W9127N21R0060.pdf
PDF 9 MB Posted
- Attached to
- FOSTER ELECTRICAL RELIABILITY UPGRADES Federal contract opportunity
- Solicitation number
- W9127N20R0060
About this file
This federal solicitation requests proposals for the Foster Electrical Reliability Upgrades project. The U.S. Army Corps of Engineers, Portland District requires a contractor to replace aging electrical equipment at Foster Dam and Powerhouse that is over 40 years old, including replacing 4160V switchgear, 480V switchgear and transformers, motor control centers, DC systems, and related components. Proposals are due by August 23, 2021. The award will be a firm-fixed-price construction contract for between $5-10 million. The solicitation instructs offerors on proposal requirements, evaluation factors, and provides templates for price proposals, representations and certifications, and past performance questionnaires.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9127N21R0060 0004.pdf | ||
| Foster ERU Inquiry Pictures.pdf | ||
| W9127N21R0060 0003.pdf | ||
| W9127N21R0060 0002.pdf | ||
| Site Visit Attendance.pdf | ||
| W9127N21R0060 0001.pdf | ||
| Standard Form 24 - Bid Bond.pdf | ||
| Brand Name Justification.pdf | ||
| Attachment A - Offeror Experience Form.pdf | ||
| Attachment C - Small Business Participation Commitment Document.pdf | ||
| Attachment B - Past Performance Questionaire.pdf | ||
| Foster ERU Reference Dwgs 22 May 2020.pdf | ||
| FOSTER ERU_COLOR_072321 Contract Dwgs.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
W9127N21R0060
FOSTER DAM
LINN COUNTY, OREGON
FOSTER DAM ELECTRICAL RELIABILITY UPGRADES
PROJECT MANUAL
TOC-1
FOSTER DAM ELECTRICAL RELIABILITY UPGRADES
TABLE OF CONTENTS
00 10 00 SOLICITATION, OFFER, AND AWARD (SF 1442)
SF 30 INFORMATION ON AMENDMENT: NOT USED
00 10 00 SOLICITATION
00 21 00 INSTRUCTIONS
00 45 00 REPRESENTATION AND CERTIFICATIONS
00 72 00 GENERAL CONDITIONS
00 73 00 SUPPLEMENTARY CONDITIONS
GENERAL AND TECHNICAL SPECIFICATION REQUIREMENTS
ATTACHMENTS
A1: Submittal Register (ENG FORM 4288-R)
A2: Transmittal Form (ENG FORM 4025-R)
A3: Construction Project Identification Sign
A4: Spill Emergency - Initial Report Form
A5: Hazardous Energy Control Program
A6: Oregon Wage Rates
00 21 16 INSTRUCTINS TO PROPORSES
00 70 00 CONDITIONS OF THE CONTRACT
A7: Notice to Large Business Subcontracting Plan
Project Title: Foster Dam Electrical Reliability Upgrades
Location: Foster Dam, Linn County, Oregon
Magnitude of Construction: $5,000,000 to $10,000,000
Socio-Economic Considerations: None
CORY R PFENNING 503-808-4398
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
23-Jul-2021
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 Aug 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
12:00 AM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W9127N21R0060 65
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Mobilization and Demobilization
FFP
Mobilization and demobilization in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job
Remove Existing SP & SQ Switchgear
FFP
Remove existing SP and SQ switchgear and substation transformer, complete with conduits and feeders in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
00 10 00-3
0003 1 Job
Remove Existing Motor Control Centers
FFP
Remove existing motor control centers DQ1 and CQ1; panels CQ2, CQ3, and CQ4, complete with conduits and feeders in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 1 Job
Remove Existing Diesel Engine-Generator
FFP
Remove existing diesel engine-generator, fuel tank, and exhaust system, including conduit and feeder in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-4
0005 1 Job
Remove Existing DC & AC Equipment
FFP
Remove existing DC and preferred AC equipment including battery, charger, inverter, and M-G sets in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0006 1 Job
Remove Existing ER Cabinets
FFP
Remove existing ER cabinets, complete with wiring, in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-5
0007 1 Job
175kW 480Volt Generator Install
FFP
In accordance with contract specifications, furnish and install New 175kW 480 Volt Diesel Engine-Generator, Automatic Transfer Switch, Manual Transfer Switch, and Load Bank, Complete with Wiring, Conduits and Feeders, Fuel Tanks, Tank Platform, Load Bank Breaker, and Structural Modifications FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0008 1 Job
4160 Volt SP Switchgear
FFP
In accordance with contract specifications, furnish and install 4160 Volt SP switchgear, complete with wiring, relays, meters, controls, control boards, autosynchronizers, 4160 volt bus duct modifications, and conduits and feeders to
SQ.
FOB: Destination
PSC CD: Z2KA
00 10 00-6
0009 1 Job
480 Volt SQ Switchgear and Substation
FFP
Furnish and install new 480 Volt SQ switchgear and substation transformers, complete with relays and meters, wiring, and conduits and feeders in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0010 1 Job
480 Volt Motor Control Centers
FFP
In accordance with contract specifications, furnish and install new 480 volt motor control centers DQ1, CQ1.1, and CQ1.2 complete with automatic bus transfer provisions; and 480 volt panels CQ2, CQ3 and CQ4, complete with wiring, relays, meters, starters, conduits and feeders.
FOB: Destination
PSC CD: Z2KA
00 10 00-7
0011 1 Job
DC & Preferred AC Equipment
FFP
Furnish and install new DC and preferred AC equipment, complete with wiring, conduits, feeders, battery, chargers, inverters, panelboards, and SB switchboard in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0012 1 Job
New ER Cabinets with Wiring
FFP
Furnish and install new ER cabinets, complete with wiring in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-8
0013 1 Job
Switchgear Erecting Engineer
FFP
Furnish the services of the SP switchgear manufacturer's erecting engineer in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0014 1 Job
High Resistance Grounding Systems
FFP
Furnish and install new high resistance grounding systems in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-9
0015 1 Job
Asbestos Survey, Sample, and Submittals
FFP
Asbestos survey, sample, and submittals in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0016 1 Job
Training
FFP
Contractor-furnished training of government personnel in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0017 1 Job
Battery Room Ventilation Upgrade
FFP
Battery room ventilation upgrade in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-10
0018 1 Job
Replace Existing Air Compressors
FFP
Replace existing air compressors in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0019 1 Job
Provide Waterstop Seal at Contraction
FFP
Provide Waterstop Seal at Contraction Joint in accordance with contract specifications.
FOB: Destination
PSC CD: Z2KA
00 10 00-11
OPTION Removal and Disposal of Asbestos
FFP
Removal and Disposal of Asbestos Containing Materials in accordance with contract specifications.
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0020AA 50 Pound OPTION First 50 Pounds
FFP
First 50 Pounds of asbestos removal. (Quantitiy Estimated) FOB: Destination
PSC CD: Z2KA
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0020AB 50 Pound OPTION Over 50 Pounds
FFP
Over 50 Pounds of asbestos removal. Not to exceed a total of 100 pounds (Quantitiy Estimated) FOB: Destination
PSC CD: Z2KA
00 10 00-12
Section 00 21 00 - Instructions
CLAUSES INCORPORATED BY REFERENCE
52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 252.215-7008 Only One Offer JUL 2019
CLAUSES INCORPORATED BY FULL TEXT
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision--
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that--
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record ``Active''.
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
00 21 00-1 http://www.sam.gov/
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of Provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Priced contract resulting from this solicitation.
(End of provision)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
00 21 00-2 https://www.sam.gov/
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20% (percent) of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE – Portland District
ATTN: CECT-NWP-C
PO BOX 2946
Portland, OR 97208-2946
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
00 21 00-3
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- 11 August 2021 at 10:00 AM PDT
(c) Participants will meet at-- Foster Dam, Foster Dam Rd., Sweet Home, OR
(d) Additional Site visit requirements
(1) All prospective offerors intending to attend the site visit must send an RSVP to Cory Pfenning, Contract Specialist at cory.r.pfenning@usace.army.mil and Adam White, Electrical Engineer at Adam.J.White@usace.army.mil before 2 August 2021 at 3:00 PM PDT with the following information
(i) Company name
(ii) Number of attendees
(iii) Name of each attendee
(iv) Citizenship of each attendee (Only U.S. citizens will be permitted to attend.)
** Approval of late attendee submissions or requests to change attendees after 2 August 2021 shall be at the discretion of the government and may be rejected.
(2) All prospective offerors intending to attend the site visit shall evaluate themselves for the following signs/symptoms of COVID-19 prior to departing to attend the site visit:
(i) Have you had a temperature over 100.4 in the past 72 hours?
(ii) Do you have the following symptoms:
- Fever or chills
- Cough
- Shortness of breath or difficulty breathing
- Fatigue
- Muscle or body aches
- Headache
- New loss of taste or smell
- Sore throat
- Congestion or runny nose
- Nausea or vomiting
- Diarrhea
(iii) Have you had close contact with or cared for someone with COVID-19 in the last 14 days?
(iv) Anyone answering yes to these question must not attend the site visit.
(3) The use of cloth face covings to cover your nose and mouth will be required the entire time during the site visit.
(4) All site visit attendees will be required to maintain social distancing of six (6) feet to the maximum extent possible.
(5) The following safety gear is required at the site: Steel toed boots, Hardhats, Safety Vests, and Safety Glasses.
(6) Each individual must have picture identification on his/her person while at the project site. There can be no substitutions of one individual for another. If an individual arrives at the site visit without having called ahead of time and/or without picture identification, that individual may not be allowed on the project.
00 21 00-4
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
5152.211-9000
5152.211-9000 EVALUATION OF SUBLINE ITEMS (DEC 2019)
Item No. 00020 is subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its subline items.
00 21 00-5
Section 00 21 16 - Instructions to Proposers
INSTRUCTIONS, CONDITIONS, AND
A. BASIS FOR AWARD.
(1) This is an unrestricted competitive acquisition using Best Value Tradeoff (BVTO) source selection procedures.
The Government intends to award a single, firm-fixed price construction contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the evaluation factors in the solicitation.
Offerors shall submit a technical proposal and a price proposal. The evaluation results of the non-price and price proposals will determine an awardee. All non-price factors are approximately equal in importance. All non-price evaluation factors other than price, when combined, are significantly more important than price.
(2) The Government intends to make an award without discussions but reserves the right to conduct discussions should discussions prove to be necessary or advantageous to the Government. Because the Government does not intend to hold discussions, offerors are encouraged to include their best pricing in their initial proposal.
(3) All proposals received will stand alone and be considered complete and final. The Government will not consider any information or data incorporated by reference or otherwise referred to. The successful offeror will be selected solely on the basis of the evaluation factors set forth below. Elaborate proposals, color brochures, and other excesses are discouraged.
(4) Joint Ventures (JV). A joint venture is defined as follows: a legal business entity formed between two or more companies (parties) to undertake the performance activities of a contract together. This does not include other arrangements such as “teaming agreements” or “strategic alliance” which are not recognized as bona fide joint ventures for the purposes of this solicitation. A company that is part of a joint venture shall submit a legally binding joint venture agreement. Joint ventures shall include a copy of the legal joint venture agreement signed by an authorized officer from each of the firms comprising the joint venture with the chief executive of each entity identified. If submitting a proposal as a joint venture, the experience and past performance of each of the joint venture partners can be submitted for the joint venture entity. The experience for each joint venture partner will be considered the experience of the joint venture entity. Page and project form limits apply to the joint venture as a whole. Prospective offerors that submit proposals may not change their firm (including Letters of Commitment (LOC) and proposed subcontractors) or their Joint Venture firms, if selected to submit Final Proposal Revisions
(FPR).
(5) The successful offeror will be selected solely on the basis of the evaluation factors set forth below. Accordingly, proposals submitted in response to this solicitation should provide clear, complete, concise, and straightforward responses to the evaluation factors. The offeror’s technical proposal will be incorporated into the awarded contract.
B. Definitions.
The Government will use the following definitions when evaluating proposals:
Deficiency- A material failure of a proposal to meet a Government requirement or a combination of weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
Strength- An aspect of an Offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Significant Strength- An aspect of an Offeror's proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
00 21 16-1
Weakness- A flaw in the proposal that increases the risk of unsuccessful contract performance. See FAR 15.001.
Significant Weakness- in the proposal is a flaw that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
5. SUBMISSION OF PROPOSALS AND EVALUATION
A. Administrative Details and General Instructions: Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442.
(1) General Proposal Format. The proposal shall be in electronic Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the proposal table of contents.
Title Page. Each copy must include the offeror’s name and address, phone number and email address, title of the solicitation, solicitation number and date of submittal clearly identified on the front cover.
Table of Contents. Each volume of the proposal shall contain a detailed and complete table of contents.
Submissions. PDF pages containing text are expected to be 8 ½ x 11 inches with at least one-inch margins at the top, bottom, and both sides. Paragraphs should be separated by at least one blank line. A standard 11-point font in either Arial or Times New Roman is required. The use of hyperlinks in proposals is prohibited.
Organization charts or schedules. An 11” x 17” PDF format may be used. Larger format drawings or tables may also be used.
All information must be confined to the appropriate volume. Each volume of the proposal is expected to contain a table of contents, summary section with a brief abstract of the volume, and the narrative discussion.
(2) Proposal Content Limitations.
The offeror must confine the proposal to relevant information and documentation sufficient to provide an adequate basis for evaluation. Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of the proposal. The page count is at the discretion of the offeror; however, the proposal may not be more than 25 typewritten (single page only) pages total. The 25-page limit does NOT include past performance information submitted under Factor 2. Evaluation of the non-price factors will end on the 25th page submitted.
Extraneous information provided in the proposals will not be considered in the evaluations;
therefore, the offeror should only provide information that satisfies the solicitation requirements.
Merely restating the specifications without sufficient elaboration demonstrates a lack of understanding of the requirement.
DO NOT cross reference past performance information. It is acceptable to repeat data, project information or experience in more than one non-price area as long as it satisfies the requirements of the factor.
Proprietary information must be clearly marked.
00 21 16-2
B. Content of Proposals: All proposals must be prepared in two volumes: A technical proposal (Volume I), a price proposal (Volume II). Each of the volumes shall be separate and complete in itself so that evaluation of one may be accomplished independently from evaluation of the other. The technical proposal (Volume I) must not contain reference to price. The narrative and content structure of the proposal shall follow the format shown under Volume I below. Offerors that fail to submit a complete proposal may be excluded and thus receive no further consideration for award.
(1) Technical Proposal, Volume I: Provide one (1) electronic proposal in Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader. Volume I shall consist of information for the three (3) factors, listed in tabular form, as noted below. Repeating or restating the specifications without sufficient elaboration will be determined to show a lack of understanding of the requirement.
Volume I – Technical (Non-Price) Factors:
Tab 1 – Factor 1 – Experience
Tab 2 – Factor 2 – Past Performance
Tab 3 – Factor 3 – Work Plan
Tab 4 – Factor 4 – Small Business Participation
(2) Price Proposal, Volume II: Provide one (1) electronic proposal in Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader of a complete and detailed Price Proposal on the forms provided in the solicitation. Provide pricing and complete all line items on Standard Form 1442 (SF 1442). The price proposal must be prepared in accordance with the following and must include:
Tab 1 – SF1442, Solicitation, Offer, and Award.
The SF1442 shall be filled out completely by the offeror and signed by an official that is authorized to bind the company. The offeror shall also acknowledge all amendments to the solicitation in accordance with the instructions on the Standard Form 30 or Block 19 of SF1442.
Tab 2 – Section 00 10 00, Proposal Price / Bid Schedule.
The offeror shall fully complete this section.
Tab 3 – Representations, Certifications and other Statements of Offerors.
The offeror shall complete all representations and certifications in Section 00 45 00 and also ensure current registration and completed/updated Annual Representations and Certifications on the System for Award Management (SAM) website, www.sam.gov.
Tab 4 – Banking and Bonding Points of Contact.
The Government is required to determine Contractor’s responsibility; the offeror shall provide contact information (company name, point of contact, address, email and phone number) for the offeror’s bank and bonding institutions.
Tab 5 – Bid/Offer Guarantee. The Bid Bond shall be at least 20% of the bid price but shall not exceed $3 million. See FAR 52.228-1 – Bid Guarantee.
Tab 6 – Small Business Subcontracting Plan (Large Businesses Only). The plan must express goals in terms of percentages of total planned subcontracting dollars and must be comparable to the dollar commitments in the small business participation commitment document, if applicable.
See 52.219-8, “Utilization of Small Business Concerns (Nov 2016)” and 52.219-9, "Small Business Subcontracting Plan (Jan 2017).
00 21 16-3
Submission of Proposals: Proposals are due no later than the time and date established in Block 13, SF 1442.
There will not be a public proposal opening.
Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable. Proposals received after the date and time in block 13A of the solicitation will be considered late and will not be considered for award.
Offeror shall submit its proposal via email to Cory Pfenning, Cory.R.Pfenning@usace.army.mil, and Kristina Morrow, Kristina.K.Morrow@usace.army.mil. Offerors should enter a description for every file submitted. For files over 20 megabytes (MB) the offeror shall break the file into smaller files sent via separate emails, each marked to identify which number the email is relative to the total number of emails submitted (i.e. “one of four”). Once all the emails submitted have been received, the Government will confirm receipt via return email.
If an offeror submits multiple proposals, the Government will only consider the last proposal submitted prior to the due date and time.
The electronic proposal shall be in Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the table of contents.
Do not assume submission will be instantaneous. File size and number of files submitted shall be considered.
Offeror/Teammate/Subcontractors should allow adequate time for submission completion because the entire proposal (i.e. offerors submission and all teammate/subcontractor(s) independent submissions) must be received by the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable.
To avoid rejection of an offer, the offeror must make every effort to ensure its electronic submission is virus-free. Proposals, or portions thereof, submitted with the presence of a virus or which are otherwise unreadable will be treated as unreadable pursuant to FAR 15.207(c).
The requirement that an original and copy(ies) be submitted as found in block 13A of the SF1442 is satisfied through the electronic submission. Additionally, electronic submission of the bid guarantee, when a bid guarantee is required, is due with the bid submission (mailing a bid guarantee is not allowed).
6. EVALUATION FACTORS
Volume I – Technical (Non-Price) Submission Requirements and Evaluation Method:
FACTOR 1 (TAB 1) – Experience
Submission Requirements:
The offeror shall submit information for at least two and no more than four complete or substantially complete projects that demonstrate the offeror’s experience performing projects similar in size, scope, and complexity to the work required by this solicitation. Each project must be completed or be substantially completed within the last ten (10) years.
“Substantially complete” is defined as having completed more than 75% of the project work at the time of proposal submission. If an offeror submits a project that it represents is “substantially complete,” the offeror must reasonably explain why the project is considered at least 75% complete. If an offeror submits an ongoing project without providing an accompanying reasonable explanation that explains how the project is at least 75% complete, the Government reserves the right to reject the project.
00 21 16-4
Information submitted for each project must include the information outlined in Attachment A, Offeror’s Experience Form.
A maximum of four (4) projects will be evaluated. If an offeror disregards these instructions and submits more than four projects, only the first four projects will be evaluated. Offerors should describe each project with enough detail to ensure that the Government can meaningfully assess how well the projects submitted meet the evaluation criteria outlined below.
Instructions on the use of major subcontractor experience: Offerors may use the experience of major subcontractors to demonstrate experience. A “major subcontractor” is a subcontractor that the offeror proposes to perform 25% or more of the work required under the solicitation. If the offeror submits experience of a major subcontractor, the offeror must submit a letter of commitment from the subcontractor on the letterhead of the firm to be subcontracted. The letter of commitment must be signed by an authorized individual from the subcontractor that is proposed to perform the work. If a letter of commitment is not submitted, the experience will not be considered.
Evaluation Method:
The Government will rate this factor using the combined technical/risk rating as follows:
COLOR RATING DESCRIPTION
Blue Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
TECHNICAL RISK RATING METHOD
ADJECTIVAL RATING DESCRIPTION
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance.
Normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties.
Moderate
Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance. Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.
High
Proposal contains a significant weakness or combination of weaknesses which is likely to cause significant disruption of schedule, increased cost or degradation of performance. Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
00 21 16-5
Unacceptable Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
In determining strengths and weaknesses, the Government will consider the following:
• The extent to which the offeror’s submitted projects demonstrate work with medium voltage (5kv to 35kv) switchgear.
• The extent to which the offeror’s submitted projects demonstrate experience related to demolition and installation of emergency diesel generators.
• The extent to which the offeror’s submitted projects demonstrate coordination of multiple major features necessitating simultaneous installation, similar to that required by this project. Examples of major features include:
o Switchgear (5kv to 35kv) o Station batteries (125V) o Temporary power (emergency diesel generator).
• The extent to which the offeror’s submitted projects demonstrate experience in developing technical documents such as Operations & Maintenance Manuals and Commissioning Plans.
• The extent to which the offeror’s submitted projects demonstrate experience working in powerhouses.
FACTOR 2 (TAB 2) – Past Performance
Submission Requirements:
The offeror shall provide past performance information for each project listed by the offeror under Factor 1
– Experience, including any projects performed by a major subcontractor.
• If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, the offeror shall submit it with the proposal.
• If there is not a completed CPARS evaluation, the offeror shall submit a Past Performance Questionnaire (PPQ) for the project. See Attachment B. Do not submit a PPQ when a completed CPARS is available.
o If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s).
o Offerors should follow up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Cory Pfenning, via email at Cory.R.Pfenning@usace.army.mil prior to proposal closing date. The offerors shall instruct the clients to refer to the solicitation number in the subject line.
o PPQs are source selection materials. All successfully submitted PPQs will receive an email confirmation upon receipt. If the offeror does not receive the confirmation, it is the offeror’s responsibility to follow up to ensure the government has received the information.
Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for
00 21 16-6 mailto:Cory.R.Pfenning@usace.army.mil other procurements. However, this does not preclude the Government from utilizing previously submitted past performance information in the past performance evaluation.
Offerors may provide explanation on problems encountered on past projects and the corrective actions taken by the offeror.
In addition to the above, the Government may review other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the PPIRS (Past Performance Information Retrieval System) including CPARS, using all CAGE/DUNS (Commercial and Government Entity Code/Data Universal Numbering System) numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), FAPIIS (Federal Awardee Performance and Integrity Information System), Electronic Subcontract Reporting System (eSRS), or other databases, telephone interviews with organizations familiar with the offeror’s performance, Government personnel with personal knowledge of the offeror’s performance capability, and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate, and complete past performance information rests with the offeror.
Evaluation Method:
The Government seeks a contractor who maintains a strong commitment to customer satisfaction and superior performance. It is the offeror’s responsibility to affirmatively document these qualities in his technical proposal. In doing so, be mindful that “past performance” and “experience” are not identical. Experience measures what the offeror has done and how many times, or for how long, the offeror has done it. Past performance, however, measures how well the offeror has performed.
The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. The recency and relevancy of the information, source of the information, context of the data, and general trends in the contractor’s performance shall be considered. These are combined to establish one performance confidence assessment rating for each offeror.
There are three aspects to the past performance evaluation: recency, relevancy (including text of data), and quality (including general trends in contractor performance and source of information).
The first aspect is to evaluate the recency of the offeror’s past performance. For this solicitation, recent projects are those completed or substantially completed (as defined above) within ten (10) years of the date that proposals are due.
The second aspect is to determine how relevant a recent effort accomplished by the offeror is to the work required by the solicitation. There are four levels of relevancy as shown in the table below.
PAST PERFORMANCE RELEVANCY
RATING DESCRIPTION
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
00 21 16-7
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
In assessing the relevancy of the offeror’s past performance, the Government will consider the following:
• The extent to which a submitted project demonstrates work with medium voltage (5kv to 35kv) switchgear.
• The extent to which a submitted project demonstrates experience related to demolition and installation of emergency diesel generators.
• The extent to which a submitted project demonstrates coordination of multiple major features necessitating simultaneous installation, similar to that required by this project.
Examples of major features include:
o Switchgear (5kv to 35kv) o Station batteries (125V) o Temporary power (emergency diesel generator).
• The extent to which a submitted project demonstrates experience in developing technical documents such as Operations & Maintenance Manuals and Commissioning Plans.
• The extent to which a submitted project demonstrates experience working in a powerhouse.
More relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
The third aspect of the past performance is to determine how well the offeror performed on its past performance projects. If any performance issues are identified, the Government will consider the number, type and severity of the problems and effectiveness of corrective actions taken.
Based on a consideration of those three aspects for each project, the Government will assign a final Performance Confidence Assessment Rating for this factor. The Government will review the past performance information and determine the quality and usefulness as it applies to performance confidence assessment. In conducting a performance confidence assessment, each offeror shall be assigned one of the ratings using the table below.
PERFORMANCE CONFIDENCE ASSESSMENT
RATING DESCRIPTION
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
00 21 16-8
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
In the case of an offeror without a record of relevant past performance or for which information on past performance is not available, the offeror will not be evaluated favorably or unfavorably on past performance, and therefore may receive a “Neutral Confidence” rating.
FACTOR 3 (TAB 3) – Work Plan
Submission Requirements:
The offeror shall submit a Work Plan that demonstrates the offeror’s approach to performing the required work as outlined in the specifications.
The Work Plan must include, at a minimum:
• Gantt Chart: Submit a project schedule in Gantt chart format using the critical path method
(MS Project or Primavera software). Provide enough detail and tasks to adequately cover the scope of the project and the activities required to successfully describe and complete the project as required by the solicitation. Items of particular interest are:
- Design/submittal order milestones for major features;
- Mobilization;
- Main unit generators returned to service;
- Returning powerhouse loads to normal power (this may happen in many phases, each one should be identified);
- Emergency diesel power available for use;
- Commissioning plan(s) submitted & approved;
- As constructed drawings and O&M manuals submitted;
- De-mobilization.
• Narrative: Submit a narrative detailing the plan (means and methods) for completing the work, meeting the schedule, and the challenges and site constraints that may be encountered during construction. Describe the proposed mitigation measures for the identified challenges and constraints to successfully complete the required major features of work described below.
For each feature of work, identify who is performing the work (offeror or a subcontractor).
- Demolition and installation of major features with sequencing (i.e., if demolition/installation will be occurring…
This is the start of the file's text. The full file is on GovTribe.