W9128F24Q0011 - Amend 2 Q and A_Final.pdf
PDF 254 KB Posted
- Attached to
- POL Tank Inspection (HUR) - Hurlburt AFB, FL
- Solicitation number
- W9128F24Q0011
About this file
This document contains questions and answers regarding solicitation number W9128F24Q0011 for POL tank inspection services at Hurlburt Air Force Base in Florida. The U.S. Army Corps of Engineers is seeking a contractor to conduct an API internal inspection on two fuel storage tanks at the base in accordance with all applicable laws, standards, regulations and guidelines. Services will include removal and disposal of up to 500 gallons of unacceptable fuel, tank cleaning, replacing wiper seals, and providing an above-ground storage tank inspection. Quotes are due by January 26, 2024 at 2:00 PM Central Time. While the site will be available immediately after award, the installation will require 30 days to drain the first tank before the inspection can be scheduled and conducted. The installation will perform draining of the first tank and any necessary fuel transfers between tanks.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9128F24Q0011
Hurlburt Field POL
Questions and Answers
Amendment #2
1st Set of Questions
1. On Page 67 of 68 of the RFQ document, at the top of the Page under the discussion of Experience, why are evidence of "disposing of unacceptable fuel" and "cleaning the tank" any longer relevant?
a. On page 67 the X next to 1 needs to be removed since they will not be transferring the fuel.
2. According to the information provided, there is no "unacceptable fuel" for the Contractor to dispose of and there is no "cleaning the tank" for the Contractor to perform.
a. They will be responsible for disposing of no more than 500 gallons of fuel and cleaning the tank to API 653 standards so the other X’s next to the numbers (2,3,5,7) need to stay. When we have the kickoff meeting to schedule the inspection the installation will need 30 days before the inspection to drain/transfer fuel from the tank.
Supplemental Documentation:
Please refer to 52.212-1 Addendum, 2. Experience for revisions
2nd Set of Questions
1. "The site will be available immediately", and "simultaneously", but "first tank will require 30 days for draining". Will there be a 30-day waiting period after contract award?
a. There will not be a 30-day waiting period after award. There are deliverables that are due after award and prior to the contractor being onsite. Once USACE reviews and approves the required deliverables, the contractor will schedule the kickoff meeting. During the kickoff meeting, the contractor schedules the inspection.
2. Thereafter, fuel in the 2nd tank to be transferred back into the 1st tank? Who is to perform the draining of the 1st tank? Contractor?
a. Installation will perform the draining of the 1st tank. If there is any fuel left in the tank, the contractor will dispose of any unacceptable fuel no more than 500 Gallons.
3. Can you provide a "date" when bids are due?
a. Quotes are due on Friday, January 26, 2024, at 1400 Central Standard
Time Zone.
4. Will any of the fuel have to be transferred back to the "second" tank?
a. Yes, the installation will transfer fuel. The contractor will have to dispose of the fuel “sludge” in accordance with Attachment B.
Supplemental Documentation:
N/A