JDTRGR22_DRAFT REVIEW PART-3 ATTACHMENT A17 and A18.pdf

PDF 38 MB Posted

Attached to
John Day Dam Turbine Runner Replacement and Generator Rewind Project - 90% Review
Solicitation number
W9127N22R0003
Issued by

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation W9127N23R0003

John Day Lock and Dam, Rufus, OR

JOHN DAY DAM TURBINE REPLACEMENT AND

GENERATOR REWIND

Project Manual

PART-3 ATTACHMENT A17 & A18

DRAFT R

EVIEW

A17: Generator Test Report

JOHN DAY DAM TURBINE REPLACEMENT AND GENERATOR REWIND

TABLE OF CONTENTS

ATTACHMENTS

A18: Schedule

TOC - 1

A17-1

A17-2

A17-3

A17-4

A17-5

A17-6

A17-7

A17-8

A17-9

A17-10

A17-11

A17-12

A17-13

A17-14

A17-15

A17-16

A17-17

A17-18

A17-19

A17-20

A17-21

A17-22

A17-23

A17-24

A17-25

A17-26

A17-27

A17-28

A17-29

A17-30

A17-31

A17-32

A17-33

A17-34

A17-35

A17-36

A17-37

A17-38

A17-39

A17-40

A17-41

A17-42

A17-43

A17-44

A17-45

A17-46

A17-47

A17-48

A17-49

A17-50

A17-51

ID Task Mode

Task Name Duration Start Finish Predeces

1 NTP 0 days Mon 1/1/24 Mon 1/1/24 2 Design ‐ Baseline 90 days Mon 1/1/24 Sat 3/30/24 1 3 Design ‐ Iteration 1A 595 days Sun 3/31/24 Sat 11/15/25 4 1A ‐ Prelim CFD 98 days Sun 3/31/24 Sat 7/6/24 2 5 1A ‐ GOV Review / Decision 7 days Sun 7/7/24 Sat 7/13/24 4 6 1A ‐ Prelim Model Test 91 days Sun 7/14/24 Sat 10/12/24 5 7 1A ‐ GOV Review / Decision 7 days Sun 10/13/24 Sat 10/19/24 6 8 1A ‐ Iteration CFD 56 days Sun 10/20/24 Sat 12/14/24 7 9 1A ‐ Iteration Model Testing 140 days Sun 12/15/24 Sat 5/3/25 8 10 1A ‐ ERDC Model Testing 196 days Sun 5/4/25 Sat 11/15/25 9 11 Design ‐ Iteration 2A 449 days Sun 5/4/25 Sun 7/26/26 12 2A ‐ Prelim CFD 36 days Sun 5/4/25 Sun 6/8/25 9 13 2A ‐ GOV Review / Decision 7 days Mon 6/9/25 Sun 6/15/25 12 14 2A ‐ Design CFD 56 days Mon 6/16/25 Sun 8/10/25 13 15 2A ‐ Model Test 140 days Mon 8/11/25 Sun 12/28/25 14 16 2A ‐ ERDC Model Testing 196 days Mon 12/29/25 Sun 7/12/26 15 17 2A ‐ Gov Decision 14 days Mon 7/13/26 Sun 7/26/26 16 18 Design ‐ Iteration 3A 448 days Mon 7/27/26 Sun 10/17/27 19 3A ‐ Prelim CFD 35 days Mon 7/27/26 Sun 8/30/26 17 20 3A ‐ Gov Review / Decision 7 days Mon 8/31/26 Sun 9/6/26 19 21 3A ‐ Iteration CFD 56 days Mon 9/7/26 Sun 11/1/26 20 22 3A ‐ Model Testing 140 days Mon 11/2/26 Sun 3/21/27 21 23 3A ‐ ERDC Model Testing 196 days Mon 3/22/27 Sun 10/3/27 22 24 3A ‐ Gov Decision 14 days Mon 10/4/27 Sun 10/17/27 23 25 Design ‐ Iteration 1F 476 days Mon 8/11/25 Sun 11/29/26 26 1F ‐ Prelim CFD 84 days Mon 8/11/25 Sun 11/2/25 14 27 1F ‐ Gov Review / Decision 7 days Mon 11/3/25 Sun 11/9/25 26 28 1F ‐ Prelim Model Test 63 days Mon 11/10/25 Sun 1/11/26 27 29 1F ‐ Gov Review / Decision 7 days Mon 1/12/26 Sun 1/18/26 28 30 1F ‐ Iteration CFD 56 days Mon 1/19/26 Sun 3/15/26 29 31 1F ‐ Model Testing 63 days Mon 3/16/26 Sun 5/17/26 30 32 1F ‐ ERDC Model Testing 196 days Mon 5/18/26 Sun 11/29/26 31 33 Design ‐ Iteration 2F 378 days Mon 5/18/26 Sun 5/30/27 34 2F ‐ Prelim CFD 42 days Mon 5/18/26 Sun 6/28/26 31 35 2F ‐ Gov Review / Decision 7 days Mon 6/29/26 Sun 7/5/26 34 36 2F ‐ Iteration CFD 56 days Mon 7/6/26 Sun 8/30/26 35 37 2F ‐ Model Testing 63 days Mon 8/31/26 Sun 11/1/26 36

1/1 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043

2024 2034 2

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Project: 90_Schedule Date: Thu 10/28/21

A18-1

ID Task Mode

Task Name Duration Start Finish Predeces

38 2F ‐ ERDC Model Testing 196 days Mon 11/2/26 Sun 5/16/27 37 39 2F ‐ Gov Decision 14 days Mon 5/17/27 Sun 5/30/27 38 40 Design ‐ Iteration 3F 371 days Mon 5/31/27 Sun 6/4/28 41 3F ‐ Gov Decision 14 days Mon 5/31/27 Sun 6/13/27 39 42 3F ‐ Prelim CFD 42 days Mon 6/14/27 Sun 7/25/27 41 43 3F ‐ Gov Decision 7 days Mon 7/26/27 Sun 8/1/27 42 44 3F ‐ Iteration CFD 35 days Mon 8/2/27 Sun 9/5/27 43 45 3F ‐ Model Testing 63 days Mon 9/6/27 Sun 11/7/27 44 46 3F ‐ ERDC Model Testing 196 days Mon 11/8/27 Sun 5/21/28 45 47 3F ‐ Gov Decision 14 days Mon 5/22/28 Sun 6/4/28 46 48 Adjustable Blade Manufacture & Site Work 5130 days Mon 10/18/27 Sat 11/2/41 49 Adjustable Blade Manufacture 730 days Mon 10/18/27 Tue 10/16/29 24 50 Unit AA Site Work 900 days Wed 10/17/29 Sat 4/3/32 49 51 Unit AB Site Work 700 days Sun 4/4/32 Sat 3/4/34 50 52 Unit AC Site Work 700 days Sun 3/5/34 Sat 2/2/36 51 53 Unit AD Site Work 700 days Sun 2/3/36 Sat 1/2/38 52 54 Unit AE Site Work 700 days Sun 1/3/38 Sat 12/3/39 53 55 Unit AF Site Work 700 days Sun 12/4/39 Sat 11/2/41 54 56 Fixed Blade Manufacture & Site Work 5130 days Mon 6/5/28 Sat 6/21/42 57 Fixed Blade Manufacture 730 days Mon 6/5/28 Tue 6/4/30 47 58 Unit FA Site Work 900 days Wed 6/5/30 Sat 11/20/32 57 59 Unit FB Site Work 700 days Sun 11/21/32 Sat 10/21/34 58 60 Unit FC Site Work 700 days Sun 10/22/34 Sat 9/20/36 59 61 Unit FD Site Work 700 days Sun 9/21/36 Sat 8/21/38 60 62 Unit FE Site Work 700 days Sun 8/22/38 Sat 7/21/40 61 63 Unit FF Site Work 700 days Sun 7/22/40 Sat 6/21/42 62

ERDC

2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2024 2034 2

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Project: 90_Schedule Date: Thu 10/28/21

A18-2

JDTRGR22_DRAFT REVIEW PART-3 ATTACHMENT 17
Cover
PART 3 Printed TOC
Attachment A17 - 48 13 16.00 26
(0) Report of Test - John Day Lock and Dam Unit 2
(1) Report of Test - John Day Lock and Dam Unit 2
(2) Report of Test - John Day Lock and Dam Unit 2
(3) Report of Test - John Day Lock and Dam Unit 2
(4) Report of Test - John Day Lock and Dam Unit 2
(5) Report of Test - John Day Lock and Dam Unit 2
(6) Report of Test - John Day Lock and Dam Unit 2
(7) Report of Test - John Day Lock and Dam Unit 2
(8) Report of Test - John Day Lock and Dam Unit 2
(9) Report of Test - John Day Lock and Dam Unit 2
(10) Report of Test - John Day Lock and Dam Unit 2
(11) Report of Test - John Day Lock and Dam Unit 2
(12) Report of Test - John Day Lock and Dam Unit 2
(13) Report of Test - John Day Lock and Dam Unit 2
(14) Report of Test - John Day Lock and Dam Unit 2
(15) Report of Test - John Day Lock and Dam Unit 2
(16) Report of Test - John Day Lock and Dam Unit 2
(17) Report of Test - John Day Lock and Dam Unit 2
(18) Report of Test - John Day Lock and Dam Unit 2
(19) Report of Test - John Day Lock and Dam Unit 2
(20) Report of Test - John Day Lock and Dam Unit 2
(21) Report of Test - John Day Lock and Dam Unit 2
(22) Report of Test - John Day Lock and Dam Unit 2
(23) Report of Test - John Day Lock and Dam Unit 2
(24) Report of Test - John Day Lock and Dam Unit 2
(25) Report of Test - John Day Lock and Dam Unit 2
(25A) Report of Test - John Day Lock and Dam Unit 2
(26) Report of Test - John Day Lock and Dam Unit 2
(27) Report of Test - John Day Lock and Dam Unit 2
(28) Report of Test - John Day Lock and Dam Unit 2
(29) Report of Test - John Day Lock and Dam Unit 2
(30) Report of Test - John Day Lock and Dam Unit 2
(31) Report of Test - John Day Lock and Dam Unit 2
(32) Report of Test - John Day Lock and Dam Unit 2
(33) Report of Test - John Day Lock and Dam Unit 2
(34) Report of Test - John Day Lock and Dam Unit 2
(35) Report of Test - John Day Lock and Dam Unit 2
(36) Report of Test - John Day Lock and Dam Unit 2
(37) Report of Test - John Day Lock and Dam Unit 2
(38) Report of Test - John Day Lock and Dam Unit 2
(39) Report of Test - John Day Lock and Dam Unit 2
(40) Report of Test - John Day Lock and Dam Unit 2
(41) Report of Test - John Day Lock and Dam Unit 2
(42) Report of Test - John Day Lock and Dam Unit 2
(43) Report of Test - John Day Lock and Dam Unit 2
(44) Report of Test - John Day Lock and Dam Unit 2
(45) Report of Test - John Day Lock and Dam Unit 2
(46) Report of Test - John Day Lock and Dam Unit 2
(47) Report of Test - John Day Lock and Dam Unit 2
(48) Report of Test - John Day Lock and Dam Unit 2
(49) Report of Test - John Day Lock and Dam Unit 2