Am_0004_Specs.pdf
PDF 547 KB Posted
- Attached to
- Construct Consolidated MilStar Satellite Communications (SATCOM) Station OFFUTT AFB, NEBRASKA
- Solicitation number
- W9128F22R0028
About this file
This solicitation requests proposals to construct a consolidated MilStar Satellite Communications (SATCOM) station at Offutt Air Force Base in Nebraska. The solicitation is seeking proposals to provide all labor, materials, equipment, and supervision necessary to construct a complete and operational SATCOM facility, including a welded steel electromagnetic shielding enclosure with shielded doors, electrical and electronic penetrations, electromagnetic filters and surge arresters, shielded pull boxes, shielded conduit runs, and protective measures for mission-essential equipment outside the shield. Proposals are due by the date specified in the solicitation, with award expected approximately 90 days thereafter. Pricing is to be provided on fixed-price basis. The solicitation identifies the relevant agencies as the Department of the Army Corps of Engineers Engineering District Omaha and Offutt Air Force Base.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SATCOM-MILSTAR campus - Offutt AFB Nebraska OF59
SECTION 01 57 20.00 10
ENVIRONMENTAL PROTECTION
03/21
PART 1 GENERAL
Attachments Offutt AFB Non-hazardous Waste Form Contractor Hazardous Material Request Form
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY (DA)
DA AR 200-5 (1999) Pest Management
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
WETLAND MANUAL Corps of Engineers Wetlands Delineation Manual Technical Report Y-87-1
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
33 CFR 328 Definitions of Waters of the United States
40 CFR 150 - 189 Pesticide Programs
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 279 Standards for the Management of Used Oil
40 CFR 302 Designation, Reportable Quantities, and Notification
40 CFR 355 Emergency Planning and Notification
40 CFR 68 Chemical Accident Prevention Provisions
49 CFR 171 - 178 Hazardous Materials Regulations
SECTION 01 57 20.00 10 Page 1
1.2 DEFINITIONS
1.2.1 Environmental Pollution and Damage
Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.
1.2.2 Environmental Protection
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction.
The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
1.2.3 Contractor Generated Hazardous Waste
Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners,excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.
1.2.4 Installation Pest Management Coordinator
Installation Pest Management Coordinator (IPMC) is the individual officially designated by the Installation Commander to oversee the Installation Pest Management Program and the Installation Pest Management Plan.
1.2.5 Land Application for Discharge Water
The term "Land Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and regulations.
1.2.6 Pesticide
Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.
1.2.7 Pests
The term "pests" means arthropods, birds, rodents, nematodes, fungi, bacteria, viruses, algae, snails, marine borers, snakes, weeds and other organisms (except for human or animal disease-causing organisms) that
SECTION 01 57 20.00 10 Page 2 adversely affect readiness, military operations, or the well-being of personnel and animals; attack or damage real property, supplies, equipment, or vegetation; or are otherwise undesirable.
1.2.8 Surface Discharge
The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers,creeks, and/or "waters of the United States" and would require a permit to discharge water from the governing agency.
1.2.9 Waters of the United States
All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328 .
1.2.10 Wetlands
Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, and bogs. Official determination of whether or not an area is classified as a wetland must be done in accordance with WETLAND MANUAL.
1.3 GENERAL REQUIREMENTS
Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations. Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.
1.4 SUBCONTRACTORS
Ensure compliance with this section by subcontractors.
1.5 PAYMENT
No separate payment will be made for work covered under this section.
Payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor, and payment of all fines/fees for violation or non-compliance with Federal, State, Regional and local laws and regulations are the Contractor's responsibility. All costs associated with this section must be included in the contract price.
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
SECTION 01 57 20.00 10 Page 3
Environmental Protection Plan ; G, AO
The environmental protection plan.
1.7 ENVIRONMENTAL PROTECTION PLAN
Prior to commencing construction activities or delivery of materials to the site, submit an Environmental Protection Plan for review and approval by the Contracting Officer. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the Contractor must address during construction. Issues of concern must be defined within the Environmental Protection Plan as outlined in this section. Address each topic at a level of detail commensurate with the environmental issue and required construction task(s). Topics or issues which are not identified in this section, but are considered necessary, must be identified and discussed after those items formally identified in this section. Prior to submittal of the Environmental Protection Plan, meet with the Contracting Officer for the purpose of discussing the implementation of the initial Environmental Protection Plan; possible subsequent additions and revisions to the plan including any reporting requirements; and methods for administration of the Contractor's Environmental Plans. The Environmental Protection Plan must be current and maintained onsite by the Contractor.
1.7.1 Compliance
No requirement in this Section will relieve the Contractor of any applicable Federal, State, and local environmental protection laws and regulations. During Construction, the Contractor will be responsible for identifying, implementing, and submitting for approval any additional requirements to be included in the Environmental Protection Plan.
1.7.2 Contents
Include in the environmental protection plan, but not limit it to, the following:
a. Name(s) of person(s) within the Contractor's organization who is(are) responsible for ensuring adherence to the Environmental Protection Plan.
b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site, if applicable.
c. Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.
d. Description of the Contractor's environmental protection personnel training program.
e. An erosion and sediment control plan which identifies the type and location of the erosion and sediment controls to be provided. The plan must include monitoring and reporting requirements to assure that the control measures are in compliance with the erosion and sediment control plan, Federal, State, and local laws and regulations. A Storm Water Pollution Prevention Plan (SWPPP) may be substituted for this plan.
f. Drawings showing locations of proposed temporary excavations or
SECTION 01 57 20.00 10 Page 4 embankments for haul roads, stream crossings, material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials including methods to control runoff and to contain materials on the site.
g. Traffic control plans including measures to reduce erosion of temporary roadbeds by construction traffic, especially during wet weather. Plan shall include measures to minimize the amount of mud transported onto paved public roads by vehicles or runoff.
h. Work area plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas including methods for protection of features to be preserved within authorized work areas.
i. Drawing showing the location of borrow areas.
j. Include in the Spill Control plan the procedures, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by 40 CFR 68 , 40 CFR 302 , 40 CFR 355 , and/or regulated under State or Local laws and regulations. The Spill Control Plan supplements the requirements of EM 385-1-1 . Include in this plan, as a minimum:
1). The name of the individual who will report any spills or hazardous substance releases and who will follow up with complete documentation. This individual will immediately notify the Contracting Officer, Facility Fire Department, and Facility Environmental Office in addition to the legally required Federal, State, and local reporting channels (including the National Response Center 1-800-424-8802) if a reportable quantity is released to the environment. Include in the plan a list of the required reporting channels and telephone numbers.
2). The name and qualifications of the individual who will be responsible for implementing and supervising the containment and cleanup.
3). Training requirements for Contractor's personnel and methods of accomplishing the training.
4). A list of materials and equipment to be immediately available at the job site, tailored to cleanup work of the potential hazard(s) identified.
5). The names and locations of suppliers of containment materials and locations of additional fuel oil recovery, cleanup, restoration, and material-placement equipment available in case of an unforeseen spill emergency.
6). The methods and procedures to be used for expeditious contaminant cleanup.
7). Spill Reporting on Offutt Air Force Base. The Contractor shall immediately also report all spills of hazardous materials to the Government, via the Offutt Fire Department at 402-994-3582 and Contracting Officer's Representative assigned to the project. The report shall include the following information: Identification
SECTION 01 57 20.00 10 Page 5 of the hazardous material spilled; Location of release; Time of release; Cause of release; Amount released and Corrective actions taken.
k. A non-hazardous solid waste disposal plan identifying methods and locations for solid waste disposal including clearing debris and schedules for disposal.
1). Identify any subcontractors responsible for the transportation and disposal of solid waste. Submit licenses or permits for solid waste disposal sites that are not a commercial operating facility.
2). Evidence of the disposal facility's acceptance of the solid waste must be attached to this plan during the construction.
Attach a copy of each of the Non-hazardous Solid Waste Diversion Reports to the disposal plan. Submit the report for the previous quarter on the first working day after the first quarter that non-hazardous solid waste has been disposed and/or diverted (e.g.
the first working day of January, April, July, and October).
3). Indicate in the report the total amount of waste generated and total amount of waste diverted in cubic yards or tons along with the percent that was diverted.
4). A recycling and solid waste minimization plan with a list of measures to reduce consumption of energy and natural resources.
Detail in the plan the Contractor's actions to comply with and to participate in Federal, State, Regional, and local government sponsored recycling programs to reduce the volume of solid waste at the source.
l. An air pollution control plan detailing provisions to assure that dust, debris, materials, trash, etc., do not become air borne and travel off the project site.
m. A contaminant prevention plan that: identifies potentially hazardous substances to be used on the job site; identifies the intended actions to prevent introduction of such materials into the air, water, or ground; and details provisions for compliance with Federal, State, and local laws and regulations for storage and handling of these materials. In accordance with EM 385-1-1 , a copy of the Safety Data Sheet (SDS) (formally called Material Safety Data Sheets (MSDS) and the maximum quantity of each hazardous material to be onsite at any given time must be included in the contaminant prevention plan. Update the plan as new hazardous materials are brought onsite or removed from the site.
n. A waste water management plan that identifies the methods and procedures for management and/or discharge of waste waters which are directly derived from construction activities, such as concrete curing water, clean-up water, dewatering of ground water, disinfection water, hydrostatic test water, and water used in flushing of lines. If a settling/retention pond is required, the plan must include the design of the pond including drawings, removal plan, and testing requirements for possible pollutants. If land application will be the method of disposal for the waste water, the plan must include a sketch showing the location for land application along with a description of the pretreatment methods to be implemented. If surface discharge will be
SECTION 01 57 20.00 10 Page 6 the method of disposal, include a copy of the permit and associated documents as an attachment prior to discharging the waste water. If disposal is to a sanitary sewer, the plan must include documentation that the Waste Water Treatment Plant Operator has approved the flow rate, volume, and type of discharge.
o. A historical, archaeological, cultural resources biological resources and wetlands plan that defines procedures for identifying and protecting historical, archaeological, cultural resources, biological resources and wetlands known to be on the project site:
and/or identifies procedures to be followed if historical archaeological, cultural resources, biological resources and wetlands not previously known to be onsite or in the area are discovered during construction. Include in the plan methods to assure the protection of known or discovered resources, identifying lines of communication between Contractor personnel and the Contracting Officer.
p. Include and update a pesticide treatment plan, as information becomes available. Include in the plan: sequence of treatment, dates, times, locations, pesticide trade name, EPA registration numbers, authorized uses, chemical composition, formulation, original and applied concentration, application rates of active ingredient (i.e.
pounds of active ingredient applied), equipment used for application and calibration of equipment. Federal, State, Regional and Local pest management record keeping and reporting requirements as well as any additional Installation Project Office specific requirements are the Contractor's responsibility in conformance with DA AR 200-5 Pest Management, Chapter 2, Section III "Pest Management Records and Reports" for data required to be reported to the Installation.
q. A Material Management Plan (MMP) which establishes procedures should landfilled material be encountered during excavation or grading activities. The purpose of the MMP shall be to establish procedures to characterize, handle, and dispose landfilled materials in accordance with applicable local, state, and federal regulations;
limit worker exposure to hazardous materials; and minimize schedule impact should landfilled materials be encountered. Topics covered in the MMP should include management of landfilled materials encountered;
field monitoring; sampling protocols; analytical testing; transport and disposal; notification/communication; and documentation.
Information on evironmental restoration sites at Offutt AFB can be obtained at the following locations:
Bellevue Public Library 1003 Lincoln Road Bellevue, Nebraska
(402) 293-3157
EPA Region 7 Records Center 901 North 5th Street Kansas City, Kansas
(913) 551-7241
1.7.3 Appendix
Attach to the Environmental Protection Plan, as an appendix, copies of all environmental permits, permit application packages, approvals to construct, notifications, certifications, reports, and termination
SECTION 01 57 20.00 10 Page 7 documents.
1.8 PROTECTION FEATURES
This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to start of any onsite construction activities, the Contractor and the Contracting Officer will make a joint condition survey. Immediately following the survey, the Contractor will prepare a brief report including a plan describing the features requiring protection under the provisions of the Contract Clauses, which are not specifically identified on the drawings as environmental features requiring protection along with the condition of trees, shrubs and grassed areas immediately adjacent to the site of work and adjacent to the Contractor's assigned storage area and access route(s), as applicable. This survey report will be signed by both the the Contractor and the Contracting Officer upon mutual agreement as to its accuracy and completeness. The Contractor must protect those environmental features included in the survey report and any indicated on the drawings, regardless of interference which their preservation may cause to the work under the contract.
1.9 SPECIAL ENVIRONMENTAL REQUIREMENTS
The Contractor shall comply with the special environmental requirements listed here and included at the end of this section.
1.9.1 Applications, Supporting Documents, and Fees
The Contractor shall obtain and complete all environmental permit applications and notices including any documents required for a modification for an existing permit held by the Facility. The Contractor is responsible for preparing all supporting documents, including but not limited to engineering reports, emission surveys, diagrams, pollutant load calculations, etc. If, in lieu of permits, the governing agency requires review and approval of the design, the Contractor shall submit and obtain approval of the design and associated documents. The Contractor shall be responsible for all fees associated with the permits, applications, reviews, approvals, and notices.
1.9.2 Environmental Permits, Notices, Reviews, and/or Approvals
The following is a listing of permits, notices, reviews, and/or approvals which may be required for this project. This listing and requirements are not to be considered all-inclusive by the Contractor, but is provided as information that may be used in successfully accomplishing the environmental compliances. See Internet site http://www.deq.state.ne.us/
a. National Pollution Discharge Elimination System permit for dewatering operations is required for the State of Nebraska. All dewatering operations (including, but no limited to, pumping from an excavation, lowering the groundwater level via well points, hydrostatic testing, etc.) require dewatering permits issued by Nebraska Department of Environmental Quality (NDEQ). The contractor is responsible for obtaining and meeting all the requirements of dewatering permits. A copy of all Notice of Intent (NOI)s for the permit shall be submitted to Offutt Air Force Base Environmental Flight Office (CEV) for review and approval in addition to NDEQ. No dewatering operation shall occur
SECTION 01 57 20.00 10 Page 8 until a permit has been issued by the NDEQ to the contractor and submitted to the CEV for verification. Copies of all reports, inspections, analytical testing, etc., required as part of the permit shall be submitted to the CEV within two (2) days of completion. If any of these items are to be submitted to NDEQ, a copy of the submittal letter to NDEQ will accompany the CEV submittal. For dewatering in areas with contaminated groundwater, the contractor shall be responsible for weekly sampling and analysis for priority pollutants (VOCs and semi-VOCs, metal, etc.)
in accordance with the permit requirements. In addition, the contractor shall submit for CEV approval the method of disposal of the water. Generally, if analysis indicates the contamination in the water exceeds the permit limits, the contractor, with approval of the CEV, can discharge the water to the sanitary sewer. If analysis indicates contamination levels below the permit limits, the contractor, upon CEV approval can discharge the water to the storm sewer. The contractor shall be responsible for all the material and labor costs associated with the requirements of the permit and discharging the water to either type of sewer based on the weekly analytical results. The contractor is not responsible for any sewer fees for disposal of effluent from a dewatering operation to the sanitary sewer.
b. If construction activities results in disturbance of 1 acre of land or more (sites that may be smaller than 1 acre but are part of common plan of development are considered to be over 1 acre), coverage under the Authorization to Discharge Under the Nebraska Pollutant Discharge Elimination System (NDPDES) Permit No.
NER160000 for storm water discharge from construction site is required. The Contractor shall be responsible for implementing the terms and requirements of the permit and shall be considered the "permittee". The Contractor shall prepare and implement a Storm Water Pollution Prevention Plan, inspections, and reporting in accordance with the NER600000 Permit. The SWPPP and a copy of an unsigned Notice of Intent (NOI) shall be submitted for review and comments by the Contracting Officer and the Offutt Air Force Base's 55 CES/CEV at a minimum 14 days prior to construction commencing. The Contractor shall be responsible for all submittals to the State of Nebraska 7 days prior to construction activity beginning in accordance with Permit No. NER160000. The Contractor shall be responsible for assuring that their SWPPP is in accordance with Offutt AFB's SWPPP (identified in the above paragraph). The Contractor shall retain copies of the storm water pollution prevention plan and all reports in accordance with the permit. All submissions to the State shall be by certified mail.
The Contractor shall include copies of all submittals to the State of Nebraska (NOI/NOT), a return certified mail receipt, plans, and reports in the Appendix to the Environmental Protection Plan. The State of Nebraska web site for the NPDES Program is http://www.deq.state.ne.us/.
c. The State of Nebraska Department of Environmental Quality requires a permit for Excavation Dewatering and Hydrostatic Testing. An application must be completed and submitted to the Department of Environmental Quality at least 10 days prior to dewatering and hydrostatic testing. An approval will be in the form of a written response from the Department of Environmental Quality after a 7-10 day period of review. The application for this permit is attached. NOTE: This application is not currently on the
SECTION 01 57 20.00 10 Page 9
Nebraska web site. (See Offutt Air Force Base's Attachment Number 2.)
[*Am-4]
d. Offutt AFB has Synthetic Minor air operating permit. Notify the
Air Quality Program Manager, through the Contracting Officer, as soon as possible and prior to bringing equipment onto the installation that emits regulated pollutants so that they can be added to Offutt's permit. The emergency generator will have air emissions that may need to be added the installation's permit.
The Air Quality Program Manager at Offutt AFB is James Ferguson at Benjamin.Ferguson.4@us.af.mil. Once it is determined what equipment will be used, forward information to the Air Quality Program Manager to start the permitting process. The State of Nebraska Department of Environment and Energy (NDEE), Air Quality Division will determine what units need to be added to Offutt's permit and if any units are exempt. No construction can begin without a construction air permit from NDEE. Be advised that the permitting process is a months-long process so this needs to be started as soon as possible. Consider necessary permitting time for construction activities.
[**Am-4]
1.10 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS
Any deviations from the drawings,plans and specifications, requested by the Contractor and which may have an environmental impact, will be subject to approval by the Contracting Officer and may require an extended review, processing, and approval time. The Contracting Officer reserves the right to disapprove alternate methods, even if they are more cost effective, if the Contracting Officer determines that the proposed alternate method will have an adverse environmental impact.
1.11 NOTIFICATION
The Contracting Officer will notify the Contractor in writing of any observed noncompliance with Federal, State or local environmental laws or regulations, permits, and other elements of the Contractor's Environmental Protection plan. After receipt of such notice, the Contractor will inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 LAND RESOURCES
Confine all activities to areas defined by the drawings and specifications. Identify any land resources to be preserved within the work area prior to the beginning of any construction. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and land forms without approval, except in areas
SECTION 01 57 20.00 10 Page 10 indicated on the drawings or specified to be cleared. Ropes, cables, or guys will not be fastened to or attached to any trees for anchorage unless specifically authorized. Provide effective protection for land and vegetation resources at all times, as defined in the following subparagraphs. Remove stone, soil, or other materials displaced into uncleared areas.
3.1.1 Work Area Limits
Mark the areas that need not be disturbed under this contract prior to commencing construction activities. Mark or fence isolated areas within the general work area which are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction operations are to be conducted during darkness, any markers must be visible in the dark. The Contractor's personnel must be knowledgeable of the purpose for marking and/or protecting particular objects.
3.1.2 Landscape
Trees, shrubs, vines, grasses, land forms and other landscape features indicated and defined on the drawings to be preserved must be clearly identified by marking, fencing, or wrapping with boards, or any other approved techniques. Restore landscape features damaged or destroyed during construction operations outside the limits of the approved work area.
3.1.3 Erosion and Sediment Controls
Providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations is the Contractor's responsibility. The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of construction activities. The area of bare soil exposed at any one time by construction operations should be kept to a minimum. Construct or install temporary and permanent erosion and sediment control best management practices (BMPs) as specified in Section 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL. BMPs may include, but not be limited to, vegetation cover, stream bank stabilization, slope stabilization, silt fences, construction of terraces, interceptor channels, sediment traps, inlet and outfall protection, diversion channels, and sedimentation basins. The Contractor's best management practices must also be in accordance with the Offut Air Force Base's National Pollutant Discharge Elimination System (NPDES) Storm Water Pollution Prevention Plan (SWPPP) which may be reviewed at the Offutt's Environmental Office. Remove any temporary measures after the area has been stabilized.
3.1.4 Contractor Facilities and Work Areas
Place field offices, staging areas, stockpile storage, and temporary buildings in areas designated by the Contracting Officer. Temporary movement or relocation of Contractor facilities will be made only when approved. Erosion and sediment controls must be provided for onsite borrow and spoil areas to prevent sediment from entering nearby waters.
Temporary excavation and embankments for plant and/or work areas must be controlled to protect adjacent areas.
SECTION 01 57 20.00 10 Page 11
3.2 WATER RESOURCES
Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated. For construction activities immediately adjacent to impaired surface waters, the Contractor must be capable of quantifying sediment or pollutant loading to that surface water when required by State or Federally issued Clean Water Act permits.
3.2.1 Wetlands
D0 not enter, disturb, destroy, or allow discharge of contaminants into any wetlands.
3.3 AIR RESOURCES
Equipment operation, activities, or processes will be in accordance with all Federal and State air emission and performance laws and standards.
3.3.1 Particulates
Dust particles; aerosols and gaseous by-products from construction activities; and processing and preparation of materials, such as from asphaltic batch plants; must be controlled at all times, including weekends, holidays and hours when work is not in progress. Maintain excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and other work areas within or outside the project boundaries free from particulates which would cause the Federal, State, and local air pollution standards to be exceeded or which would cause a hazard or a nuisance. Sprinkling, chemical treatment of an approved type, baghouse, scrubbers, electrostatic precipitators or other methods will be permitted to control particulates in the work area.
Sprinkling, to be efficient, must be repeated to keep the disturbed area damp at all times. Provide sufficient, competent equipment available to accomplish these tasks. Perform particulate control as the work proceeds and whenever a particulate nuisance or hazard occurs. Comply with all State and local visibility regulations.
3.3.2 Odors
Odors from construction activities must be controlled at all times. The odors must be in compliance with State regulations and/or local ordinances and may not constitute a health hazard.
3.3.3 Sound Intrusions
Keep construction activities under surveillance and control to minimize environment damage by noise. Comply with the provisions of the State of Nebraska rules.
3.3.4 Burning
Burning is prohibited on the Government premises.
3.4 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL
Disposal of wastes will be as directed below, unless otherwise specified in other sections and/or shown on the drawings.
SECTION 01 57 20.00 10 Page 12
3.4.1 Hazardous Materials
The Contractor shall supply to the Construction Management Flight officials or contract OPR, the Material Safety Data Sheets and quantity information on all hazardous material they intend to use throughout the life of the contract prior to bringing any hazardous materials on to Offutt Air Force Base. The Contractor will be required to complete Offutt's hazardous waste training couse prior to bringing any hazardous material on base. The Contractor will submit to Offutt's Construction Management Flight at the end of the contract and every fiscal year a total amount of hazardous material used. See Hazardous Waste Form attached.
3.4.2 Solid Wastes
Place solid wastes (excluding clearing debris) in containers which are emptied on a regular schedule. Handling, storage, and disposal must be conducted to prevent contamination. Employ segregation measures so that no hazardous or toxic waste will become co-mingled with solid waste.
Transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill will be the minimum acceptable offsite solid waste disposal option. Verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. See Offutt AFB Non-hazardous Waste Form attached.
3.4.3 Chemicals and Chemical Wastes
Dispense chemicals ensuring no spillage to the ground or water. Perform and document periodic inspections of dispensing areas to identify leakage and initiate corrective action. This documentation will be periodically reviewed by the Government. Collect chemical waste in corrosion resistant, compatible containers. Collection drums must be monitored and removed to a staging or storage area when contents are within 6 inches of the top. Wastes will be classified, managed, stored, and disposed of in accordance with Federal, State, and local laws and regulations.
3.4.4 Contractor Generated Hazardous Wastes/Excess Hazardous Materials
Hazardous wastes are defined in 40 CFR 261 , or are as defined by applicable State and local regulations. Hazardous materials are defined in 49 CFR 171 - 178 . At a minimum, manage and store hazardous waste in compliance with 40 CFR 262 in accordance with the Installation hazardous waste management plan. Take sufficient measures to prevent spillage of hazardous and toxic materials during dispensing. Segregate hazardous waste from other materials and wastes, protect it from the weather by placing it in a safe covered location, and take precautionary measures such as berming or other appropriate measures against accidental spillage. Storage, describing, packaging, labeling, marking, and placarding of hazardous waste and hazardous material in accordance with 49 CFR 171 - 178 , State, and local laws and regulations is the Contractor's responsibility. Transport Contractor generated hazardous waste off Government property within 60 days in accordance with the Environmental Protection Agency and the Department of Transportation laws and regulations. Dispose of hazardous waste in compliance with Federal, State and local laws and regulations. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Facility Environmental Office. Cleanup and cleanup costs due to spills are the Contractor's responsibility. The disposition of Contractor
SECTION 01 57 20.00 10 Page 13 generated hazardous waste and excess hazardous materials are the Contractor's responsibility. Coordinate the disposition of hazardous waste with the Facility's Hazardous Waste Manager and the Contracting Officer.
3.4.5 Fuel and Lubricants
Storage, fueling and lubrication of equipment and motor vehicles must be conducted in a manner that affords the maximum protection against spill and evaporation. Manage and store fuel, lubricants and oil in accordance with all Federal, State, Regional, and local laws and regulations. Used lubricants and used oil to be discarded must be stored in marked corrosion-resistant containers and recycled or disposed in accordance with 40 CFR 279 , State, and local laws and regulations. Storage of fuel on the project site is not allowed. Fuel must be brought to the project site each day that work is performed. Storage of fuel on the project site will be in accordance with all Federal, State, and local laws and regulations.
(See Offut Air Force Base's Attachment Number 5.)
3.4.6 Waste Water
Disposal of waste water will be as specified below.
a. Waste water from construction activities, such as onsite material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, forms, etc. will not be allowed to enter water ways or to be discharged prior to being treated to remove pollutants. Dispose of the construction related waste water off-Government property in accordance with all Federal, State, Regional and Local laws and regulations.
b. For discharge of ground water, the Contractor will obtain a State or Federal permit specific for pumping and discharging ground water prior to surface discharging. Based on the contaminates in the ground water it will either be discharged to the sanitary or storm water sewer with the approval of the Offutt Air Force Base Environmental Flight Office (CEV).
c. Water generated from the flushing of lines after disinfection or disinfection in conjunction with hydrostatic testing will be discharged into the sanitary sewer with prior approval and/or notification to the Waste Water Treatment Plant's Operator.
3.5 RECYCLING AND WASTE MINIMIZATION
Participate in State and local government sponsored recycling programs.
The Contractor is further encouraged to minimize solid waste generation throughout the duration of the project.
3.6 NON-HAZARDOUS SOLID WASTE DIVERSION REPORT
Maintain an inventory of non-hazardous solid waste diversion and disposal of construction and demolition debris. Submit a report to Offutt Environmental Flight through the Contracting Officer on the first working day after each fiscal year quarter, starting the first quarter that non-hazardous solid waste has been generated. The Contractor shall divert to reuse or recycle at least 50% of the construction and demolition debris generated during the project per the Air Force solid waste diversion rate goal. A non-hazardous waste report is included as an attachment.
SECTION 01 57 20.00 10 Page 14
3.7 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES
If during excavation or other construction activities any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, all activities that may damage or alter such resources will be temporarily suspended. Resources covered by this paragraph include but are not limited to: any human skeletal remains or burials; artifacts; shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer so that the appropriate authorities may be notified and a determination made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in impact to or the destruction of these resources. Secure the area and prevent employees or other persons from trespassing on, removing, or otherwise disturbing such resources.
3.8 BIOLOGICAL RESOURCES
Minimize interference with, disturbance to, and damage to fish, wildlife, and plants including their habitat. The protection of threatened and endangered animal and plant species, including their habitat, is the Contractor's responsibility in accordance with Federal, State, Regional, and local laws and regulations.
3.8.1 Migratory Bird Treaty Act
Clearing and grubbing shall be scheduled so as to avoid disturbance to any active nests of migratory birds covered by the above Act. Normally, that allows clearing only from 15 September to 31 January. However, subject to the results of a survey by a qualified biologist, the CO may determine that trees in the work area are free of nests, and allow such trees to be cleared outside the stated time window. Adherence to these guidelines will help avoid any unnecessary take of migratory birds and the penalties specified in the Act and associated regulations.
3.8.1.1 Bald Eagles
The Contractor shall be responsible for identifying and avoiding disturbing any bald eagles which may be roosting or nesting in the project area. Bald Eagles shall not be disturbed. The Government recommends avoiding roosting bald eagles by eliminating activity within 83 yards of the roosting bald eagle and 0.5 miles (880 yards) of active bald eagle nests . However, this is a general recommendation, and may change dependent upon location, available cover, and concealment. It is the Contractor's responsibility to accurately determine appropriate distances to avoid disturbing the Bald Eagle. The Contractor shall ensure that his employees are able to identify bald eagles and shall avoid disturbing bald eagles. Bald eagles have been known to nest as early as January, and the chicks are usually fledged by mid-July.
3.9 INTEGRATED PEST MANAGEMENT
In order to minimize impacts to existing fauna and flora, the Contractor through the Contracting Officer, must coordinate with the Installation Pest Management Coordinator (IPMC) at the earliest possible time prior to pesticide application. Discuss integrated pest management strategies with
SECTION 01 57 20.00 10 Page 15 the IPMC and receive concurrence from the IPMC through the COR prior to the application of any pesticide associated with these specifications.
Installation Project Office Pest Management personnel will be given the opportunity to be present at all meetings concerning treatment measures for pest or disease control and during application of the pesticide. The use and management of pesticides are regulated under 40 CFR 150 - 189 .
3.9.1 Pesticide Delivery and Storage
Deliver pesticides to the site in the original, unopened containers bearing legible labels indicating the EPA registration number and the manufacturer's registered uses. Store pesticides according to manufacturer's instructions and under lock and key when unattended.
3.9.2 Qualifications
For the application of pesticides, use the services of a subcontractor whose principal business is pest control. The subcontractor must be licensed and certified in the state where the work is to be performed.
3.9.3 Pesticide Handling Requirements
Formulate, treat with, and dispose of pesticides and associated containers in accordance with label directions and use the clothing and personal protective equipment specified on the labeling for use during all phases of the application. Furnish Safety Data Sheets (SDS) for all pesticide products.
3.9.4 Application
Apply pesticides using a State Certified Pesticide Applicator in accordance with EPA label restrictions and recommendation. The Certified Applicator must wear clothing and personal protective equipment as specified on the pesticide label. The Contracting Officer will designate locations for water used in formulating. Do not allow the equipment to overflow. All equipment must be inspected for leaks, clogging, wear, or damage and repaired prior to application of pesticide.
3.10 PREVIOUSLY USED EQUIPMENT
Clean all previously used construction equipment prior to bringing it onto the project site. Ensure that the equipment is free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. Consult with the USDA jurisdictional office for additional cleaning requirements.
3.11 MAINTENANCE OF POLLUTION FACILITIES
Maintain permanent and temporary pollution control facilities and devices for the duration of the contract or for that length of time construction activities create the particular pollutant.
3.12 MILITARY MUNITIONS
In the event military munitions, as defined in 40 CFR 260 , are discovered or uncovered, the Contractor will immediately stop work in that area and immediately inform the Contracting Officer.
SECTION 01 57 20.00 10 Page 16
3.13 TRAINING OF CONTRACTOR PERSONNEL
The Contractor's personnel must be trained in all phases of environmental protection and pollution control. Conduct environmental protection/pollution control meetings for all personnel prior to commencing construction activities. Additional meetings must be conducted for new personnel and when site conditions change. Include in the training and meeting agenda: methods of detecting and avoiding pollution;
familiarization with statutory and contractual pollution standards;
installation and care of devices, vegetative covers, and instruments required for monitoring purposes to ensure adequate and continuous environmental protection/pollution control; anticipated hazardous or toxic chemicals or wastes, and other regulated contaminants; recognition and protection of archaeological sites, artifacts, wetlands, and endangered species and their habitat that are known to be in the area.
3.14 POST CONSTRUCTION CLEANUP
The Contractor will clean up all areas used for construction in accordance with Contract Clause: "Cleaning Up". Unless otherwise instructed in writing by the Contracting Officer, obliterate all signs of temporary construction facilities such as haul roads, work area, structures, foundations of temporary structures, stockpiles of excess or waste materials, and other vestiges of construction prior to final acceptance of the work. The disturbed area must be graded, filled and the entire area seeded unless otherwise indicated.
-- End of Section --
SECTION 01 57 20.00 10 Page 17
MILSTAR D3469200
RTA Submittal
SECTION 13 49 20.00 10
RFI/EMI SHIELDING
10/07
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 325 (2017) Steel Construction Manual
AMERICAN WELDING SOCIETY (AWS)
AWS A5.18/A5.18M (2021) Specification for Carbon Steel Electrodes and Rods for Gas Shielded Arc Welding
AWS BRH (2007; 5th Ed) Brazing Handbook
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
AWS D1.3/D1.3M (2018) Structural Welding Code - Sheet Steel
AWS D9.1/D9.1M (2018) Sheet Metal Welding Code
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A568/A568M (2019a) Standard Specification for Steel, Sheet, Carbon, Structural, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements for
ASTM A653/A653M (2020) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM B194 (2008) Standard Specification for Copper-Beryllium Alloy Plate, Sheet, Strip, and Rolled Bar
ASTM B545 (2013; R 2021) Standard Specification for Electrodeposited Coatings of Tin
SECTION 13 49 20.00 10 Page 1
ASTM E90 (2009; R2016) Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 142 (2007; Errata 2014) Recommended Practice for Grounding of Industrial and Commercial Power Systems - IEEE Green Book
IEEE 299 (2006; R 2012) Standard Method for Measuring the Effectiveness of Electromagnetic Shielding Enclosures
IEEE C62.11 (2020) Standard for Metal-Oxide Surge Arresters for Alternating Current Power Circuits (>1kV)
IEEE C62.33 (2016) Test Methods and Performance Values for Metal-Oxide Varistor Surge Protective Components
IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits
IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA ICS 6 (1993; R 2016) Industrial Control and Systems: Enclosures
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA
20-1; TIA 20-2; TIA 20-3; TIA 20-4)
National Electrical Code
NFPA 77 (2014) Recommended Practice on Static Electricity
NFPA 80 (2019) Standard for Fire Doors and Other Opening Protectives
NFPA 80A (2022) Recommended Practice for Protection of Buildings from Exterior Fire Exposures
NFPA 101 (2021) Life Safety Code
NFPA 780 (2020) Standard for the Installation of Lightning Protection Systems
SECTION 13 49 20.00 10 Page 2
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-HDBK-419 (1987; Rev A) Grounding, Bonding, and Shielding for Electronic Equipments and Facilities Volumes 1 of 2 Basic Theory
MIL-STD-188-124 (1998; Rev B; Notice 2 1998; Notice 3 2000; Notice 4 2013)…