FOSTER ELECTRICAL RELIABILITY UPGRADES Federal contract opportunity
Solicitation number
W9127N20R0060
Issued by
Department of the Army Corps of Engineers Engineering District Portland

About this file

This document provides an amendment to a solicitation for electrical reliability upgrades at Foster Dam and Powerhouse. The amendment updates specification sections to replace references to outdated IEEE standards and extends the proposal due date from August 23, 2021 to August 26, 2021 at 2:00 PM PDT. The related federal contract opportunity seeks a contractor to replace aging electrical equipment at Foster Dam and Powerhouse for the U.S. Army Corps of Engineers, Portland District. Work includes replacing main unit breakers, station service equipment, station service transformers, powerhouse motor control centers, 480V switchgear, the DC system including a new battery bank, preferred AC equipment, and associated protection and controls.

View the file

Other files for this federal contract opportunity

Other files attached to FOSTER ELECTRICAL RELIABILITY UPGRADES, newest first.
File Type Posted
W9127N21R0060 0004.pdf PDF
Foster ERU Inquiry Pictures.pdf PDF
W9127N21R0060 0003.pdf PDF
Site Visit Attendance.pdf PDF
W9127N21R0060 0001.pdf PDF
Standard Form 24 - Bid Bond.pdf PDF
Brand Name Justification.pdf PDF
Attachment A - Offeror Experience Form.pdf PDF
W9127N21R0060.pdf PDF
Attachment C - Small Business Participation Commitment Document.pdf PDF
Foster ERU Reference Dwgs 22 May 2020.pdf PDF
FOSTER ERU_COLOR_072321 Contract Dwgs.pdf PDF
Attachment B - Past Performance Questionaire.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment serves to update specification section 26 13 13 SEE CONTINUATION PAGE and to extend the proposal due date to August 26, 2021 at 2:00 PM PDT

All other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N21R0060

X 9B. DATED (SEE ITEM 11)

23-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Aug-2021

CODE

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N21R0060

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

CONTINUATION PAGE

SECTION 26 13 13.00 26 Paragraph 1.2 Which read;

IEEE C37.013 (1997; R 2008) Standard for AC

High-Voltage Generator Circuit Breakers Rated on a Symmetrical Current Basis

Shall now read:

IEEE C37.013 NOT USED

SECTION 26 13 13.00 26 Paragraph 2.2.1 Which read;

The circuit breakers will be drawout cubicle switchgear as indicated on the contract drawings and shall be arranged to match up with the existing 5kV metal-enclosed bus at the top using maximum 36-inch wide sections. The standard phasing within equipment housings for AC power circuits is A-B-C from left to right, A-B-C from top to bottom, or A-B-C from front to back, when facing the front of the equipment. Power cables in conduit will enter the switchgear from the top and bottom as shown. Bottoms must be open to the maximum extend practicable to allow for variations in cable entry from existing embedded conduits. Furnish all necessary material and instructions for connection of the switchgear to the terminations. Where power cable terminations are indicated, provide sufficient space for terminating the cables with medium-voltage cable terminations. Each breaker must have provisions for remote manual operation. Provide remote racking provisions for the breaker cubicles. Prepare and submit outline drawings, assembly and detail drawings, schematic diagrams and connection diagrams as described in paragraph "SUBMITTALS".

Shall now read;

The circuit breakers will be drawout cubicle switchgear as indicated on the contract drawings and shall be arranged to match up with the existing 5kV metal-enclosed bus at the top using minimum section width 26 inches to match up with existing nonsegregated-phase bus duct connections as shown in the Contract Drawings. If for some reason wider switchgear is necessary to meet the ratings specified in paragraph 2.3.2, the Contractor must include modifications to the existing nonsegregated-phase bus duct to accommodate these connections. The standard phasing within equipment housings for AC power circuits is A-B-C from left to right, A-B-C from top to bottom, or A-B- C from front to back, when facing the front of the equipment. Power cables in

W9127N21R0060 conduit will enter the switchgear from the top and bottom as shown. Bottoms must be open to the maximum extend practicable to allow for variations in cable entry from existing embedded conduits. Furnish all necessary material and instructions for connection of the switchgear to the terminations. Where power cable terminations are indicated, provide sufficient space for terminating the cables with medium-voltage cable terminations. Each breaker must have provisions for remote manual operation. Provide remote racking provisions for the breaker cubicles. Prepare and submit outline drawings, assembly and detail drawings, schematic diagrams and connection diagrams as described in paragraph "SUBMITTALS".

SECTION 26 13 13.00 26 Paragraph 2.3.1 Which read;

Except as otherwise specified, the circuit breakers must conform to the applicable requirements of IEEE C37.010, IEEE C37.013 IEEE C37.04, IEEE C37.06, IEEE C37.09, IEEE C37.20.2, NEMA C37.55, and IEEE C37.100. Provide documentation substantiating that the circuit breaker design and assemblies are ANSI certified. Each circuit breaker is to be of the electrically operated, metal-clad, vacuum type suitable for indoor 60-Hz service. The full-load temperature rise must not exceed the limits established in IEEE C37.20.2. Ratings are as defined in IEEE C37.04 Part 5, and as supplemented below.

Shall now read;

Except as otherwise specified, the circuit breakers must conform to the applicable requirements of IEEE C37.010, IEEE C37.04, IEEE C37.06, IEEE C37.09, IEEE C37.20.2, NEMA C37.55, and IEEE C37.100. Provide documentation substantiating that the circuit breaker design and assemblies are ANSI certified. Each circuit breaker is to be of the electrically operated, metal-clad, vacuum type suitable for indoor 60-Hz service. The full-load temperature rise must not exceed the limits established in IEEE C37.20.2.

Ratings are as defined in IEEE C37.04 Part 5, and as supplemented below.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 23-Aug-2021 02:00 PM to 26-Aug-2021 02:00 PM.

(End of Summary of Changes)