Text version
0010866929 WG-33-8J
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose for this solicitation amendment is to:
a. Update draw ings to Revision 3 FS-3670.
b. Update Revision list for specification coordinator of changes.
c. Add SOW for add alternate Re-roofing. Add one CLIN for alternate (Re-roofing) option "K" Work Subject to Availability of Funds (SAF).
d. Add SOW for ejector removal instructions.
e. All other terms and conditions of the solicitation remain unchamged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Mar-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124M-16-B-0020
X 9B. DATED (SEE ITEM 11)
09-Sep-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Mar-2017
CODE
MISSION & INSTALLATION CONTRACTING CMND
MICC-FORT STEWART ATTN:SFC ANGEL DEL VALLLE 9
H WILSON AVE STE 100 (BLDG 621)
FORT STEWART GA 31314
W9124M 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124M-16-B-0020
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
RE-ROOFING SOW
Add Alternate (Re-roofing) to Renovate Building 620, Fort Stewart (FS), Georgia;
IJO: WG-33-8J (AWP: 17-007) FS3670
Work to be executed: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Add Alternate to Renovate Building 620 complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items:
1. Demolition Scope
a. Remove and dispose of the all existing roofing membrane
b. Remove and dispose of the existing rigid insulation material down to concrete deck.
c. Remove and dispose of the existing aluminum flashing.
d. Remove roof curbs and equipment.
e. Remove existing expansion joint covers.
2. Installation Scope
a. Install treated 2 x 4 lumber blocking.
b. Install 4 x 4 cant strips.
c. Install 2” of polyisocyanurate insulation board.
d. Install #15 roofing felt.
e. Install 1” Perlite insulation.
f. Install .032” thick aluminum flashing at equipment support curbs.
g. Install aluminum drip edge, .016” thick, 5” girth, mill finish.
h. Install a two-ply SBS modified bitumen roof system.
i. Replace roof curbs and equipment.
j. Provide flashing for plumbing vents.
k. Install new expansions joint covers between building sections.
3. Specifications for Roofing are found in project manual under Division 07
a. Section 07.13.53 Elastomeric Sheet Waterproofing
b. Section 07.16.19 Metallic Oxide Waterproofing
c. Section 07.51.13 Built-up Asphalt Roofing
d. Section 07.60.00 Flashing and Sheet Metal
e. Section 07.84.00 Firestopping
REVISION LIST FOR SPECIFICATIO
Renovate Building 620, Fort Stewart (FS), Georgia; IJO: WG-33-8J
(AWP: 17-007) FS3670
1. Specification Changes
General Note -
i. Remove all references to “BOC & NOC”
ii. Remove all references to “Crack Unit”
Remove specification section 23.81.23 in its entirety.
Specification Section 22.00.00
i. Remove 2.4.11 in its entirety
ii. Remove 2.4.12 in its entirety
Specification Section 23.05.93
i. Item 3.3.10.1 Delete “computer room” from Group 1.
Specification Section 23.08.00
i. Remove “Pre-Functional Performance Testing Checklist Computer
Room Unit” in its entirety.
ii. Remove ““Functional Performance Testing Checklist Computer
Room Unit” in its entirety.
SEWAGE EJECTOR REMOVAL SOW
Renovate Building 620, Fort Stewart (FS), Georgia; IJO: WG-33-8J
(AWP: 17-007) FS3670
1. Sewage Ejector Removal SOW
a. Disconnect all utilities from Ejector
i. Power
ii. Water
iii. Sewer
b. Contents of ejector are to be pumped out into an approved transport vehicle to deliver to a waste water treatment facility
c. Triple Rinse out interior of injector of all remaining solids and pump out into an approved transport vehicle to deliver to a waste water treatment facility
d. Removal from Space
i. Option 1 – Removal through existing openings only.
1. Disassembly of ejector is required to remove it from location.
2. Largest section must be of a size to fit through existing doorways and stairwells
ii. Option 2 – Remove Ejector through reopened Masonry wall and open mechanical pit next to space on exterior of building.
1. This option may not require the disassembly of the ejector itself to remove.
e. All sanitary lines feeding the ejector are to be removed.
i. Lines supplying ejector are to be removed to source.
ii. Lines leaving the ejector are to be removed to sanitary main line and capped per plumbing plan notes.
f. Sanitize all surfaces where contaminate materials are spilled or splattered in the process of emptying, disassembly and removal from building.
g. Provide documentation that the ejector was disposed of in accordance with environmental requirements.
i. Location of disposal
ii. Weight ticket.
The following have been deleted:
ENVIRONMENTAL CONSIDERATION
GEOTECHNICAL INVESTIGATION
RESULTS OF ASBESTOS RE-INSPEC.
SECTION B - SUPPLIES OR SERVICES AND PRICES
Global Changes
CLIN 0001 -- CLIN 0004
The PROG code C20 has been added.
The WSC Equipment code 000 has been added.
The SIC code 1542 has been added.
The MDAP/MAIS Code 000 has been added.
CLIN 0002
This CLIN has been renumbered to CLIN 0003.
CLIN 0003
This CLIN has been renumbered to CLIN 0004.
CLIN 0004
This CLIN has been renumbered to CLIN 0005.
The FSC code 5680 has been added.
The NAICS code 236220 has been added.
CLIN 0002 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job Renovate Bldg 620 "K" Work (SAF)
FFP
Renovate Bldg 620 "K" Work. Work for re-roofing (Add Alternate) FOB: Destination
NET AMT
SECTION E - INSPECTION AND ACCEPTANCE
The Acceptance/Inspection Schedule for CLIN 0001 has been changed from:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
N/A N/A N/A Government
To:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
Destination Government Destination Government
The following Acceptance/Inspection Schedule was added for CLIN 0002:
The Acceptance/Inspection Schedule for CLIN 0003 has been changed from:
N/A N/A N/A Government
To:
The Acceptance/Inspection Schedule for CLIN 0004 has been changed from:
N/A N/A N/A Government
To:
The Acceptance/Inspection Schedule for CLIN 0005 has been changed from:
N/A N/A N/A Government
To:
(End of Summary of Changes)
File details come from the government source that posted it. Updated .