53.243Changes made to Section 00 11 00 Page 2 of 4 Note No.8 (Not Used) and Note No. 11 corrected to remove "Design" and Section 00 72 00 changed to read 00 73 00. All other terms and conditions remain unchanged.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section: 00 11 00 W9126G18B0030
B2263, Rpr 502 ABW/FSH Multi-Svc Troop & Fam Readiness
FY 18, PN 465205
JBSA - FSH, Texas
CONTRACT LINE ITEM SCHEDULE
<AMENDMENT #0003>
NOTES:
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items of the CLIN Schedule. Failure to do so may result in the offer being unacceptable
NOTE NO. 3. Not Used.
NOTE NO. 4. CONDITIONS GOVERNING EVALUATION OF OFFERS AND AWARD OF CONTRACTS:
The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule. Subject to the availability of funds, the Contracting Officer may exercise the option by written notice to the Contractor within the time indicated below from the Task Order:
NOTE NO. 5. All the extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
NOTE NO. 6. Not Used.
NOTE NO. 7. Not Used
NOTE NO. 8. <AM#0003> CLIN 0001, design includes costs for efforts related to the design of the complex, as well as any related costs for the constructor’s coordination during design (see Section 00 73 00 Special Contract Requirement (SCR): Constructor’s Role During Design). In general, include engineering and designer costs for efforts after the Design Complete or Issued for Construction documents in the construction CLIN’s. Not Used
</AM#0003>
NOTE NO. 9. Include all costs for coordination and accommodation of Government-Furnished, Government- Installed Equipment as described in Section TASK ORDER in the Contract Line Items for construction of the associated facilities.
NOTE NO. 10. Not Used
NOTE NO. 11. The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to Proceed (NTP) is received by the Contractor, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for design and construction through completion, ready for turnover shall not exceed the number of calendar days specified in Section 01 00 00.00 44 Design and Construction Schedule. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP. Also see Sections <AM#0003> 00 72 00 Contract Clauses, clause Commencement, Prosecution and Completion of Work 00 73 00 Supplementary Conditions, Commencement, Prosecution and Completion of Work. </AM#0003>
Section: 00 11 00 W9126G18B0030
B2263, Rpr 502 ABW/FSH Multi-Svc Troop & Fam Readiness
FY 18, PN 465205
JBSA - FSH, Texas
CONTRACT LINE ITEM SCHEDULE
<AMENDMENT #0003>
NOTE NO. 12. At the option of the Government, the Government may require the Contractor to perform the work identified as Optional line item(s) at the price(s) stated in the CLIN Schedule. The Contracting Officer may exercise one or more of the Option(s) by written notice to the Contractor within [__] calendar days after the date of the acknowledgment of the Task Order by the Contractor. There is no separate completion period for these option(s) and the work included therein shall be completed within the contract duration as proposed above.
Exercise of the Option(s) shall be evidenced on Standard Form 30, citing this CLIN Schedule note as the authority for exercising the Option. The Option shall be deemed exercised at the time the Government deposits the SF30 in the mail or, if earlier, at the time it is delivered to the Contractor.
NOTE NO. 13. 52.217-5 EVALUATION OF OPTIONS (JUL 1990)
(a) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(b) The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
NOTE NO. 14. Responders are advised that this requirement may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process based on decisions related to DOD changes in force structure and disposition of the Armed Forces.
NOTE NO. 15. The Army will procure this facility through a design and cost competition in accordance with the provisions set forth in this Request for Proposals (RFP). When the task order is awarded, it will be a "Firm Fixed Price Contract."
NOTE NO. 16. Any proposal that is materially unbalanced as to prices for the Base Schedule may be rejected.
An unbalanced proposal is one that is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work and can also exist where only overpricing or underpricing exists.
NOTE NO. 17. ABBREVIATIONS
For the purpose of this solicitation, the units of measure are represented as follows:
a. JOB
END OF CLIN SCHEDULE