JDTRGR22_DRAFT REVIEW PART-3 ATTACHMENT A17 and A18 R1.pdf

PDF 38 MB Posted

Attached to
John Day Dam Turbine Runner Replacement and Generator Rewind Project - 90% Review
Solicitation number
W9127N22R0003
Issued by

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation W9127N23R0003

John Day Lock and Dam, Rufus, OR

JOHN DAY DAM TURBINE REPLACEMENT AND

GENERATOR REWIND

Project Manual

PART-3 ATTACHMENT A17 & A18

DRAFT R

EVIEW

A17: Generator Test Report

JOHN DAY DAM TURBINE REPLACEMENT AND GENERATOR REWIND

TABLE OF CONTENTS

ATTACHMENTS

A18: Schedule

TOC - 1

A17-1

A17-2

A17-3

A17-4

A17-5

A17-6

A17-7

A17-8

A17-9

A17-10

A17-11

A17-12

A17-13

A17-14

A17-15

A17-16

A17-17

A17-18

A17-19

A17-20

A17-21

A17-22

A17-23

A17-24

A17-25

A17-26

A17-27

A17-28

A17-29

A17-30

A17-31

A17-32

A17-33

A17-34

A17-35

A17-36

A17-37

A17-38

A17-39

A17-40

A17-41

A17-42

A17-43

A17-44

A17-45

A17-46

A17-47

A17-48

A17-49

A17-50

A17-51

ID Task Mode

Task Name Duration Start Finish Predeces

1 NTP 0 days Mon 1/1/24 Mon 1/1/24 2 Design ‐ Baseline 140 days Mon 1/1/24 Sun 5/19/24 1 3 Design ‐ Iteration 1A 616 days Mon 5/20/24 Sun 1/25/26 4 1A ‐ Prelim CFD 105 days Mon 5/20/24 Sun 9/1/24 2 5 1A ‐ GOV Review / Decision 7 days Mon 9/2/24 Sun 9/8/24 4 6 1A ‐ Prelim Model Test 105 days Mon 9/9/24 Sun 12/22/24 5 7 1A ‐ GOV Review / Decision 7 days Mon 12/23/24 Sun 12/29/24 6 8 1A ‐ Iteration CFD 56 days Mon 12/30/24 Sun 2/23/25 7 9 1A ‐ Iteration Model Testing 140 days Mon 2/24/25 Sun 7/13/25 8 10 1A ‐ ERDC Model Testing 196 days Mon 7/14/25 Sun 1/25/26 9 11 Design ‐ Iteration 2A 462 days Mon 7/14/25 Sun 10/18/26 12 2A ‐ Prelim CFD 49 days Mon 7/14/25 Sun 8/31/25 9 13 2A ‐ GOV Review / Decision 7 days Mon 9/1/25 Sun 9/7/25 12 14 2A ‐ Design CFD 56 days Mon 9/8/25 Sun 11/2/25 13 15 2A ‐ Model Test 140 days Mon 11/3/25 Sun 3/22/26 14 16 2A ‐ ERDC Model Testing 196 days Mon 3/23/26 Sun 10/4/26 15 17 2A ‐ Gov Decision 14 days Mon 10/5/26 Sun 10/18/26 16 18 Design ‐ Iteration 3A 462 days Mon 10/19/26 Sun 1/23/28 19 3A ‐ Prelim CFD 49 days Mon 10/19/26 Sun 12/6/26 17 20 3A ‐ Gov Review / Decision 7 days Mon 12/7/26 Sun 12/13/26 19 21 3A ‐ Iteration CFD 56 days Mon 12/14/26 Sun 2/7/27 20 22 3A ‐ Model Testing 140 days Mon 2/8/27 Sun 6/27/27 21 23 3A ‐ ERDC Model Testing 196 days Mon 6/28/27 Sun 1/9/28 22 24 3A ‐ Gov Decision 14 days Mon 1/10/28 Sun 1/23/28 23 25 Design ‐ Iteration 1F 588 days Mon 11/3/25 Sun 6/13/27 26 1F ‐ Prelim CFD 77 days Mon 11/3/25 Sun 1/18/26 14 27 1F ‐ Gov Review / Decision 7 days Mon 1/19/26 Sun 1/25/26 26 28 1F ‐ Prelim Model Test 105 days Mon 1/26/26 Sun 5/10/26 27 29 1F ‐ Gov Review / Decision 7 days Mon 5/11/26 Sun 5/17/26 28 30 1F ‐ Iteration CFD 56 days Mon 5/18/26 Sun 7/12/26 29 31 1F ‐ Model Testing 140 days Mon 7/13/26 Sun 11/29/26 30 32 1F ‐ ERDC Model Testing 196 days Mon 11/30/26 Sun 6/13/27 31 33 Design ‐ Iteration 2F 462 days Mon 11/30/26 Sun 3/5/28 34 2F ‐ Prelim CFD 49 days Mon 11/30/26 Sun 1/17/27 31 35 2F ‐ Gov Review / Decision 7 days Mon 1/18/27 Sun 1/24/27 34 36 2F ‐ Iteration CFD 56 days Mon 1/25/27 Sun 3/21/27 35 37 2F ‐ Model Testing 140 days Mon 3/22/27 Sun 8/8/27 36

1/1 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045

2024 2034 2044

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Project: 90_Schedule.mpp Date: Fri 10/29/21

A18-1

ID Task Mode

Task Name Duration Start Finish Predeces

38 2F ‐ ERDC Model Testing 196 days Mon 8/9/27 Sun 2/20/28 37 39 2F ‐ Gov Decision 14 days Mon 2/21/28 Sun 3/5/28 38 40 Design ‐ Iteration 3F 476 days Mon 3/6/28 Sun 6/24/29 41 3F ‐ Gov Decision 14 days Mon 3/6/28 Sun 3/19/28 39 42 3F ‐ Prelim CFD 49 days Mon 3/20/28 Sun 5/7/28 41 43 3F ‐ Gov Decision 7 days Mon 5/8/28 Sun 5/14/28 42 44 3F ‐ Iteration CFD 56 days Mon 5/15/28 Sun 7/9/28 43 45 3F ‐ Model Testing 140 days Mon 7/10/28 Sun 11/26/28 44 46 3F ‐ ERDC Model Testing 196 days Mon 11/27/28 Sun 6/10/29 45 47 3F ‐ Gov Decision 14 days Mon 6/11/29 Sun 6/24/29 46 48 Adjustable Blade Manufacture & Site Work 5100 days Mon 1/24/28 Thu 1/9/42 49 Adjustable Blade Manufacture 730 days Mon 1/24/28 Tue 1/22/30 24 50 Unit AA Site Work 870 days Wed 1/23/30 Thu 6/10/32 49 51 Unit AB Site Work 700 days Fri 6/11/32 Thu 5/11/34 50 52 Unit AC Site Work 700 days Fri 5/12/34 Thu 4/10/36 51 53 Unit AD Site Work 700 days Fri 4/11/36 Thu 3/11/38 52 54 Unit AE Site Work 700 days Fri 3/12/38 Thu 2/9/40 53 55 Unit AF Site Work 700 days Fri 2/10/40 Thu 1/9/42 54 56 Fixed Blade Manufacture & Site Work 5402 days Mon 6/25/29 Fri 4/8/44 57 Fixed Blade Manufacture 730 days Mon 6/25/29 Tue 6/24/31 47 58 Unit FA Site Work 820 days Fri 6/11/32 Fri 9/8/34 57,50 59 Unit FB Site Work 700 days Sat 9/9/34 Fri 8/8/36 58 60 Unit FC Site Work 700 days Sat 8/9/36 Fri 7/9/38 59 61 Unit FD Site Work 700 days Sat 7/10/38 Fri 6/8/40 60 62 Unit FE Site Work 700 days Sat 6/9/40 Fri 5/9/42 61 63 Unit FF Site Work 700 days Sat 5/10/42 Fri 4/8/44 62

ERDC

2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2024 2034 2044

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Project: 90_Schedule.mpp Date: Fri 10/29/21

A18-2

JDTRGR22_DRAFT REVIEW PART-3 ATTACHMENT 17
Cover
PART 3 Printed TOC
Attachment A17 - 48 13 16.00 26
(0) Report of Test - John Day Lock and Dam Unit 2
(1) Report of Test - John Day Lock and Dam Unit 2
(2) Report of Test - John Day Lock and Dam Unit 2
(3) Report of Test - John Day Lock and Dam Unit 2
(4) Report of Test - John Day Lock and Dam Unit 2
(5) Report of Test - John Day Lock and Dam Unit 2
(6) Report of Test - John Day Lock and Dam Unit 2
(7) Report of Test - John Day Lock and Dam Unit 2
(8) Report of Test - John Day Lock and Dam Unit 2
(9) Report of Test - John Day Lock and Dam Unit 2
(10) Report of Test - John Day Lock and Dam Unit 2
(11) Report of Test - John Day Lock and Dam Unit 2
(12) Report of Test - John Day Lock and Dam Unit 2
(13) Report of Test - John Day Lock and Dam Unit 2
(14) Report of Test - John Day Lock and Dam Unit 2
(15) Report of Test - John Day Lock and Dam Unit 2
(16) Report of Test - John Day Lock and Dam Unit 2
(17) Report of Test - John Day Lock and Dam Unit 2
(18) Report of Test - John Day Lock and Dam Unit 2
(19) Report of Test - John Day Lock and Dam Unit 2
(20) Report of Test - John Day Lock and Dam Unit 2
(21) Report of Test - John Day Lock and Dam Unit 2
(22) Report of Test - John Day Lock and Dam Unit 2
(23) Report of Test - John Day Lock and Dam Unit 2
(24) Report of Test - John Day Lock and Dam Unit 2
(25) Report of Test - John Day Lock and Dam Unit 2
(25A) Report of Test - John Day Lock and Dam Unit 2
(26) Report of Test - John Day Lock and Dam Unit 2
(27) Report of Test - John Day Lock and Dam Unit 2
(28) Report of Test - John Day Lock and Dam Unit 2
(29) Report of Test - John Day Lock and Dam Unit 2
(30) Report of Test - John Day Lock and Dam Unit 2
(31) Report of Test - John Day Lock and Dam Unit 2
(32) Report of Test - John Day Lock and Dam Unit 2
(33) Report of Test - John Day Lock and Dam Unit 2
(34) Report of Test - John Day Lock and Dam Unit 2
(35) Report of Test - John Day Lock and Dam Unit 2
(36) Report of Test - John Day Lock and Dam Unit 2
(37) Report of Test - John Day Lock and Dam Unit 2
(38) Report of Test - John Day Lock and Dam Unit 2
(39) Report of Test - John Day Lock and Dam Unit 2
(40) Report of Test - John Day Lock and Dam Unit 2
(41) Report of Test - John Day Lock and Dam Unit 2
(42) Report of Test - John Day Lock and Dam Unit 2
(43) Report of Test - John Day Lock and Dam Unit 2
(44) Report of Test - John Day Lock and Dam Unit 2
(45) Report of Test - John Day Lock and Dam Unit 2
(46) Report of Test - John Day Lock and Dam Unit 2
(47) Report of Test - John Day Lock and Dam Unit 2
(48) Report of Test - John Day Lock and Dam Unit 2
(49) Report of Test - John Day Lock and Dam Unit 2