Questions_HUAC_AAA00011-4J_Repair_and_Modernize_Elevators_1-4_with_attachment.pdf

PDF 4 MB Posted

Attached to
Elevator Repair and Modernization
Solicitation number
W9124A-19-R-0012
Issued by

About this file

Questions and Answers for Repair and Modernize Elevators Requirement.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers - 20190802: Modernize Elevators 1-8 in Building 61801/WO# AAA00011-4J Requirement

Questions

1. What is the reasoning behind replacing the guide rails? On typical modernizations everything structurally attached to the building remains. It is incredibly rare to hold the elevator vendor responsible for structural attachments to an existing building. This also adds additional time to an already aggressive schedule to disassemble the elevator cab, remove the existing rails, and run new ones for the car and counterweights. ANSWER:

The guide rails shall be replaced if the Qualified Elevator Inspector (QEI) in SOO Paragraphs 4.01.23 and 4.02.21 determines the existing guide rails are worn and will not pass inspection.

2. Are mini-split AC systems acceptable in the rooms that presently have no atmospheric control? ANSWER: Yes.

3. The documents differ on whether or not 3-4 can be modernized concurrently.

Clarification is needed to build an accurate schedule. ANSWER: Yes, Elevators 3 and 4 can be modernized, concurrently.

4. Please identify where space is available for onsite material and a refuse container? ANSWER: An exterior location is approved behind Building 61801 that is within the Building 61801 backside fenced compound for the contractor to drop storage container(s) and refuse container(s). An open lay down area is also authorized within the backside fenced compound or the frontside of Building 61801.

5. Can the tenant provide a toolbox storage/project staging area within the building? ANSWER: The contractor can use the respective elevator machine rooms that have been taken out of service for repair and modernization of the elevators as toolbox storage. Review ANSWER to Question #4 for a project staging area.

6. Can we work 4 days a week at 10 hours a day instead of 5 days a week at 8 hours a day? ANSWER: Yes.

7. Does the project include replacing the Backup Generator ATS as the existing one is manually operated? ANSWER: No.

8. On what date where the shunt trips last tested? ANSWER: The shunt trip was not tested in the known past. If unknown, should testing reveal they are no longer functioning properly is their replacement to be included in the bid or a change order item? ANSWER: A change order item.

9. Is the backup generator and conductor wire capable of supplying power for all cars to run at the same time? ANSWER: Only Elevators 1-2 and 3-4 are currently backed up on the 100 KW (125 KVA) emergency backup generator.

The emergency backup generator and wiring is capable of supporting the existing 480V buses in Elevators 1-2 and 3-4 machine rooms. Elevators 5-8 are not backed up on the emergency backup generator.

10. Who currently services your fire control system? ANSWER: Simplex® When was the last reported test and were there any faults? ANSWER: The last tests were completed 4th Quarter 2018 by Simplex®. The smoke detectors in the lobbies of Elevators 1-8 were verified in July 2019 and each smoke detector reports to the respective Fire Alarm Control Panels (FACP) as shown in Questions and Answers (Q&A) Attachment AA. The smoke detectors in Elevator 1-2 and 3-4 elevator shafts and pits could not be verified. All heat detectors in the lobbies of Elevators 1-8, and the heat detectors in Elevator 1- 2 and 3-4 machine rooms, were verified to not cause a FACP but should have if the heat detectors were functioning correctly.

Without assistance from Simplex®, the heat detectors are assumed to not be connected to the respective FACP for the particular zone.

11. When was the last time the smoke/heat detectors were last tested that are integrated with the elevator control system? ANSWER: Not tested in the known past. Are there any smoke/heat detectors that are non-functioning, and if so, please identify which ones? ANSWER: Review ANSWER to Question #10.

12. What is the total length for all cloth insulated electrical cables for supply and back up electrical feeds that needs to be replaced? ANSWER: The distance from the elevator machine rooms to the respective mechanical/electrical rooms on the 3rd Floor are approximately 100 feet. The contractor will need to determine the total amount of cable length. Does the conduit associated with these cables require replacing or can we reuse existing? ANSWER: The contractor will need to determine if the conduit is undamaged and sufficient.

13. What is the ability to obtain an additional maintenance period beyond the 5-year warranty period? ANSWER: An additional maintenance period is not required.

14. Will the new controllers be required to be regenerative AC-VVVF? ANSWER:

The contractor shall determine.

15. Will the replacement machines be required to be geared or PMAC gearless?

ANSWER: There is no preference for either; the contractor shall determine.

16. On the passenger elevators, is a closed-loop, AC linear drive door operator and related equipment requested/required for enhanced/improved operation?

ANSWER: No, not unless UFC 3-490-06, ASME A17.1 or ASME A17.3 requires the equipment.

17. Why are guide rails being replaced (smaller 8lb. existing?)? ANSWER:

Review ANSWER to Question #1.

18. What seismic code is required for this project? ANSWER: Fort Huachuca Master Planning states Seismic Zone 2B. Review SOO Attachment D for As Constructed drawing 35-06-01 of Building 61801 Ground Floor and Foundation Plan for a seismic zone as of August 1959.

19. Do the freight elevators require new bumper rails to be installed on the sides and rear of the elevator and if yes, are upper and lower rails required to be priced? ANSWER: The bumper rails shall be installed if the Qualified Elevator Inspector (QEI) in SOO Paragraphs 4.01.23 and 4.02.21 determines the freight elevators will not pass inspection.

20. Is LED lighting required to be installed in the elevator OH also? ANSWER:

LED lighting is required to be installed where existing non-LED lighting exists, and LED lighting is required where the Qualified Elevator Inspector (QEI) in SOO Paragraphs 4.01.23 and 4.02.21 determines lighting needs to be installed.

21. If suspected asbestos is found NOT listed in the report provided, will we be required to cease working in that area or can work continue exclusive of disturbing the suspected asbestos? ANSWER: Upon discovery, the contractor shall stop work and identify the location(s). The contractor will need to submit a Request For Information (RFI) to the contracting office of the discovery and ask what course of action to be taken.

22. Will the new hall and car door equipment be replaced with new on the passenger elevators (i.e. car and hall tracks, hangers, pick-ups, interlocks, linkage, gate switch, operator, restrictor, clutch, etc.)? Answer: Review SOO Modification #1 dated 17 July 2019, Paragraphs 4.01.14 through 4.01.16 for requirements.

23. For the freight elevator nos. 5-8 alternate where new replacement doors are specified, does this include all linkage, retiring cams, motors, gates, tracks AND door panels? ANSWER: Review SOO Modification #1 dated 17 July 2019 as no new replacement doors for freight elevators 5-8 are required.

24. Are hall position indicators and/or hall lanterns required at each landing of the passenger elevators? ANSWER: Yes.

25. Does the traveling cable/hoistway wiring require RG5/6U cabling and 10-15% spare wiring? ANSWER: The new traveling cables need to satisfy the existing technology currently in use with each elevator unless the contractor determines newly installed equipment under SOO Modification #1 for work order HUAC AAA00011-4J requires a different traveling cable. No new technology is expected to be installed for the elevators in the future.

26. Are 24-hour callbacks to be covered at no cost for all warranty-service calls or will it be based on an OT-ST split with the client paying the overtime cost differential for after-hours callbacks? ANSWER: SOO Modification #1 Paragraphs 4.01.24, 4.02.22, and 18.0 are to be addressed proposal.

27. Will non-Code compliant machine room entrances need to be replaced to meet Code? ANSWER: Yes as required in SOO Modification #1 Paragraphs

4.01.21 and 4.02.20.

28. Will the signal fixtures are surface mount fixtures in the hallways acceptable?

ANSWER: No, the lobby and hallway fixtures need to be recessed.

29. How many crews are required simultaneously on this project as each elevator undergoing modernization requires its own crew? ANSWER: The contractor shall determine the crews in order to comply with SOO Modification #1, Paragraphs 3.13 through 3.15.

30. The Line Items do not make it clear if the total project length is 255 days total or 255 working days for the base bid and an additional 255 days for the Option, thus 510 days total. Can you clarify? ANSWER: The total project duration for the base award and the OPTION award is 255 working days.

SOO Modification #1, Paragraph 5.01, requires no later than 180 working days to complete all work to satisfy Paragraph 4.01 and all subparagraphs of Paragraph 4.01. SOO Modification #1, Paragraph 5.02, requires an additional 75 working days for the OPTION to be added to the base award duration.

31. The speed of the freight elevators should be denoted on the governor or the crosshead data tag. The tag was missing on the governor and we did not access the top of the car where we could have looked at the crosshead data tag to get the car speed. What is the speed of Freight Elevators 5 & 6 and 7 & 8? ANSWER: The speed of Elevators 5, 6, 7, and 8 is 100 FPM as gathered from each respective crosshead data tag.

32. What is the empty car weight of the freight elevators? ANSWER: The empty car weight is 8500 lb. for Elevators 5 and 6. The empty car weight is 20,600

lb. for Elevators 7 and 8. The car weight values are gathered from each respective crosshead data tag.

33. We were not able to see the top of the inside the Hoistway of the passenger elevators. Are the existing door operators manufactured by MAC?

ANSWER: The door operators for each of the passenger elevators (Elevators 1, 2, 3, and 4) are GAL-mov.

34. Are the Main Guiderails for the Passenger Elevators 15# or18# rails?

ANSWER: The Main Guiderails are 15 lb. /ft. for Elevators 1, 2, 3, and 4.

35. Are the Counterweight Guiderails for the Passenger Elevators 8# or 15# rails? ANSWER: The Counterweight Guiderails are 8 lb. /ft. for Elevators 1, 2, 3, and 4.

36. Are the Main Guiderails for the Freight Elevators 15#, 18# or 30# rails?

ANSWER: The Main Guiderails are 30 lb. /ft. for Elevators 5, 6, 7, and 8.

37. Are the Counterweight Guiderails for the Freight Elevators 8#, 15# or 18# rails? ANSWER: The Counterweight Guiderails are 8 lb. /ft. for Elevators 5 and 6. The Counterweight Guiderails are 15 lb. /ft. for Elevators 7 and 8.

38. Can the machine room wall be saw cut where the ventilation in a size large enough to move the new machine in in one (1) piece? A door or panel can then be installed in the sawcut hole for future removal of any other elevator equipment. ANSWER: Yes, provided the contractor submits structural engineer approved designs of the work to include shoring and repair of the cutout beforehand to the government for review and approval.

39. Is the elevator contractor to perform any warranty and/or interim maintenance? ANSWER: The contractor is obligated to adhere to SOO Modification #1 Paragraphs 4.01.24, 4.02.22, and 18.0 for warranty duration and requirements.

40. Is the warranty on new equipment 12 months? ANSWER: Review ANSWER to Question #39.

41. Are Passenger Elevators 1 through 4 the base bid and Freight Elevators 5 through 8 are alternate bid items? ANSWER: Elevators 1-4 in SOO Modification #1, Paragraph 1.01, is the base award. Elevators 5-8 in SOO Modification #1, Paragraph 1.02, is the OPTION award.

42. We would like to get a quote for any fire alarm work that is necessary for this elevator modernization. Does the army have contact information for the existing Fire Prevention Fire Alarm Maintenance Contractor? ANSWER: The fire alarm control system is by TYCO SimplexGrinnell at (520) 887-0245. The Simplex Point of Contact is Steve Linde (steven.linde@jci.com) who is the Fire and Life Safety Account Rep at direct (520) 407-4029 and mobile (520) 305-6501.

43. We would like to get a quote for any Emergency Generator/ATS work that is necessary for this elevator modernization. Does the army have contact information for the existing Emergency Generator / ATS Maintenance Contractor? ANSWER: The contact for the emergency backup generator and the ATS for Elevators 1-4 in Building 61801 is John Morales at (520) 533- 1248.

44. There are no pictures of the inside of the freight elevator cars and no pictures of the car operating panels. Can you please verify the number of stops and the number of openings for each of the four (4) freight elevators? ANSWER:

Elevators 5-6 have two (2) doors with four (4) stops at Floors 1, 2, 3, and Rooftop. Elevators 7-8 have two (2) doors with three (3) stops at Floors 1, 2, and 3.

45. Do the exterior floor indicators for Elevators 7 and 8 need to be within a

NEMA enclosure? ANSWER: The contractor is required to provide design/build services as stated in SOO Paragraph 2.04.

46. Is there a table and drawing that shows the locations of the FACP for

Elevators 1-4 and Elevators 5-8? ANSWER: Review Q&A Attachment AA.

Q&A Attachment AA contains Building 61801 FACP Locations for Elevators 1-8 and a Building 61801 drawing of fire alarm system nodes and zones.

47. Correction to SOO Modification #1, Paragraph 3.14. ANSWER: The contractor shall initially repair and modernize elevators 1-2 and place both elevator cars into operational service before removing elevators 3-4 from service.

48. Correction to SOO Modification #1, Paragraph 3.15. ANSWER: Upon award of the SOO OPTION, the contractor shall initially repair and modernize elevators 1-2, 5, and 7 simultaneously.

49. Please confirm the “Buy American Act” applies to this project?

Yes the Buy American Act Applies

50. Will the Army consider change orders to eliminate unnecessary work, with associated deduction in contract amount, should we find components, like the safeties, to be properly functioning without wear and a 20 year remaining service life?

Yes

51. Item #1. Bid Bond. Para 13.b, SF1442 (Pg 1) indicates no bid bond required.

We've found a Company unable to provide a bid bond is highly unlikely to provide Pay and Performance bonds. Thus, requiring a bid bond largely eliminates the post-award problem of a Low Bidder who cannot bond the work.

This has been corrected. A bid bond it required.

52. Will any cab interior modifications or replacement items be included in the base proposal? ANSWER: Yes. Review SOO Modification #1, Paragraphs 4.01.04, 4.01.06, 4.01.14, 4.01.15, 4.01.16, and 4.01.17. If yes, is this per an allowance or is there a set design to price? ANSWER: The items are a set design as the contractor is required to replace the items as stated in the SOO Modification #1, Paragraphs 4.01.04, 4.01.06, 4.01.14, 4.01.15, 4.01.16, and 4.01.17.

53. Specify Multiple Elevators. ACC-APG has ample justification to require an Offeror to simultaneously modernize multiple elevators instead of doing one at a time sequentially. Discussed at the Pre-Bid but I could not locate in the Draft Solicitation, the building's mission and secure nature requires Soldiers to physically escort Project Personnel while onsite, and there are tool checks, electronic devices, and the inherent liability of unsecure personnel overhearing or seeing something they shouldn't. Plus, the nature of elevator modernizations will routinely require 2 Soldier escorts given elevator tasks often place one elevator mechanic in the car while the other is in the control/machine room. Loosing 2 Soldiers to daily escort duty is a drain on the Command and adversely impacts mission, so ACC-APG is well within its right to require an Offeror to provide multiple elevator crews as an explicit condition of the contract to minimize the security risks and Soldier escort.

SUGGESTION: Specify in Solicitation that Offerors must identify in their Technical Proposal how they will modernize 2 or more elevators simultaneously throughout the duration of the Project.

ANSWER: SOO Modification #1, Paragraph 3.14, states the contractor initially shall repair and modernize elevator sets 3-4 which are a pair of passenger elevators. Upon award of the SOO OPTION, SOO Modification #1 Paragraph 3.15 states the contractor shall initially repair and modernize elevators 3-4, 6, and 8 simultaneously. The HHC commander has committed to provide escorts for the duration of the awarded project, HUAC AAA00011- 4J.

54. Materials Onsite. The FAR allows, and nature of elevator modernization is customarily payment for, materials once onsite, inventoried and securely stored. Every site's elevators are somewhat unique to that site and factories tool to fabricate these site-specific items all at once, and provide all at once, rather than trickle them out a couple at a time for economy, consistency and commonality. So, materials for all elevators will arrive Ft. Huachuca all at once, and be inventoried locally and placed onsite in secured containers or in a bonded warehouse out in town. The Contractor is following the FAR and you cannot reasonably expect a contractor to bear the considerable cost of these materials when they are quite expensive, unique to the Project's elevators, and would be retained by the Government and used to modernize the elevators even if the Contractor defaulted. It's a significant--if not huge--effort to do the engineering surveys, get the submittals assembled, reviewed, accepted and materials fabricated, assembled and shipped to Ft. Huachuca.

Whomever receives the award deserves payment for the considerable amount of work it takes to get materials onsite.

SUGGESTION: Remove the uncustomary statement that materials will not be paid until installed.

Payment will be in accordance with FAR 52.232-5

QUESTIONS ATTACHMENT AA

Building 61801 Fire Alarm Control Panel (FACP) Locations for Elevators 1-8

Q&A 1-7
Ed Addressed Questions for Contracting Modernize Elevators 1-8 Building 61801
Q&A8-10