This document is a Contractor's Operations and Requirements section (Section 01 10 10.00 25) for the MSH Sediment Retention Structure Crest Raise project. The section outlines comprehensive operational requirements for the contractor, including specific guidelines for in-water work periods (July 1 to October 4), time-lapse camera documentation, equipment usage, utilities, and work area management. Key contractor obligations include providing a temporary government office with detailed specifications, submitting detailed equipment and planning documentation, establishing weekly coordination meetings, and protecting existing facilities and project infrastructure.

The document specifies strict requirements for contractor operations, such as protecting existing utilities, maintaining daily cleanup, and managing employee access and parking. The contractor must provide non-potable construction water from a sump upstream of the dam, submit comprehensive equipment lists, and adhere to specific transportation and equipment movement protocols. Additional requirements include installing a project identification sign, providing VHF radios and wireless signal boosters for government use, and ensuring all work areas are neat, protected, and restored to original conditions upon project completion.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MSH SEDIMENT RETENTION STRUCTURE CREST RAISE

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 10.00 25

CONTRACTOR'S OPERATIONS AND REQUIREMENTS

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.2 REFERENCES

1.3 SUBMITTALS

1.4 IN-WATER WORK

1.4.1 In-Water Work Periods

1.4.2 In-Water Work Activities

1.5 TIME LAPSE CAMERA

1.6 INCLEMENT WEATHER CONSTRUCTION

1.7 NOTIFICATION OF EQUIPMENT OUTAGE

1.8 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

1.9 WEEKLY COORDINATION MEETINGS

1.10 CONTRACTOR EMPLOYEES

1.11 ACCESS AGREEMENTS AND WORK AREAS

1.11.1 Access Agreements

1.11.2 Work Areas

1.11.3 Employee Access and Parking

1.11.4 Public Access

1.12 CONTRACTOR SUPPLIED EQUIPMENT AND ACCOMMODATIONS

1.13 CONSTRUCTION PROJECT IDENTIFICATION SIGN

1.14 UTILITIES

1.14.1 Sanitary Facilities

1.14.2 Electrical Power

1.14.2.1 General

1.14.2.2 Temporary Electrical Wiring

1.14.3 Water

1.15 CONTRACTOR'S EQUIPMENT

1.15.1 Contractor's Planned Equipment Methods

1.15.2 Plant and Equipment List

1.15.3 Movement of Equipment by the Contractor

1.16 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS

1.17 USE OF EXPLOSIVES

1.18 DAILY CLEANUP AND DISPOSAL

1.19 DISPOSAL OF EQUIPMENT AND MISCELLANEOUS MATERIALS

1.20 PROTECTION OF MATERIAL AND WORK

1.21 PROTECTION OF EXISTING UTILITIES

1.22 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.23 RESTORATION OF PROJECT ROADS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 10 10.00 25 Page 1 Amendment 0006

SECTION 01 10 10.00 25

CONTRACTOR'S OPERATIONS AND REQUIREMENTS

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

This Section covers general requirements applicable to specific Contractor's operations and equipment.

1.2 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

EP 310-1-6A (2006; 2019 Change 2) Project Operation -- Sign Standards Manual, VOL 1

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO LRFD (8th Edition; 2017) Bridge Design Specifications

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Access Agreements and Work Areas; G

Temporary Electrical Wiring Plan; G

Contractor's Planned Equipment Methods; G

Plant and Equipment List; G

Loading Diagram; G

Protection of Material and Work; G

Contractor Supplied Equipment And Accommodations; G

Notification Of Equipment Outage

Access Road Photographs and Notes; G

SECTION 01 10 10.00 25 Page 2 Amendment 0006

1.4 IN-WATER WORK

1.4.1 In-Water Work Periods

The Government has established periods, described as "in-water work periods," coinciding with the annual cycles of fish migration and related allowed maintenance periods. In general, this is a work period that allows for work in the water, on the water, and adjacent to the water where the work might affect fish passage (usually a 50 foot rule from the work site to the water). The in-water work (IWW) period established for this Contract is: July 1 to October 4. All in-water work must be completed during the IWW period and the dates indicated.

1.4.2 In-Water Work Activities

For purposes of this Contract, work items that must be restricted to the IWW period, along with further work restrictions, are described below:

The in-water work window applies to work below the ordinary high water mark (OHWM). Normal construction activities are permitted within 50 feet of the OHWM with the exception of the placement of staging areas and storage of fuel or other chemicals that would adversely affect the water.

Comply with the Washington Department of Ecology (DOE) Water Quality Certificate, see Attachment A5 - USACE Nationwide Permit and WADOE Determination.

1.5 TIME LAPSE CAMERA

Provide a time-lapse video and selection of still images documenting the construction process on the subject Contract. Document all work performed in and around the Sediment Retention Structure by coordinating with the on-site GQAR to position one camera on USACE property. The camera must be operational 10 days prior to commencing site operations. Pictures must be taken every 15 minutes and uploaded to an internet based site daily.

Government personnel must have access to the pictures on the internet based site. Use the resulting images to create at least one video approximately 20 minutes in length. Transmit the finished video through a Government furnished online data portal designated by the Contracting Officer (CO) in Windows Media File format. Coordinate with the CO and Project Engineer for an example of the desired finished videos. Provide a representative selection of approximately 100 print-quality (8 by 10 inch, 300 pixels per inch (PPI) .jpg or .tif format) digital images spanning the Contract work period. The Government will own the rights to all digital files used in the creation of the video(s).

1.6 INCLEMENT WEATHER CONSTRUCTION

The Contractor's schedule must reflect adverse weather days in all weather dependent activities as defined in FAR 52.236-4, PHYSICAL DATA. Protect work areas from inclement weather, wind damage, and precipitation so that no delay in the prosecution of critical work items, or damage to Government property occurs. No time extensions will be authorized for materials, work in place, or equipment damaged due to negligence during periods of inclement weather.

1.7 NOTIFICATION OF EQUIPMENT OUTAGE

Where an equipment outage is required to accomplish the work outlined in this Contract, notify the Government 14 days in advance. This will allow

SECTION 01 10 10.00 25 Page 3 Amendment 0006 the Government to de-energize the equipment for Contractor access.

1.8 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor will coordinate as necessary.

1.9 WEEKLY COORDINATION MEETINGS

Weekly coordination meetings must be held between the Contractor and the Government. This meeting will be used to discuss Contractor's safety, Quality Control Program, joint risk management, submittals, deficiencies, Contract administration, schedule, actual progress in the last week, and work planned in the upcoming two weeks. Any work requiring Project support or potential impacts to Project operations or maintenance must be noted.

During the Preconstruction Meeting, the Government will determine responsibility of running this meeting. If the Government elects to run the coordination meeting, the Contractor must provide a two week look ahead, with the previous week as-builts, 48 hours before each weekly meeting to the Government representative. The responsible party must prepare and distribute, by e-mail, the coordination meeting agenda with a two week look ahead no later than 24 hours before each meeting. A meeting time and place will be mutually agreed upon for the same time each week.

Distribute weekly coordination meeting minutes no later than the close of business the next business day.

1.10 CONTRACTOR EMPLOYEES

Ensure that all employees are capable of demonstrating adequate knowledge of tools, supplies, equipment, and techniques necessary to competently perform the work. All personnel employed by the Contractor must be fully qualified in their respective fields to render the services necessary. The Government may require the Contractor to discontinue using any employee in the performance of the work specified in this Contract determined by the Government to be unsatisfactory. Contractor employees will not be permitted to bring guests, family members, or non-employees to the job site at any time.

1.11 ACCESS AGREEMENTS AND WORK AREAS

1.11.1 Access Agreements

a. Submit access procedures to and from the work site after the Contractor, the CO, and the Project's Representative have coordinated and determined the most advantageous access to, and staging of, the Contractor's assets deployed to the work site.

b. The right-of-way for the work (or delivery site) and access thereto will be furnished as stated in this Paragraph subject to mutual agreement between the Contractor and the Government concerning the specific route the Contractor is to use. Such mutual agreement must be reached prior to initiation, construction, or delivery.

c. The existing access roadway and any associated access roads on the Project, must not be closed as a result of construction or delivery activities associated with this Contract unless previously coordinated and approved by the Government. Traffic delays will only be permitted in accordance with the provisions of this Section.

SECTION 01 10 10.00 25 Page 4 Amendment 0006

d. When necessary to operate on or to cross existing highways or roads, all necessary permits must be obtained from the appropriate private or public authority.

e. In accordance with FAR 52.236-13 Alt I, ACCIDENT PREVENTION - ALTERNATE I, and EM 385-1-1, flaggers, signs, lights, or other safeguards must be provided to safely control and direct the flow of traffic when necessary for equipment to operate on or to cross access roads, arterial roads, or highways.

f. Spillage on Project roads and state or county roads will not be permitted, and the spillage must be immediately cleaned up at the expense of the Contractor.

g. No cleated or crawler-type equipment can be operated on paved surfaces.

h. Damage to all roads caused by the Contractor's operations must be repaired to pre-existing conditions at the expense of the Contractor.

i. Photograph the existing condition of all staging areas prior to mobilization and submit all photographs in the Access Agreements submittal. Failure to properly document existing conditions will result in a Government determination of necessary repairs.

1.11.2 Work Areas

a. Drawings showing the layout of the area proposed for use must be submitted for review and approval and comply with FAR 52.236-10 OPERATIONS AND STORAGE AREAS. The drawing(s) must show the location of the principal components: offices, access roads, parking, storage facilities and disposal areas, which the Contractor proposes to construct within the designated limits.

b. Only Contractor and subcontractor parts trailers and lunch trailers may be allowed in the Contractor work areas and these must be subject to CO and Project approval. All Contractor and subcontractor trailers are required to be adequately and physically anchored to prevent overturning due to high winds.

c. Should additional working space or lands within the Government right-of-way be required for material yards, job offices, or other purposes obtain prior Government approval in writing. When directed at any time during the progress of the work when space is needed within the right-of-way for other purposes, any part of the grounds that have been in use must be promptly vacated and cleaned up. However, it is not the intent to require the Contractor's plant or material to be removed from an area while such plant, material, or area is still being actively used.

1.11.3 Employee Access and Parking

Contractor's employee private vehicle parking areas must be restricted to the area as agreed upon before construction or delivery. All Contractor vehicles used for prosecuting the work must have a Contractor sign or other permanent identification and must carry the required insurance. Private vehicles not owned by the Prime Contractor or subcontractors must not be used for prosecuting the work. Private vehicles of the Contractor and its

SECTION 01 10 10.00 25 Page 5 Amendment 0006 employees must enter and leave the project as directed. Keep the parking areas free of litter and debris. An adequate number and size of trash receptacles must be placed in the parking areas and emptied, as necessary to avoid overflowing. Trash receptacles must be adequately secured to provide protection from the wind and animals.

1.11.4 Public Access

The public must not have permanent access to the Contractor work areas, including the top of the dam. Barricades or temporary fencing must be provided to prevent the public from entering the Contractor's work areas as applicable. The nature trail and associated public parking area must remain open to the public. Erect a sign notifying the public "The nature trail is open but access to the dam is restricted due to construction."

1.12 CONTRACTOR SUPPLIED EQUIPMENT AND ACCOMMODATIONS

a. All Contractor supplied equipment will be returned on completion of work under this Contract.

b. The entire cost to the Contractor for furnishing, equipping, insuring, and maintaining the foregoing accommodations and equipment must be included in the Contract price for Mobilization and Demobilization.

c. Provide the Government Project Engineer with a temporary office not less than 400 square feet in floor area. The office is to be for the exclusive use of the Government and physically separated from Contractor facilities. Locate the office where directed within the Contract designated staging area or alternate location if access to the Contract designated staging area is unavailable. If an alternate location is utilized the office must be relocated to the Contract designated staging area when the staging area is developed. The office must be fully functional and available for Government occupancy at all times site work is underway. All furniture must be in good, working condition and acceptable to the CO. At completion of the work, the office will remain the property of the Contractor and must be removed from the site. Provide the following in the Government Project Engineer office:

(1) Two covered stair accesses with exterior lighting, and a coat rack with eight or more hooks hung immediately inside the primary entrance. Include a boot brush cleaner or similar outside the primary entrance.

(2) Matching dead bolts and locks, keyed alike, on all doors with twenty keys provided to the COR.

(3) A minimum of one hard wall office no smaller than 10' by 10'.

The office must contain a minimum of one 2' by 3' or larger window and have a locking door.

(4) Uninterrupted electrical service provided during all working hours.

(5) Thermostatically controlled heating and air conditioning unit capable of maintaining 72 degrees F during active work seasons.

(6) One color copier/printer and associated supplies. Anticipate

SECTION 01 10 10.00 25 Page 6 Amendment 0006 usage equivalent to 50 copies or prints per week during active work.

(7) Wireless internet service. Provided internet speed exclusively for Government use must be a minimum of 15 Mbps download, 3 Mbps upload, and latency of less than 650 milliseconds as measured by the Government's computer. Internet service must be maintained at all times during active site work.

(8) Three work stations. Each work station must include:

(a) One Double-pedestal desk 2'6" by 5'0" or COR approved substitute.

(b) One Desk chair approximately 37 to 44 inches high by 25 inches wide by 26 inches deep, which can revolve a full 360 degrees, has adjustable height and back tilt-tension mechanism, lumbar support, adjustable armrests, and is upholstered with cloth for heavy use. Desk chairs must have five equally spaced casters intended for the surface used.

(c) Two 24 inch monitors with 1920 X 1080 or better resolution.

Provide appropriate cables to connect with and provide a USB-C docking station, wireless keyboard, and wireless mouse, including replacement batteries.

(d) Power receptacle capable of powering all Contractor furnished equipment with a minimum of two additional plugs.

(9) Two wall-mounted white boards, at least 3' by 4', with six dry erase markers, white board cleaning solution and one eraser each.

Replace markers upon exhaustion.

(10) One cork board, at least 3' by 4', with 100 removable thumbtacks.

(11) Two folding tables approximately 30" by 6'.

(12) Eight folding chairs.

(13) Four 2' by 3' or larger windows with operable blinds.

Windows must open and include tight fitting but removable screens.

(14) Bottled drinking water and drinkware with cooling/heating support frame. Anticipate an average of 15 gallons of water to be consumed by Government employees on a weekly basis.

(15) Provide four trash cans, trash can liners, broom, dust pan, mop and bucket. Make a vacuum cleaner available upon request.

Provide trash disposal.

(16) One minimum four cubic feet capacity refrigerator and one microwave oven.

(17) Four double-sided copies of half-size Contract drawings, spiral bound with laminated sheets.

(18) Five individual full-size drawings from the Contract package.

Specific sheets will be selected by the CO for printing.

SECTION 01 10 10.00 25 Page 7 Amendment 0006

(19) Sanitary facilities for Government employees within 200 feet of the office trailer to the satisfaction of the COR. Include a handwashing station with water.

d. Provide the following equipment to the Government:

(1) Four VHF radios, four chargers, and four spare batteries (with separate charger if appropriate). Radios must operate on the same frequency the Contractor utilizes. Provide a separate subchannel for Government use only. Radios must have suitable range to establish reliable contact across the project work area.

(2) One signal booster for wireless service. Booster must be compatible with mobile phone carriers that advertise coverage in the vicinity of the worksite.

1.13 CONSTRUCTION PROJECT IDENTIFICATION SIGN

Fabricate and install one construction project identification sign in accordance with EP 310-1-6A, Attachment A3, within three days of beginning site work. The sign must be prepared and installed within three days of beginning site work. The sign must have the following information:

a. Group 1: "Design and Construction Supervised by;".

b. Group 2: "Portland District".

c. Group 2a: leave blank.

d. Group 3: "Sediment Retention Structure Spillway Raise".

e. Group 4: "Mt. St. Helens".

1.14 UTILITIES

Provide utilities required for the performance of work under this Contract except water as described below.

1.14.1 Sanitary Facilities

Use of the Project restroom by Contractor personnel will not be permitted.

Provide portable, temporary sanitary facilities in accordance with

EM 385-1-1.

1.14.2 Electrical Power

1.14.2.1 General

Government-furnished or public utility electrical power is not available for the Contractor's use.

1.14.2.2 Temporary Electrical Wiring

Submit a Temporary Electrical Wiring Plan for temporary electrical wiring.

Install all temporary electrical wiring in accordance with EM 385-1-1 and as approved. All temporary electrical wiring must be removed prior to completion of the Contract. Include load calculations to ensure conduit capacity is not exceeded.

SECTION 01 10 10.00 25 Page 8 Amendment 0006

1.14.3 Water

Non-potable construction water must be available from a Contractor furnished sump upstream of the dam. No charge will be made for the water.

Contractor must account for the volcanic sediments and their abrasive effect on water pumps.

1.15 CONTRACTOR'S EQUIPMENT

1.15.1 Contractor's Planned Equipment Methods

Submit proposed methods of transportation and operation of cranes and other heavy equipment for approval prior to commencement of those operations.

Submittals must include the type, size, loadings of equipment, placement of outriggers, and the proposed transportation routes and work areas to be used on the project. Operation of heavy equipment adjacent to existing structures must be avoided when possible. Testing requirements and operation of cranes and other heavy equipment must be in accordance with EM 385-1-1. All cranes, rigging, lifts, operators, vehicles, and other necessary means to move equipment or items must be Contractor-furnished as required to pursue and complete the work and must comply with EM 385-1-1.

1.15.2 Plant and Equipment List

Within seven days prior to commencing site operations, provide a complete list of all plant and equipment to be used on the job site, exclusive of shop equipment. Throughout the life of the Contract, submit an up-to-date plant and equipment list with each progress payment request. Include rented equipment as well as lease purchase or sale leaseback equipment on the lists. Initial list and the revised monthly lists must indicate dates equipment is assigned to or removed from the project; deadline dates for repairs and returned for use; dates of the most recent and planned inspections; and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.

1.15.3 Movement of Equipment by the Contractor

a. Unless otherwise noted, any vehicle crossing a project bridge is limited to AASHTO LRFD, HL-93 vehicle and load requirements. Submit a loading diagram for approval showing wheel loads, wheel spacing, and travel speed a minimum of 30 days prior to operating any equipment or vehicles whose loading conditions are in excess of a HL-93 vehicle.

Prior coordination and approval for such loads must be obtained before proceeding. No exclusion trucks, multi-axle specialized hauling vehicles (SHV) or mobile cranes will be allowed on a bridge deck without prior review and approval. At a minimum, the loading diagram must include but not be limited to the following information:

(1) A typical section and plan view of the bridge, the position of the wheel loads and wheel spacing of the truck or crane.

(2) The GVW of the vehicle and all axle weights.

(3) For cranes, the location and weight of axles before and after counter weights are installed, all outrigger loads, required crane boom length, weight and location of center of gravity. This

SECTION 01 10 10.00 25 Page 9 Amendment 0006 should also include the effects of guy lines, upper spreader and jib mast. If using a jib, show the length, weight, and location of the center of gravity.

b. Any SHV's authorized to drive on the bridge deck must have all lift axles lowered and fully engaged while the vehicle has any load. For cranes, all specialized boom trailers must be engaged until a final set up with the outriggers are made and approved.

1.16 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS

Inform the CO immediately upon finding any damaged equipment or other abnormal conditions involving additional work in which the Contractor believes it has no responsibility. The failure or abnormality must not be disturbed until witnessed by the CO. Prior to proceeding further with work, the Contractor and the Government must agree in writing as to the responsibility for the damage or abnormality. Any damage or abnormal conditions not reported as specified above must also be corrected.

1.17 USE OF EXPLOSIVES

Use of explosives will not be permitted.

1.18 DAILY CLEANUP AND DISPOSAL

Keep all work areas reasonably neat on a daily basis. Collect, remove, and dispose of all debris resulting from the work, such as waste metalwork, packing cases, scrap lumber, and other debris off-site at least once per week. Do not use the Government's trash cans, dump boxes, and other containers. Do not dispose of liquid waste in Project drains. All costs of removing debris must be incidental to the work, and therefore, no separate payment will be made.

1.19 DISPOSAL OF EQUIPMENT AND MISCELLANEOUS MATERIALS

Title to all materials and equipment to be disposed of, excepting materials salvaged for the Government, will be vested in the Contractor when beginning disassembly work or when such materials and equipment are designated as scrap. The Government will not be responsible for the condition, loss, or damage to such property after title transfer. The Contractor may retain these items in usable form and take possession of them providing that there is no subsequent cost or inconvenience to the Government. The Government does not guarantee that these items are complete or in working order and the Contractor must assume responsibility for any damages caused by their use immediately upon taking possession of them.

1.20 PROTECTION OF MATERIAL AND WORK

All materials, supplies, tools, equipment and Government property (including all tools, equipment, and special devices supplied by the Contractor and to be turned over to the Government at the end of the Contract) must at all times be protected and preserved in an approved manner. Existing instrumentation and a toe drain system needs to be protected during construction. If material, equipment, supplies, and work performed are not adequately protected, such property may be protected by the Government and the cost thereof will be charged to the Contractor or deducted from any payment due.

SECTION 01 10 10.00 25 Page 10 Amendment 0006

1.21 PROTECTION OF EXISTING UTILITIES

Protect existing utilities in accordance with FAR 52.236-9, PROTECTION OF

EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.

Repairs must be made immediately and at Contractor's expense.

1.22 PROTECTION AND RESTORATION OF EXISTING FACILITIES

Protect all existing facilities whether or not shown on the drawings or referenced in the specifications. Upon completion of the work, all the existing facilities, not included as a portion of the work, must be left in a condition equal to the original condition prior to the Contract. Costs for repair and restoration of any facilities must be considered to be incidental to the work and included in the Contract price.

1.23 RESTORATION OF PROJECT ROADS

Submit Access Road Photographs and Notes, taken in the presence of the GQAR, showing the condition of the roads prior to the start of construction. Project roads used for construction access will be evaluated and restored to their original condition by the Contractor.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --