This document is an amendment to a solicitation for construction services for the Middle Logan Creek Flood Risk Management Project, Phase 2 in Randolph, Nebraska. The amendment provides revised specifications, drawings, and bid schedule. Key changes include adding language regarding Nebraska wastewater permitting requirements, revising asbestos and lead abatement specifications, and reissuing design drawings. The bid schedule was also modified by adding item numbers for an optional bridge and associated pile work. Contractors must acknowledge and use the revised bid documents provided in the amendment when submitting responses to the solicitation issued by the Department of the Army Corps of Engineers Omaha District for flood risk reduction work along Middle Logan Creek.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W59XQG10828776
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Am0002 in the SF30 Block 14 - Continuation Page for description of the amendment changes.
1. CONTRACT ID CODE PAGE OF PAGES
1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F21B0012
X 9B. DATED (SEE ITEM 11)
20-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Aug-2021
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F21B0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AM0002
SUBJECT: Amendment No. 0002 to Specifications and Drawings for Construction of Middle Logan Creek, Flood Risk Management Project, Phase 2, Randolph NE.
1. The specifications and drawings for subject project are hereby changed as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.)
(1) Section 01 57 20.00 10 Page 10, delete paragraph 3.1.2 and substitute the following:
“3.1.2 Nebraska Department of Environment and Energy Title 123 Rules and Regulations for the Design, Operation and Maintenance of Wastewater Works
The State of Nebraska requires a permit for addition to any wastewater works. This project includes a siphon and will require a permit. See http://deq.ne.gov/RuleAndR.nsf/RuleAndReg.xsp?documentId=9A59462AE6FE4CF306256BB9005475E1& action=openDocument for a copy of the Nebraska Administrative Code for Title 123 Rules and Regulations for the Design, Operations and Maintenance of Waste water Works for information on the required permit.
The US Army Corps of Engineers will apply for this permit with two sets of plans, specifications, calculations, and the Construction Permit Application Form Wastewater Works from Nebraska DEE. There are no fees associated with this permit. A copy of the permit will be provided to Contractor when obtained by the Corps of Engineers. “
(2) Section 02 82 00 Page 4, remove PART 1 GENERAL and substitute the following:
“Part 1 General
Attachment: Hazardous Materials Survey Technical Memorandum, 212 South Douglas Street, Randolph, NE
Structures at 212 S. Douglas Street, Randolph, NE will be demolished, including the residence containing the asbestos-containing building materials identified in the attached technical memorandum. Approximate quantities and locations of the materials are identified in the attachment. Asbestos-containing materials identified in the residence include wall and ceiling plaster, 9”x9” floor tiles, window glazing on the main porch windows, door window glazing on the main porch door, air cell pipe insulation on pipes in the basement, pipe insulation wrap on pipe joints in the basement, and roof flashing around roof penetrations. In addition, materials containing less than 1% asbestos include door window glazing on the breezeway door exterior and floor tile adhesive associated with the asbestos-containing floor tiles. As an alternative to removing asbestos-containing glazing from doors and windows, the Contractor may choose to remove doors and windows with asbestos-containing glazing intact. Materials containing less than 1% asbestos are not required to be removed, however, the Contractor shall comply with the applicable work practices required by 29 CFR 1926.1101(g)(1)(ii) and 29 CFR 1926.1101(g)(1)(iii) to protect workers during any tasks that may disturb such materials.
No asbestos-containing materials were identified in the outbuildings for this residence. Remove asbestos-containing materials from the residence prior to demolition in accordance with this specification and applicable regulations.”
(3) Section 02 83 00 Page 3, remove PART 1 GENERAL and substitute the following:
“Part 1 General
Structures at 212 S. Douglas Street, Randolph, NE will be demolished. See the Hazardous Materials Survey Technical Memorandum, 212 South Douglas Street, Randolph, NE attached to section 02 82 00 ASBESTOS REMEDIATION for information about the presence of lead-based and lead-containing paint located on the structures. In addition, the interior paint in the residence contains poly-chlorinated biphenyls (PCBs) (see the Hazardous Materials Survey Technical Memorandum). The concentration of PCBs in the paint is not at regulated levels and does not require special disposal action. Protect workers and the environment from exposure to lead and PCBs during the demolition process in accordance with this specification and applicable regulations. Removal of paint from the structures prior to demolition is not required.”
b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.
Pages or Sections Deleted Pages or Sections Substituted or Added
--- Attachment to Section 02 82 00: Hazardous Materials Survey Technical
Memorandum, 212 South Douglas Street, Randolph, NE
c. Drawings (Reissued). The following drawings are revised with latest revision date of 13 August 2021 and reissued with this amendment.
(1) Sheets: CD101 & CD102.
d. Bid Schedule. See Section 00 10 00 for revised bid schedule. All offerors must use the bid schedule from Amendment 0002, unless changed by a subsequent amendment.
2. This amendment is a part of the bidding papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.
3. Attachments.
a. Am0002 Drawings listed in 1c above.
b. Specification attachment listed in 1b above.
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Specifications - July 2021 480
Attachment 2 Drawings 1 of 3 - July
Attachment 3 Drawings 2 of 3 - July
Attachment 4 Drawings 3 of 3 - July
Attachment 5 Am0001 Drawings 3 11-AUG-2021 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Specifications - July 2021 480 Attachment 2 Drawings 1 of 3 - July
Attachment 3 Drawings 2 of 3 - July
Attachment 4 Drawings 3 of 3 - July
Attachment 5 Am0001 Drawings 3 11-AUG-2021 Attachment 6 Am0002 Drawings 2 13-AUG-2021 Attachment 7 Attachment to 02 82 00 64
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The following have been modified:
BID SCHEDULE
BID SCHEDULE
ITEM NO. DESCRIPTION
ESTIMATED
QUANTITY
UNIT
UNIT
PRICE
ESTIMATED AMOUNT
BASIC ITEMS
Entire work complete for Main Street Bridge, exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).
1 Job XXX $_____________________
Entire work complete for 558th Ave. Bridge exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).
Job
XXX
All plant, material, and labor required for Earth Excavation.
110,000
CY
labor required for on project site placement of Compacted Earthen Fill.
68,000 labor required for off project site placement of surplus Earthen Spoil.
42,000
All plant, material, and labor required for Riprap, including riprap rock, spalls and bedding material.
6,832
TON
All plant, material, and labor required for furnishing and delivering Steel H-piles.
5,840
LF
All plant, material, and labor required for Driving Steel H-piles.
5,840
LF
All plant, material, and labor required for Driving Tests for Steel H-piles.
EA
All plant, material, and labor required for waterlines 1, 2 and 3.
labor required for sanitary sewer siphon.
All remaining work for basic items above.
1 Job XXX $_____________________
TOTAL AMOUNT BASIC (ITEMS 0001 THRU 0012) $____________________________
OPTION #1
Entire work complete for Douglas Street Bridge exclusive of the Steel H-piles and associated work (Items 0014 thru 0016).
1 Job XXX $_____________________
All plant, material, and labor required for furnishing and delivering Steel H-piles Douglas Street Bridge
3,570 LF $_________ $_____________________
All plant, material, and labor required for Driving Steel H-piles for Douglas Street Bridge
3,570 LF $_________ $_____________________
All plant, material, and labor required for Driving Tests for Steel H-piles for Douglas Street Bridge
3 EA $_________ $_____________________
All remaining work for Douglas Street Bridge.
1 Job XXX $_____________________
TOTAL AMOUNT OPTION (ITEMS 0013 THRU 0017) $____________________________
TOTAL AMOUNT BASIC PLUS OPTION (ITEMS 0001 THRU 0017) $______________________
NOTES:
1. See SECTION 00 21 00, INSTRUCTIONS, FAR 52.217-5 for information on evaluation of options.
2. The quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to FAR 52.211-18 Variation in Estimated Quantity.
3. Bidders must enter prices for all bid schedule items. See SECTION 00 21 00, INSTRUCTIONS, paragraph
1.1.11 REJECTION OF BIDS for information on rejection of bids. See SECTION 00 21 00, INSTRUCTIONS, paragraph 1.1.4 ARITHMETIC DISCREPANCIES for information on clerical mistakes.
4. See SECTION 00 21 00, INSTRUCTIONS, paragraph 1.1.3 INFORMATION FOR MODIFYING BIDS for information if the bidder needs to modify the bid.
5. See SECTION 01 22 00 MEASUREMENT AND PAYMENT for additional information.
6. See SECTION 00 72 00, GENERAL CONDITIONS, FAR 52.217-7 Option for Increased Quantity – Separately Priced Line Items for additional information for how the Government will award option items.