AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to update clauses 52.211-10 and 52.217-7 and change CLINs 0003, 0005, 0008, and 0009 to optional items. All other requirements remain the same. There is no time extension included w ith this amendment.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N19B0004

X 9B. DATED (SEE ITEM 11)

13-Dec-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Dec-2018

CODE

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N19B0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

CLIN 0003

The option status has changed from No Status to Option.

CLIN 0005

CLIN 0008

CLIN 0009

SECTION 00 72 00 - GENERAL CONDITIONS

The following have been modified:

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule.

(a) The Contracting Officer may exercise optional CLIN 0003, Demolition & Disposal of Existing Ancillary Roofs, by written notice to the Contractor up to 150 days prior to the contract physical completion date.

(b) The Contracting Officer may exercise optional CLIN 0005, Ancillary Roofs Asbestos Abatement, by written notice to the Contractor up to 150 days prior to the contract physical completion date.

(c) The Contracting Officer may exercise optional CLIN 0008, Install New Ancillary Roofs, by written notice to the Contractor up to 150 days prior to the contract physical completion date.

(d) The Contracting Officer may exercise optional CLIN 0009, Install New Ancillary Roofs Guardrails, by written notice to the Contractor up to 150 days prior to the contract physical completion date.

(e) The Contracting Officer may exercise optional CLIN 0012, Replace Additional Existing Powerhouse Roof Drains and Associated Downspout Drain Pipes, Over 12 Drains, by written notice to the Contractor up to 90 days prior to the contract physical completion date.

(f) The Contracting Officer may exercise optional CLIN 0013, Monolith Joint 11/12 Repair, by written notice to the Contractor up to 90 days prior to the contract physical completion date. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) – ALTERNATE

I (APR 1984)

a. The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than:

b. BEGIN FIRST SEASON PHYSICAL CONSTRUCTION JOINT SEALANT DATE: February 15, 2019 All work related to the sealing of the horizontal monolith joints on the intake deck shall begin no earlier than February 15, 2019. Overview of the horizontal monolith joint sealing at the intake deck is presented on A-415.

c. END FIRST SEASON PHYSICAL CONSTRUCTION JOINT SEALANT DATE: May 01, 2019 All work related to the sealing of the horizontal monolith joints on the intake deck shall end no later than May 01, 2019. Overview of the horizontal monolith joint sealing at the intake deck is presented on A-415.

d. INTERIM CONSTRUCTION DATE: October 31, 2019 Due to the size of the roof to be replaced, the Contractor is required to mobilize to the construction site and to physically complete a minimum of eight (8) bays prior to the INTERIM CONSTRUCTION DATE.

(1) Completion of a bay is defined as: demolition and removal of existing roof systems, to include asbestos abatement and disposal; preparation of steel deck surface and replacement of roof drains or installation of roof drain inserts, as applicable; installation of vapor retarder and insulation, including supporting accessories such as wood supports and curbs; and installation of new EPDM membrane including flashing, walkpads, and parapet caps.

e. BEGIN SECOND SEASON PHYSICAL CONSTRUCTION JOINT SEALANT DATE: February 15, 2020 All work related to the sealing of the horizontal monolith joints on the intake deck shall begin no earlier than February 15, 2020. Overview of the horizontal monolith joint sealing at the intake deck is presented on A-415.

f. END SECOND SEASON PHYSICAL CONSTRUCTION JOINT SEALANT DATE: May 01, 2020 All work related to the sealing of the horizontal monolith joints on the intake deck shall end no later than May 01, 2020. Overview of the horizontal monolith joint sealing at the intake deck is presented on A-415.

g. FINAL PHYSICAL CONSTRUCTION COMPLETION DATE: October 31, 2020 The time stated for FINAL PHYSICAL CONSTRUCTION COMPLETION shall include all construction, features in the Plans and Specifications, temporary construction supports, construction aids and construction debris must be removed from the site. The date stated for completion shall include all work, demobilization, and final cleanup of the premises.

h. CONTRACT END DATE: January 31, 2021

The time stated for CONTRACT END DATE shall include all final remaining work documents, to include closeout submittals, As-Constructed Drawings, Operation & Maintenance Manuals and all other requirements submitted and approved.

The time stated for CONTRACT END DATE shall include all final remaining work documents, to include closeout submittals, As-Constructed Drawings, Operation & Maintenance Manuals and all other requirements submitted and approved.

(End of clause)

(End of Summary of Changes)

John Day Dam Powerhouse and Ancillary Roofs Replacement

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00.00 25 CONTRACT ADMINISTRATION DATA

01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS

01 11 00.00 25 SUMMARY OF WORK

01 22 00.00 25 MEASUREMENT AND PAYMENT

01 32 01.00 25 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 25 QUALITY CONTROL

01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 23.00 25 OPERATION AND MAINTENANCE DATA

01 78 39.00 25 PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

02 82 14.00 28 ASBESTOS CONTAINING MATERIAL (ACM) REMOVAL AND DISPOSAL

02 83 20.00 25 LEAD BASE PAINT (LBP) ABATEMENT, REMOVAL, AND DISPOSAL

DIVISION 03 - CONCRETE

03 01 32.00 25 CONCRETE REHABILITATION FOR CIVIL WORKS AND CORE DRILL

DIVISION 05 - METALS

05 50 00.10 28 METAL: MISCELLANEOUS AND FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.10 28 ROOF REMOVAL AND DISPOSAL

07 18 00.00 28 TRAFFIC-BEARING POLYURETHANE WATERPROOF SYSTEM AND

POLYURETHANE JOINT SEALANT

07 22 00.00 28 ROOF INSULATION

07 53 23.00 28 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING

07 56 00.10 28 PMMA FLUID-APPLIED ROOFING

07 61 00.00 28 SHEET METAL FLASHING

07 72 00.00 28 ROOF ACCESSORIES

07 92 00.00 28 JOINT SEALANTS

DIVISION 09 - FINISHES

09 22 16.00 28 NON-STRUCTURAL METAL FRAMING

DIVISION 22 - PLUMBING

22 00 00.00 25 PLUMBING, GENERAL PURPOSE

DIVISION 26 - ELECTRICAL

26 05 00.00 28 GENERAL ELECTRICAL WORK

26 05 19.00 28 WIRE AND CABLE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 UNIT PRICE PAYMENT ITEMS

1.3 JOB PAYMENT ITEMS

1.4 MEASUREMENT AND PAYMENT

1.4.1 Mobilization and Demobilization, CLIN 0001

1.4.2 Demolition & Disposal of Existing Powerhouse Roof, CLIN 0002

1.4.3 Demolition & Disposal of Existing Ancillary Roofs, OPTIONAL

CLIN 0003

1.4.4 Powerhouse Roof Asbestos Abatement, CLIN 0004

1.4.5 Ancillary Roofs Asbestos Abatement, OPTIONAL CLIN 0005

1.4.6 Install New Powerhouse Roof, CLIN 0006

1.4.7 Install New Powerhouse Roof Guardrails, CLIN 0007

1.4.8 Install New Ancillary Roofs, OPTIONAL CLIN 0008

1.4.9 Install New Ancillary Roofs Guardrails, OPTIONAL CLIN 0009

1.4.10 Replace Existing Damaged Powerhouse 20 Gauge Steel Roof

Decking, CLIN 0010

1.4.10.1 First 80 Square Feet, CLIN 0010AA

1.4.10.2 Over 80 Square Feet, CLIN 0010AB

1.4.11 Replace Existing Damaged Powerhouse Roof Drains and Associated

Downspout Drain Pipes, First 12 Drains, CLIN 0011

1.4.12 Replace Additional Existing Powerhouse Roof Drains and

Associated Downspout Drain Pipes, Over 12 Drains, OPTIONAL CLIN

1.4.13 Monolith Joint 11/12 Repair, OPTIONAL CLIN 0013

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

SECTION 01 22 00.00 25 Page 1

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule. Payment for work activities involving lead based paint will be incidental to the related CLIN.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.

1.3 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided.

Provide a schedule of values for job items prior to the first pay request.

Update with each subsequent payment request.

1.4 MEASUREMENT AND PAYMENT

1.4.1 Mobilization and Demobilization, CLIN 0001

a. Measurement: Measurement will be made as a job for mobilizing and demobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site. This Contract Line Item Number

SECTION 01 22 00.00 25 Page 2

(CLIN) applies to the Prime Contractor and all subcontractor mobilization and demobilization.

b. Payment: Payment will be made as stated in Contract Clause 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (Dec 1991).

Submit a schedule of mobilization and demobilization costs prior to submitting the first request for payment.

1.4.2 Demolition & Disposal of Existing Powerhouse Roof, CLIN 0002

a. Measurement: Measurement will be made as a job item providing all labor, plant, equipment, materials, and incidentals required for demolition of existing Powerhouse Roof, and must include disposal of any items as applicable.

b. Payment: Payment will be made at the Contract amount under CLIN 0002. Price and payment shall constitute full compensation for the demolition and disposal of the existing Powerhouse Roof and designated fixtures.

1.4.3 Demolition & Disposal of Existing Ancillary Roofs, OPTIONAL CLIN 0003

a. Measurement: Measurement will be made as a job item providing all labor, plant, equipment, materials, and incidentals required for demolition of Ancillary Roofs, and must include disposal of any items as applicable. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof.

b. Payment: Payment will be made at the Contract amount under CLIN 0003. Price and payment shall constitute full compensation for the demolition and disposal of the existing Ancillary Roofs and designated fixtures. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof.

1.4.4 Powerhouse Roof Asbestos Abatement, CLIN 0004

a. Asbestos is known to be present in the roofing material, joints, and electrical wiring and it is determined that the workers will be exposed to asbestos. This CLIN will be paid by the job for roofing material abated, to include successfully bagging, labeling, and disposing of the waste according to state, federal, and county laws and regulations. Unit price shall include providing all labor, plant, equipment, materials, and incidentals required for this work, and shall include disposal of any items as applicable.

b. Payment: Payment will be made at the Contract amount under CLIN 0004.

1.4.5 Ancillary Roofs Asbestos Abatement, OPTIONAL CLIN 0005

a. Asbestos is known to be present in the roofing material, joints, and electrical wiring and it is determined that the workers will be exposed to asbestos. This CLIN will be paid by the job for roofing material abated, to include successfully bagging, labeling, and disposing of the waste according to state, federal, and county laws and

SECTION 01 22 00.00 25 Page 3 regulations. Unit price shall include providing all labor, plant, equipment, materials, and incidentals required for this work, and shall include disposal of any items as applicable.

b. Payment: Payment will be made at the Contract amount under CLIN 0005.

1.4.6 Install New Powerhouse Roof, CLIN 0006

a. Measurement: Measurement will be made as a job item providing all labor, plant equipment, materials, and incidentals to install new Powerhouse Roof. This CLIN shall include new roofing membrane, drainage, insulation, gypsum sheathing, sheet metal finishing, asphalt foundation coating, structural and electrical, and related framing and ventilators as detailed in project design. This CLIN shall also include the horizontal monoliths joint sealing at the intake deck as detailed on sheet A-415.

b. Payment: Payment will be made at the contract amount under CLIN 0006. Price and payment shall constitute full compensation for the installation of Powerhouse Roof.

1.4.7 Install New Powerhouse Roof Guardrails, CLIN 0007

a. Measurement: Measurement will be made as a job item providing all labor, plant equipment, materials, and incidentals to install new guardrails at the perimeter parapet of the Powerhouse Roof. The work shall include design and installation of the guardrail system as well as design and installation of the fall protection anchors.

b. Payment: Payment will be made at the contract amount under CLIN 0007. Price and payment shall constitute full compensation for the installation of guardrails at the Powerhouse Roof.

1.4.8 Install New Ancillary Roofs, OPTIONAL CLIN 0008

a. Measurement: Measurement will be made as a job item providing all labor, plant equipment, materials, and incidentals to install new Ancillary Roofs. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof. This CLIN shall include new roofing membrane, drainage, insulation, gypsum sheathing, sheet metal finishing, asphalt foundation coating, structural and electrical, and related framing and ventilators as detailed in project design.

b. Payment: Payment will be made at the contract amount under CLIN 0008. Price and payment shall constitute full compensation for the installation of Ancillary Roofs. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof.

1.4.9 Install New Ancillary Roofs Guardrails, OPTIONAL CLIN 0009

a. Measurement: Measurement will be made as a job item providing all labor, plant equipment, materials, and incidentals to install new guardrails at the perimeter parapet of the Ancillary Roofs. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse

SECTION 01 22 00.00 25 Page 4

Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof.

The work shall include design and installation of the guardrail system and shall include design and installation of fall protection anchors for the appropriate Ancillary Roofs as detailed within the plans.

b. Payment: Payment will be made at the contract amount under CLIN 0009. Price and payment shall constitute full compensation for the installation of guardrails at the Ancillary Roofs. Ancillary Roofs shall mean; 8th Floor Office Roof, Powerhouse Elevator Penthouse Roof, Bay 17 Elevator Penthouse Roof, Bay 9 Elevator Penthouse Roof, Visitor's Gallery Entrance Roof, and Freight Elevator Penthouse Roof.

1.4.10 Replace Existing Damaged Powerhouse 20 Gauge Steel Roof Decking, CLIN 0010

1.4.10.1 First 80 Square Feet, CLIN 0010AA

a. Measurement: The estimated quantity of replaced 20 ga. steel roof decking for which payment will be made is estimated to be approximately 80 square feet and will physically identified during onsite inspection by the Government. Square footage will be calculated by the physically demarcated area during onsite inspection. Unit price must include providing all labor, plant, equipment, materials, and incidentals required for common replacement of 20 ga. steel roof decking. Include all demolition, lead paint removal as may be necessary, loading, hauling, and disposing of materials.

b. Payment: The quantity determined as stated above will be paid for at the Contract price per square foot for deck replaced under CLIN 0010AA. Price and payment shall constitute full compensation for removal of existing steel roof deck and the installation of new steel roof deck.

1.4.10.2 Over 80 Square Feet, CLIN 0010AB

a. Measurement: The estimated quantity of replaced 20 ga. steel roof decking for which payment will be made is estimated to be up to approximately an additional 160 square feet and will physically identified during onsite inspection by the Government. Square footage will be calculated by the physically demarcated area during onsite inspection. Unit price must include providing all labor, plant, equipment, materials, and incidentals required for common replacement of 20 ga. steel roof decking. Include all demolition, lead paint removal as may be necessary, loading, hauling, and disposing of materials.

b. Payment: The quantity determined as stated above will be paid for at the Contract price per square foot for deck replaced under CLIN 0010AB. Price and payment shall constitute full compensation for removal of existing steel roof deck and the installation of new steel roof deck.

1.4.11 Replace Existing Damaged Powerhouse Roof Drains and Associated Downspout Drain Pipes, First 12 Drains, CLIN 0011

a. Measurement: The total quantity of replaced drains and associated downspout drain pipes for which payment will be made is to be 12 drains as labeled and detailed within the contract plans. Unit price must

SECTION 01 22 00.00 25 Page 5 include providing all labor, plant, testing, equipment, materials, and incidentals required for common replacement of cast iron roof drains and galvanized steel drain pipe. Include all demolition, loading, hauling, and disposing of materials. Include all testing and flushing as detailed within 22 00 00.00 25 PLUMBING, GENERAL PURPOSE.

b. Payment: Payment will be made per unit basis for each drain at the Contract amount under CLIN 0011. Price and payment shall constitute full compensation for the removal of existing roof drains and associated downspouts and the installation of roof drains and associated downspout drain pipes.

1.4.12 Replace Additional Existing Powerhouse Roof Drains and Associated Downspout Drain Pipes, Over 12 Drains, OPTIONAL CLIN 0012

a. Measurement: The total estimated quantity of replaced drains and associated downspout drain pipes for which payment will be made is estimated to be up to 12 additional drains. Unit price must include providing all labor, plant, testing, equipment, materials, and incidentals required for common replacement of cast iron roof drains and galvanized steel drain pipe. Include all demolition, loading, hauling, and disposing of materials. Include testing and flushing for completed drain systems as detailed within 22 00 00.00 25 PLUMBING, GENERAL PURPOSE.

b. Payment: Payment will be made per unit basis for each drain at the Contract amount under CLIN 0012. Price and payment shall constitute full compensation for the removal of existing roof drains and associated downspouts and the installation of roof drains and associated downspout drain pipes.

1.4.13 Monolith Joint 11/12 Repair, OPTIONAL CLIN 0013

a. Measurement: Measurement will be made as a job item providing all labor, plant equipment, materials, and incidentals to repair and seal Monolith Joint 11/12 as detailed on drawings SD001 and S-303.

b. Payment: Payment will be made at the contract amount under CLIN 0013. Price and payment shall constitute full compensation for the repair and sealing of the Monolith Joint 11/12.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

SECTION 01 22 00.00 25 Page 6

A.07.24 JD Roof Amendment 0001
Technical_Sections
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 25 - MEASUREMENT AND PAYMENT
01 22 00.00 25 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 UNIT PRICE PAYMENT ITEMS
1.3 JOB PAYMENT ITEMS
1.4 MEASUREMENT AND PAYMENT
1.4.1 Mobilization and Demobilization, CLIN 0001
1.4.2 Demolition & Disposal of Existing Powerhouse Roof, CLIN 0002
1.4.3 Demolition & Disposal of Existing Ancillary Roofs, OPTIONAL CLIN 0003
1.4.4 Powerhouse Roof Asbestos Abatement, CLIN 0004
1.4.5 Ancillary Roofs Asbestos Abatement, OPTIONAL CLIN 0005
1.4.6 Install New Powerhouse Roof, CLIN 0006
1.4.7 Install New Powerhouse Roof Guardrails, CLIN 0007
1.4.8 Install New Ancillary Roofs, OPTIONAL CLIN 0008
1.4.9 Install New Ancillary Roofs Guardrails, OPTIONAL CLIN 0009
1.4.10 Replace Existing Damaged Powerhouse 20 Gauge Steel Roof Decking,
1.4.10.1 First 80 Square Feet, CLIN 0010AA
1.4.10.2 Over 80 Square Feet, CLIN 0010AB
1.4.11 Replace Existing Damaged Powerhouse Roof Drains and Associated
1.4.12 Replace Additional Existing Powerhouse Roof Drains and Associated
1.4.13 Monolith Joint 11/12 Repair, OPTIONAL CLIN 0013
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
[1]: [1]
Amd0001: AMD #0001