This is a Bid Schedule for road maintenance services under the Oahe IDCC Road Maintenance 2026 contract (Solicitation W9128F26BA019), issued by the Department of the Army Corps of Engineers Engineering District Omaha. The contract covers a four-year period from 2026 through March 2030, with pricing required for the base year (2026-2027), Year 2 (2027-2028), Year 3 (2028-2029), and Year 4 (July 2029-March 2030, an 8-month period).

The bid schedule contains 36 line items across multiple work categories including earthwork, aggregate materials, concrete work, crack sealing, asphalt seal and fog coats, hot mix asphalt, asphalt pothole repair, pavement markings, seed and sodding, cold milling bituminous pavements, geotextile fabric, and storm drainage utilities. Bidders must provide unit prices and extended total prices for all items, with all prices limited to two decimal places. Quantities are estimated and subject to variation under the contract's variation in estimated quantities clause. Unit prices will prevail in cases of discrepancy between unit and total prices. The bid schedule requires bidders to submit total amounts for each contract year, with a final total for all years combined.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE BASE YEAR (2026- 2027)

ItemEstimatedUnit
No.DescriptionQuantity UnitPriceAmount
0001.Earthwork * (31 00 00)
0001a.100-499 CY100CY.$ $
0001b.Over 500 CY500 CY.$ $
0002.Aggregate Material (32 11 23)
0002a.Gravel Surfacing (Stockpiled)1,000TON$ $
0002b.Aggregate Base Course1,000TON $ $
(Stockpiled)
0002c.Fine Aggregate (Stockpiled)1,000TON $ $
0002d.Gravel Surfacing1,000TON$ $
(Supplied-In-Place)
0002e.Aggregate Base Course1,000TON $ $
(Supplied-In-Place)
0002f.Fine Aggregate1,000TON $ $
(Supplied-In-Place)
0003.Concrete Work (32 16 13)
0003a.Pavement 4” thick800SQ.FT. $ $
0003b.Pavement 6” thick800SQ.FT. $ $
0003c.Pavement 8” thick800SQ.FT. $ $ 0003d.Straight Curb100FT.$ $
0003e.Curb & Gutter (Cast)100FT.$ $
0003f.Curb & Gutter (Slip Form)1,000FT.$ $
0003g.Rebar (#3 or #4)100LB. $ $
0004.Crack Sealing (32 01 17.16)
0004a.Asphalt20,000FT.$ $
0004b.Concrete500FT.$ $
0005.Asphalt Seal & Fog Coats (31 12 36.13)
0005a.Asphalt Surface Treatment10,000SQ.YD. $ $
0005b.Flush Seal10,000 SQ.YD. $ $
0005c.Fog Seal10,000 SQ.YD. $ $
0006.Hot Mix Asphalt (32 12 16)
0006a.Pave Gravel Surface400 TON$ $
0006b.Overlay Paved Surface400TON$ $
0007.Asphalt Pothole Repair (32 12 16)
0007a.Asphalt Patch ≤ 2” depth400 SQ.FT.$ $
0007b.Asphalt Patch 2” ≥ 4” depth400 SQ.FT. $ $
0008.Pavement Markings (32 17 24.00 10)
0008a.Shoulder Striping10,000FT. $ $
0008b.Centerline Striping5,000FT.$ $
0008c.Parking Area Striping300FT. $ $
0008d.Stop Line Striping (12”)20FT. $ $
0008e.Handicap & Misc. Symbols2EA. $ $
0009.Seed & Sodding (32 92 19)
0009a.Seeding300SQ.YD.$ $
0009b.Sodding300SQ.YD.$ $
0009c.Erosion Blanket300SQ.YD.$ $
00010.Cold Milling Bituminous Pavements (32 01 16.17)
00010a.Asphalt Milling (≤2”)2,500SQ.YD.$ $
00010b.Asphalt Milling (>2”- 4”)2,500 SQ.YD. $ $
00010c.Full Depth Reclamation2,500SQ. YD.$ $
00011.Geotextile Fabric (31 05 19)
00011a.Supplied in Place100SQ.YD.$ $
00012.Storm Drainage Utilities (33 40 00)
00012a.18” CMP Culvert (0’-5’ Depth)30FT.$ $
00012b.18” CMP Culvert (5’-10’ Depth)30FT.$ $
00012c.24” CMP Culvert (0’-5’ Depth)30FT.$ $
00012d.24” CMP Culvert (5’-10’ Depth)30FT.$ $
00012e.18” CMP Culvert Flared End2EACH$ $
00012f.24” CMP Culvert Flared End2EACH$ $

TOTAL BASE YEAR AMOUNT $

BID SCHEDULE YEAR 2 (2027-2028)

ItemEstimatedUnit
No.DescriptionQuantity UnitPriceAmount
00013.Earthwork * (31 00 00)
00013a.100-499 CY100CY.$ $
00013b.Over 500 CY500 CY.$ $
00014.Aggregate Material (32 11 23)
00014a.Gravel Surfacing (Stockpiled)1,000TON$ $
00014b.Aggregate Base Course1,000TON $ $
(Stockpiled)
00014c.Fine Aggregate (Stockpiled)1,000TON $ $
00014d.Gravel Surfacing1,000TON$ $
(Supplied-In-Place)
00014e.Aggregate Base Course1,000TON $ $
(Supplied-In-Place)
00014f.Fine Aggregate1,000TON $ $
(Supplied-In-Place)
00015.Concrete Work (32 16 13)
00015a.Pavement 4” thick800SQ.FT. $ $
00015b.Pavement 6” thick800SQ.FT. $ $
00015c.Pavement 8” thick800SQ.FT. $ $ 00015d.Straight Curb100FT.$ $
00015e.Curb & Gutter (Cast)100FT.$ $
00015f.Curb & Gutter (Slip Form)1,000FT.$ $
00015g.Rebar (#3 or #4)100LB. $ $
00016.Crack Sealing (32 01 17.16)
00016a.Asphalt20,000FT.$ $
00016b.Concrete500FT.$ $
00017.Asphalt Seal & Fog Coats (31 12 36.13)
00017a.Asphalt Surface Treatment10,000SQ.YD. $ $
00017b.Flush Seal10,000 SQ.YD. $ $
00017c.Fog Seal10,000 SQ.YD. $ $
00018.Hot Mix Asphalt (32 12 16)
00018a.Pave Gravel Surface400 TON$ $
00018b.Overlay Paved Surface400TON$ $
00019.Asphalt Pothole Repair (32 12 16)
00019a.Asphalt Patch ≤ 2” depth400 SQ.FT.$ $
00019b.Asphalt Patch 2” ≥ 4” depth400 SQ.FT. $ $
00020.Pavement Markings (32 17 24.00 10)
00020a.Shoulder Striping10,000FT. $ $
00020b.Centerline Striping5,000FT.$ $
00020c.Parking Area Striping300FT. $ $
00020d.Stop Line Striping (12”)20FT. $ $
00020e.Handicap & Misc. Symbols2EA. $ $
00021.Seed & Sodding (32 92 19)
00021a.Seeding300SQ.YD.$ $
00021b.Sodding300SQ.YD.$ $
00021c.Erosion Blanket300SQ.YD.$ $
00022.Cold Milling Bituminous Pavements (32 01 16.17)
00022a.Asphalt Milling (≤2”)2,500SQ.YD.$ $
00022b.Asphalt Milling (>2”- 4”)2,500 SQ.YD. $ $
00022c.Full Depth Reclamation2,500SQ. YD.$ $
00023.Geotextile Fabric (31 05 19)
00023a.Supplied in Place100SQ.YD.$ $
00024.Storm Drainage Utilities (33 40 00)
00024a.18” CMP Culvert (0’-5’ Depth)30FT.$ $
00024b.18” CMP Culvert (5’-10’ Depth)30FT.$ $
00024c.24” CMP Culvert (0’-5’ Depth)30FT.$ $
00024d.24” CMP Culvert (5’-10’ Depth)30FT.$ $
00024e.18” CMP Culvert Flared End2EACH$ $
00024f.24” CMP Culvert Flared End2EACH$ $

TOTAL YEAR 2 AMOUNT $

BID SCHEDULE YEAR 3 (2028-2029)

ItemEstimatedUnit
No.DescriptionQuantity UnitPriceAmount
00025.Earthwork * (31 00 00)
00025a.100-499 CY100CY.$ $
00025b.Over 500 CY500 CY.$ $
00026.Aggregate Material (32 11 23)
00026a.Gravel Surfacing (Stockpiled)1,000TON$ $
00026b.Aggregate Base Course1,000TON $ $
(Stockpiled)
00026c.Fine Aggregate (Stockpiled)1,000TON $ $
00026d.Gravel Surfacing1,000TON$ $
(Supplied-In-Place)
00026e.Aggregate Base Course1,000TON $ $
(Supplied-In-Place)
00026f.Fine Aggregate1,000TON $ $
(Supplied-In-Place)
00027.Concrete Work (32 16 13)
00027a.Pavement 4” thick800SQ.FT. $ $
00027b.Pavement 6” thick800SQ.FT. $ $
00027c.Pavement 8” thick800SQ.FT. $ $ 00027d.Straight Curb100FT.$ $
00027e.Curb & Gutter (Cast)100FT.$ $
00027f.Curb & Gutter (Slip Form)1,000FT.$ $
00027g.Rebar (#3 or #4)100LB. $ $
00028.Crack Sealing (32 01 17.16)
00028a.Asphalt20,000FT.$ $
00028b.Concrete500FT.$ $
00029.Asphalt Seal & Fog Coats (31 12 36.13)
00029a.Asphalt Surface Treatment10,000SQ.YD. $ $
00029b.Flush Seal10,000 SQ.YD. $ $
00029c.Fog Seal10,000 SQ.YD. $ $
00030.Hot Mix Asphalt (32 12 16)
00030a.Pave Gravel Surface400 TON$ $
00030b.Overlay Paved Surface400TON$ $
00031.Asphalt Pothole Repair (32 12 16)
00031a.Asphalt Patch ≤ 2” depth400 SQ.FT.$ $
00031b.Asphalt Patch 2” ≥ 4” depth400 SQ.FT. $ $
00032.Pavement Markings (32 17 24.00 10)
00032a.Shoulder Striping10,000FT. $ $
00032b.Centerline Striping5,000FT.$ $
00032c.Parking Area Striping300FT. $ $
00032d.Stop Line Striping (12”)20FT. $ $
00032e.Handicap & Misc. Symbols2EA. $ $
00033.Seed & Sodding (32 92 19)
00033a.Seeding300SQ.YD.$ $
00033b.Sodding300SQ.YD.$ $
00033c.Erosion Blanket300SQ.YD.$ $
00034.Cold Milling Bituminous Pavements (32 01 16.17)
00034a.Asphalt Milling (≤2”)2,500SQ.YD.$ $
00034b.Asphalt Milling (>2”- 4”)2,500 SQ.YD. $ $
00034c.Full Depth Reclamation2,500SQ. YD.$ $
00035.Geotextile Fabric (31 05 19)
00035a.Supplied in Place100SQ.YD.$ $
00036.Storm Drainage Utilities (33 40 00)
00036a.18” CMP Culvert (0’-5’ Depth)30FT.$ $
00036b.18” CMP Culvert (5’-10’ Depth)30FT.$ $
00036c.24” CMP Culvert (0’-5’ Depth)30FT.$ $
00036d.24” CMP Culvert (5’-10’ Depth)30FT.$ $
00036e.18” CMP Culvert Flared End2EACH$ $
00036f.24” CMP Culvert Flared End2EACH$ $

TOTAL YEAR 3 AMOUNT $

BID SCHEDULE YEAR 4 (8 months) (July 2029- March 2030)

ItemEstimatedUnit
No.DescriptionQuantity UnitPriceAmount
00025.Earthwork * (31 00 00)
00025a.100-499 CY100CY.$ $
00025b.Over 500 CY500 CY.$ $
00026.Aggregate Material (32 11 23)
00026a.Gravel Surfacing (Stockpiled)1,000TON$ $
00026b.Aggregate Base Course1,000TON $ $
(Stockpiled)
00026c.Fine Aggregate (Stockpiled)1,000TON $ $
00026d.Gravel Surfacing1,000TON$ $
(Supplied-In-Place)
00026e.Aggregate Base Course1,000TON $ $
(Supplied-In-Place)
00026f.Fine Aggregate1,000TON $ $
(Supplied-In-Place)
00027.Concrete Work (32 16 13)
00027a.Pavement 4” thick800SQ.FT. $ $
00027b.Pavement 6” thick800SQ.FT. $ $
00027c.Pavement 8” thick800SQ.FT. $ $ 00027d.Straight Curb100FT.$ $
00027e.Curb & Gutter (Cast)100FT.$ $
00027f.Curb & Gutter (Slip Form)1,000FT.$ $
00027g.Rebar (#3 or #4)100LB. $ $
00028.Crack Sealing (32 01 17.16)
00028a.Asphalt20,000FT.$ $
00028b.Concrete500FT.$ $
00029.Asphalt Seal & Fog Coats (31 12 36.13)
00029a.Asphalt Surface Treatment10,000SQ.YD. $ $
00029b.Flush Seal10,000 SQ.YD. $ $
00029c.Fog Seal10,000 SQ.YD. $ $
00030.Hot Mix Asphalt (32 12 16)
00030a.Pave Gravel Surface400 TON$ $
00030b.Overlay Paved Surface400TON$ $
00031.Asphalt Pothole Repair (32 12 16)
00031a.Asphalt Patch ≤ 2” depth400 SQ.FT.$ $
00031b.Asphalt Patch 2” ≥ 4” depth400 SQ.FT. $ $
00032.Pavement Markings (32 17 24.00 10)
00032a.Shoulder Striping10,000FT. $ $
00032b.Centerline Striping5,000FT.$ $
00032c.Parking Area Striping300FT. $ $
00032d.Stop Line Striping (12”)20FT. $ $
00032e.Handicap & Misc. Symbols2EA. $ $
00033.Seed & Sodding (32 92 19)
00033a.Seeding300SQ.YD.$ $
00033b.Sodding300SQ.YD.$ $
00033c.Erosion Blanket300SQ.YD.$ $
00034.Cold Milling Bituminous Pavements (32 01 16.17)
00034a.Asphalt Milling (≤2”)2,500SQ.YD.$ $
00034b.Asphalt Milling (>2”- 4”)2,500 SQ.YD. $ $
00034c.Full Depth Reclamation2,500SQ. YD.$ $
00035.Geotextile Fabric (31 05 19)
00035a.Supplied in Place100SQ.YD.$ $
00036.Storm Drainage Utilities (33 40 00)
00036a.18” CMP Culvert (0’-5’ Depth)30FT.$ $
00036b.18” CMP Culvert (5’-10’ Depth)30FT.$ $
00036c.24” CMP Culvert (0’-5’ Depth)30FT.$ $
00036d.24” CMP Culvert (5’-10’ Depth)30FT.$ $
00036e.18” CMP Culvert Flared End2EACH$ $
00036f.24” CMP Culvert Flared End2EACH$ $

TOTAL YEAR 4 AMOUNT $

TOTAL BASE + YEAR 2 + YEAR 3 + YEAR 4 AMOUNT $

Notes:

1. Quantities for unit priced items are estimated only and the representative unit price will prevail in the event of an overrun or under run subject to Contract Clauses (Section 00700) Clause “Variation in Estimated Quantities”.

2. Bid prices must be entered for all unit and total prices on the Bid Schedule. Total amount bids submitted without unit prices being entered on individual items will be rejected. In case of variation between the unit price and the total price, the unit price will be considered the bid.

3. All unit and total prices cannot exceed 2 decimal places.

4. * Refers to the number of the specification section for referencing technical and measurement and payment information for the various bid items.

File details come from the government source that posted it. Updated .