Solicitation W9127N23R0003
John Day Lock and Dam, Rufus, OR
JOHN DAY DAM TURBINE REPLACEMENT AND
GENERATOR REWIND
Project Manual
PART-1 SPECIFICATIONS
DRAFT R
EVIEW
TOC-1
JOHN DAY DAM TURBINE REPLACEMENT AND GENERATOR REWIND
00 10 00
00 10 00
GENERAL AND TECHNICAL SPECIFICATION REQUIREMENTS
00 70 00
TABLE OF CONTENTS
SOLICITATION, OFFER, AND AWARD FORM (SF 1442)
SOLICITATION
00 72 00 GENERAL CONDITIONS
00 73 00 SUPPLEMENTARY CONDITIONS
CONDITIONS OF THE CONTRACT
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 21 00 INSTRUCTIONS
00 20 00 INSTRUCTIONS FOR PROCUREMENT
90% INDUSTRY REVIEW
PROJECT TITLE: John Day Dam Turbine Replacement and Generator Rew ind
LOCATION OF PERFORMANCE: John Day Lock and Dam, Rufus, OR 97050
MAGNITUDE OF CONSTRUCTION: Over $500,000,000
SOCIOECONOMIC: Unrestricted, Full and Open
CAROLYN J RANDOLPH
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
10-Nov-2021
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W9127N23R0003 98
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0100 1 Job
Hydraulic Turbine Design
FFP
EXAMPLE CLIN: All CLINS numbered in the 0100s will be mandatory and optional CLINS for Hydraulic Turbine Design Iterations FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0200 1 Job
Prototype Design
FFP
EXAMPLE CLIN: All CLINS numbered in the 0200s will be mandatory and optional CLINS for Prototype Design Iterations FOB: Destination
NET AMT
00 10 00-3
0300 1 Job
Miscellaneous Equipment, Spare Parts
FFP
EXAMPLE CLIN: All CLINs numbered in the 0300s will be mandatory and optional CLINS for Miscellaneous Equipment, Spare Parts, and Oil Disposal FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0400 1 Job
Unit AA Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0400s will be mandatory and optional CLINS for Unit AA Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0500 1 Job
Unit AB Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0500s will be mandatory and optional CLINS for Unit AB Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-4
0600 1 Job
Unit FA Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0600s will be mandatory and optional CLINS for Unit FA Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0700 1 Job
Unit AC Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0700s will be mandatory and optional CLINS for Unit AC Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-5
0800 1 Job
Unit FB Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0800s will be mandatory and optional CLINS for Unit FB Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0900 1 Job
Unit AD Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 0900s will be mandatory and optional CLINS for Unit AD Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1000 1 Job
Unit FC Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1000s will be mandatory and optional CLINS for Unit FC Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-6
1100 1 Job
Unit AE Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1100s will be mandatory and optional CLINS for Unit AE Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1200 1 Job
Unit FD Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1200s will be mandatory and optional CLINS for Unit FD Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-7
1300 1 Job
Unit AF Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1300s will be mandatory and optional CLINS for Unit AF Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1400 1 Job
Unit FE Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1400s will be mandatory and optional CLINS for Unit FE Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1500 1 Job
Unit FF Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1500s will be mandatory and optional CLINS for Unit FF Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-8
1600 1 Job OPTION Unit AG Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1600s will be optional CLINS for Unit AG Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1700 1 Job OPTION Unit FG Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1700s will be optional CLINS for Unit FG Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-9
1800 1 Job OPTION Unit AH Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1800s will be optional CLINS for Unit AH Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1900 1 Job OPTION Unit FH Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 1900s will be optional CLINS for Unit FH Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
2000 1 Job OPTION Unit AI Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 2000s will be optional CLINS for Unit AI Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-10
2100 1 Job OPTION Unit FI Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 2100s will be optional CLINS for Unit FI Prototype Supply and Install FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
2200 1 Job OPTION Unit AJ Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 2200s will be optional CLINS for Unit AJ Prototype Supply and Install FOB: Destination
NET AMT
00 10 00-11
2300 1 Job OPTION Unit FJ Prototype Supply & Install
FFP
EXAMPLE CLIN: All CLINS numbered in the 2300s will be optional CLINS for Unit FJ Prototype Supply and Install FOB: Destination
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0100 N/A N/A N/A N/A
0200 N/A N/A N/A N/A
0300 N/A N/A N/A N/A
0400 N/A N/A N/A N/A
0500 N/A N/A N/A N/A
0600 N/A N/A N/A N/A
0700 N/A N/A N/A N/A
0800 N/A N/A N/A N/A
0900 N/A N/A N/A N/A
1000 N/A N/A N/A N/A
1100 N/A N/A N/A N/A
1200 N/A N/A N/A N/A
1300 N/A N/A N/A N/A
1400 N/A N/A N/A N/A
00 10 00-12
1500 N/A N/A N/A N/A
1600 N/A N/A N/A N/A
1700 N/A N/A N/A N/A
1800 N/A N/A N/A N/A
1900 N/A N/A N/A N/A
2000 N/A N/A N/A N/A
2100 N/A N/A N/A N/A
2200 N/A N/A N/A N/A
2300 N/A N/A N/A N/A
00 10 00-13
Section 00 20 00 - Instructions for Procurement
OTHER INSTRUCTIONS
BIDDER INQUIRY INFORMATION
All comments regarding this 90% Industry Review are to be submitted via ProjNet-Bid at https://www.projnet.org/projnet/. Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that allows offerors to post questions and comments regarding the 90% Industry Review package, and to view all questions by other offerors, and answers by the U.S. Army Corps of Engineers.
No response will be posted to inquiries made after the Close of Business on the third day preceding the review closing date. All bidders will be held to have reviewed the questions and responses in ProjNet –Bid prior to review submission. Nothing in the 90% Industry Review is changed unless an amendment is sent out.
The Bidder Inquiry Key for this industry review is: IKU745-TD8GYY
To access the ProjNet-Bid website the first time:
1) Register.
2) Click Quick Add Key. (The Agency is USACE.)
3) Enter the following information for access:
The Bidder Inquiry Key for this industry review Valid business contact information
Submit questions or review questions and answers. When an answer is posted to a question, the question and answer is then available for all other bidders to review.
For questions about the ProjNet-Bid, access the help tab on the ProjNet website.
THIS IS NOT A SOLICITATION AND PROPOSALS ARE NOT REQUESTED AT THIS TIME, THIS IS
FOR INFORMATION ONLY
Price Proposal Submission Requirements –
1. SF1442, Solicitation, Offer, and Award.
The SF1442 shall be filled out completely by the offeror and signed by an official that is authorized to bind the company. The offeror shall also acknowledge all amendments to the solicitation in accordance with the instructions on the Standard Form 30 or Block 19 of SF1442.
2. Section 00 10 00, Proposal Price / Bid Schedule.
The offeror shall fully complete this section.
3. Section 00 45 00 - Representations, Certifications and other Statements of Offeror’s.
The offeror shall complete all representations and certifications in Section 00 45 00 and also ensure current registration and completed/updated Annual Representations and Certifications on the System for Award Management (SAM) website, www.sam.gov.
4. Section 00 21 00 – FAR 52.229-15 (Dev) Performance and Payment Bonds – Construction (Deviation):
Performance and payment bonds will be required only for the installation (onsite construction) portion of the work. Bonds must be furnished within 10 calendar days after the Contractor receives notice to proceed with the construction portion of the work. The Contractor must have the capability to bond 100% of the construction CLINs over the anticipated performance period; however, bonding will be permitted on a rolling, per unit basis such that after each unit is installed and the one-year construction warranty period ends for that unit, bonding will commence for the next unit in the queue for installation. Bond amount must be the sum of all CLINs (mandatory and exercised options) for each unit.
00 20 00-1
5. Banking and Bonding point of contacts.
The Government is required to determine Contractor’s responsibility; the offeror shall provide contact information (Company name, point of contact, address, email, and phone number) for the offeror’s bank and bonding institutions.
WAGE DETERMINATIONS
The Contractor shall adhere to the DBA Wage Determinations for the areas in which performance will occur. The most current wage determinations can be found at www.SAM.gov. Applicable Wage Determinations will be incorporated into the Contract Award (See Appendix B). Current Wage Determinations applicable as of the date of solicitation are:
Davis-Bacon Act WD #: OR20210080 Rev 4, Sherman County, Oregon
00 20 00-2
Section 00 21 00 - Instructions
PRICE SCHEDULE
Price Schedule
Unrestricted Competition
The magnitude of the project is estimated at over $500,000,000
1. The bid schedule is divided into categories/tables for the following:
Hydraulic Turbine Design (0100s) Prototype Design (0200s) Miscellaneous Equipment, Spare Parts, and Oil Disposal (0300s) Unit AA Prototype Supply and Install (0400s) Unit AB Prototype Supply and Install (0500s) Unit FA Prototype Supply and Install (0600s) Unit AC Prototype Supply and Install (0700s) Unit FB Prototype Supply and Install (0800s) Unit AD Prototype Supply and Install (0900s) Unit FC Prototype Supply and Install (1000s) Unit AE Prototype Supply and Install (1100s) Unit FD Prototype Supply and Install (1200s) Unit AF Prototype Supply and Install (1300s) Unit FE Prototype Supply and Install (1400s) Unit FF Prototype Supply and Install (1500s) Optional Unit AG Prototype Supply and Install (1600s) Optional Unit FG Prototype Supply and Install (1700s) Optional Unit AH Prototype Supply and Install (1800s) Optional Unit FH Prototype Supply and Install (1900s) Optional Unit AI Prototype Supply and Install (2000s) Optional Unit FI Prototype Supply and Install (2100s) Optional Unit AJ Prototype Supply and Install (2200s) Optional Unit FJ Prototype Supply and Install (2300s)
2. Where variations of an item are priced under one CLIN, the first item (AA) will be awarded as the base requirement. As required based on the final turbine configuration chosen by the Government, subsequent items (optional) will be awarded based upon the outcome of the hydraulic design. No more than one subsequent item (optional) will be awarded for each CLIN and this optional item represents the incremental price difference relative to the first item (AA). All mandatory and optional CLINs will be evaluated during the selection process consistent with the evaluation factor instructions within the solicitation. The solicitation will state, for award purposes, that price will be evaluated based on the total sum anticipated for all base and option CLINs. Evaluation of the option shall not obligate the Government to exercise the option.
3. The price schedule categories provided generally align with the phases of work as defined in Section 01
11.00 00 25 (with some overlapping exceptions).
4. The tables include a column that delineates which CLINs are governed by supply clauses and those that are governed by construction clauses. The Supply clauses defined in this contract apply to the CLINs with an ‘S’ designation in the tables and the Construction clauses apply to the CLINs with a ‘C’ designation in the tables.
5. Some prototype bid items, dependent on the outcome of the hydraulic and prototype designs, include a defined basis for bid. The basis and specification technical requirements define the configuration of the
00 21 00-1 item for bidding purposes. The basis for some bid items include blanks where the Offeror must provide $/ton and labor percentages. Following the completion of the hydraulic design process, if final weights differ from basis weights as a result of Government direction, those CLINs that include a basis (i.e., anything other than “None”) will be subject to price adjustments as described below. Basis weights of materials have been included and are to be assumed for pricing. NOTE: Weights provided in this draft solicitation are preliminary, and most are yet to be determined.
6. The prototype bid items that will be dependent on the outcome of the hydraulic and prototype designs will be adjusted based on the final weights of carbon steel and stainless steel. The price of labor will not be adjusted; only the price associated with materials will be adjusted. Example of how price will be adjusted:
a. Example:
i. Proposed price of CLIN X is $1,000,000
ii. Proposed percent labor is 50%
iii. Carbon steel weight and $/ton in basis: 100 tons at proposed $2,000/ton
iv. Stainless steel weight and $/ton in basis: 50 tons at proposed $3,500/ton
v. Final carbon steel weight: 120 tons
vi. Final stainless steel weight: 45 tons
vii. Price adjustment:
1. Labor - $1 million*50% = $500,000 (stays the same)
2. Fixed Material Portion - $1,000,000 – [(100*$2000) + (50*$3500)] - $500,000
= $125,000 (stays the same)
3. Adjusted Material Portion - (120*$2000) + (45*$3500) = $397,500 (increase)
4. Final Adjusted Total Price - $500,000 + $125,000 + $397,500 = $1,022,500
7. Prototype bid item “Description” column verbs are defined as follows:
Design – Prototype design/engineering including analysis and the preparation of design documentation (reports, drawings, etc.).
Furnish – Design/engineering, manufacturing, procurement, and delivery of components to John
Day Powerhouse.
Supply – Manufacturing/procurement and delivery to John Day Powerhouse Install (Installation) – Field work to incorporate new, modified, and/or existing components into the finished generating unit.
Refurbish (Refurbishment) – Rehabilitation of existing components (including incorporation of replacement/modified components) for usage in the rebuilt generating unit.
Replace (Replacement) – Removal of existing component (if require for installation of replacement components) and installation of replacement component.
Hydraulic Turbine Design
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
Pre Iteration Coordination, Design, Analysis, and Performance Model Construction
1 JOB S $________ None
Adjustable Blade Iteration 1A Base Design Work
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 1A - Preliminary Design Five Blade, 309-inch Diameter CFD (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 1A - Preliminary Design Five Blade, 317-inch Diameter CFD (Optional)
1 JOB S $________ None
00 21 00-2
(Optional)
Adjustable Blade Iteration 1A - Preliminary Design Performance Model Testing (Diameter TBD) (Optional)
1 JOB S $________ None
Adjustable Blade Iteration 2A Base Design Work
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 2A - Preliminary Design Six Blade, TBD-inch Diameter CFD (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 2A - Preliminary Design Performance Model Testing (Diameter TBD) (Optional)
1 JOB S $________ None
Adjustable Blade Iteration 3A Base Design Work
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 3A - Preliminary Design CFD With Draft Tube Modification 1 (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 3A - Preliminary Design CFD With Draft Tube Modification 2 (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 3A - Preliminary Design Performance Model Testing With Draft Tube Modification (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 4A Design Work (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 4A - ERDC Observational Model Testing Coordination (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 5A Design Work (Optional)
1 JOB S $________ None
(Optional)
Adjustable Blade Iteration 5A - ERDC Observational Model Testing Coordination (Optional)
1 JOB S $________ None
Adjustable Blade Final Design Performance Model Testing
1 JOB S $________ None
0118 Fixed Blade Iteration 1F Base Design Work 1 JOB S $________ None
(Optional)
Fixed Blade Iteration 1F - Preliminary Design Five Blade, 319-inch Diameter CFD (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 1F - Preliminary Design Five Blade, 327-inch Diameter CFD (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 1F - Preliminary Design Performance Model Testing (Diameter TBD) (Optional)
1 JOB S $________ None
0122 Fixed Blade Iteration 2F Base Design Work 1 JOB S $________ None
(Optional)
Fixed Blade Iteration 2F - Preliminary Design Six Blade, TBD-inch Diameter CFD (Optional)
1 JOB S $________ None
00 21 00-3
Fixed Blade Iteration 2F - Preliminary Design Performance Model Testing (Diameter TBD) (Optional)
1 JOB S $________ None
0125 Fixed Blade Iteration 3F Base Design Work 1 JOB S $________ None
(Optional)
Fixed Blade Iteration 3F - Preliminary Design CFD With Modified Distributor (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 3F - Preliminary Design CFD With Draft Tube Modification 1 (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 3F - Preliminary Design CFD With Draft Tube Modification 2 (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 3F - Preliminary Design Performance Model Testing With Draft Tube Modification (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 4F Design Work (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Iteration 4F - ERDC Observational Model Testing Coordination (Optional)
1 JOB S $________ None
Fixed Blade Final Design Performance Model Testing
1 JOB S $________ None
(Optional)
Supply Set of Model Wicket Gates (Optional) 2 SET S $________ None
Hydraulic Design Sub-Total $_____________
Prototype Design
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
Discharge Ring Diameter Preliminary Analyses
1 JOB S $________ None
202 Adjustable Blade Runner Prototype Design 1 JOB S $________ None
Adjustable Blade Discharge Ring and Draft Tube Liner Transition Prototype Design
1 JOB S $________ None
Adjustable Blade Stay Vane Modifications Prototype Design
1 JOB S $________ None
Adjustable Blade Wicket Gate Prototype Design
1 JOB S $________ None
Adjustable Blade Lower Turbine Shaft and Blade Servomotor Shaft Prototype Design
1 JOB S $________ None
(Optional)
Adjustable Blade Replacement Inner Head Cover Prototype Design (Optional)
1 JOB S $________ None
00 21 00-4
208 Fixed Blade Runner Prototype Design 1 JOB S $________ None
Fixed Blade Discharge Ring and Draft Tube Liner Transition Prototype Design
1 JOB S $________ None
(Optional)
Fixed Blade Stay Vane Modifications Prototype Design (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Wicket Gate Prototype Design (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Replacement Inner Head Cover Prototype Design (Optional)
1 JOB S $________ None
(Optional)
Modified Outer Head Cover Prototype Design (Optional)
1 JOB S $________ None
(Optional)
Replacement Outer Head Cover Prototype Design (Optional)
1 JOB S $________ None
(Optional)
Modified Intermediate Head Cover Prototype Design (Optional)
1 JOB S $________ None
216 Surface Air Coolers Design 1 JOB S $________ None
Prototype Stator Bar Design, Manufacture, and Test
1 JOB S $________ None
(Optional)
Thrust Bearing Structural Analysis (Optional) 1 JOB S $________ None
(Optional)
Adjustable Blade Draft Tube Modification Design (Optional)
1 JOB S $________ None
(Optional)
Fixed Blade Draft Tube Modification Design (Optional)
1 JOB S $________ None
Prototype Design Sub-Total $_____________
Miscellaneous Equipment, Spare Parts, and Oil Disposal
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
Design and Supply One Stator Core Including Materials, Accessories, and Factory Testing
1 JOB S $________ None
Supply Special Tools and Scaffolding for Generators
1 JOB S $________ None
Supply Adjustable Blade Special Equipment, Tools, Scaffolding, and Runner Blade Maintenance Templates
1 JOB S $________ None
00 21 00-5
Supply Fixed Blade Special Equipment, Tools, Scaffolding, and Runner Blade Maintenance Templates
1 JOB S $________ None
305 Mobilization and Demobilization 1 According to CLIN
C $________ None
306 Supply Spare Wicket Gates 1 JOB S $________ None
307 Supply Generator Spare Parts 1 JOB S $________ None
308 Supply Required Spares 1 JOB S $________ None
(Optional)
Oil Disposal - 5,000 Gallons (Optional) 8 EA C
Unit Price
Total
None
(Optional)
Oil Disposal - 500 Gallons (Optional) 5 EA C
Unit Price
Total
None
Miscellaneous Equipment, Spare Parts, and Oil Disposal Sub-Total $_____________
Unit AA Prototype Supply and Install
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
0401AA
Supply 299.5-Inch Adjustable Five Blade Runner (Base Requirement)
1 JOB S $________
Fully spherical hub, 299.5-inch blade tip diameter. Runner construction method as shown on proposal drawings.
90 tons of martensitic stainless steel (blades, trunnions, sleeves, and appurtenances) @ $___/ton
4,000 pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
130 tons of carbon steel (hub, discharge cone(s), internal mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
00 21 00-6
0401AB
Supply 299.5-Inch Adjustable Six Blade Runner - Incremental Difference Relative to
CLIN 0401AA
(Optional)
1 JOB S $________
Fully spherical hub, 299.5-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and trunnions) @ $___/ton
TBD pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), internal mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0401AC
(Optional)
Supply 309-Inch Adjustable Five Blade Runner - Incremental Difference Relative to
CLIN 0401AA
(Optional)
1 JOB S $________
Fully spherical hub, 309-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades, trunnions, sleeves, and appurtenances) @ $___/ton
TBD pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), internal
00 21 00-7 mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0401AD
(Optional)
Supply 309-Inch Adjustable Six Blade Runner - Incremental Difference Relative to
CLIN 0401AA
(Optional)
1 JOB S $________
Fully spherical hub, 309-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades, trunnions, sleeves, and appurtenances) @ $___/ton
TBD pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), internal mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0401AE
(Optional)
Supply 317-Inch Adjustable Five Blade Runner - Incremental Difference Relative to
CLIN 0401AA
(Optional)
1 JOB S $________
Fully spherical hub, 317-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades, trunnions, sleeves, and appurtenances) @ $___/ton
TBD pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
00 21 00-8
TBD tons of carbon steel (hub, discharge cone(s), internal mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0401AF
(Optional)
Supply 317-Inch Adjustable Six Blade Runner - Incremental Difference Relative to
CLIN 0401AA
(Optional)
1 JOB S $________
Fully spherical hub, 317-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades, trunnions, sleeves, and appurtenances) @ $___/ton
TBD pounds of stainless steel overlay (on hub to protect against blade/hub leakage cavitation) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), internal mechanism components, operating rod, piston, piston cap, coupling fasteners, and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0402AA
Supply Permanent Discharge Ring Section and Insert for 299.5-Inch Adjustable Blade Runner (Base Requirement)
1 JOB S $________
Fully spherical runner blade tip diameter. Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
00 21 00-9
1 ton = 2,000 U.S. pounds finished material weight
0402AB
(Optional)
Supply Embedded Discharge Ring Section and Insert for 309-Inch Adjustable Blade Runner
- Incremental Difference Relative to CLIN 0402AA (Optional)
1 JOB S $________
Fully spherical runner blade tip diameter. Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0402AC
(Optional)
Supply Embedded Discharge Ring Section and Insert for 317-Inch Adjustable Blade Runner
- Incremental Difference Relative to CLIN 0402AA (Optional)
1 JOB S $________
Fully spherical runner blade tip diameter. Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0403AA
Modify Existing Discharge Ring Without Demolition and Install Permanent Discharge Ring Section for 299.5- Inch Adjustable Blade
1 JOB C $________ TBD
00 21 00-10
Runner (Base Requirement)
0403AB
(Optional)
Install Embedded Discharge Ring Section With Demolition for 309-Inch Adjustable Blade Runner - Incremental Difference Relative to CLIN 0403AA (Optional)
1 JOB C $________ TBD
0403AC
(Optional)
Install Embedded Discharge Ring Section With Demolition for 317-Inch Adjustable Blade Runner - Incremental Difference Relative to CLIN 0403AA (Optional)
1 JOB C $________ TBD
0404AA
Supply Permanent Draft Tube Liner Transition Section for 299.5-Inch Adjustable Blade Runner (Base Requirement)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0404AB
(Optional)
Supply Permanent Draft Tube Liner Transition Section for 309-Inch Adjustable Blade Runner
- Incremental Difference Relative to CLIN 0404AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
00 21 00-11
0404AC
Supply Permanent Draft Tube Liner Transition Section for 317-Inch Adjustable Blade Runner
- Incremental Difference Relative to CLIN 0404AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0404AD
(Optional)
Supply Embedded Draft Tube Liner Transition Section for 317-Inch Adjustable Blade Runner
- Incremental Difference Relative to CLIN 0404AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0405AA
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 299.5-Inch Adjustable Blade Runner (Base Requirement)
1 JOB C $________ TBD
00 21 00-12
0405AB
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 309-Inch Adjustable Blade Runner - Incremental Difference Relative to CLIN 0405AA (Optional)
1 JOB C $________ TBD
0405AC
(Optional)
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 317-Inch Adjustable Blade Runner - Incremental Difference Relative to CLIN 0405AA (Optional)
1 JOB C $________ TBD
0405AD
(Optional)
Install Embedded Draft Tube Liner Transition Section With Demolition for 317-Inch Adjustable Blade Runner - Incremental Difference Relative to CLIN 0405AA (Optional)
1 JOB C $________ TBD
0406AA
Refurbish Existing Outer Head Cover (Base Requirement)
1 JOB C $________ None
0406AB
(Optional)
Refurbish and Modify Existing Outer Head Cover - Incremental Difference Relative to
CLIN 0406AA
(Optional)
1 JOB C $________ None
0406AC
(Optional)
Supply Replacement Outer Head Cover - Incremental Difference Relative to CLIN 0406AA (Optional)
1 JOB S $________ None
0407AA
Refurbish Existing Intermediate Head Cover (Base Requirement)
1 JOB C $________ None
0407AB
(Optional)
Refurbish and Modify Existing Intermediate Head Cover - Incremental Difference Relative to CLIN 0407AA (Optional)
1 JOB C $________ None
0408AA
Refurbish Existing Inner Head Cover (Base Requirement)
1 JOB C $________ None
00 21 00-13
0408AB
Supply Replacement Inner Head Cover - Incremental Difference Relative to CLIN 0408AA (Optional)
1 JOB S $________
TBD tons of carbon steel @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
Supply Stay Vane Modification Components
1 JOB S $________
TBD tons of carbon steel @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
Refurbish Stay Vanes/Ring Including Installation of Stay Vane Modification Components
1 JOB C $________ TBD
0411 Supply Wicket Gates 1 JOB S $________ TBD
Supply Wicket Gate Operating Mechanism Bushings and Bearing Plate
1 JOB S $________ None
Supply Head Cover and Bottom Ring Facing Plates
1 JOB S $________ None
Supply Blade Servomotor Shaft and Appurtenances
1 JOB S $________ None
Supply Lower Turbine Shaft and Appurtenances
1 JOB S $________ None
Supply Oil and Water Basin at the Blade Servomotor (OIL FREE
ONLY)
1 JOB S $________ None
Supply Turbine Shaft Packing Box
1 JOB S $________ None
Supply Turbine Guide Bearing Oil Sump
1 JOB S $________ None
Supply Complete Set of Stator Bars, Including Supplies and Accessories for a Complete New Winding Including Factoring Testing
1 JOB S $________ None
Remove Existing Stator Winding and Install and Test New Stator Winding
1 JOB C $________ None
00 21 00-14
Supply Surface Air Coolers
1 JOB S $________ None
Install Surface Air Coolers
1 JOB C $________ None
Pre-Disassembly Watered Operational Testing
1 JOB C $________ None
Generating Unit Disassembly
1 JOB C $________ None
Refurbish Existing Turbine Shaft to Become Intermediate Shaft
1 JOB C $________ None
0426 Not Used N/A N/A N/A N/A N/A 0427 Not Used N/A N/A N/A N/A N/A
Machine Stay Ring Head Cover Mounting Flange
1 JOB C $________ None
0429 Refurbish Bottom Ring 1 JOB C $________ None
Refurbish Miscellaneous Wicket Gate Operating Mechanism Components
1 JOB C $________ None
Line Boring and Installation of Wicket Gate Stem Bushings
1 JOB C $________ None
Refurbish Automatic Air Valves and Replace Gate Valves, Scroll Case Drain Valves, and Draft Tube Drain Valves
1 JOB C $________ None
Refurbish Wicket Gate Operating Ring
1 JOB C $________ None
Refurbish Wicket Gate Servomotors
1 JOB C $________ None
(Optional)
Bore and Hone Wicket Gate Servomotors (Optional)
1 JOB C $________ None
(Optional)
Provide Wicket Gate Servomotor Piston Rings (Optional)
1 JOB C $________ None
Provide Water and Oil Piping Systems and Components
1 JOB C $________ None
Provide Electrical Devices, Temperature Indicating Devices, and Wiring/Cable
1 JOB C $________ None
Provide High Pressure Oil Injection System Components
1 JOB C $________ None
Thrust Bearing Phase 1 Inspections
1 JOB C $________ None
(Optional)
Thrust Bearing Phase 2 Inspections (Optional)
1 JOB C $________ None
00 21 00-15
Refurbish Thrust Bearing Shoes (Optional)
1 JOB C $________ None
(Optional)
Refurbish Thrust Bearing Runner and Collar (Optional)
1 JOB C $________ None
(Optional)
Upper Generator Guide Bearing NDT (Optional)
1 JOB C $________ None
(Optional)
Refurbish Upper Generator Guide Bearing Shoes (Optional)
1 JOB C $________ None
(Optional)
Lower Generator Guide Bearing NDT (Optional)
1 JOB C $________ None
(Optional)
Refurbish Lower Generator Guide Bearing (Optional)
1 JOB C $________ None
(Optional)
Turbine Guide Bearing NDT (Optional)
1 JOB C $________ None
(Optional)
Refurbish Turbine Guide Bearing (Optional)
1 JOB C $________ None
0450 Refurbish Oil Head 1 JOB C $________ None
0451 Not Used N/A N/A N/A N/A N/A
Refurbish and Modify Blade Servomotor Oil Pipes
1 JOB C $________ None
0453 Not Used N/A N/A N/A N/A N/A
Provide Thrust Bearing Oil Coolers
1 JOB C $________ None
Lead Based Paint Removal and Disposal
1 JOB C $________ None
0456 Painting 1 JOB C $________ None
(Optional)
Draft Tube Floor Fill Modification (Optional)
1 JOB C $________ None
(Optional)
Draft Tube Roof Fill Modification (Optional)
1 JOB C $________ None
Inspect, Clean, and Test Stator Core
1 JOB C $________ None
(Optional)
Perform Additional Interlaminar Insulation Testing (Optional)
1 JOB C $________ None
(Optional)
Remove Existing Stator Core and Install and Test New Stator Core (Optional)
1 JOB C $________ None
(Optional)
Supply Stator Core Including Materials, Accessories, and Factory Testing (Optional)
1 JOB S $________ None
Clean and Inspect Rotor, Reinsulate Rotor Field
1 JOB C $________ None
00 21 00-16
Leads, and Test Rotor Field Windings
(Optional)
Refurbish Rotor Field Pole (Optional)
20 EA C
Unit Price
Total
None
Furnish, Install, and Test Surge Arrestors
1 JOB C $________ None
Provide Machine Condition Monitoring System Sensors
1 JOB C $________ None
(Optional)
Provide Generator Stator Heaters (Optional)
1 JOB C $________ None
(Optional)
Provide Generator Heater Controls (Optional)
1 JOB C $________ None
Generating Unit Reassembly
1 JOB C $________ None
Generating Unit Commissioning
1 JOB C $________ None
Perform Generator Special Field Test
1 JOB C $________ None
(Optional)
Perform Model Validation Testing on Generator (Optional)
1 JOB C $________ None
(Optional)
Adjustable Blade Time and Materials (Optional)
1 JOB C $________ None
Unit AA Prototype Supply and Install Sub-Total $_____________
Unit AB Prototype Supply and Install
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
NOTE: To be filled in prior to solicitation. CLINs will match CLINs for Unit AA except CLIN 0471 as generator special field testing is only required on Unit AA.
Unit AB Prototype Supply and Install Sub-Total $_____________
Unit FA Prototype Supply and Install
ITEM DESCRIPTION Q U/M CLAUSES AMOUNT BASIS
0601AA
Supply 309-Inch Fixed Five Blade Runner (Base Requirement)
1 JOB S $________
Fully spherical hub, 309-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
00 21 00-17
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0601AB
(Optional)
Supply 309-Inch Fixed Six Blade Runner - Incremental Difference Relative to CLIN 0501AA (Optional)
1 JOB S $________
Fully spherical hub, 309-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0601AC
(Optional)
Supply 319-Inch Fixed Five Blade Runner - Incremental Difference Relative to CLIN 0501AA (Optional)
1 JOB S $________
Fully spherical hub, 319-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0601AD
(Optional)
Supply 319-Inch Fixed Six Blade Runner - Incremental Difference
1 JOB S $________
Fully spherical hub, 319-inch blade tip diameter. Runner construction method as shown on proposal drawings.
00 21 00-18
Relative to CLIN 0501AA (Optional) TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0601AE
(Optional)
Supply 327-Inch Fixed Five Blade Runner - Incremental Difference Relative to CLIN 0501AA (Optional)
1 JOB S $________
Fully spherical hub, 327-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0601AF
(Optional)
Supply 327-Inch Fixed Six Blade Runner - Incremental Difference Relative to CLIN 0501AA (Optional)
1 JOB S $________
Fully spherical hub, 327-inch blade tip diameter. Runner construction method as shown on proposal drawings.
TBD tons of martensitic stainless steel (blades and appurtenances) @ $___/ton
TBD tons of carbon steel (hub, discharge cone(s), and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0602AA
Supply Permanent Discharge Ring Section for 309-Inch Fixed Blade Runner (Base Requirement)
1 JOB S $________
Construction method as shown on proposal drawings.
00 21 00-19
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0602AB
(Optional)
Supply Embedded Discharge Ring Section for 319-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0502AA
(Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0602AC
(Optional)
Supply Embedded Discharge Ring Section for 327-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0502AA
(Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0603AA
Modify Existing Discharge Ring Without Demolition and Install Permanent Discharge
1 JOB C $________ TBD
00 21 00-20
Ring Section for 309- Inch Fixed Blade Runner (Base Requirement)
0603AB
(Optional)
Install Embedded Discharge Ring Section With Demolition for 319-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0503AA
(Optional)
1 JOB C $________ TBD
0603AC
(Optional)
Install Embedded Discharge Ring Section With Demolition for 327-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0503AA
(Optional)
1 JOB C $________ TBD
0604AA
Supply Permanent Draft Tube Liner Transition Section for 309-Inch Fixed Blade Runner (Base Requirement)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0604AB
(Optional)
Supply Permanent Draft Tube Liner Transition Section for 319-Inch Fixed Blade Runner - Incremental Difference Relative to CLIN 0504AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
00 21 00-21
1 ton = 2,000 U.S. pounds finished material weight
0604AC
(Optional)
Supply Permanent Draft Tube Liner Transition Section for 327-Inch Fixed Blade Runner - Incremental Difference Relative to CLIN 0504AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0604AD
(Optional)
Supply Embedded Draft Tube Liner Transition Section for 327-Inch Fixed Blade Runner - Incremental Difference Relative to CLIN 0504AA (Optional)
1 JOB S $________
Construction method as shown on proposal drawings.
TBD tons of carbon steel (portions not exposed to water and appurtenances) @ $___/ton
TBD tons of martensitic stainless steel (portion exposed to water and appurtenances) @ $___/ton
Percent of total bid item price that is labor: ___%
1 ton = 2,000 U.S. pounds finished material weight
0605AA
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 309-Inch Fixed Blade
1 JOB C $________ TBD
00 21 00-22
Runner (Base Requirement)
0605AB
(Optional)
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 319-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0505AA
(Optional)
1 JOB C $________ TBD
0605AC
(Optional)
Modify Existing Draft Tube Liner Without Demolition and Install Permanent Draft Tube Liner Transition Section for 327-Inch Fixed Blade Runner - Incremental Difference Relative to
CLIN 0505AA
(Optional)
1 JOB C $________ TBD
0605AD
(Optional)
Install Embedded Draft…