REQUEST FOR PROPOSAL NO. W9128A-19-R-0009

SPECIFICATIONS

FOR

PN 92743 REPAIR BUCHOLZ ARMY

AIRFIELD (BAAF)

US. ARMY KWAJALEIN ATOLL (USAKA)

REPUBLIC OF THE MARSHALL

ISLANDS

U.S. Army Corps of Engineers

HONOLULU DISTRICT

W9128A-19-R-0009

MAIN TABLE OF CONTENTS

Request for Proposal (RFP) No. W9128A-19-R-0009, PN 92743 Repair Bucholz Army Airfield (BAAF), U.S. Army Kwajalein Atoll (USAKA), Republic of the Marshall Islands

Section 00 10 00 SF 1442 and Proposal Schedule

Section 00 21 16 Instructions to Proposers

Provisions

Section 00 22 16 Proposal Submission Requirements and Evaluation Factors

Section 00 45 00 Representations and Certifications

Appendix A, SF LLL, Disclosure of Lobbying Activities

Section 00 72 00 General Conditions

Section 00 73 00 Supplementary Conditions

Appendix A, Project Signs

Division 1 General Requirements

Division 2 through 33 Technical Requirements

INSTRUCTIONS TO OFFERORS:

1. This procurement method is unrestricted design-bid-build procurement.

2. The Offeror is REQUIRED to COMPLETE AND RETURN: See Section 00 22 16, “Instructions to

Proposers” - Proposal Submission Requirements and Evaluation Factors.

3. Offeror must have and/or maintain an active registration with the System for Award Management

(SAM) website. To register in SAM, go to https://www.sam.gov. Please note that the representations and certifications must also be completed electronically via the System for Award Management (SAM) website

4. Submit all Request for Information (RFIs) to W9128A-19-R-0009@usace.army.mil. The last day to submit RFIs is April 26, 2019 at 10:00 a.m., Hawaii Standard Time.

5. Background checks. Background checks will be done for individuals prior to traveling to Kwajalein. If a person does not pass the background check, the person will not be authorized to travel to Kwajalein.

https://www.sam.gov/ mailto:merbbyjoyce.n.nichols@usace.army.mil mailto:raymond.r.greenheck@usace.army.mil

Project Magnitude: $100,000,000 to $250,000,000

This project will be incrementally funded. See Section 00 72 00, CLAUSE 252.232-7007, Limitation of Government's Obligation

RAYMOND R GREENHECK 808-835-4380

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

NEGOTIATED

08-Apr-2019

(RFP)

(IFB)

X

CALL:

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

PN 92743 Repair Bucholz Army Airfield (BAAF), Kwajalein Island, U.S. Army Kwajalein Atoll (USAKA), Republic of the Marshall Islands

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance within _______ 10 calendar days and complete it within ________ 738 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ 5 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 08 May 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______ 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CECT - CONTRACTING DIVISION

USACE, HONOLULU DISTRICT

BLDG 252 (CECT-POH)

FT. SHAFTER HI 96858-5440

W9128A

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

92743

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX: TEL: TEL: FAX:

W9128A19R0009 78

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 21 16 – Page 1

Section 00 21 16 – Instructions to Proposers

OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in

ProjNet at (https://www.projnet.org ) no later than 10 calendar days prior to the proposal due date. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team. Offerors are requested to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted as an amendment to the solicitation in the form of a report generated from

ProjNet as soon as the comment/question entering period is over and all answers are finalized.

The Solicitation Number is: W9128A19R0009

The Bidder Inquiry Key is: IRIT4R-4GCNTW

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

http://www.projnet.org/

Section 00 010 00 - Page 1

Request for Proposal

SECTION 00 10 00

PROPOSAL SCHEDULE

PN 92743 Repair Bucholz Army Airfield, Kwajalein Island

U.S. Army Kwajalein Atoll (USAKA)

Republic of the Marshall Islands

BASE SCHEDULE

Item

No Description Quantity Unit

(a)

Amount

(b)

LSC Amt

(a)+(b)=(c)

Total Price

Repair Bucholz Army Airfield

Runway

1 JOB $ $ $

0002 Mobilization 1 JOB $ $

0003 Demobilization 1 JOB $ $

0004 Contract Manpower Reporting 1 JOB $ $

Total Base Schedule $ $ $

Note: LSC Support Services (See Special Contract Clause K-32)

OPTION

Item

No Description Quantity Unit

(a)

Amount

(b)

LSC Amt

(a)+(b)=(c)

Total Price

Option 1 - Operations Apron, Taxiways D and F

1 JOB $ $ $

Option 2 - Hot Cargo Pad Apron, Taxiway A

1 JOB $ $ $

Total Options 1 and 2

(Item Nos. 0005 and 0006)

Total Base Schedule

(Item Nos. 0001 through 0004)

Total Proposal Schedule Plus Options $ $ $

THE FOLLOWING WILL BE COMPLETED BY CONTRACTING OFFICER UPON AWARD:

TOTAL AWARD AMOUNT (Total Base Schedule plus Option Nos. __________) $_________________

Section 00 010 00 - Page 2

NOTES TO PROPOSAL SCHEDULE:

1. Offeror must insert a price on each numbered items in the Proposal Schedule. Failure to do so may cause the

Offeror to be ineligible for award.

2. Evaluation of the proposal schedule for award will be based on the TOTAL BASE SCHEDULE PLUS

OPTIONS (column c), see FAR 52.217-5, Evaluation of Options.

3. By submission of a price proposal in the Proposal Schedule under OPTIONS (Item Nos. 0005 and 0006), the

Offeror agrees that the Government may exercise:

Option Nos. 1 and 2 at time of award or within 180 calendar days following the date of award of the contract

4. Options 1 and 2 (Item Nos. 0005 and 0006), if and when executed, will NOT be in numerical order.

Section 00 010 00 - Page 3

PAYMENT(S)

Compensation for all work to be performed under this contract will be made under the payment item(s) listed herein.

The principal features of the work to be included under the payment item(s) are noted. Work required by the drawings and specifications are not particularly mentioned shall be included in and be paid for under the contract price for the item to which the work pertains. Prices(s) and payment(s) for the item(s) shall cover all work, complete and finished in accordance with the specifications, schedules, and drawings, and shall be full compensation for all work in connection therewith, including quality control and cost performance-and payment-bond premiums as specified in the CONTRACT CLAUSES. Price(s) and payment(s) shall constitute full and final compensation for furnishing all materials, equipment, management, supervision, labor, transportation, fuel, power, water, and all incidental items necessary to complete the work, except as otherwise specified to be furnished by the

Government. For the purpose of CONTRACT CLAUSE entitled "PROMPT PAYMENT FOR CONSTRUCTION

CONTRACTS", the term "designated billing office" and "designated payment office" are as follows:

a. Billing Office U.S. Army Corps of Engineers, Honolulu District Kwajalein Resident Office, Bldg 1075

PSC 701

APO, AP 96555

b. Payment Office USACE Finance Center Attn: CEFC-FP 5722 Integrity Drive

Millington, TN 38054-5005

Item number mentioned hereinafter correspond to the item number in the PROPOSAL SCHEDULE.

a. Item No. 0001, Repair Bucholz Army Airfield Runway, will be paid for at the contract price, complete in place and ready for use, including repairs by replacement of the runway pavement, airfield lights, Navigation Aids and Navigation Aid vault Building, repairs to the airfield electrical distribution system including the maintenance hole and ductine systems. Work will include reconstruction of the failed pavement and replacing with new asphalt concrete and Portland cement concrete to restore the airfield to the condition requirements of Army Regulation (AR

420-72 and the structural requirements of current and projected mission traffic), and all incidentals necessary to complete the work. Airfield will continue to function without completely shutting down during construction. No

HAZMAT is identified as part of this repair project. Surface demolition shall be disposed according to the local and DoD requirements.

b. Item No. 0002, Mobilization, will be paid for at the contract price, complete, including erosion control measures; setup of contractor’s life support, work and storage areas, and concrete batch plant; temporary project signs, dismantling of temporary work areas and removal from the island, cleanup, and all incidental items necessary to complete the work. Payment will also include the cost of premiums for performance and payment bonds specified in the CONTRACT CLAUSES. Payment for this item will be in the proportion of 70 percent mobilization and 30 percent demobilization.

c. Item No. 0003, Demobilization, will be paid for at the contract price, complete, including erosion control measures; setup of contractor’s life support, work and storage areas, and concrete batch plant; temporary project signs, dismantling of temporary work areas and removal from the island, cleanup, and all incidental items necessary to complete the work. Payment will also include the cost of premiums for performance and payment bonds specified in the CONTRACT CLAUSES. Payment for this item will be in the proportion of 30 percent demobilization.

d. Item No. 0004, Contract Manpower Reporting Requirements. Provide a price for reporting ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the

Section 00 010 00 - Page 4 following web address: https://ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance. Contractors may direct questions to the help desk at help desk at:

https://ecmra.mil/ to review user manuals and gain an understanding about the data fields that will be included in the reporting structure that is hosted at https://ecmra.mil/.

e. Item No. 0005 Option 1, Operations Apron, Taxiways D and F, including airfield lights, will be paid for at the contract price, complete in place and ready for use, including repairs by replacement the Airfield operations apron pavement, airfield lights, Navigation Aids, airfield electrical distribution system including maintenance holes and ductline systems. Work will include reconstruction of the failed pavement and replacing with new asphalt concrete and Portland cement concrete to restore the airfield to condition requirements of Army Regulation (AR 420-72 and the structural requirements of current and project mission traffic), and all incidentals necessary to complete the work. Airfield operations will continue to function without completing shutting down during construction. No

HAZMAT is identified as part of this repair project. Surface demolition shall be disposed according to local and

DoD requirements.

f. Item No. 0006 Option 2, Hot Cargo Pad Apron, Taxiway A, will be paid for at the contract price, complete in place and ready for use, including repair Bucholz Army Airfield, Hot Spot Apron, Taxiway A including airfield lights, including repairs by replacement the Airfield operations apron pavement, airfield lights, Navigation Aids, airfield electrical distribution system including maintenance holes and ductline systems. Work will include reconstruction of the failed pavement and replacing with new asphalt concrete and Portland cement concrete to restore the airfield to condition requirements of Army Regulation (AR 420-72 and the structural requirements of current and project mission traffic), and all incidentals necessary to complete the work. Airfield operations will continue to function without completing shutting down during construction. No HAZMAT is identified as part of this repair project. Surface demolition shall be disposed according to local and DoD requirements.

Section 00 21 16 – Page 2

PROVISIONS INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018

52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017

52.217-5 Evaluation of Options JUL 1990

52.222-24 Preaward On-Site Equal Opportunity Compliance Evaluation FEB 1999

52.232-13 Notice Of Progress Payments APR 1984

52.236-28 Preparation of Proposals--Construction OCT 1997

252.203-7005 Representation Relating to Compensation of Former DoD Officials NOV 2011

252.215-7008 Only One Offer OCT 2013

252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data

JAN 2018

252.236-7012 Military Construction on Kwajalein Atoll--Evaluation Preference MAR 1998

PROVISIONS INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm-fixed price construction contract resulting from this solicitation.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance

Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

69.1% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract

Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from

Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

http://farsite.hill.af.mil/ http://farsite.hill.af.mil/vfdfara.htm

Section 00 21 16 – Page 3

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract

Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Kwajalein Atoll.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, Honolulu District

Contracting Division, ATTN: Contracting Officer (W9128A19R0009)

Walker Street, Building 252

Fort Shafter, Hawaii 96585-5440

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/ http://farsite.hill.af.mil/vfdfara.htm

Section 00 22 16 – Page 1

Section 00 22 16 – Supplementary Instructions to Proposers

EVALUATION FACTORS

A. PROPOSAL SUBMISSION (Section 00 21 16)

1.0 Proposal Submission Requirements

a. Each volume shall be submitted; one (1) CD for each volume, as well as hard copies; five (5) of technical Volume 1, and three (3) of Pricing Volume 2. Any portion of the proposal that is changed (as a result of negotiations or proposal revisions) should be annotated and dated. Each volume shall be clearly labeled with its title and a copy number (e.g., copy 1 of 5).

b. Each paragraph should be single spaced. Do not use a font size smaller than 10 pitch, an unusual font style such as script, or condensed print. Arial or Times New Roman fonts are required for any submission. Tables and illustrations may use a reduced font size no less than 8-point and may be produced in landscape mode.

c. The following volumes of material shall be submitted:

Volume Title Hard Copies

I Technical (Factors 1 through 4) 5

II Price and Bonding 3

II

Solicitation, Offer and Award Documents, and

Certifications / Representations

1.1 Cost of Preparing Proposals.

The Government will not reimburse any Offeror for any costs incurred in the preparation and submittal of its proposal in response to this solicitation.

1.2 Submittal of Proposals

Proposals may be submitted via U.S. Postal Service, courier service, or personally delivered as follows:

Proposals submitted via U.S. Postal Services shall be mailed to:

Contracting Division (CEPOH-CT), ATTN: Mr. Raymond Greenheck / Ms. Merbby Nicolas

Bldg. 230, Otake Street

Fort Shafter, Hawaii 96858-5440

Proposals submitted via courier service or hand delivered shall be delivered to:

Contracting Division (CEPOH-CT), ATTN: Mr. Raymond Greenheck / Ms. Merbby Nicolas

Bldg. 252, Walker Drive

Fort Shafter, Hawaii 96858-5440

Proposals must be clearly identified on the shipping package with the RFP number.

Proposal received by telegraph, facsimile and/or e-mail will not be accepted.

Section 00 22 16 – Page 2

Proposals received by the Government after the date and time set for receipt of proposals will be handled in accordance with the requirements of Provision “52.215-1, Instructions to Offerors Competitive Acquisition (Jan

2017),” subparagraph (c), found in Section 00 22 16.

1.3 Proposal Format

1.3.1 Format. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be identified with the appropriate page number, centered at the bottom of the page, and the complete company name, date and Request for Proposal (RFP) number shall be identified in the header and/or footer. The terms RFP and solicitation are used interchangeably. All pages margins must be at least one (1) inch wide, and may include headers and footers. Sheet size of the proposal contents shall be 8 ½ inches by 11 inches, unless another paper size is specifically authorized.

The following additional restrictions apply:

1.3.2 File Packaging. Provide read-only PDF file format in searchable text software containing the technical and price volume. Proposals shall be tabbed and labeled in a manner to afford easy identification from a Table of

Contents. Each disc shall be externally labeled with the solicitation number, volume number, date, and the Offeror’s name. If the hard copy proposal differs from the electronic version, the hard copy will govern. If the electronic files are of a size which it must be compressed (zipped), it shall be compressed into one file using WinZip version 6.2 or later. Self-extracting .exe files are not acceptable.

1.3.3 Content Requirement. All information shall be confined to the appropriate file. The technical proposal will be appropriately organized using the tabs specified in the chart below. The proposals shall contain a detailed table of contents. A cover sheet identifying the Offeror (name, address, and point of contact), contract description, and solicitation number shall be provided. The second sheet shall be a Table of Contents. Proprietary information shall be clearly marked.

TAB CONTENTS OF THE TECHNICAL PROPOSAL – Volume 1

A The Proposal Cover Sheet

B Airfield Paving Construction Experience

C Organization and Management Plan

D Technical Approach

E Past Performance

1.3.4 Specific Instructions for the Technical Proposal (Volume 1)

Proposal shall contain the entire proposal in .pdf format using Adobe Acrobat software to print to a .pdf file; do

NOT scan the document(s) into a .pdf file. The text portion of the Volume I proposal shall be contained as a single

.pdf file in searchable text. Sections of the proposal shall be bookmarked (linked to the index) in logical order.

Offerors shall submit all technical proposal documentation in Adobe PDF format on:

Five (5) hard copies each for each proposal (1 original and 4 copies); and

One (1) CD ROM as one PDF file titled:

W9128A-19-R-0009_COMPANY NAME_TECHNICAL PROPOSAL

1.4 Specific Instructions for the Price Proposal (Volume 2)

1.4.1 Format and Contents of the Price Proposal and List of Tabs. The Price Proposal shall be tabbed and labeled in a manner to afford easy identification from a Table of Contents, as indicated in the following chart below.

Section 00 22 16 – Page 3

TAB CONTENTS OF THE PRICE PROPOSAL – Volume 2

1 Coversheet

2 The SF1442 and Acknowledgement of Amendments

3 Section 00 10 00, Proposal Schedule

4 Bonding Capability

Copy of Representations and Certifications completed electronically via the System for

Award Management (SAM.gov).

6 JV Agreement or Articles of Organization for LLC, if applicable.

Volume 2, Tab 2: The SF 1442, Solicitation, Offer, and Award is to be completed by all Offerors and duly executed with an original signature by an official authorized to bind the company in accordance with FAR 4.102. All amendments must be acknowledged by all Offerors in accordance with the instructions on the Standard Form 30, Amendment of Solicitation.

Volume 2, Tab 3: The Offeror shall provide a completed Section 00 10 00, Proposal Schedule in read-only PDF format. The PDF file may not be password protected.

Offerors shall submit the price proposal in a second envelope that is clearly marked, “PRICE PROPOSAL, VOLUME 2, RFP NO. W9128A-19-R-0009.”

Offerors shall submit the price proposal documentation on:

Three (3) hard copies for each proposal (1 original and 2 copies); and

One (1) CD ROM as one PDF file titled:

W9128A-19-R-0009_COMPANY NAME_PRICE PROPOSAL

Volume 2, Tab 4: Submit an original letter from the Offeror’s suret(ies) stating that the Offeror has sufficient bonding capacity for performance and payment bonds equal to or greater than the proposed Total Base Schedule

Plus Options, and the Surety’s assurance that it intends to provide such bonds if the Offeror is awarded the contract.

Volume 2, Tab 5: All Offerors must have electronically completed the annual Representations and Certifications on the System for Award Management (SAM) Website at www.sam.gov or respond with the completed

Representations / Certifications found in the solicitation. The Offerors are responsible for ensuring that these on-line

Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that it is kept current, accurate and complete. Additionally, the Offeror must also complete and return the

“Representations, Certifications, and Other Statements of Offerors” included in the solicitation. If the Offeror is a

Joint Venture (JV) and it does not have the SAM Representations and Certifications as a JV, all participants of the

JV must separately complete the SAM Representations and Certification.

Volume 2, Tab 6: Joint Venture Agreement (if applicable): If the Offeror is a Joint Venture (JV), include a copy of the finalized / approved JV Agreement. JV Agreements must clearly indicate the percentages of the JV participants, in particular the percent of the controlling party, and a clear delineation of responsibilities and authorities between the JV parties. If the Offeror is a Limited Liability Company, include a copy of the Articles of

Organization / Incorporation.

In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract.

Section 00 22 16 – Page 4

Note: If the Offeror is not required to submit any information under a listed Tab (such as a JV Agreement) in accordance with the instructions below, the tab can be omitted.

Solicitations, Offer and Award Documents and Certifications/Representations shall not be addressed separately from that submitted in VOLUME 2.

1.5 Page Limitations. The following page limitations are established for each Factor:

Factor 1 – Airfield Paving Construction Experience

Factor 2 – Organization and Management Plan. A total of five (5) single-sided pages. Of the five (5) pages, one (1) single-sided no larger than 11”x17” shall be for the Organizational Chart in accordance with Volume 1, Tab C, paragraph 2.1.

Factor 3 – Technical Approach. A total of five (5) single-sided pages.

Factor 4 – Past Performance – No page limitation

Factor 5 – Price – No page limitation

For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page;

information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, fold-out pages (11” x 14” or 11” x 17”) will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.

B. BASIS FOR AWARD

The Government intends to award a single contract to the responsible Offeror whose proposal conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, considering the evaluation factors described herein. The non-price technical factors when combined, are significantly more important than price. Offerors will be cautioned that the award may not necessarily be made to the lowest price offered. The

Government reserves the right to accept other than the lowest priced Offeror or to reject all Offerors. To receive consideration for award, an Offeror must receive a rating of no less than “Acceptable” for each of the Technical factors.

If awarded the contract, the Offeror shall construct the project in accordance with the plans and specifications.

1.0 Contract Award

The evaluation will be conducted in accordance with the, Federal Acquisition Regulation (FAR) 15.3, Department of Defense Federal Acquisition Regulation Supplement (DFARS) 215.3, Army Federal Acquisition Regulation

Supplement (AFARS) 5225.3, Department of Defense Source Selection Procedures, Army Source Selection

Supplement (AS3) to the Department of Defense Source Selection Procedures, and this solicitation. Award will be made to the Offeror who is deemed responsible in accordance with Federal Acquisition Regulation (FAR) Part 9, conforms to the solicitation requirements (such as terms and conditions, representations and certifications).

Failure to comply with the terms and conditions of the solicitation may result in the Offeror being considered non awardable.

1.1. Award without Discussions

The Government intends to award without discussions IAW FAR 52.215-1; however, IAW FAR Subpart 15.306, should discussions become necessary, the Government reserves the right to conduct discussions. Therefore, Offerors are advised to submit proposals that are fully and clearly acceptable without additional information. If award will be made without conducting discussions, the Offeror may only be given the opportunity to clarify certain aspects of proposals (e.g., the relevance of an Offeror’s past performance information and adverse past performance information to which the Offeror has not previously had an opportunity to respond) or to resolve minor or clerical errors.

1.2 Competitive Range/Discussions

The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with Offerors in the competitive range; and to award the contract to the Offeror

Section 00 22 16 – Page 5 whose proposal is determined to represent the best value to the Government, price and other factors considered.

If discussions are deemed necessary, they will be held only with those Offerors determined to be in the competitive range. The Contracting Officer may establish a competitive range comprised of the most highly rated proposals based on the rating of each evaluation factor against the evaluation criteria. The competitive range may be further reduced for purposes of efficiency pursuant to FAR 15.306(c)(2). If the Government elects to open discussions, it has sole discretion as to whether an Offeror is in the competitive range, and may include proposals rated

“Unacceptable” under the Technical factors. Offerors whose proposals are not included in the competitive range will be notified as soon as practicable.

Discussions will include issuance of evaluation notices with its significant weaknesses, deficiencies, adverse past performance, and any other aspects of the Offeror’s proposal that could enhance materially the Offeror’s proposal for award. During discussions, the Government may ask the Offeror to further explain and / or to answer questions about its proposal. An Offeror initially included in the competitive range may be eliminated from consideration for award during discussions. At the conclusion of discussions, each Offeror still within the competitive range shall be given an opportunity to submit a Final Proposal Revision (FPR) for final evaluation and selection.

C. FACTORS TO BE EVALUATED

The following evaluation factors will be used to evaluate each proposal:

VOLUME 1 – TECHNICAL PROPOSAL

TAB A The Proposal Cover Sheet

Factor LOCATION DESCRIPTION RELATIVE IMPORTANCE

FACTOR 1 Vol 1 Tab B Airfield Paving

Construction Experience

Most Important Technical Factor

(Equally important to Factor 4)

FACTOR 2 Vol 1 Tab C Management Plan /

Organization

Equally important to Factor 3, less important than Factor 1.

FACTOR 3 Vol 1 Tab D Technical Approach Equally important to Factor 2, less important than Factor 1.

FACTOR 4 Vol 1 Tab E Past Performance More Important than Factors 2 and

3 (Equally important to Factor 1)

Factor 5, Price, is the least important factor. The resulting award will be a Firm Fixed Price contract. Price reasonableness will be utilized in the evaluation of the Firm-Fixed Price effort.

D. EVALUATION APPROACH

The Offeror’s Volume 1 and Volume 2 proposal will be evaluated as specified below:

1.0 VOLUME 1, TAB B – FACTOR 1 - AIRFIELD PAVING CONSTRUCTION EXPERIENCE

1.1 Submission Requirements:

1.2 Factor 1 Overview.

This factor evaluates the Offeror’s proposed Airfield Paving Construction Experience for the base contract and all options. The Offeror (or prime contractor) and its team shall demonstrate experience on contracts with similar features, magnitudes, and complexities to this RFP. The Offeror is expected to explain how its experience is similar to airfield paving construction as described in this RFP (including but not limited to Specification Section 32 13 11).

The Offeror shall explain how its experience is similar to the management and coordination complexity (such as multiple contractors, stakeholders, joint occupancies and a Temporary Workforce Camp) expected for this RFP.

Section 00 22 16 – Page 6

1.2.1 The Offeror shall submit a maximum of five (5) contracts.

A “contract” is defined as a single contract or a single task order performed under a MATOC (Multiple Award Task

Order Contract)/SATOC (Single Award Task Order Contract)/IDIQ (Indefinite Delivery Indefinite Quantity

Contract).

Data presented shall include construction contracts relevant to this requirement as provided in the solicitation’s technical narrative which the Offeror’s team has completed, or which are currently under construction and are substantially complete. Relevant construction experience will be limited to performance of contracts similar in size, scope, and complexity to that outlined in the solicitation. The Offeror shall submit a maximum of five (5) contracts. If more than five (5) contracts are submitted, only the first five (5) contracts will be evaluated. The

Offeror shall submit a completed Attachment A “Experience Information” form for each contract. All blocks must be filled in and all data should be accurate, current and complete. Each contract shall be described in two pages or less. Any pages that exceed this limitation will not be considered. The information in Attachment A includes, but is not limited to, the following contract information:

a. Contract title, contract number, and location.

b. Contract type (for example, Indefinite-Delivery, Indefinite-Quantity task order; Design/Build;

Design-Bid-Build; Firm Fixed-Price; Cost Plus, etc.)

c. Total dollar award amount, and the total dollar amount at completion of the contract.

d. Start and completion dates (month/year) or percentage until complete to include actual completion date

(month/year).

e. Role of Offeror, provide a detailed description (address type of work self-performed, to include design, and percentage and type of self-performed work, as applicable for each team member, and type of work sub-contracted out)

f. Brief description of contract and how it relates to this solicitation.

g. Customer primary Point of Contact (POC) and alternate POC (name, relationship to the contract [Administering Contracting Officer / Contracting Officer Representative, etc.], agency/firm affiliation, city, state, current phone number, and e-mail address)

h. Awards or recognition received, where applicable

Note: If the Offeror is a Joint Venture (JV) and the JV does not have experience working as a JV, the partners of the

JV may submit experience on behalf of the Offeror. All references herein to “the Offeror” include all proposed joint venture partners. Submitted contracts by members of a joint-venture or from the joint-venture itself will be considered and evaluated as long as the member or joint-venture itself was the prime contractor. Information provided from potential sub-contractors (not included in the joint venture) will not be considered or evaluated.

The JV shall submit no more than five (5) contracts, but each respective JV partner must submit at least one (1) contract under this Factor.

1.2.2 Evaluation Criteria:

The Government will evaluate the extent of relevant experience of the prime contractor. If an Offeror submits a proposal as a joint venture, the Government will evaluate the experience of its proposed JV team and the roles each member of the JV team will have in performing this contract. The extent of relevant experience will be determined based on the similarity of the submitted contracts to the size, scope, and complexity of the construction required by the solicitation. For the purposes of this solicitation, a recent contract is defined as at least 80% complete or turned over within the past seven (7) years preceding the issuance date of this RFP.

When assessing an Offeror’s relevant experience, the Government intends to give greater weight to each of the following:

a. Proposals that include a higher number of relevant contracts, up to a maximum of five.

b. Construction contracts for airfield paving with asphalt paving.

c. Construction contracts for airfield paving with Portland Cement concrete.

d. New / renovation construction contracts for airfield paving with an award amount of $50,000,000 or more.

Section 00 22 16 – Page 7

e. Construction contracts for airfield paving where airfield operations continue within and/or adjacent to the project site.

f. New / renovation construction contracts demonstrating experience with underground electrical and plumbing.

g. New / renovation construction contracts with a temporary workforce camp.

See paragraph 6.2, Combined Technical / Risk Rating, Table 1, for the evaluation rating system for Factor 1, Airfield Paving Construction Experience.

2.0 VOLUME 1, TAB C – FACTOR 2 – MANAGEMENT PLAN / ORGANIZATION

2.1 Submission Requirements:

Organization. Describe what firms will be included to include its roles and responsibilities and any contractual arrangements the Offeror has established. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. Include a simple organizational chart, illustrating the organization, including the proposed quality control group(s), and risk management team(s). Identify the firms selected for the project, if work is not to be self-performed. The Offeror shall describe the proposed management structure of the team, and how the construction process will be managed.

1.2.3 Evaluation Criteria:

The Government will evaluate the clarity and strength of the overall organization and how well it is organized, structured, and staffed to execute the entire scope of work. If applicable, joint venture participants’ contribution to the organization shall be commensurate with its skills and background.

See paragraph 6.2, Combined Technical / Risk Rating, Table 1, for the evaluation rating system for Factor 2.

3.0 VOLUME 1, TAB D – FACTOR 3 – TECHNICAL APPROACH

3.1 Submission Requirements:

3.1.1 Technical Approach. Offerors shall provide a narrative of how it will manage and construct the project.

The Offeror shall describe its ability to maintain operability using reliable and proven methods in consideration of the following challenges:

Construction of an airfield, during ongoing flight operations.

Ongoing construction of an airfield and how the Offeror will provide access and protection to the aircraft, aircraft personnel, and aircraft passengers during construction.

Risk management framework interrelationship between ongoing flight operations.

Coordination with the Government, and other stakeholders.

Scheduling around adverse / seasonal weather conditions.

The Offeror shall relate the project scope features to the construction process considering the impact of environmental considerations, work sequencing, work by others, and resource management. The Offeror shall describe its understanding of construction in highly corrosive climates, construction in isolated areas, working with other prime contractors on the same work site and/or in the same facility during on-going construction, while achieving beneficial occupancy date milestone.

The Offeror shall describe its understanding of airfield paving construction and explain how it will execute the construction of the project to include mobilization and demobilization of equipment, and the storage and management of supplies and materials.

Offeror shall describe reliable/proven methods for construction of an airfield at a confined area adjacent to on-going construction by another prime contractor.

Section 00 22 16 – Page 8

3.1.2 Self-Performed Work. Generally describe the types of work the Offeror will self-perform to comply with the requirements in clause 52.236-1, Performance of Work by the Contactor, for self-performed work.

3.2 Evaluation Criteria:

3.2.1 Technical Approach. The Government will evaluate the strengths, weaknesses, and any deficiencies in the technical approach to which the Offeror is expected to be able to successfully complete the requirements within the required schedule based upon proven methods and techniques. The Government will evaluate the Offeror’s understanding of the requirements described in the technical specification of the solicitation. The Government will evaluate the Offeror’s proposal to determine if the proposed approach is workable and achievable. The Government intends to assess each Offeror’s plan to determine how well the Offeror understands the project. The Government will evaluate the Offeror’s understanding of construction in highly corrosive climates, construction in isolated areas, working with other prime contractors on the same work site and/or same facility under construction to achieve the beneficial occupancy date milestone. Additional consideration will be given to a detailed approach that identifies specific elements that present the greatest risk to project success and describe the approach to mitigate the risks.

See paragraph 6.4, Combined Technical / Risk Rating, Table 1, for the evaluation rating system for Factor 3.

3.2.2 Self-Performed Work. The Government will evaluate the Offeror’s proposal to ensure that self-performed work complies with the requirements of Clause 52.236-1 for self-performed work.

4.0 VOLUME 1, TAB E – FACTOR 4 – PAST PERFORMANCE

4.1 Submission Requirements:

4.1.1 Past performance refers to the quality of recent project experience from the owner's perspective. For each project submitted under Factor 1, the Offeror shall provide past performance information. For Federal projects, the

Offeror may submit finalized CCASS or CPARS reports. If a finalized CCASS or CPARS report is not available, the Past Performance Questionnaire (PPQ) included in the RFP is provided for the Offeror or its team members to submit to the client for each project. The Offeror shall provide customer reference name(s), company affiliation and current contact information (phone number and email address) on the PPQ form, for each experience submitted for

Factor 1. Previously completed PPQ’s may be submitted; however, ensure current phone numbers and email addresses are provided for the client point of contact. The completed Past Performance Questionnaires should be submitted with your proposal and may be duplicated for submission on future solicitations. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the Offeror should complete and submit with the proposal the first 2 pages of the PPQ (Attachment 1), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to Government via e-mail to W9128A-19-R-0009@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the

Government from utilizing previously submitted PPQ information in the past performance evaluation.

4.1.2 Projects for which past performance information is submitted shall be well underway (fully designed and at least 80% construction progress completed) or completed and turned over no more than seven (7)…