AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to update the plans and spec sections listed below . All other terms and conditions remain the same.

Plans changes:

Sheets S-107, A-412, A-413, A-414, AD402, E-102, E-103, E-104, E-405 are updated.

Specif ication changes:

03 62 16.00 28 (added new spec section to contract); 07 22 00.00 28 Paragraph 1.1 updated; 07 18 00.00 28 Paragraphs 1.3 and 1.7.3 updated; 07 56 00.10 28 Paragraph 1.1 and 1.8 updated; 26 05 19.00 28 (new ly added spec); included Updated Submittal Register

The updated plans and specif ications are attached and replace the old versions in their entirety.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Jan-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N19B0004

X 9B. DATED (SEE ITEM 11)

13-Dec-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Jan-2019

CODE

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N19B0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

John Day Dam Powerhouse and Ancillary Roofs Replacement

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00.00 25 CONTRACT ADMINISTRATION DATA

01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS

01 11 00.00 25 SUMMARY OF WORK

01 22 00.00 25 MEASUREMENT AND PAYMENT

01 32 01.00 25 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 25 QUALITY CONTROL

01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 23.00 25 OPERATION AND MAINTENANCE DATA

01 78 39.00 25 PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

02 82 14.00 28 ASBESTOS CONTAINING MATERIAL (ACM) REMOVAL AND DISPOSAL

02 83 20.00 25 LEAD BASE PAINT (LBP) ABATEMENT, REMOVAL, AND DISPOSAL

DIVISION 03 - CONCRETE

03 01 32.00 25 CONCRETE REHABILITATION FOR CIVIL WORKS AND CORE DRILL

03 62 16.00 28 CHEMICAL GROUTING

DIVISION 05 - METALS

05 50 00.10 28 METAL: MISCELLANEOUS AND FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.10 28 ROOF REMOVAL AND DISPOSAL

07 18 00.00 28 TRAFFIC-BEARING POLYURETHANE WATERPROOF SYSTEM AND

POLYURETHANE JOINT SEALANT

07 22 00.00 28 ROOF INSULATION

07 53 23.00 28 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING

07 56 00.10 28 PMMA FLUID-APPLIED ROOFING

07 61 00.00 28 SHEET METAL FLASHING

07 72 00.00 28 ROOF ACCESSORIES

07 92 00.00 28 JOINT SEALANTS

DIVISION 09 - FINISHES

09 22 16.00 28 NON-STRUCTURAL METAL FRAMING

DIVISION 22 - PLUMBING

22 00 00.00 25 PLUMBING, GENERAL PURPOSE

DIVISION 26 - ELECTRICAL

26 05 00.00 28 GENERAL ELECTRICAL WORK

26 05 19.00 28 WIRE AND CABLE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 03 - CONCRETE

SECTION 03 62 16.00 28

CHEMICAL GROUTING

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 CHEMICAL GROUT PLACEMENT PLAN AND INSPECTION REPORTS

1.4 CERTIFICATION OF QUALIFICATIONS AND EXPERIENCE

1.4.1 Chemical Grout Manufacturer Qualifications

1.4.2 Chemical Grout Applicator Qualifications

PART 2 PRODUCTS

2.1 HYDROPHOBIC POLYURETHANE GROUT

2.2 DRY OAKUM

2.3 CLOSED-CELL BACKER ROD

2.4 MIXING WATER

PART 3 EXECUTION

3.1 REMOVAL OF OLD SEALANT AND CLEANING OF JOINTS

3.2 SEALING HORIZONTAL JOINTS

3.2.1 Sealant Injection Timeframe

3.2.2 Installing Closed-Cell Backer Rod

3.2.3 Injecting Chemical Grout

3.2.4 Patching the Injection Holes

3.2.5 Removing Excess Grout and Cleaning

3.3 PROTECTION AND CURING

-- End of Section Table of Contents --

SECTION 03 62 16.00 28 Page 1

ADDED BY AMENDMENT

AMD #0004

SECTION 03 62 16.00 28

CHEMICAL GROUTING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D1042-01a Test Method for Linear Dimensional Changes of Plastic under Accelerated Service Conditions

ASTM D2196 (2010) Standard Test Methods for Rheological Properties of Non-Newtonian Materials by Rotational (Brookfield type) Viscometer

ASTM D2939 (2003) Emulsified Bitumens Used as Protective Coatings

ASTM D3574 (2011) Standard Test Methods for Flexible Cellular Materials—Slab, Bonded, and Molded Urethane Foams

NSF INTERNATIONAL (NSF)

NSF/ANSI 60 (2012) Drinking Water Treatment Chemicals

- Health Effects

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Chemical Grout Placement and Inspection Reports; G

SD-03 Product Data

Hydrophobic Polyurethane Grout; G

Dry Oakum; G

Closed-Cell Backer Rod

SD-04 Samples

SECTION 03 62 16.00 28 Page 2

Hydrophobic Polyurethane Grout; G

Dry Oakum; G

SD-06 Test Reports

Chemical Grout Placement and Inspection Reports; G

SD-07 Certificates

Chemical Grout Manufacturer Qualifications; G

Certify that the manufacturer of the chemical grout meets requirements specified under paragraph entitled "Certification of Qualifications and Experience."

Chemical Grout Applicator Qualifications; G

Certify that applicator meets the requirements specified under paragraph entitled "Certification of Qualifications and Experience."

1.3 CHEMICAL GROUT PLACEMENT PLAN AND INSPECTION REPORTS

a. Provide examples of Chemical Grout Placement and Inspection Reports.

Show details of proposed methods of application with written instructions from the manufacturer for the use of accelerator.

b. Include a copy of records of inspections and tests as well as the records of corrective action taken. Include descriptions of preparation of cavities for placement of chemical grout; proper mixing, placement, expansion, and cure time of chemical grout.

1.4 CERTIFICATION OF QUALIFICATIONS AND EXPERIENCE

1.4.1 Chemical Grout Manufacturer Qualifications

The chemical grout manufacturer must have been successfully producing and marketing the specified materials for a minimum 10 years. A letter of testament directly from chemical grout manufacturer must be submitted as proof of experience. The letter must be prepared by a sales and marketing manager or technical services manager employed by the manufacturer and must contain contact information for that person.

1.4.2 Chemical Grout Applicator Qualifications

The applicator must submit proof of experience in the installation of chemical grout systems. Specifically, the applicator must provide proof of at least five years of experience with expansive foam chemical grout utilizing the installation methodologies required in this specification section. Along with the firm name and contact information, the applicator must submit a minimum five examples of projects where a similar type of chemical grout waterproofing system was used. Examples must include the names of the projects, descriptions of the chemical grout waterproofing process used for each project, and contact information for each client the waterproofing work was performed for. Additionally, the applicator must provide resumes of key employees who will be conducting and overseeing the actual installation work.

SECTION 03 62 16.00 28 Page 3

PART 2 PRODUCTS

2.1 HYDROPHOBIC POLYURETHANE GROUT

Provide a single-component injectable hydrophobic polyurethane resin for the purpose of creating flexible joint stopping material in horizontal joints. Saturated oakum rope must be placed to the back of monolith joints to confine hydrophilic polyurethane expansive foam chemical grout placement. Upon curing, the hydrophobic resin-soaked oakum must form a strong adhesion bond to the concrete surfaces it is contact with such that expansion of the chemical grout is contained. Hydrophobic polyurethane grout must meet or exceed the following material and performance properties:

Properties ASTM Test Value Units

Solids ASTM D2939 100 percent

Viscosity ASTM D2196 650 + OR - 200 cp at 77 degrees F

Uncured Density ASTM D3574 8.5 - 9.3 lbs/gal

Tensile Strength (Cured)

ASTM D3574 150 minimum psi

Elongation ASTM D3574 250 percent

Shrinkage ASTM D1042-01a <4 percent

2.2 DRY OAKUM

Dry oakum used for joint stopping shall be as recommended by the chemical grout manufacturer. It must be made from thoroughly carded jute fiber that is free from hard, coarse fibers and extraneous matter. Dry oakum must be manufactured in rope form with at least eight strands having a twist of approximately 1.25 turns per foot. Rope must be approximately 2-inches in diameter and weigh approximately 0.4 lbs. per foot and must be made such that it is possible to strip away jute fibers of smaller diameter as necessary to fit monolith joints of varying widths. Dry oakum must conform to Federal Specification HH-P-117 as published in the Federal Standard Stock Catalog, Section IV, Part 5.

SECTION 03 62 16.00 28 Page 4

2.3 CLOSED-CELL BACKER ROD

Closed-cell backer rod must be expanded, closed-cell polyethylene foam designed for use as filler or with cold-applied sealant. Diameter of backer rod must be sized 2-1/2 times the width of the joint it is used in.

2.4 MIXING WATER

Provide clean potable water complying with NSF/ANSI 60.

(NOTE: Only non-potable water will be available on site at the John Day Project.)

PART 3 EXECUTION

3.1 REMOVAL OF OLD SEALANT AND CLEANING OF JOINTS

Old joint sealant, joint backer, spalled concrete, rust and dirt must be completely removed from the existing horizontal joints to receive chemical grout. Open joints that are contaminated with grease or oil must be cleaned with a solvent approved by the chemical grout manufacturer.

Application of solvent shall be by means of clean, dry rags. Pouring solvent directly onto grease and oil contamination will not be allowed.

After removal of all old sealant and foreign material from a monolith joint, it must be vacuumed to remove all loose waste material or the joint must be blown clean with compressed air to remove all loose material. At the approval of the Government, high pressure water may be used for final joint cleaning where non-water cleaning methodologies do not provide adequate results. Before using high pressure water cleaning, the Contractor must prepare and submit a written plan for conducting the cleaning and mitigating water intrusion into the Powerhouse and adjacent galleries of the dam. If high pressure water cleaning is used, the Contractor must be fully responsible for immediately mopping up any water that gets inside the Powerhouse and adjacent galleries of the dam. The Contractor must also be fully responsible for repairing or restoring any Powerhouse equipment and finishes that are damaged by the water intrusion.

All cleaned joints must be inspected and approved by the Government before beginning grout installation.

3.2 SEALING HORIZONTAL JOINTS

3.2.1 Sealant Injection Timeframe

To ensure the chemical grout system maintains a watertight seal throughout seasonal cycles of expansion and contraction, it must be installed at the anticipated mid-point of joint movement. It is estimated that this will occur at John Day Dam in the early spring. Thus, as long as all required environmental conditions for installation are met, the Contractor must plan on injecting the chemical grout during this timeframe. Notify the COR of any delays necessary due to unsuitable installation conditions.

3.2.2 Installing Closed-Cell Backer Rod

Before installation of the closed-cell backer rod at the top of the monolith joints, ensure the joint is clear of all excess joint stopping material that may interfere with a uniform and complete application of the hydrophilic joint filling polyurethane grout. After cleaning, compress the closed-cell backer rod into the top of monolith joints to the depth indicated on the drawings. Ensure the backer rod is continuous in the

SECTION 03 62 16.00 28 Page 5 joint with no breaks or gaps.

3.2.3 Injecting Chemical Grout

As far as practicable, concrete must be wetted per the polyurethane grout manufacturer's recommendations before the grout is injected into the joint. Leave the tips off all of the injection ports that do not have grout in them to allow air and water to vent out of the joints. Pump the hydrophobic polyurethane resin into the injection ports by using increasing pressure to ensure the grout completely fills the joint. Do not increase the application pressure beyond that necessary to achieve grout flow through the joint. Strictly follow the manufacturer's recommendations for application during extreme temperatures.

3.2.4 Patching the Injection Holes

After grouting is complete, patch the injection holes to a minimum depth of 2 inches. The patching material must be an epoxy gel as recommended by the chemical grout manufacturer.

3.2.5 Removing Excess Grout and Cleaning

Remove excess chemical grout with scraping knives, grinding wheels or wire wheels. Removal and cleaning methodologies must minimize damage to existing concrete and steel finishes on the intake deck. A solvent recommended by the chemical grout manufacturer must be used to clean chemical grout from surfaces to receive the trafficable sealant system (See specification SECTION 07 18 00.00 28).

3.3 PROTECTION AND CURING

Protect freshly placed grout from premature drying and excessive cold or hot temperatures. Comply with manufacturer's requirements for cold-weather and hot-weather protection during curing. Additionally, new grouting work must be protected from foot and vehicle traffic until installation of the trafficable sealant system (See SECTION 07 18 00.00 28).

-- End of Section --

SECTION 03 62 16.00 28 Page 6

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

SECTION 07 18 00.00 28

TRAFFIC-BEARING POLYURETHANE WATERPROOF SYSTEM AND POLYURETHANE JOINT SEALANT

PART 1 GENERAL

1.1 REFERENCES

1.2 SCOPE

1.2.1 Design Requirements

1.2.2 Performance Requirements

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Qualification of Polyurethane Waterproof System Manufacturer

1.4.2 Qualification of Polyurethane Waterproof System Applicator

1.4.3 Pre-Work Conference

1.4.4 Moisture Content

1.5 DELIVERY, STORAGE, AND HANDLING

1.6 ENVIRONMENTAL CONDITIONS

1.7 WARRANTY

1.7.1 Sample Warranty

1.7.2 Polyurethane Waterproof System Manufacturer Warranty

1.7.3 Polyurethane Waterproofing System Installer Warranty

1.7.4 Continuance of Warranty

1.8 POLYURETHANE WATERPROOF SYSTEM SHOP DRAWINGS

1.9 MANUFACTURER'S INSTRUCTIONS

PART 2 PRODUCTS

2.1 POLYURETHANE WATERPROOF SYSTEM

2.1.1 System Primer

2.1.2 Polyurethane Base Coat

2.1.3 Polyurethane Intermediate (Broadcast) and Top Coats

2.1.4 Aggregate

2.1.5 Cleaning Solution/Solvent

2.2 POLYURETHANE JOINT SEALANT

PART 3 EXECUTION

3.1 PREPARATION

3.1.1 Preparation of Existing Surfaces

3.1.2 Protection of Installed Chemical Grout

3.1.3 Adhesion Testing for Substrates to Receive the Waterproof System

3.1.4 Repair and Leveling of Concrete

3.1.5 Joint Sealant

3.1.6 Primer Application

3.2 SPECIAL PRECAUTIONS

3.3 APPLICATION

3.3.1 Application Timeframe

3.3.2 Application of Base Coat

3.3.3 Application of Intermediate Coat and Aggregate

SECTION 07 18 00.00 28 Page 1

3.3.4 Application of Topcoat

3.3.5 Interruption of Work

3.4 FIELD QUALITY CONTROL

3.4.1 Moisture Test

3.4.2 Film Thickness

3.4.3 Warranty Inspection and Issuance

3.5 INSTRUCTIONS TO GOVERNMENT PERSONNEL

SECTION 07 18 00.00 28 Page 2

SECTION 07 18 00.00 28

TRAFFIC-BEARING POLYURETHANE WATERPROOF SYSTEM AND POLYURETHANE JOINT SEALANT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C639 (2001; R 2011) Rheological (Flow) Properties of Elastomeric Sealants

ASTM C661 (2015) Indentation Hardness of Elastomeric-Type Sealants by Means of a Durometer

ASTM C719 (2014) Adhesion and Cohesion of Elastomeric Joint Sealants Under Cyclic Movement (Hockman Cycle)

ASTM C792 (2004; R 2008) Effects of Heat Aging on Weight Loss, Cracking, and Chalking of Elastomeric Sealants

ASTM C793 (2005; R 2010) Effects of Accelerated Weathering on Elastomeric Joint Sealants

ASTM C794 (2015) Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants

ASTM C 957 (2015) Standard Specification for High-Solids Content, Cold Liquid-Applied Elastomeric Waterproofing Membrane With Integral Wearing Surface

ASTM C920 (2014a) Standard Specification for Elastomeric Joint Sealants

ASTM C1247 (2014) Standard Test Method for Durability of Sealants Exposed to Continuous Immersion in Liquids

ASTM D2240 (2005; R 2010) Standard Test Method for Rubber Property - Durometer Hardness

ASTM D4060 (2014) Abrasion Resistance of Organic Coatings by the Taber Abraser

ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic

SECTION 07 18 00.00 28 Page 3

Elastomers - Tension

ASTM D4541 (2017) Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers

1.2 SCOPE

The following specification is for a cold fluid-applied, polyurethane waterproofing system to be applied over the monolith joints on the intake deck at elevation 281.0 of the Powerhouse. The cured system must be suitable for service in light vehicle traffic areas.

1.2.1 Design Requirements

1.2.2 Performance Requirements

The installed free of defects including blistering, or voids; suitable for the climatic and traffic conditions of the installation.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals having an "I" designation are for information only. The following must be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Polyurethane Waterproof System Shop Drawings; G

Submit shop drawings of the fluid-applied polyurethane waterproof system showing the complete system installation at a typical monolith joint.

SD-03 Product Data

System Primer; G

Polyurethane Base Coat; G

Polyurethane Intermediate (Broadcast) and Top Coats; G

Aggregate; G

Cleaning Solution/Solvent

Polyurethane Joint Sealant; G

SD-04 Samples

Sample Warranty; G

Polyurethane Waterproof System; G

Submit a sample of the polyurethane waterproof system to include all required coatings, quartz aggregate and final color finish as required in this specification section for the complete installed system. The sample must be created on wood or steel backing not

SECTION 07 18 00.00 28 Page 4 less than 6 inches square in size.

SD-06 Test Reports

Adhesion Testing for Substrates to Receive the Waterproof System; G

SD-07 Certificates

Qualification of Polyurethane Waterproof System Manufacturer; G

Qualification of Polyurethane Waterproof System Applicator; G

SD-08 Manufacturer's Instructions

Polyurethane Waterproof System; G

SD-10 Operation and Maintenance Data

Polyurethane Waterproof System; G

Preprinted cleaning and maintenance instructions must be provided.

SD-11 Closeout Submittals

Warranty; G

Submit a ten year "No-Dollar-Limit" warranty for materials and a two year installer warranty.

Instructions To Government Personnel

Include copies of Material Safety Data Sheets for maintenance/repair materials.

1.4 QUALITY ASSURANCE

1.4.1 Qualification of Polyurethane Waterproof System Manufacturer

The polyurethane waterproof system manufacturer must have a minimum of 10 years experience in the manufacture the products specified in this section.

1.4.2 Qualification of Polyurethane Waterproof System Applicator

a. The applicator specializing in performing the work of this section must have a minimum of three years documented experience and be approved by system manufacturer for warranted waterproof system installation.

b. Applicator must submit documentation from the waterproof system manufacturer to verify Contractor's status as an approved applicator for warranted installations.

1.4.3 Pre-Work Conference

a. After approval of submittals and before installing the waterproofing system, hold a pre-work conference to review the following:

(1) Drawings, specifications and submittals related to the work

SECTION 07 18 00.00 28 Page 5

(2) Field inspection and verification of all existing conditions, including all existing surfaces and equipment which may require additional protection during installation

(3) Waterproof system components installation

(4) Application timeframe selected to ensure the mid-point of joint movement

(5) Procedure for the waterproof system manufacturer's technical representative's onsite inspection and acceptance of the installed work

(6) Quality control, (ARMA PMBRG98) plan for the installed waterproof system

(7) Safety requirements

b. Coordinate preroofing conference scheduling with the Government.

The conference must be attended by the Contractor, the Government, and personnel directly responsible for the installation of the polyurethane waterproof system. Before beginning work, provide a copy of meeting notes and action items to all attending parties. Note action items requiring resolution prior to start of work.

1.4.4 Moisture Content

Evaluate and determine substrate moisture content throughout the work and record with Daily Inspection Reports.

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver waterproofing materials in manufacturer's original, unopened containers, with labels intact and legible. Containers of materials covered by a referenced specification number must bear the specification number, type, and class of the contents. Deliver materials in sufficient quantity to continue work without interruption. Store and protect materials in accordance with manufacturer's instructions, and use within their indicated shelf life. When hazardous materials are involved, adhere to special precautions of the manufacturer, unless precautions conflict with local, state, and federal regulations. Promptly remove from the site materials or incomplete work adversely affected by exposure to moisture or freezing. Store materials on pallets and cover from top to bottom with canvas tarpaulins.

1.6 ENVIRONMENTAL CONDITIONS

Apply materials when ambient temperature is 40 degrees F or above for a period of 24 hours prior to the application and when there is no ice, frost, surface moisture, or visible dampness on the substrate surface.

Apply materials when air temperature is expected to remain above 40 degrees F during the cure period recommended by the manufacturer. Moisture test for substrate is specified under paragraph entitled "Moisture Test." Work may be performed within heated enclosures, provided the surface temperature of the substrate is maintained at a minimum of 40 degrees F for 24 hours prior to the application of the waterproofing, and remains above that temperature during the cure period recommended by the manufacturer. See the "application" part of this specification section for installation

SECTION 07 18 00.00 28 Page 6 timeframe requirements.

1.7 WARRANTY

1.7.1 Sample Warranty

Submit sample warranty for the complete monolith joint waterproofing system meeting the specified warranty requirements. Sample warranty must be submitted and approved by the Government prior to commencement of roof work.

1.7.2 Polyurethane Waterproof System Manufacturer Warranty

Furnish the manufacturer's 10-year no dollar limit system materials and installation workmanship warranty to include all system components necessary for a watertight system construction. Write the warranty directly to the Government commencing at time of Government's acceptance of the work. Provide the the following statements for such warranty:

a. If within the warranty period the polyurethane waterproof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non-watertight, shows evidence of moisture intrusion within the assembly, blisters, splits, tears, cracks, delaminates, separates at the seams, or shows evidence of excessive weathering or wear due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the polyurethane waterproof system assembly and correction of defective workmanship are the responsibility of the manufacturer.

All cost associated with the repair or replacement work are the responsibility of the polyurethane waterproof system manufacturer.

b. The warranty must remain in full force and effect, including emergency temporary repairs performed by others, when the manufacturer or his approved applicator fail to perform the repairs within 72 hours of notification.

1.7.3 Polyurethane Waterproofing System Installer Warranty

The polyurethane waterproof system installer must warrant for a minimum period of two years that the system, as installed, is free from defects in installation workmanship. Write the warranty directly to the Government.

The installer is responsible for correction of defective workmanship and replacement of damaged or affected materials. The installer is also responsible for all costs associated with the repair or replacement work.

1.7.4 Continuance of Warranty

Approve repair or replacement work that becomes necessary within the warranty period and accomplished in a manner so as to restore the integrity of the polyurethane waterproof system assembly and validity of the manufacturer warranty for the remainder of the manufacturer warranty period.

1.8 POLYURETHANE WATERPROOF SYSTEM SHOP DRAWINGS

Submit shop drawings of the polyurethane waterproof system to include details necessary to show all components of the installed system and describe how they are to be properly assembled.

SECTION 07 18 00.00 28 Page 7

1.9 MANUFACTURER'S INSTRUCTIONS

Submit manufacturer's complete application instructions and details for the polyurethane waterproof system. Instructions must also include storage, handling, and warnings or precautions on flammability and toxicity and recommendations for primers and for surface preparation of the steel and concrete to which the polyurethane waterproof system will be applied.

PART 2 PRODUCTS

2.1 POLYURETHANE WATERPROOF SYSTEM

The system must be a cold, fluid-applied flexible polyurethane waterproofing system. The system must use a fast-setting two-component reactive curing mechanism and must be VOC-compliant and low odor. The system must be applied in a minimum three coats excluding a surface primer. Final coats must be light gray in color to approximate the color of the surrounding existing concrete and must have embedded quartz aggregate suitable to resist wear from light vehicle traffic.

2.1.1 System Primer

Primer must be a two-component adhesive-based polyurethane.

2.1.2 Polyurethane Base Coat

The base coat must be a two-component, fast-curing traffic grade polyurethane. The base coat must have a solids content of 99 percent and it must be low odor.

2.1.3 Polyurethane Intermediate (Broadcast) and Top Coats

The intermediate and top coats must be a two-component aliphatic, fast-curing traffic grade polyurethane meeting the following minimum physical property and performance requirements:

Physical Property Value Test Method

Adhesion Peel (primer and base coat on concrete)

14 lb/inch ASTM C 957

Adhesion (pull-off, base coat)

400 psi ASTM D4541

Tensile Strength Base Coat Intermediate and Top Coats

2,500 psi

2,980 psi

ASTM D412

Elongation Base Coat Intermediate and Top Coats

900%

375%

ASTM D412

Hardness, Shore A 45 ASTM D2240

SECTION 07 18 00.00 28 Page 8

Physical Property Value Test Method

Taber Abrasion Resistance Complete System (CS-17 Wheel, 1,000 g load, 1,000 cycles)

69 mgms

ASTM D4060

2.1.4 Aggregate

Aggregate must be 16 to 30 mesh rounded silica. It must be a natural-colored, kiln-dried silica aggregate suitable for broadcast into the wear layer of the waterproof system and subsequently coated with a color finish.

2.1.5 Cleaning Solution/Solvent

A clear solvent used to clean and prepare transition areas of in-place catalyzed resin to receive subsequent coats of resin and to clean substrate materials to receive resin.

2.2 POLYURETHANE JOINT SEALANT

Sealant for the top of monolith joints and open cracks in concrete must be a two-component polyurethane complying with ASTM C920, Type M, Grade NS, Class 25, use T. The polyurethane sealant must meet or exceed the following performance characteristics:

Physical Property Value Test Method

Tensile Strength 160 psi ASTM D412

Ultimate Elongation at Break

280% ASTM D412

Rheological (flow) at 120 degrees F nonsag ASTM C639

Hardness, Shore A At Standard Conditions After Heat Aging

ASTM C661

Bond Durability (on concrete)

+ 25 ASTM C719

Cracking and Chalking (after heat aging) none ASTM C792

Artificial Weathering Xenon Arc, 250 hours passes ASTM C793

Adhesion in Peel (on concrete)

> 10 pli ASTM C794

Water Immersion 122 degrees F passes 10 weeks with movement cycle

ASTM C1247

SECTION 07 18 00.00 28 Page 9

PART 3 EXECUTION

3.1 PREPARATION

3.1.1 Preparation of Existing Surfaces

Ensure that substrates are free from large irregularities, loose, unsound or foreign material such as dirt, ice, snow, water, grease, oil, bituminous products, old elastomeric sealant, laitance, paint, loose particles/friable matter, rust or any other material that would be detrimental to adhesion of the catalyzed primer and/or resin to the substrate. Shot blast or scarify existing concrete surfaces to provide a sound substrate free from laitance, carbonated concrete, asphalt or coal tar bitumen or old sealant elastomeric sealant. Generate a concrete surface profile of CSP-2 to CSP-4 as defined by the ICRI. Grinding may be used as a preparation method for localized areas that cannot be reached by shot blasting equipment provided that a surface profile of CSP-2 to CSP-4 can be achieved. Repair concrete spalls and voids using the specified primer and preparation paste.

3.1.2 Protection of Installed Chemical Grout

During all polyurethane waterproof system installation, take care and precautions as necessary to not disturb the newly installed chemical grout in joints. Any damage caused to installed chemical grout must be repaired before continuation of work.

3.1.3 Adhesion Testing for Substrates to Receive the Waterproof System

a. Tests to determine tensile bond strength of the polyurethane waterproof system to the concrete and steel substrate must be conducted by the Contractor at the job site using an Elcometer Adhesion Tester Model 106 or similar device in accordance with ASTM D4541. Contractor must perform tests at the beginning of the Work, and at intervals as required to assure specified adhesion with a minimum of three tests.

Test results must be submitted to the Government and the polyurethane waterproof system manufacturer. Contractor must immediately notify the Government and manufacturer in the event tensile bond test results are below specified values.

b. Adequate surface preparation will be indicated by tensile bond strength of membrane to substrate greater than or equal to 220 psi (1.5 N/mm2).

c. In the event the tensile bond strengths are lower than the minimum specified, additional substrate preparation is required. Repeat testing to verify suitability of substrate preparation.

3.1.4 Repair and Leveling of Concrete

Before application of the polyurethane waterproof system primer, fill all of the monolith joints above the newly installed top backer rod as well as all cracks, voids, fractures, depressions, small indentations and low areas in the concrete substrate using epoxy patching material as approved by the waterproof system manufacturer. Allow the leveling material to cure before beginning installation of the waterproof system.

3.1.5 Joint Sealant

Seal the tops of monolith joints that have been filled with the hydrophobic

SECTION 07 18 00.00 28 Page 10 polyurethane grout with a two component polyurethane sealant. Mix and apply the sealant in accordance with manufacturer instructions.

3.1.6 Primer Application

Prime horizontal and vertical concrete surfaces to receive the polyurethane waterproof system, but do not prime over polyurethane sealant used to seal the tops of joints. Apply primer at the rate and with the installation methodology complying with the manufacturer's instructions.

3.2 SPECIAL PRECAUTIONS

Protect waterproofing materials during transport and application. Do not dilute primers and other materials, unless specifically recommended by materials manufacturer. Keep containers closed except when removing contents. Do not mix remains of unlike materials. Thoroughly remove residual materials before using application equipment for mixing and transporting materials. Do not permit equipment on the project site that has residue of materials used on previous projects. Use cleaners only for cleaning, not for thinning primers or the waterproofing materials. Ensure that workers and others who walk on the cured waterproofing system wear clean, soft-soled shoes to avoid damaging the waterproofing materials.

3.3 APPLICATION

Closely follow the Membrane Manufacturer's recommendation for hot and cold weather application. Monitor surface and ambient temperatures, including the effects of wind chill. Apply mixed resin to the prepared surface in accordance with the following specifications and in accordance with manufacturer's written instructions and details where specifically referenced in this specification. Where there is a conflict between the procedures contained in this specification section and written manufacturer instructions, the stricter of the two sets of criteria must be followed.

3.3.1 Application Timeframe

To ensure the polyurethane deck coating system maintains continuity and a watertight seal throughout seasonal cycles of expansion and contraction, it must be installed at the anticipated mid-point of joint movement. It is estimated that this will occur at John Day Dam in the early spring. Thus, as long as all required environmental conditions for installation are met, the Contractor must plan on applying the deck coating during this timeframe. If temperature and moisture conditions during this time are unsuitable for meeting the required environmental restrictions for installation, then the Contractor may delay the application until an acceptable window of good weather conditions becomes available. Notify the COR of any delays necessary due to unsuitable installation conditions.

3.3.2 Application of Base Coat

Wipe primed surfaces with the specified cleaner/solvent. Allow the surface to dry a minimum 20 minutes before continuing work. Mix A and B components of the base coat as recommended by the manufacturer. Apply the base coating on horizontal and vertical concrete surfaces as indicated on the drawings. Using a properly notched squeegee, apply the base coating over the primed substrate at the minimum rate specified by the manufacturer.

Backroll the base coating with a spiked roller to remove any air bubbles.

Allow the base coating to cure three to four hours before application of the intermediate coat of polyurethane.

SECTION 07 18 00.00 28 Page 11

3.3.3 Application of Intermediate Coat and Aggregate

Apply the intermediate coat over the cured base coat with a roller at the rate recommended by the manufacturer. While the intermediate coating is still wet and before it skims over, broadcast the approved silica aggregate into it. Apply the aggregate only on horizontal and use a sufficient amount of aggregate to ensure good slip resistance and suitable wear-resistance for light vehicle traffic. Lightly backroll the aggregate immediately after application. Allow the aggregate intermediate coat to cure three to four hours before application of the top coat. After curing and before application of the polyurethane top coat, sweep or vacuum up all loose silica aggregate.

3.3.4 Application of Topcoat

Apply the top coat over the cured intermediate coat with a roller at the rate recommended by the manufacturer. Lightly backroll the coating to ensure it is uniform and level. Allow a minimum 24 hours of curing before before allowing vehicular traffic onto the coating.

3.3.5 Interruption of Work

If work is interrupted for more than 12 hours, or the surface of a coating becomes dirty or contaminated from exposure to the elements, thoroughly clean the area with the cleaner/solvent before continuing with the application work. Allow a minimum of 20 minutes for the solvent to evaporate before restarting the application work. Complete the next application procedure within 60 minutes following evaporation of the cleaner/solvent.

3.4 FIELD QUALITY CONTROL

3.4.1 Moisture Test

Prior to application of polyurethane waterproofing system, measure moisture content of substrate with a moisture meter in the presence of the Contracting Officer. An acceptable device is the Delmhorst Moisture Meter, Model BD7/2E/CS, Type 21 E. Similar meters by other manufacturers, which are suitable for the purpose, may be used as approved by the Government.

Do not begin application until meter reading indicates "dry" range.

3.4.2 Film Thickness

Measure wet film thickness every 100 square feet during application by placing flat metal plates on the substrate or using a mil-thickness gage especially manufactured for the purpose.

3.4.3 Warranty Inspection and Issuance

Upon completion of work, schedule a final inspection by the polyurethane waterproof system manufacturer technical representative pursuant to issuance of the manufacturer 10-year material warranty. The Government must be notified at least 10 working days in advance of the manufacturer inspection. A punch list of items required for completion or reworking must be compiled by the Contractor and the manufacture's technical representative. A copy of the list must be provided to the Government and all items must be completed prior to issuance of the warranty.

SECTION 07 18 00.00 28 Page 12

3.5 INSTRUCTIONS TO GOVERNMENT PERSONNEL

Furnish written and verbal instructions on proper maintenance procedures to the Government. Furnish instructions by a competent representative of the polyurethane waterproof system manufacturer and include a minimum one hour training session on maintenance and emergency repair of the waterproof system. Include a demonstration of system repair, and give sources of required special tools. Furnish information on safety requirements during maintenance and emergency repair operations.

SECTION 07 18 00.00 28 Page 13

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

SECTION 07 22 00.00 28

ROOF INSULATION

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.2 REFERENCES

1.3 SUBMITTALS

1.4 MANUFACTURER'S CERTIFICATE

1.5 QUALITY ASSURANCE

1.5.1 Flame and Smoke Resistance

1.5.2 Wind Uplift Resistance

1.6 DELIVERY, STORAGE, AND HANDLING

1.6.1 Delivery

1.6.2 Storage and Handling

1.6.3 Environmental Conditions

1.7 PROTECTION OF PROPERTY

1.7.1 Special Protection

1.7.2 Plan and Methodologies for Protecting Generators

PART 2 PRODUCTS

2.1 ROOF INSULATION

2.1.1 General Roof Insulation

2.1.2 Tapered Roof Insulation

2.1.3 Recovered Materials

2.1.4 Roof Insulation Thickness and Size

2.2 GYPSUM ROOF BOARD

2.3 VAPOR BARRIER

2.4 INSULATION FASTENERS

2.5 INSULATION ADHESIVE

2.6 EXTERIOR FIRE RETARDANT TREATED WOOD

2.6.1 Wood Screws

2.6.2 Self-Drilling Screws (for attaching wood members to steel decking or other steel components)

2.6.3 Adhesive Anchors (for attaching the wood plate to the top of the existing concrete parapet wall)

PART 3 EXECUTION

3.1 EXAMINATION AND PREPARATION

3.2 INSTALLATION OF WOOD CURBS AND PERIMETER FASTENING

3.3 INSTALLATION OF BASE LAYER OF GYPSUM ROOF BOARD

3.3.1 Protection Measures

3.3.2 Fastener Pull Out Test

3.3.3 Installation

3.4 INSTALLATION OF VAPOR BARRIER

3.5 INSTALLATION OF ROOF INSULATION

3.5.1 Required Conditions for Adhesion of Insulation and Gypsum Roof

SECTION 07 22 00.00 28 Page 1

Board

3.5.2 General Insulation

3.5.3 Tapered Roof Insulation

3.6 INSTALLATION OF THE TOP LAYER OF GYPSUM ROOF BOARD

3.7 PROTECTION

3.7.1 Protection of Applied Insulation

3.7.2 Damaged Work and Materials

3.8 INSPECTION

SECTION 07 22 00.00 28 Page 2

SECTION 07 22 00.00 28

ROOF INSULATION

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

a. This Section covers installation of new roof insulation at John Day Lock and Dam. The following is a description of the new roofing system at the Powerhouse to be constructed (bottom up):

(1) Gypsum roof board (base layer), mechanically attached

(2) Vapor barrier, torch-applied

(3) General roof insulation, fully adhered

(4) Tapered roof insulation, fully adhered

(5) Gypsum roof board (top layer), fully adhered

(6) EPDM roofing membrane, fully adhered

b. The following is a description of the new roofing system at the 8th Floor Office, South Powerhouse Entrance, Powerhouse Elevator Penthouse, Freight Elevator Penthouse, Bay 9 Elevator Penthouse and the Bay 17 Elevator Penthouse to be constructed (bottom up):

(1) Vapor barrier, torch-applied

(2) General roof insulation, fully adhered

(3) Tapered roof insulation, fully adhered

(4) Gypsum roof board (top layer), fully adhered

(5) PMMA roofing membrane

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN FOREST & PAPER ASSOCIATION (AF&PA)

AF&PA T10 (2001) Wood Frame Construction Manual for One- and Two-Family Dwellings

AF&PA T101 (2005) National Design Specification (NDS) for Wood Construction

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 7-10 WIND LOADS (2010) Guide to the Wind Load Provisions

SECTION 07 22 00.00 28 Page 3 of ASCE 7-10

ASTM INTERNATIONAL (ASTM)

ASTM C 209 (1998) Test Methods for Cellulosic Fiber Insulating Board

ASTM C 1177/C 1177M (2006) Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing

ASTM C 1289 (2007) Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board

ASTM D 143 (2014) Standard Test Methods for Small Clear Specimens of Timber

ASTM D 1622 (2003) Apparent Density of Rigid Cellular Plastics

ASTM D 2126 (2004) Response of Rigid Cellular Plastics to Thermal and Humid Aging

ASTM D1876 (2008) Standard Test Method for Peel Resistance of Adhesives (T-Peel Test)

ASTM D1970/D1970M (2017) Standard Specification for Self-Adhering Polymer Modified Bituminous Sheet Materials Used as Steep Roofing Underlayment for Ice Dam Protection

ASTM D2898 (2010) Accelerated Weathering of Fire-Retardant-Treated Wood for Fire Testing

ASTM D5147/D5147M (2014) Standard Test Methods for Sampling and Testing Modified Bituminous Sheet Material

ASTM D5602/D5602M (2011) Standard Test Method for Static Puncture Resistance of Roofing Membrane Specimens

ASTM D903 (1998; R 2010) Peel or Stripping Strength of Adhesive Bonds

ASTM E 96 (2005) Standard Test Methods for Water Vapor Transmission of Materials

ASTM E84 (2014) Standard Test Method for Surface Burning Characteristics of Building Materials

ASTM F593 (2013a) Stainless Steel Bolts, Hex Cap Screws, and Studs

FM GLOBAL (FM)

FM P7825 Factory Mutual Research Approval Guide

SECTION 07 22 00.00 28 Page 4

FM P9513 (2002) Specialist Data Book Set for Roofing Contractors; contains 1-22 (2001), 1-28 (2002), 1-29 (2002), 1-28R/1-29R (1998), 1-30 (2000), 1-31 (2000), 1-32 (2000), 1-33 (2000), 1-34 (2001), 1-49 (2000), 1-52 (2000), 1-54 (2001)

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2012) International Building Code

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

UNDERWRITERS LABORATORIES (UL)

UL Bld Mat Dir (2007) Building Materials Directory

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following must be submitted in accordance with SECTION 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Plan and Methodologies for Protecting Generators

SD-03 Product Data

General Roof Insulation; G

Tapered Roof Insulation; G

Gypsum Roof Board; G

Vapor Barrier; G

Insulation Fasteners; G

Insulation Adhesive; G

Exterior Fire Retardant Treated Wood; G

Wood Screws; G

Self-Drilling Screws; G

Adhesive Anchors; G

Metal Primer; G

SD-04 Samples

General Roof Insulation; G

SECTION 07 22 00.00 28 Page 5

Vapor Barrier; G

Insulation Fasteners; G

SD-05 Design Data

Wind Uplift Calculations; G

SD-06 Test Reports

Flame Spread and Smoke Developed Ratings; G

Wind Uplift Resistance; G

Results Of Fastener Pull Out Tests

SD-07 Certificates

Installer Qualifications; G

SD-08 Manufacturer's Instructions

General Roof Insulation; G

Tapered Roof Insulation; G

Gypsum Roof Board; G

Vapor Barrier; G

Insulation Fasteners; G

Insulation Adhesive; G

1.4 MANUFACTURER'S CERTIFICATE

Submit certificate from the insulation manufacturer attesting that the installer has the proper qualifications for installing tapered roof insulation systems.

Certificate attesting that the polyisocyanurate insulation contains recovered material and showing estimated percent of recovered material. Certificates of compliance for felt materials.

1.5 QUALITY ASSURANCE

1.5.1 Flame and Smoke Resistance

Roof insulation must have a flame spread rating not greater than 25 and a smoke developed rating not greater than 250, exclusive of covering, when tested in accordance with ASTM E84. Insulation bearing the UL label and listed in the UL Bld Mat Dir as meeting the flame spread and smoke developed ratings will be accepted in lieu of copies of test reports.

Compliance with flame spread and smoke developed ratings shall not be required when insulation has been tested as part of a roof construction assembly of the type used for this project and the construction is listed as fire-classified in the UL Bld Mat Dir or listed as Class I roof deck construction in the FM P7825. Insulation tested as part of a roof

SECTION 07 22 00.00 28 Page 6 construction assembly must bear UL or FM labels attesting to the ratings specified herein.

1.5.2 Wind Uplift Resistance

The complete roof system assembly, including the screw and plate washer attachment for the base layer of gypsum roof board and subsequent layers of fully adhered insulation, must be rated and installed to resist wind loads calculated in accordance with ASCE 7-10 WIND LOADS and validated by uplift resistance testing in accordance with Factory Mutual (FM) test procedures.

Submit licensed engineer's wind uplift calculations and substantiating data to validate any non-rated roof system. Base wind uplift measurements on a peak wind gust speed of 110 mph in accordance with ASCE 7-10 WIND LOADS and/or other applicable building code requirements. Coordinate wind uplift resistance criteria with Section 07 53 23.00 28, ETHYLENE-PROPYLENE-DIENE- MONOMER (EPDM) ROOFING. Provide one of the following:

a. The actual Factory Mutual test report for the submitted system showing compliance with the specified wind uplift criteria.

b. Copies from FM P7825 may be provided in lieu of an actual FM test report, provided this data clearly lists the roof membrane manufacturer, testing and compliance based on the peak wind gust, and the required application methodology to meet the specified wind uplift criteria.

1.6 DELIVERY, STORAGE, AND HANDLING

1.6.1 Delivery

a. Deliver materials to site in manufacturer's unopened and undamaged standard commercial containers bearing the following legible information:

(1) Name of manufacturer;

(2) Brand designation;

(3) Specification number, type, and class, as applicable, where materials are covered by a referenced specification.

b. Deliver materials in sufficient quantity to allow continuity of the work.

1.6.2 Storage and Handling

Store and handle materials in a manner…