AM03.pdf
PDF 2 MB Posted
- Solicitation number
- W9127820R0037
About this file
This solicitation and related documents outline requirements for the construction of an aviation test, instrumentation, and integration hangar facility at Redstone Arsenal in Alabama. The project involves constructing a hangar, administrative space, hangar access apron, aircraft parking apron, and supporting facilities including site development, utilities, lighting, paving, parking, walks, curbs, storm drainage, landscaping, signage, physical security, and AT/FP systems. The procurement will award a single construction contract between $25-$100 million. Offerors must submit sealed bids by 6 August 2020 with performance required within 120 calendar days of award. The U.S. Army Corps of Engineers Mobile District will administer the contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AM04.pdf | ||
| AM03 DRAWINGS.pdf | ||
| AM02.pdf | ||
| AM02 DRAWINGS.pdf | ||
| Redstone Aircraft PreBid Signin.pdf | ||
| AM01 DRAWINGS.pdf | ||
| AM01.pdf | ||
| EM 385-1-1.pdf | ||
| RTA Drawings VOL1.pdf | ||
| RTA Drawings VOL2.pdf | ||
| VOL4.PDF | ||
| VOL2.PDF | ||
| VOL1.PDF | ||
| VOL3.PDF |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable)
W9127820R0037-0003 31 JULY 2020 MHY20008
6. ISSUED BY CODE 7. ADMINISTERED BY(If other than item 6)
CODE
Corps of Engineers 109 St. Joseph St.
Mobile, AL 36602
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION
NO.
W9127820R0037
9B. DATED (SEE ITEM 11)
29 JUNE 2020
10A. MODIFICATION OF
CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE
FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
The subject solicitation for: AIRCRAFT AND FLIGHT EQUIPMENT BUILDINGS
REDSTONE ARSENAL, ALABAMA
Is modified in the following: REFER TO THE ENCLOSED REVISED AND ADDED SPECIFICATIONS/DRAWINGS FOR AMENDMENT NO. 0003 NOTE: THE RECEIPT OF PROPOSAL DATE IS HEREBY REVISED BY THIS AMENDMENT. REFER TO THE ENCLOSED SF1442, SOLICITATION, OFFER & AWARD FORM.
Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of contracting officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
AIRCRAFT AND FLIGHT EQUIPMENT BUILDINGS W9127820R0037
REDSTONE ARSENAL, ALABAMA MHY20008
SF 30 Page 2 W9127820R0037-0003
PART I - REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS
The items listed below are to be replaced by the corresponding added and/or revised paragraphs/pages or sections. Added and/or revised paragraphs/pages or sections are indicated by a note in bottom right hand corner of each paragraph or page. Added sections are hereby made a part of the contract and are to be inserted in the specification in the proper numerical/alphabetical sequence.
Within the specifications, deletions from the specifications are indicated by strikethrough, e.g.: deletions are marked with strikethrough and additions to the specifications including revisions/substitutions are indicated in bold, italic and underlined, e.g.: additions are indicated thus.
Corresponding Added or Revised Paragraph SECTION Page, and/or Section
SF1442, Solicitation, Offer & Award Form Revised Block 13.A as indicated herein.
07 42 63 Revised Paragraph 2.6 Deleted Paragraphs 2.6.1, 2.6.2 and 2.6.3
09 90 00 Deleted Paragraph 1.4.2 Revised Paragraph 3.15.2
23 08 00.00 10 Revised Appendix A
41 22 13.15 Revised Paragraphs 1.3, 2.1 and 2.8
PART II - NOTE: Revised drawings are listed below. These revised drawings are to be inserted into the folio in the proper numerical sequence. Drawings that have been revised by this amendment shall be deleted from the folio. All drawings listed below are revised unless indicated otherwise.
SHT
REF. TITLE OF DRAWINGS
COVER SHEET
G-002 INDEX OF DRAWINGS
A-001 GENERAL NOTES, ABBREVIATIONS
A-113 COMPOSITE REFLECTED CEILING PLAN
A-120 COMPOSITE ROOF PLAN
A-121 ROOF PLAN AREA-A
A-122 ROOF PLAN AREA-B
A-123 ROOF PLAN AREA-C
A-124 ROOF PLAN AREA-D
A-125 ROOF PLAN AREA-F
A-210 ENLARGED EXTERIOR ELEVATIONS
A-310 WALL SECTIONS
A-513 DETAILS – MISCELLANEOUS
A-601 PARTITION TYPES
A-602 ROOM FINISH – SIGNAGE SCHEDULE & DETAILS
Encl as stated Replaced pages of the specifications as indicated in Part I.
15 Revised drawing as indicated in Part II.
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
W9127820R0037
2. TYPE OF
SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
29 JUNE 2020
PAGES OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
6. PROJECT NO.
MHY20008
7. ISSUED BY CODE CT 8. ADDRESS OFFER TO
U.S. ARMY ENGINEER DISTRICT, MOBILE
CONTRACTING DIVISION (CESAM-CT)
(109 ST. JOSEPH ST. 36602) P.O. BOX 2288
MOBILE, AL 36628-0001
SAME AS BLOCK 7
IF HAND CARRIED, DELIVER TO
CONTRACT SPECIALIST IDENTIFIED IN BLOCK 9.
9. FOR INFORMATION
CALL : Lanell Roberts
Kyle Rodgers
A. NAME
Lanell.A.Roberts@usace.army.mil Kyle.M.Rodgers@usace.army.mil
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(251) 694-3859 (251)-690-3356
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
AIRCRAFT AND FLIGHT EQUIPMENT BUILDINGS, REDSTONE ARSENAL, ALABAMA
* See Section 01 00 00, Paragraph “COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK”.
**Block 13A. : Refer to Section 00 11 00 for the number of copies to submit with the original offer.
11. The Contractor shall begin performance within _8________ calendar days and complete it within __*________ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _ __.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and ___**____ copies to perform the work required are due at the place specified in Item 8 by__1400___ (hour) local time 6 11 AUGUST 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than ____120_______ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101
STANDARD FORM 1442(REV. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1€
Revised by Amendment No. W9127820R0037-0003
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within _________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation – give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304© ( ) 41 U.S.C. 253© ( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (contractor is required to sign this document and return _______ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award con-summates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE 31B. UNITED STATES OF AMERICA
BY
31C. AWARD
DATE
STANDARD FORM 1442 BACK (REV. 4-85)
Reissued by Amendment No. W9127820R0037-0003
SECTION 07 42 63
SECTION 07 42 63
2.6 INTEGRATED WALL LOUVER UNITS (NOT USED)
2.6.1 Exterior Wall Louvers
Exterior Wall Louvers shall be designed to integrate with metal wall panel profile and secondary support system without receptor channels or other flashing, nominal thickness not less than 0.060 inch for blades and 0.080 inch for frames, of types and performance indicated. See Specification Section 08 91 00 METAL WALL LOUVERS.
2.6.2 AMCA Seal
Provide louver units marked with AMCA Certified Ratings Seal, tested in accordance with AMCA 500L.
2.6.3 Bird Screen
Unless otherwise indicated, all louvers to be furnished with mill finish bird or insect screens
1. Screens to be 5/8" (15.9mm) mesh, 0.050" (1.27mm) thick expanded and flattened aluminum bird screen secured within 0.055" (1.40mm) thick extruded aluminum frames. Frams to have mitered corners and corner locks.
OR
2. Screens to be 18 x 16 aluminum mesh 0.011" (0.279mm) diameter wire insect screens secured within 0.055" (1.40mm) thick extruded aluminum frames. Frames to have mitered corners and corner locks.
(NOTE: The remainder of the section is unchanged by the amendment.)
This page was intentionally left blank for duplex printing.
SECTION 09 90 00
SECTION 09 90 00
1.4.2 SSPC QP 1 Certification
All contractors and subcontractors that perform surface preparation or coating application must be certified by the Society for Protective Coatings (formerly Steel Structures Painting Council) (SSPC) to the requirements of SSPC QP 1 prior to contract award, and must remain certified while accomplishing any surface preparation or coating application. If a contractor's or subcontractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply.
Notify the Contracting Officer of any change in contractor certification status.
3.15.2 Interior Paint Tables
DIVISION 3: INTERIOR CONCRETE PAINT TABLE
B. New concrete floors in areas scheduled as “SC” Epoxy, New; MPI 3.2C-G6 (Gloss); Primer MPI 77; Intermediate MPI 77; Topcoat: MPI 77; System DFT 5 mils; Note: Primer may be reduced for penetration per manufacturer’s instructions
(NOTE: The remainder of Paragraph 3.15.2 is unchanged by the amendment.)
SECTION 23 08 00.00 10
SECTION 23 08 00.00 10
APPENDIX A
PRE-FUNCTIONAL PERFORMANCE TEST CHECKLISTS
Pre-functional Performance Test Checklist – Variable Constant Volume Air Handling Unit – FOR AHU: AIR HANDLERS SHALL ALL BE VERIFIED - CONTRACTOR TO
PROVIDE A SEPARATE SHEET FOR EACH AHU INSTALLED
Coils A M E T C O
a. Refrigerant piping properly connected. X X X
Pre-Functional Performance Test Checklist - Variable CONSTANT Volume Air Handling Unit
Controls A M E T C O
a. b. Dampers/actuators properly installed. X X X
(NOTE: The remainder of the Checklist Items in Appendix A is unchanged by the amendment.)
For Air Handling Unit: AHU-1
Checklist Item A M E T C O
Installation
a. Inspection and access doors and sealed.
are operable
X
X
SECTION 41 22 13.15
SECTION 41 22 13.15
1.3 REQUIREMENTS
The requirements for the crane runway and rail supporting structures are specified in Section 05 12 00, STRUCTURAL STEEL, and must conform to AISC 325. See also part 2.8 “CRANE RUNWAY TRACK SYSTEM” of this specification section.
2.1 UNDER RUNNING CRANE SYSTEM
Provide 2-10 ton under running bridge overhead electric cranes, with under running trolley mounted hoist, conforming to CMAA 74, Class B (Light Service) for indoor service. Crane must be controlled by a pendant push button station mounted on the hoist.
(NOTE: The remainder of Paragraph 2.1 is unchanged by the amendment.)
2.8 CRANE RUNWAY TRACK SYSTEM
Provide patented track runway track beams designed and constructed in compliance with MHI MH27.1 and CMAA 74, Class B (Light Service), except as modified and supplemented in the section. Runway capacity between supports spacing shall be a minimum of 10 tons.
(NOTE: The remainder of Paragraph 2.8 is unchanged by the amendment.)
File details come from the government source that posted it. Updated .