PDT Includes:
Michael Howe, PM Forward
Gary Shirakata, Project Manager
Jianping Pu, Technical Lead
Blair Jones P.E., Kwajalein Resident Engineer
Mike McMahon, Kwajalein Project Engineer
Raymond Greenheck, Contracting Officer
FY19 BUCHOLZ ARMY AIRFIELD
KWAJALEIN ATOLL, MARSHALL ISLANDS
SITE VISIT AND PRE-BID CONFERENCE
DATE: 17 APRIL 2019
BUILDING STRONG®
WELCOME
Sign In Sheet
Introduction of Government Personnel USAG-KA Staff USAG-KA DPW Staff POH Staff
ALL Questions / Inquiries shall be submitted via the PROJNET Bidder Inquiry Model at: https://www.projnet.org/projnet/.
Bidder Inquiry Key: IRIT4R-4GCNTW
***Last day to submit questions / inquiries is April 26th 2019 at 10am Hawaii Standard Time ***
Site visit itinerary
Rules of conference
Quick tips for solicitations
Contracting requirements
Project Overview
General construction requirements
Typical Challenges For Contractors
DISCUSSION OVERVIEW
0900: Welcome 0910: Pre-bid conference briefing 1030: BAAF Site Visit
Navaid building Taxiways Runway
LSA
COSA
Hot Cargo Pad
1230: Lunch Zamperini Dining Facility 1330: Kwajalein Base tour
BSR (Barge Slip Ramp) Echo Pier Housing Area
1430: Release
SITE VISIT ITINERARY
17 APRIL 2019
RULES FOR CONFERENCE
Unofficial and non-binding
If there is any conflict between the information discussed during this conference and the solicitation, the terms and conditions of the solicitation will govern
No recording devices permitted. Cameras are allowed, however, please only take pictures of areas relevant to the scope of this contract.
No posting of pictures on the internet
Review all the solicitation requirements
Follow solicitation format as required
Acknowledge all amendment(s)
Respond to every submission requirement
Solicitations will be accepted from Prime Contractors only
QUICK TIPS FOR ALL SOLICITATIONS
RFP SOLICITATION FORMAT
Standard Form 1442 Section 00 10 00, CLIN Schedule Section 00 22 16, Instructions to Proposer Basis for Award Evaluation Criteria Rating Criteria
Request for Information instructions Contract Clauses
FAR
S Clauses K Clauses
Division 01, General Requirements Divisions 02 thru 34 Drawings
Make sure to note the proposal due date and time in Block 13A of
SF1442.
Proposals are due May 8th 2019, 2:00pm HST.
Offers shall be no less than 90 calendar days for Government acceptance (see block 13D).
Fill out Blocks 14, 15, 16, 18, 19, 20A, 20B, and 20C.
STANDARD FORM (SF) 1442
SECTION 00 10 00
SOLICITATION CONTRACT LINE ITEM (CLIN)
CLIN 0001 – Repair Bucholz Army Airfield Runway CLIN 0002 – Mobilization CLIN 0003 – Demobilization CLIN 0004 – Contractor Manpower Reporting CLIN 0005 – LSC Support Services
CLIN 0006 – OPS Apron, Taxiways D and F (Option Item 1) CLIN 0007 – Hot Cargo Pad Apron, Taxiway A (Option Item 2) CLIN 0008 – 400ft concrete touchdown areas (Option Item 3)
Government reserves the right to exercise option(s) up to 180 calendar days after award of the Base Schedule.
The offeror must provide proposed pricing for each CLIN, separately priced, and completed in its entirety.
SECTION 00 10 00
SOLICITATION CONTRACT LINE ITEM (CLIN)
PROJECT OVERVIEW
BASE BID
PHASE 1
***Note: Solid black indicates areas of the runway and apron that will remain in use***
BASE BID
PHASE 2
BASE BID
PHASE 3
BASE BID
PHASE 4
BASE BID
PHASE 5
OPTION 1
PHASE 1
OPTION 1
PHASE 2
OPTION 2
CONSTRUCTION GENERAL REQUIREMENTS
This project is required to complete documentation through the RMS Contractor Module system. New Project now utilizes RMS 3.0.
Project is to restore the airfield to the condition requirements of Army Regulation (AR 420-72)
This contract is required to implement the Three Phase Inspection process for all features of work as part of the Contractor’s Quality Control Plan.
Schedule reviews and updates shall be made and submitted monthly with the requested progress payments.
The project will be required to follow latest version EM 385-1-1 USACE Safety and Health Requirements Manual.
Construction regular working hours are Tues ~ Sat 9 hour days.. Sunday, federal holiday, and other than normal working hours may be arranged if coordinated 21 calendar days in advance and if approved by the government.
CONSTRUCTION GENERAL REQUIREMENTS
S-36.22 Notice of Partnering The Government intends to encourage the foundation of a cohesive partnering arrangement with the contractor and its subcontractors. This partnering arrangement will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance intended to achieve completion within budget, on schedule, and in accordance with contract plans and specifications. This partnering arrangement will be bilateral in membership. To implement this partnering initiative, it is anticipated that within 60-days of Notice to Proceed, the contractor and Government management teams to include on-site and offsite management will attend a one (1) day partnering development seminar/team building workshop. Any costs associated with this initial partnering workshop, or any other follow-on sessions if necessary, excluding salaries, travel, lodging, and food for Government personnel, shall be borne by the contractor. The facilitator for the workshop shall be an objective and neutral third party participant, skilled in team building and group dynamics, has no vested interest in the decisions reached by the group. Up to ten (10) Government personnel will attend this workshop. The partnering workshop will be held in Kwajalein.
KWAJALEIN RESIDENT OFFICE COMMITMENT TO
CONTRACTORS
• Success can never be one sided. Together the Contractor and the Kwajalein RO will work together as a team to complete this project on time, within the budgeted amount, and with no time lost to accidents.
• Help the Contractor be successful with all aspects of this project
• Submittals
• Request for Information (RFI)
• Coordination with the installation
• Overall Documentation
• Communication
• Openly
• Honestly
• Timely
• Assumptions
• Contractors know how to build
• Kwajalein RO focus on areas where assistance is required
TYPICAL PROJECT ORGANIZATION AT KWAJALEIN
RESIDENT OFFICE
Project Engineer/ Quality Assurance
Rep.
Honolulu Engineer District
USACE Quality Assurance
Representatives
Omaha District Center of Expertise for Airfield paving Designer of Record
Resident Engineer/Administrative
Contracting Officer Administrative
Assistant
US Army Garrison Kwajalein Atoll
Base Operations Contractor
TYPICAL CHALLENGES FOR CONTRACTORS
Logistics
Scheduling
Understanding requirements
Impacts to project schedules on long lead items
Submittal documentation
Security requirements for contractor personnel
KWAJALEIN RESIDENT OFFICE’S APPROACH TO CHALLENGES
Logistics ► KRO will advise and assist as needed with base operations to aid in shipping issues
Scheduling ► On-going communication, collaboration and coordination ► KRO will aid in coordinating locations, times, dates of work hours with Airfield Management as necessary to ensure smooth coordination ► Discuss expectations up front ► Submittal duration ► RFI duration ► Contract modification duration ► Constant monitoring
KWAJALEIN RESIDENT OFFICE’S APPROACH TO CHALLENGES
Understanding Requirements ► KRO is available and tasked to interpret the contract requirement as they are presented in the contract.
► The contractor is responsible to read and understand the entire contract as it is written.
Impacts to project schedules on long lead items ► KRO will place priority on submittal reviews for long lead items ► Contractor is responsible for making KRO aware of long lead submittals and submitting them within the appropriate time limits
Submittal documentation ► KRO will provide timely reviews of submittals with specific comments directly referenced within the specifications.
► Contractor is responsible for reviewing and approving each submittal before it is submitted to
KRO for review as outlined within the QC process.
FORMULA FOR SUCCESS
• The Contractor and the U.S. Army Corps of Engineers are one team.
• Success can never be one sided. Together the Contractor and the Kwajalein RO will work together as a team to complete this project on time, within the budgeted amount, meet quality requirements, and no time lost from accidents.
• Kwajalein RO wants the Contractor to bid on future U.S. Army Corps of Engineer projects
• Your success means that we as a team succeed.
SITE VISIT ITINERARY
UP COMING PROJECT FOR KWAJALEIN ATOLL
• FY20 Army Family Housing
• FY20 ATC Tower/ Ops Bldg.
• FY21 Med Clinic
• FY21 Army Family Housing
• FY22 Landfill Closure
***Estimated $750 million to be awarded over the next 4 years***
THANK YOU