$ 37,000.00$ 00026b Aggregate Base Course (Stockpiled) 1,000 TON $40.04 $40,040.00 37.00$ 37,000.00$ 00026c Fine Aggregate (Stockpiled) 1,000 TON $37.49 $37,490.00 57.00$ 57,000.00$ 00026d Gravel Surfacing (Supplied-In-Place) 1,000 TON $46.16 $46,160.00 57.00$ 57,000.00$ 00026e Aggregate Base Course (Supplied-In-Place)1,000 TON $52.24 $52,240.00 57.00$ 57,000.00$ 00026f Fine Aggregate (Supplied-In-Place) 1,000 TON $44.50 $44,500.00 67.00$ 67,000.00$ 00026g Crushing Asphalt Mix Material 500 TON $20.43 $10,215.00 14.15$ 7,075.00$
00027 Concrete Work (32 16 13) 00027a Pavement 4” thick 800 SQ FT $8.22 $6,576.00 15.50$ 12,400.00$ 00027b Pavement 6” thick 800 SQ FT $11.35 $9,080.00 18.00$ 14,400.00$ 00027c Pavement 8” thick 800 SQ FT $14.11 $11,288.00 20.50$ 16,400.00$ 00027d Straight Curb 100 FT $65.06 $6,506.00 90.00$ 9,000.00$ 00027e Curb & Gutter (Cast) 100 FT $65.06 $6,506.00 90.00$ 9,000.00$ 00027f Curb & Gutter (Slip Form) 1,000 FT $26.07 $26,070.00 70.00$ 70,000.00$ 00027g Rebar (#3 or #4) 100 LB $3.41 $341.00 4.50$ 450.00$
00028 Crack Sealing (32 01 17.16) 00028a Asphalt 20,000 FT $5.30 $106,000.00 3.50$ 70,000.00$ 00028b Concrete 500 FT $9.29 $4,645.00 4.50$ 2,250.00$
BID SCHEDULE YEAR 3 (2028-2029)
00029 Asphalt Seal & Fog Coats (31 12 36.13) 00029a Asphalt Surface Treatment 10,000 SQ YD $3.81 $38,100.00 9.75$ 97,500.00$ 00029b Flush Seal 10,000 SQ YD $2.77 $27,700.00 2.50$ 25,000.00$ 00029c Fog Seal 10,000 SQ YD $2.13 $21,300.00 2.50$ 25,000.00$
00030 Hot Mix Asphalt (32 12 16) 00030a Pave Gravel Surface 400 TON $224.23 $89,692.00 192.00$ 76,800.00$ 00030b Overlay Paved Surface 400 TON $224.23 $89,692.00 192.00$ 76,800.00$
00031 Asphalt Pothole Repair (32 12 16) 00031a Asphalt Patch ≤ 2” depth 400 SQ FT $3.87 $1,548.00 12.50$ 5,000.00$ 00031b Asphalt Patch 2” ≥ 4” depth 400 SQ FT $5.20 $2,080.00 17.50$ 7,000.00$
00032 Pavement Markings (32 17 24.00 10) 00032a Shoulder Striping 10,000 FT $1.40 $14,000.00 2.50$ 25,000.00$ 00032b Centerline Striping 5,000 FT $1.40 $7,000.00 2.50$ 12,500.00$ 00032c Parking Area Striping 300 FT $4.50 $1,350.00 7.50$ 2,250.00$ 00032d Stop Line Striping (12”) 20 FT $11.27 $225.40 75.00$ 1,500.00$ 00032e Handicap & Misc. Symbols 2 EA $146.31 $292.62 1,000.00$ 2,000.00$
00033 Seed & Sodding (32 92 19) 00033a Seeding 300 SQ YD $0.98 $294.00 3.00$ 900.00$ 00033b Sodding 300 SQ YD $23.51 $7,053.00 6.50$ 1,950.00$ 00033c Erosion Blanket 300 SQ YD $4.99 $1,497.00 3.00$ 900.00$
00034 Cold Milling Bituminous Pavements (32 01 16.17) 00034a Asphalt Milling (≤2”) 2,500 SQ YD $7.92 $19,800.00 7.50$ 18,750.00$ 00034b Asphalt Milling (>2”- 4”) 2,500 SQ YD $9.90 $24,750.00 10.00$ 25,000.00$ 00034c Full Depth Reclamation 2,500 SQ YD $12.01 $30,025.00 12.50$ 31,250.00$
00035 Geotextile Fabric (31 05 19) 00035a Supplied in Place 100 SQ YD $4.27 $427.00 5.00$ 500.00$
00036 Storm Drainage Utilities (33 40 00) 00036a 18” CMP Culvert (0’-5’ Depth) 30 FT $112.33 $3,369.90 150.00$ 4,500.00$ 00036b 18” CMP Culvert (5’-10’ Depth) 30 FT $141.40 $4,242.00 175.00$ 5,250.00$ 00036c 24” CMP Culvert (0’-5’ Depth) 30 FT $125.89 $3,776.70 175.00$ 5,250.00$ 00036d 24” CMP Culvert (5’-10’ Depth) 30 FT $154.97 $4,649.10 200.00$ 6,000.00$ 00036e 18” CMP Culvert Flared End 2 EA $1,200 $2,400.00 2,000.00$ 4,000.00$ 00036f 24” CMP Culvert Flared End 2 EA $1,540 $3,080.00 2,500.00$ 5,000.00$
IGE TOTAL $858,049.72 BID TOTAL 1,007,575.00$
00037 Earthwork * (31 00 00) 00037a 100-499 CY 100 CY $31.49 $3,149.00 40.00$ 4,000.00$
BID SCHEDULE YEAR 4 (8 MONTHS)
00037b Over 500 CY 500 CY $18.74 $9,370.00 30.00$ 15,000.00$
00038 Aggregate Material (32 11 23) 00038a Gravel Surfacing (Stockpiled) 1,000 TON $41.74 $41,740.00 38.00$ 38,000.00$ 00038b Aggregate Base Course (Stockpiled) 1,000 TON $41.74 $41,740.00 38.00$ 38,000.00$ 00038c Fine Aggregate (Stockpiled) 1,000 TON $39.08 $39,080.00 58.00$ 58,000.00$ 00038d Gravel Surfacing (Supplied-In-Place) 1,000 TON $48.12 $48,120.00 58.00$ 58,000.00$ 00038e Aggregate Base Course (Supplied-In-Place)1,000 TON $54.46 $54,460.00 58.00$ 58,000.00$ 00038f Fine Aggregate (Supplied-In-Place) 1,000 TON $46.39 $46,390.00 68.00$ 68,000.00$ 00038g Crushing Asphalt Mix Material 500 TON $21.29 $10,645.00 14.30$ 7,150.00$
00039 Concrete Work (32 16 13) 00039a Pavement 4” thick 800 SQ FT $8.57 $6,856.00 15.75$ 12,600.00$ 00039b Pavement 6” thick 800 SQ FT $11.83 $9,464.00 18.25$ 14,600.00$ 00039c Pavement 8” thick 800 SQ FT $14.71 $11,768.00 20.75$ 16,600.00$ 00039d Straight Curb 100 FT $67.83 $6,783.00 90.00$ 9,000.00$ 00039e Curb & Gutter (Cast) 100 FT $67.83 $6,783.00 90.00$ 9,000.00$ 00039f Curb & Gutter (Slip Form) 1,000 FT $27.18 $27,180.00 70.00$ 70,000.00$ 00039g Rebar (#3 or #4) 100 LB $3.56 $356.00 4.50$ 450.00$
00040 Crack Sealing (32 01 17.16) 00040a Asphalt 20,000 FT $5.53 $110,600.00 3.50$ 70,000.00$ 00040b Concrete 500 FT $9.70 $4,850.00 4.50$ 2,250.00$
00041 Asphalt Seal & Fog Coats (31 12 36.13) 00041a Asphalt Surface Treatment 10,000 SQ YD $3.97 $39,700.00 9.75$ 97,500.00$ 00041b Flush Seal 10,000 SQ YD $2.89 $28,900.00 2.50$ 25,000.00$ 00041c Fog Seal 10,000 SQ YD $2.22 $22,200.00 2.50$ 25,000.00$
00042 Hot Mix Asphalt (32 12 16) 00042a Pave Gravel Surface 400 TON $233.77 $93,508.00 193.00$ 77,200.00$ 00042b Overlay Paved Surface 400 TON $233.77 $93,508.00 193.00$ 77,200.00$
00043 Asphalt Pothole Repair (32 12 16) 00043a Asphalt Patch ≤ 2” depth 400 SQ FT $4.04 $1,616.00 12.50$ 5,000.00$ 00043b Asphalt Patch 2” ≥ 4” depth 400 SQ FT $5.42 $2,168.00 17.50$ 7,000.00$
00044 Pavement Markings (32 17 24.00 10) 00044a Shoulder Striping 10,000 FT $1.46 $14,600.00 2.50$ 25,000.00$ 00044b Centerline Striping 5,000 FT $1.46 $7,300.00 2.50$ 12,500.00$ 00044c Parking Area Striping 300 FT $4.44 $1,332.00 7.50$ 2,250.00$ 00044d Stop Line Striping (12”) 20 FT $11.75 $235.00 75.00$ 1,500.00$ 00044e Handicap & Misc. Symbols 2 EA $153.00 $306.00 1,000.00$ 2,000.00$
00045 Seed & Sodding (32 92 19) 00045a Seeding 300 SQ YD $1.02 $306.00 3.00$ 900.00$ 00045b Sodding 300 SQ YD $24.51 $7,353.00 6.50$ 1,950.00$
00045c Erosion Blanket 300 SQ YD $5.20 $1,560.00 3.00$ 900.00$
00046 Cold Milling Bituminous Pavements (32 01 16.17) 00046a Asphalt Milling (≤2”) 2,500 SQ YD $8.26 $20,650.00 7.50$ 18,750.00$ 00046b Asphalt Milling (>2”- 4”) 2,500 SQ YD $10.33 $25,825.00 10.00$ 25,000.00$ 00046c Full Depth Reclamation 2,500 SQ YD $12.53 $31,325.00 12.50$ 31,250.00$
00047 Geotextile Fabric (31 05 19) 00047a Supplied in Place 100 SQ YD $4.45 $445.00 5.00$ 500.00$
00048 Storm Drainage Utilities (33 40 00) 00048a 18” CMP Culvert (0’-5’ Depth) 30 FT $117.14 $3,514.20 150.00$ 4,500.00$ 00048b 18” CMP Culvert (5’-10’ Depth) 30 FT $147.47 $4,424.10 175.00$ 5,250.00$ 00048c 24” CMP Culvert (0’-5’ Depth) 30 FT $131.29 $3,938.70 175.00$ 5,250.00$ 00048d 24” CMP Culvert (5’-10’ Depth) 30 FT $161.61 $4,848.30 200.00$ 6,000.00$ 00048e 18” CMP Culvert Flared End 2 EA $1,250 $2,500.00 2,000.00$ 4,000.00$ 00048f 24” CMP Culvert Flared End 2 EA $1,607 $3,214.00 2,500.00$ 5,000.00$
IGE TOTAL $894,610.30 BID TOTAL 1,015,050.00$
$3,343,181.18 GRAND TOTAL 4,015,350.00$ IGE GRAND TOTAL