W9128F21B0013 Bid Abstract.pdf
PDF 494 KB Posted
- Attached to
- 2021 Bank Stabilization & Navigation Project (BSNP) Structures Repair Project Federal contract opportunity
- Solicitation number
- W9128F21B0013
About this file
This abstract of offers document summarizes bids received in response to a solicitation for the 2021 Bank Stabilization and Navigation Project Structures Repair Project on the Missouri River from River Mile 611 to 498. The solicitation seeks a contractor to rehabilitate critical damaged bank stabilization and navigation structures by adding quarried rock to replace areas of deterioration and effectively rebuild parts of structures with substantial material loss. The Army Corps of Engineers issued the solicitation and received bids from five contractors ranging in total cost from $12.74 million to $22.30 million for the base work and options to add additional structures. The document provides unit pricing for stone placement and remaining work for the base requirements and eight options that would add further structures to the scope of work. Completion is required by 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 6. AM0004 Drawings.pdf | ||
| AM0004_21B0013_1Aug2021.pdf | ||
| AM0003_21B0013_27Jul2021.pdf | ||
| AM0002_21B0013_22Jul2021.pdf | ||
| 4. AM0002 01 22 00.pdf | ||
| 5. AM0002 Drawings.pdf | ||
| 2021 BSNP site visit sign-in sheet.pdf | ||
| AM0001 drawings.pdf | ||
| AM0001_21B0013.pdf | ||
| W9128F21B0013_6-29-2021.pdf | ||
| Specs 2021 Mo River BSNP.pdf | ||
| BSNP 2021 RTA Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED
9-Aug-21
I CERTIFY THAT I HAVE OPENED, READ AND
AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED
2021 Bank Stabilization & Navigation Project (BSNP) Structures Repair Project (RM 611 to 498) Missouri River, IA, MO, and NE
C. REASONABLE CONTRACT
7A 7B 7C D. E. F.
ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 498 to 520 (10 Structures)
23,306 Tons $56.26 $1,311,195.56 $62.00 $1,444,972.00 $109.00 $2,540,354.00 $57.50 $1,340,095.00 $75.00 $1,747,950.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 520 to 540 (9 Structures)
24,595 Tons $56.26 $1,383,714.70 $62.00 $1,524,890.00 $102.00 $2,508,690.00 $59.50 $1,463,402.50 $75.00 $1,844,625.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 540 to 560 (11 Structures)
22,882 Tons $56.26 $1,287,341.32 $63.00 $1,441,566.00 $97.00 $2,219,554.00 $61.50 $1,407,243.00 $75.00 $1,716,150.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 560 to 580 (5 Structures)
11,955 Tons $56.26 $672,588.30 $63.00 $753,165.00 $88.00 $1,052,040.00 $55.50 $663,502.50 $75.00 $896,625.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 580 to 590 (3 Structures)
11,081 Tons $56.26 $623,417.06 $63.00 $698,103.00 $82.00 $908,642.00 $55.50 $614,995.50 $75.00 $831,075.00
Entire work, complete, for quarried stone as shown on the drawings and specifications from River Mile 520 to 530 (7 Structures)
6,603 Tons $56.26 $371,484.78 $65.00 $429,195.00 $114.00 $752,742.00 $59.50 $392,878.50 $75.00 $495,225.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 518 to 519 (1 Structure)
9,884 Tons $56.26 $556,073.84 $60.00 $593,040.00 $108.00 $1,067,472.00 $57.50 $568,330.00 $75.00 $741,300.00
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 542 to 555 (17 Structures)
20,389 Tons $56.26 $1,147,085.14 $70.00 $1,427,230.00 $97.00 $1,977,733.00 $67.50 $1,376,257.50 $75.00 $1,529,175.00
0009 All remaining work except for Option Items listed below 1 Job $510,370.00 $510,370.00 $1,750,000.00 $1,750,000.00 $1,046,000.00 $1,046,000.00 $260,000.00 $260,000.00 $100,000.00 $100,000.00
Total Amount Basic Items (Items 0001 - 0009) $7,863,270.70 $10,062,161.00 $14,073,227.00 $8,086,704.50 $9,902,125.00
Option 1
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 505 to 520 (4 Structures)
15,453 Tons $56.26 $869,385.78 $54.00 $834,462.00 $110.00 $1,699,830.00 $56.50 $873,094.50 $75.00 $1,158,975.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $26,310.00 $26,310.00 $13,000.00 $13,000.00 $6,000.00 $6,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #1 Items (Items 0010 - 0011) $895,695.78 $847,462.00 $1,705,830.00 $877,094.50 $1,258,975.00
Option 2
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 530 to 540 (4 Structures)
7,948 Tons $57.15 $454,228.20 $57.00 $453,036.00 $107.00 $850,436.00 $58.50 $464,958.00 $75.00 $596,100.00
All remaining work in the option are as shown on the drawings and in the specifications
1 Job $26,310.00 $26,310.00 $14,000.00 $14,000.00 $1,000.00 $1,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #2 Items (Items 0012 - 0013) $480,538.20 $467,036.00 $851,436.00 $468,958.00 $696,100.00
Option 3
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 530 to 535 (1 Structure)
17,130 Tons $56.26 $963,733.80 $56.00 $959,280.00 $102.00 $1,747,260.00 $58.50 $1,002,105.00 $75.00 $1,284,750.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $26,310.00 $26,310.00 $22,000.00 $22,000.00 $1,000.00 $1,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #3 Items (Items 0014 - 0015) $990,043.80 $981,280.00 $1,748,260.00 $1,006,105.00 $1,384,750.00
Option 4
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 537 to 539 (3 Structures)
4,639 Tons $58.56 $271,659.84 $62.00 $287,618.00 $99.00 $459,261.00 $58.50 $271,381.50 $75.00 $347,925.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $19,730.00 $19,730.00 $14,000.00 $14,000.00 $3,000.00 $3,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #4 Items (Items 0016 - 0017) $291,389.84 $301,618.00 $462,261.00 $275,381.50 $447,925.00
Option 5
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 548 to 556 (3 Structures)
15,253 Tons $56.26 $858,133.78 $56.00 $854,168.00 $93.00 $1,418,529.00 $60.50 $922,806.50 $75.00 $1,143,975.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $32,890.00 $32,890.00 $22,000.00 $22,000.00 $1,000.00 $1,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #5 Items (Items 0018 - 0019) $891,023.78 $876,168.00 $1,419,529.00 $926,806.50 $1,243,975.00
Option 6
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 555 to 560 (3 Structures)
10,117 Tons $56.26 $569,182.42 $56.00 $566,552.00 $88.00 $890,296.00 $60.50 $612,078.50 $75.00 $758,775.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $19,730.00 $19,730.00 $9,000.00 $9,000.00 $3,000.00 $3,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #6 Items (Items 0020 - 0021) $588,912.42 $575,552.00 $893,296.00 $616,078.50 $858,775.00
Option 7
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 560 to 565 (1 Structures)
5,656 Tons $57.15 $323,240.40 $56.00 $316,736.00 $88.00 $497,728.00 $54.50 $308,252.00 $75.00 $424,200.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $13,160.00 $13,160.00 $9,000.00 $9,000.00 $1,000.00 $1,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #7 Items (Items 0022 - 0023) $336,400.40 $325,736.00 $498,728.00 $312,252.00 $524,200.00
Option 8
Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 590 to 612 (2 Structures)
6,882 Tons $57.15 $393,306.30 $62.00 $426,684.00 $94.00 $646,908.00 $56.50 $388,833.00 $75.00 $516,150.00
All remaining work in the option area as shown on the drawings and in the specifications
1 Job $13,160.00 $13,160.00 $9,000.00 $9,000.00 $1,000.00 $1,000.00 $4,000.00 $4,000.00 $100,000.00 $100,000.00
Total Amount Option #8 Items (Items 0024 - 0025) $406,466.30 $435,684.00 $647,908.00 $392,833.00 $616,150.00
TOTAL $12,743,741.22 $14,872,697.00 $22,300,475.00 $12,962,213.50 $16,932,975.00
Bid Security 20% C. AMENDMENTS ACKNOWLEDGED: Yes
NO. 3
C. OFFEROR
Western Contracting Corporation
705 Douglas St, Ste 400
Sioux City, IA 51101-1087
Bid Security 20% C. AMENDMENTS ACKNOWLEDGED : Yes
Bid Security 20% C. AMENDMENTS ACKNOWLEDGED : Yes
(Without Profit)
(Including Profit)
Nebraska City, NE 68410 Dubuque, IA 52001-7674
B. REASONABLE CONTRACT
6. NUMBER OF AMENDMENTS ISSUED
A. OFFEROR B. OFFEROR
PO Box 610 5 Jones St, Ste 2
A. HIRED LABOR
IGE Midwest Construction Company Newt Marine Service
NO. 1 NO. 2
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F21B0013
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE
(Check A, B or C AND COMPLETE D, E AND F)
5. PROJECT TITLE 9. OFFERS
TO THIS SOLICITATION
SIGNATURE
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
OMAHA, NE 68102-1618
1616 CAPITOL AVENUE
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
l PAGES
Bid Security N/A C. AMENDMENTS ACKNOWLEDGED: Yes
NO. 4
C. OFFEROR
Common Construction LLC
1906 Hwy 38 W
Des Arc AR, 72040
David W. Neal, Contracting Officer
9-Aug-2021
| 2021-08-09T15:29:32-0500 | |
| NEAL.DAVID.W.1115489000 |