AM0002_21B0013_22Jul2021.pdf
PDF 404 KB Posted
- Attached to
- 2021 Bank Stabilization & Navigation Project (BSNP) Structures Repair Project Federal contract opportunity
- Solicitation number
- W9128F21B0013
About this file
This document is an amendment to a solicitation for construction services to repair structures along the Missouri River Bank Stabilization and Navigation Project between River Miles 611 to 498.
The amendment modifies the specifications, drawings, bid schedule and contract clauses. It adds language clarifying requirements regarding the endangered pallid sturgeon. The bid schedule is revised to include additional repair areas and options to extend work, and completion dates are set between July 2022 and November 2021 for certain structures. The Department of the Army Corps of Engineers Omaha District is seeking bids for rock placement and repair work across 113 structures to rehabilitate areas damaged in 2019 floods and maintain the navigation channel. The pre-bid site visit was scheduled for July 15, 2021.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9128F21B0013 Bid Abstract.pdf | ||
| 6. AM0004 Drawings.pdf | ||
| AM0004_21B0013_1Aug2021.pdf | ||
| AM0003_21B0013_27Jul2021.pdf | ||
| 4. AM0002 01 22 00.pdf | ||
| 5. AM0002 Drawings.pdf | ||
| 2021 BSNP site visit sign-in sheet.pdf | ||
| AM0001 drawings.pdf | ||
| AM0001_21B0013.pdf | ||
| W9128F21B0013_6-29-2021.pdf | ||
| Specs 2021 Mo River BSNP.pdf | ||
| BSNP 2021 RTA Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W59XQG10989674
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Am0002 in SF30 Block 14 Continuation Page for description of amendment changes.
1. CONTRACT ID CODE PAGE OF PAGES
1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jul-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F21B0013
X 9B. DATED (SEE ITEM 11)
29-Jun-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jul-2021
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F21B0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AM0002
SUBJECT: Amendment No. 0002 to Specifications and Drawings for Construction of 2021 Bank Stabilization & Navigation Project (BSNP) Structures Repair project (Rm 611 to 498), Missouri River, IA, MO and NE.
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.)
(1) Section 01 57 20.00 10 Page 14, delete paragraph 3.8.1.2 “Pallid sturgeon” and substitute the following
“3.8.1.2 Pallid Sturgeon
The pallid sturgeon is a federally listed endangered species that may be found within the proposed project area.
The proposed maintenance and repair activities fall within the range of activities consulted on during the development of the U.S. Army Corps of Engineers (Corps) 2017 Biological Assessment for the Operation of the Missouri River Mainstem Reservoir System, the Operation and Maintenance of the Missouri River Bank Stabilization and Navigation Project (BSNP), Operation of the Kansas River Reservoir System, and the Implementation of the Missouri River Recovery Management Plan (2017 BA), and the U.S. Fish and Wildlife Service’s (USFWS) 2018 Biological Opinion for the Operation of the Missouri River Mainstem Reservoir System, the Operation and Maintenance of the BSNP, Operation of the Kansas River Reservoir System, and the Implementation of the Missouri River Recovery Management Plan (2018 BiOp). In the 2018 BiOp, the USFWS concurred with the Corps’ determination in the 2017 BA that activities associated with operation, maintenance, and repair of the BSNP may affect, but are not likely to adversely affect pallid surgeon.”
b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.
Pages or Sections Deleted Pages or Sections Substituted or Added
Section 01 22 00 Section 01 22 00 Measurement and Payment Measurement and Payment
c. Drawings (Reissued). The following drawings are revised with latest revision date of 22 July 2021, and reissued with this amendment.
(1) Sheets: C2.04, C2.05, C2.06, C3.01, C3.02
d. Bid Schedule. See Section 00 10 00 for revised bid schedule. All offerors must use the bid schedule from Amendment 0002, unless changed by a subsequent amendment.
e. FAR 52.217-7 Option for Increased Quantity-Separately Priced Line Item. Clause revised to reflect options in revised bid schedule.
f. FAR 52.211-10 Commencement, Prosecution, and Completion of Work. Clause revised to reflect completion date requirements included revised Drawing Sheet’s C3.01 & C3.02.
2. Attachments.
a. Am0002 Drawings listed in 1(c) above.
b. Section 01 22 00 Measurement and Payment
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Specs 2021 Mo River
BSNP - June 2021
Attachment 2 BSNP 2021 RTA Drawings - June 2021
Attachment 3 AM0001 Drawings 5 09-JUL-2021 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Specs 2021 Mo River
BSNP - June 2021
Attachment 2 BSNP 2021 RTA Drawings - June 2021
Attachment 3 AM0001 Drawings 5 09-JUL-2021 Attachment 4 AM0002 01 22 00
Measurement & Payment
Attachment 5 AM0002 Drawings 5 22-JUL-2021
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The following have been modified:
BID SCHEDULE
BID SCHEDULE
Item Estimated Unit No. Description Quantity Unit Price Amount
BASIC
0001. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 498 to 520 (10 Structures) 23,306 Tons $_________ $___________
0002. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 520 to 540 (10 Structures) 30,535 Tons $_________ $___________
0003. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 540 to 560 (11 Structures) 22,882 Tons $_________ $___________
0004. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 560 to 580 (5 Structures) 11,955 Tons $_________ $___________
0005. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 580 to 590 (3 Structures) 11,081 Tons $_________ $___________
0006. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 520 to 530 (8 Structures) 12,550 Tons $_________ $___________
0007. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 518 to 519 (1 Structure) 9,884 Tons $_________ $___________
0008. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 542 to 555 (17 Structures) 20,389 Tons $_________ $___________
0009. All remaining work Except for Option
Items listed below 1 Job XXX $___________
TOTAL BASIC AMOUNT (Items 0001 thru 0009) $_______________
OPTION 1
0010. Entire work, complete, as shown on the drawings and in the specifications from River Mile 505 to 520 (4 Structures) 15,453 Tons $_________ $___________
0011. All remaining work in the option area as shown on the drawings and 1 Job XXX $___________ in the specifications
TOTAL AMOUNT – OPTION 1 (Items 0010 & 0011) $_______________
OPTION 2
0012. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 530 to 540 (4 Structures) 7,948 Tons $_________ $___________
0013. All remaining work in the option area
TOTAL AMOUNT – OPTION 2 (Items 0012 & 0013) $_______________
OPTION 3
0014. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 530 to 535 (1 Structure) 17,130 Tons $_________ $___________
0015. All remaining work in the option area
TOTAL AMOUNT – OPTION 3 (Items 0014 & 0015) $_______________
OPTION 4
0016. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 537 to 539 (3 Structures) 4,639 Tons $_________ $___________
0017. All remaining work in the option area as shown on the drawings and 1 Job XXX $___________
TOTAL AMOUNT – OPTION 4 (Items 0016 & 0017) $_______________
OPTION 5
0018. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 548 to 556 (3 Structures) 15,253 Tons $_________ $___________
0019. All remaining work as shown on the drawings and in the specifications 1 Job XXX $___________
TOTAL AMOUNT – OPTION 5 (Items 0018 & 0019) $_______________
OPTION 6
0020. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 555 to 560 (3 Structures) 10,117 Tons $_________ $___________
0021. All remaining work in the option area
TOTAL AMOUNT – OPTION 6 (Items 0020 & 0021) $_______________
OPTION 7
0022. Entire work, complete, as shown on the drawings and in the specifications from River Mile 560 to 565 (1 Structures) 5,656 Tons $_________ $___________
0023. All remaining work in the option area
TOTAL AMOUNT – OPTION 7 (Items 0022 & 0023) $_______________
OPTION 8
0024. Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 590 to 612 (2 Structures) 6,882 Tons $_________ $___________
0025. All remaining work
TOTAL AMOUNT – OPTION 8 (Items 0024 & 0025) $_______________
TOTAL BASIC AMOUNT (Items 0001 thru 0009) $_______________
TOTAL AMOUNT BASIC PLUS OPTIONS (Items 0001 thru 0025) $_______________
Notes:
1. See SECTION 00 21 00, INSTRUCTIONS, FAR 52.217-5 for information on evaluation of options.
2. The quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to FAR 52.211-18 "Variation in Estimated Quantity."
3. Bid prices must be entered for all items of the schedule. See SECTION 00 21 00, INSTRUCTIONS, paragraph 1.1.11 REJECTION OF BIDS FOR information on rejection of bids. See SECTION 00 21 00, INSTRUCTIONS, paragraph 1.1.4 Arithmetic Discrepancies for information on clerical mistakes.
4. See SECTION 00 21 00, INSTRUCTIONS, paragraph 1.1.3 INFORMATION FOR MODIFYING BIDS for information if bid modifications are needed.
5. See SECTION 01 22 00 MEASUREMENT AND PAYMENT for additional information.
6. See SECTION 00 72 00, GENERAL CONDITIONS, FAR 52.217-7 Option for Increased Quantity—Separately Priced Line Items for additional information on how the Government will award option items.
SECTION 00 72 00 - GENERAL CONDITIONS
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require continued performance of option line items at the price stated in the bid schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 365 calendar days after issuance of the notice to proceed.. Performance of option items shall continue at the option price under the contract unless the parties otherwise agree.
The Government will exercise Option 1, Items 0010 & 0011 together or not at all. The Government will exercise Option 2, Items 0012 & 0013 together or not all. The Government will exercise Option 3, Items 0014 & 0015 together or not all. The Government will exercise Option 4, Items 0016 & 0017 together or not all. The Government will exercise Option 5, Items 0018 & 0019 together or not all. The Government will exercise Option 6, Items 0020 & 0021 together or not all. The Government will exercise Option 7, Items 0022 & 0023 together or not all. The Government will exercise Option 8, Items 0024 & 0025 together or not all.
If the Government exercises options items, the contractor must perform the work within the time left under the contract, meaning the Government will not add time to the contract.
The Contracting Officer may require additional bond security per FAR 52.228-2 Additional Bond Security when option items are exercised
(End of clause)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the following:
- 30 November 2021 for all work in bid schedule item 0008; Entire work, complete, for quarried stone as shown on the drawings and in the specifications from River Mile 542 to 555 (17 Structures).
- 31 July 2022 for the nine structures listed on Drawing Sheet C3.01 (Amendment 0002).
- 870 calendar days for all other work.
*The time stated for completion shall include final cleanup of the premises.
(End of clause)
(End of Summary of Changes)