REPAIR BUILDING 600

MAINTENANCE HANGAR

TYPE B-3 FINAL

NEBRASKA AIR NATIONAL GUARD

LINCOLN, NE

PROJECT MANUAL

VOLUME 1

May 9, 2017

Contract Number: W91243-14-D-0001 Task Order: 0002

Project Number: NGCB112003

SCHEMMER PROJECT NO. 06565.002

NEANG BUILDING 600 06565.002 MAY 2017

TABLE OF CONTENTS TOC - 1

REPAIR BUILDING 600

MAINTENANCE HANGAR

TABLE OF CONTENTS

VOLUME 1

DIVISION 1 - GENERAL REQUIREMENTS

Section 010000 Section 011000 Section 012300 Section 012500 Section 012600 Section 013100 Section 013200 Section 013300 Section 014000 Section 015000 Section 016000 Section 017300 Section 017329 Section 017419 Section 017700 Section 017823 Section 017839 Section 017900 Section 018113 Section 019113

General Requirements Summary Options Substitution Procedures Contract Modifications Procedures Project Management and Coordination Construction Progress Documentation Submittal Procedures Quality Requirements Temporary Facilities and Controls Product Requirements Execution Cutting and Patching Construction Waste Management and Disposal Closeout Procedures Operation and Maintenance Data Project Record Documents Demonstration and Training Sustainable Design Requirements General Commissioning Requirements

DIVISION 2 – EXISTING CONDITIONS

Section 024119 Selective Demolition Section 028213.00 10 Asbestos Abatement Section 028313.00 20 Lead in Construction

DIVISION 3 - CONCRETE

Section 033000 Cast-in-Place Concrete Section 034100 Precast Structural Concrete

DIVISION 4 - MASONRY

Section 040120.64 Brick Masonry Repointing, Repair, and Concrete Cleaning (Option No. 6) Section 042000 Unit Masonry

DIVISION 5 - METALS

Section 051200 Structural Steel Framing Section 053100 Steel Decking Section 055000 Metal Fabrications Section 055113 Metal Stairs Section 055213 Pipe and Tube Railings

TABLE OF CONTENTS TOC - 2

DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES

Section 061000 Rough Carpentry Section 062023 Interior Finish Carpentry Section 064113 Wood-Veneer-Faced Architectural Cabinets Section 064116 Plastic-Laminate-Faced Architectural Cabinets

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

Section 071900 Water Repellents Section 072100 Thermal Insulation Section 072120 Spray Acoustic-Thermal Insulation Section 072140 Foam-In-Place Insulation Section 072726 Fluid-Applied Membrane Air Barriers Section 074113 Metal Roof Panels Section 074219 Smooth Aluminum Metal Plate Wall Panels Section 075323 Ethylene-Propylene-Diene-Monomer (EPDM) Roofing Section 076200 Sheet Metal Flashing and Trim Section 078413 Penetration Firestopping Section 079200 Joint Sealants

DIVISION 8 - OPENINGS

Section 081113 Hollow Metal Doors and Frames Section 081416 Flush Wood Doors Section 083113 Access Doors and Frames Section 083323 Overhead Coiling Doors Section 083416.10 Bi-Parting Bottom Rolling Hangar Door Refurbishment (Base Bid) Section 083416.20 Bi-Parting Bottom Rolling Hangar Door (Option No. 3) Section 083613 Sectional Doors Section 084113 Aluminum-Framed Entrances and Windows Section 087100 Door Hardware Section 088000 Glazing Section 089520 Insulated Translucent Fiberglas Sandwich Panel Wall System

DIVISION 9 - FINISHES

Section 092216 Non-Structural Metal Framing Section 092900 Gypsum Board Assemblies Section 093013 Ceramic Tiling Section 095113 Acoustical Panel Ceilings Section 096513 Resilient Base and Accessories Section 096519 Resilient Tile Flooring Section 096536 Static Dissipative Resilient Flooring Section 096723.16 Fuel Resistive Resinous Flooring, 5-Coat System Section 096813 Tile Carpeting Section 097200 Wall Coverings Section 098433 Sound-Absorbing Wall Units Section 099113 Exterior Painting Section 099123 Interior Painting Section 099300 Staining and Transparent Finishing Section 099990 Color Schedule

TABLE OF CONTENTS TOC - 3

DIVISION 10 - SPECIALTIES

Section 101200 Display Cases Section 101400 Metal Signage Section 101423.13 Room Identification Signage Section 102113 Toilet Compartments Section 102239 Folding Panel Partitions Section 102600 Wall Protection Section 102800 Toilet Room Accessories Section 104413 Fire Extinguisher Cabinets Section 104416 Fire Extinguishers Section 105113 Metal Lockers

DIVISION 11 - EQUIPMENT

Section 115213 Projection Screens

DIVISION 12 - FURNISHINGS

Section 126100 Fixed Audience Seating

DIVISION 13 - SPECIAL CONSTRUCTION

Not Used

DIVISION 14 - CONVEYING SYSTEMS

TABLE OF CONTENTS TOC - 4

VOLUME 2

DIVISION 21 – FIRE SUPPRESSION

Section 211313 Automatic Sprinklers and Standpipes – Support Areas Section 211313-01 Automatic Sprinklers and Standpipes – Hangar Areas Section 211340 HEF Foam Fire Protection Specification

DIVISION 22 – PLUMBING

Section 220513 Common Motor Requirements for Plumbing Equipment Section 220516 Expansion Fittings and Loops for Plumbing Piping Section 220517 Sleeves and Sleeve Seals for Plumbing Piping Section 220518 Escutcheons for Plumbing Piping Section 220519 Meters and Gages for Plumbing Piping Section 220523.12 Ball Valves for Plumbing Piping Section 220523.14 Check Valves for Plumbing Piping Section 220529 Hangers and Supports for Plumbing Piping and Equipment Section 220553 Identification for Plumbing Piping and Equipment Section 220719 Plumbing Piping Insulation Section 221116 Domestic Water Piping Section 221119 Domestic Water Piping Specialties Section 221316 Sanitary Waste and Vent Piping Section 221319 Sanitary Waste Piping Specialties Section 221319.13 Sanitary Drains Section 224213.13 Commercial Water Closets Section 224213.16 Commercial Urinals Section 224216.13 Commercial Lavatories Section 224216.16 Commercial Sinks Section 224223 Commercial Showers Section 224500 Emergency Plumbing Fixtures Section 224716 Pressure Water Coolers

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING

Section 230130.51 HVAC Air Duct Cleaning Section 230513 Common Motor Requirements for HVAC Equipment Section 230517 Sleeves and Sleeve Seals for HVAC Piping Section 230518 Escutcheons for HVAC Piping Section 230519 Meters and Gages for HVAC Piping Section 230523.12 Ball Valves for HVAC Piping Section 230523.13 Butterfly Valves for HVAC Piping Section 230523.14 Check Valves for HVAC Piping Section 230529 Hangers and Supports for HVAC Piping and Equipment Section 230548.13 Vibration Controls for HVAC Section 230553 Identification for HVAC Piping and Equipment Section 230593 Testing, Adjusting, and Balancing for HVAC Section 230713 Duct Insulation Section 230716 HVAC Equipment Insulation Section 230719 HVAC Piping Insulation Section 230800 Commissioning of HVAC Systems Section 230923 Direct Digital Control (DDC) System for HVAC Section 230923.11 Control Valves Section 230993.11 Sequence of Operations for HVAC DDC

TABLE OF CONTENTS TOC - 5

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING (continued)

Section 231123 Facility Natural-Gas Piping Section 232113 Hydronic Piping Section 232116 Hydronic Piping Specialties Section 232123 Hydronic Pumps Section 232300 Refrigerant Piping Section 233113 Metal Ducts Section 233300 Air Duct Accessories Section 233346 Flexible Ducts Section 233423 HVAC Power Ventilators Section 233600 Air Terminal Units Section 233713.13 Air Diffusers Section 233713.23 Registers and Grilles Section 236423.21 Air-Cooled, Scroll Water Chillers Section 237200 Air-to-Air Energy Recovery Equipment Section 237313 Modular Indoor Central-Station Air-Handling Units Section 238239.13 Cabinet Unit Heaters

DIVISION 26 - ELECTRICAL

Section 260513 Medium-Voltage Cables Section 260519 Low-Voltage Electrical Power Conductors and Cables Section 260526 Grounding and Bonding for Electrical Systems Section 260529 Hangers and Supports for Electrical Systems Section 260533 Raceway and Boxes for Electrical Systems Section 260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling Section 260553 Identification for Electrical Systems Section 260572 Overcurrent Protective Device Short-Circuit Study Section 260574 Overcurrent Protective Device Arc-Flash Study Section 260800 Commissioning of Electrical Systems Section 260923 Lighting Control Devices Section 260943.23 Relay-Based Lighting Controls Section 261116.12 Secondary Unit substations with Switchboards Secondary Section 262200 Low-Voltage Transformers Section 262413 Switchboards Section 262416 Panelboards Section 262726 Wiring Devices Section 262813 Fuses Section 262816 Enclosed Switches and Circuit Breakers Section 262913.03 Manual and Magnetic Motor Controllers Section 263213.13 Diesel Emergency Engine Generators Section 263323.11 Central Battery Equipment for Emergency Lighting Section 263600 Transfer Switches Section 264313 Surge Protection for Low-Voltage Electrical Power Circuits Section 265119 LED Interior Lighting Section 265619 LED Exterior Lighting

TABLE OF CONTENTS TOC - 6

DIVISION 27 - COMMUNICATIONS

Section 270526 Grounding and Bonding for Communications Systems Section 270528 Pathways for Communications Systems Section 270536 Cable Trays for Communications Systems Section 271100 Communications Equipment Room Fittings Section 271313 Communications Copper Backbone Cabling Section 271323 Communications Optical Fiber Backbone Cabling Section 271333 Communications Coaxial Backbone Cabling Section 271513 Communications Copper Horizontal Cabling Section 271523 Communications Optical Fiber Horizontal Cabling Section 275120 Digital Signal Matrix Switcher and Transmission System Section 275123.20 Commercial Intercommunications and Program Systems

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

Section 280513 Conductors and Cables for Electronic Safety and Security Section 280528 Pathways for Electronic Safety and Security Section 283100 Fire Detection and Mass Notification System

DIVISION 31 – EARTHWORK

Section 311000 Site Clearing Section 312000 Earth Moving

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 320119.61 Resealing of Joints in Rigid Pavement Section 321313 Concrete Paving Section 321373 Concrete Paving Joint Sealants Section 321723 Pavement Markings Section 329200 Turf and Grasses

DIVISION 33 thru 41

GENERAL REQUIREMENTS 010000 - 1

SECTION 010000

GENERAL REQUIREMENTS

PART 1 – INSURANCE – MINIMUM AMOUNTS

1.1. Reference Contract Clause titled, “Insurance -Work on a Government Installation (FAR 52.228-5).

Kinds and minimum amounts are as follows:

KIND AMOUNTS (FAR 28.307-2)

Workmen’s Compensation $100,000 (see paragraph 1.2, below)

Comprehensive General Liability $500,000 per occurrence for bodily injury

Comprehensive Automobile Liability $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage

(If applicable) $200,000 per person and $500,000 per occurrence Aircraft Public and Passenger for bodily injury, other than passenger Liability liability and $200,000 per occurrence for property damage; coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats $200,000 multiplied by the number of seats or passengers, whichever is greater

1.2. Except in states with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.

1.3. NOTE: Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government’s interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The Contractor shall maintain a copy of proofs of required insurance, and shall make copies available to the Contracting Officer upon request. The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

PART 2 - ORDER OF PRECEDENCE (REFERENCE FAR 52.236-21)

Any inconsistency in this solicitation or contract will be resolved by giving precedence in the following order:

1) Representations and other instructions,

2) Contract clauses,

3) Other documents, to include special contract requirements Section 00800, exhibits, and attachments,

4) The specifications

5) The drawings

GENERAL REQUIREMENTS 010000 - 2

PART 3 - SCHEDULING

3.1. Normal base work hours for the Contractor will be between the hours of 7:00 AM through 4:30 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer’s Representative (COR) five (5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces. When the COR determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days.

However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

3.2. The following Federal legal Holidays are observed by this base:

New Year’s Day 1 January Martin Luther King’s Birthday Third Monday of January President’s Day Third Monday of February Memorial Day Last Monday of May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veteran’s Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

3.3. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday;

holidays falling on a Sunday will be observed on the following Monday.

3.4. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the contractor must notify the Contracting Officer (or the Contracting Officer’s Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The purpose of the above precautions is to ensure construction inspection and recording of work proceedings.

3.5. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.

PART 4 - INVOICING AND PAYMENT

4.1. Properly prepared invoices, bearing the contract number, shall be submitted electronically to the contracting officer on the designated invoice forms provided at the pre-construction meeting PRIOR to uploading in Wide Area Workflow (WAWF), the DFAS payment system. This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow (WAWF). See end of this Section for important information and codes needed.).

Payment will be made by in accordance with FAR Clause 52.232-5 Fixed-Price Construction Contracts and FAR Clause 52.232-27, Prompt Payment for Construction Contracts. All payments will be made by electronic transfer of funds (EFT).

4.2. To meet compliance with DFARS 252.232-7003, Electronic Submission of Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://wawf.eb.mil. Payment will be made by the

GENERAL REQUIREMENTS 010000 - 3

payment office specified in the contract award in accordance with the clauses Payments under Fixed-Price Construction Contracts, FAR 52.232-5, and Prompt Payment for Construction Contracts, FAR 52.232-27.

4.3. The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment. Do not input invoice into WAWF until the pre-approval of invoice is received from the contracting officer. This will lessen the need for rejections in WAWF Payment may be withheld unless all contractual requirements including but not limited to: RECEIPT OF PROPER WEEKLY PAYROLLS IAW DAVIS BACON REQUIREMENTS, have been timely received.

4.4. All requests for payments through WAWF must include a Subcontractor Payment Register pursuant to FAR Clause 52.232-5 and a contractor’s certification that reads as follows:

I hereby certify, to the best of my knowledge and belief that – All amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract; All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and requirements of Chapter 39 of Title 31, United States Code; This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from subcontractor or supplier in accordance with the terms and conditions of the subcontract; and This certification is not to be construed as final acceptance of a subcontractor’s performance.

4.5. A release of claims is required for all final payment requests and shall be submitted by the contractor with the final invoice.

PART 5 - CONTRACT ADMINISTRATION

5.1. The contracting office of the USPFO for Nebraska, Contracting Office, 2433 NW 24th St., Lincoln, NE is the office having administrative jurisdiction over this contract for all matters. A list of the names and telephone numbers of the Government team comprising the contract administrator, Contracting Officer’s Representative (COR), consultant, and point of contact at the project site will be provided at the post-award/pre-construction conference.

5.2. All correspondence shall be addressed to the Contracting Officer. A copy of all correspondence shall be furnished to the contracting officer’s representative. Enclosures attached to or transmitted with the correspondence shall also be furnished with an original and one copy. Each letter shall make reference to the contract name, contract number, project number, and project title, and shall have only one subject. For tracking purposes, a sequential numbering system should be used for all correspondence.

PART 6 - PAPERLESS CONTRACTING

6.1. The National Guard is fully committed to the Federal Government’s electronic commerce and paperless contracting initiatives. As such, it is anticipated that to the maximum extent possible to include but not limited to correspondence, modification distribution, etc., to include specifications and drawings, will be issued using electronic methods, i.e., electronic mail (e-mail). Contractors shall have and maintain capability to receive documents in this manner.

6.2. Additionally, it is anticipated that within the life of this contract, other electronic processes will be enacted. These include, but are not limited to, electronic bidding/offers, change order proposals, and electronic invoicing. When implemented by the Contracting Officer, contractors shall participate fully in any of these new requirements at no additional cost to the Government.

GENERAL REQUIREMENTS 010000 - 4

PART 7 - TELEPHONE COMMUNICATIONS SECURITY MONITORING

7.1. All communications with DOD organizations are subject to communications security (COMSEC) review. Contractor personnel must be aware that telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The contractor shall assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.

PART 8 - UTILITY SERVICES

8.1. The Contracting Officer has determined that Government-operated utilities are adequate and will be furnished to the contractor without charge where existing outlets are available. The contractor is responsible for installing temporary service outlets, as necessary, at its own expense in accordance with the clause entitled “Availability and Use of Utility Services” (FAR Clause 52.236- 14).

PART 9 - PREPARATION OF MATERIAL APPROVAL SUBMITTALS

9.1. The contractor shall submit all materials and articles requiring approval, as required by the Material and Workmanship Clause, FAR 52.236-5 and Specification Section 01 33 00.

Submittals shall be made using AF Form 3000. Submittals shall be processed in accordance with the procedures in Section 01 33 00, Submittals. Submittals shall be given a distinct identification system as per the Specification requirements. Address for delivery of submittals will be provided at the post award/pre-construction conference. The contractor is reminded that an individual within the company who has authority to make the certification must sign the certification on the AF Form 3000.

PART 10 - WORK PROGRESS AND PREPARATION OF PROGRESS SCHEDULES AND REPORTS

10.1. A bi-weekly meeting may be held with the Contractor, COR and Contracting Officer (KO), if necessary, to discuss work progress, problems and potential change orders. The Contractor shall attend these meetings at no additional cost to the Government. Prior to beginning work on specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premises and buildings; space for storage of materials and equipment; delivery of materials; and use of approaches, use of corridors, stairways and similar means of passage.

A. In accordance with FAR Clause 52.236-15, “Schedules for Construction Contracts”, the contractor shall within five days after work commences on the contract, or another period of time determined by the KO, prepare and submit to the KO for approval three copies of a practicable schedule showing the order in which the contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing features of work.

A composite schedule for the overall contract shall also be provided. The schedule shall be on an AF Form 3064, Contract Progress Schedule, or an approved computer generated format similar to the AF Form 3064. The work shall be scheduled so that, upon the start of construction, work progresses in a continuous and diligent manner. A schedule which does not reflect steady and reasonable progress throughout the construction period will be rejected.

Both the Contractor and the COR are required to provide monthly progress reports covering the period from notice to proceed through final inspection. Unless agreement cannot be made on the applicable percentage of progress a joint report will be submitted to the Contracting Officer. This reports shall be submitted on the NGB Contract Progress Report form (similar to an AF Form 3065), or an approved computer generated similar format. These reports shall

GENERAL REQUIREMENTS 010000 - 5

track progress by CLIN, if contract contains multiple CLINs, multiple AF Form 3064 and NG Contract Progress Reports will also be required for payment purposes.

10.2. Additionally, for projects exceeding $1M, the contractor shall provide a project plan in a commercially available network scheduling software that meets requirements of the specification to define work tasks and track progress. At least five days prior to work initiation, the contractor shall provide the Contracting Officer a hardcopy CPM and a formatted diskette or CD copy, or e-mail file copy, of the plan that shall include definition of rescues. No work may start until the Contracting Officer approves the plan in writing.

10.3. The Contractor shall prepare a work progress schedule required for completion of each of the various divisions of work. Updated plans and Form 3064 showing work progress (hardcopy and formatted diskette or CD, or e-mail file copy), unless otherwise directed by the Contracting Officer, shall be provided on a monthly basis with the pay application, also if there are possible deviations from the original plan, those must be noted and approved by the Contracting Officer before work changes are implemented. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts”. The reports contemplated by the clause herein titled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule” and a National Guard Contract Progress Report”.

PART 11 - NOTICE OF COMPLETION OF CONSTRUCTION/PRE-FINAL AND FINAL INSPECTION

11.1. The contractor shall conduct a pre-final inspection in the presence of the Contracting Officer’s Representative (COR) prior to the date scheduled for Final Inspection. Any discrepancies noted shall be corrected prior to Final Inspection.

11.2. The contractor shall request scheduling of a final inspection in writing to the Contracting Officer at least fourteen (14) working days prior to the desired date or as otherwise negotiated with the Contracting Officer.

11.3. Civil Engineering personnel and the Contracting Officer will perform the Final Inspection in the presence of the contractor, and any discrepancies noted shall be corrected within the time specified by the Contracting Officer.

11.4. Final Inspection shall not constitute acceptance of a project unless so stipulated by issuance of a separate acceptance notice.

11.5. The contractor is cautioned to ensure they have completed adequate Quality Control reviews prior to scheduling pre-final or final inspections. In the event the Contracting Officer finds that the project is not ready for the applicable inspection, (too many discrepancies) the contractor may be held liable for the costs of a repeat inspection. If the inspection involves A/E personnel these costs may include additional labor, travel and miscellaneous expenses.

PART 12 - DESIGNATION OF TECHNICAL REPRESENTATIVE

12.1. The Contracting Officer will appoint a qualified Contracting Officer’s Representative (COR) for the purposes of technically administering the contract; however, all matters concerning this contract or any work ordered placed against this contract must first be approved by the Contracting Officer. This in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in terms of the contract.

PART 13 - CONTRACTOR STAFF AND EMPLOYEES

GENERAL REQUIREMENTS 010000 - 6

13.1. Prior to commencing on-site construction, the contractor shall provide the Contracting Officer with a telephone number and FAX number at which the contractor or his representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.

13.2. Supervision. The Government shall not exercise any supervision or control over the contractor employees performing services under this contract; such employees shall be accountable not to the Government, but solely to the contractor, who in turn is responsible to the Government.

13.3. Contractor’s Employees. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may, in writing, require the contractor to remove from the job site, any employee the Contracting Officer deems incompetent, careless or otherwise objectionable.

PART 14 - CONTRACTOR OFFICE AND STORAGE

14.1. Parking of contractor vehicles shall be restricted to the contractor’s designed on-site area or the work area. The company name shall be prominently displayed on all construction vehicles parked on the job site.

14.2. Security of material storage areas on the job site shall be the responsibility of the contractor. The area shall be kept neat and orderly and free of debris.

PART 15 - RECORD DRAWINGS

15.1. During construction of a project and on the job site, the contractor shall maintain a completed record of all changes and corrections from the layout shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly, and submit the “red line” drawings to the Contracting Officer upon completion of the project. The record drawings shall indicate all changes and corrections concerning the actual locations of all sub-surface utility lines. In order for the location of these lines and appurtenances to be determined in the event the surface opening or indictors become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of the each run including each change in direction. Valves splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded. The Government does not guarantee the accuracy of existing record drawings; it is the contractor’s responsibility to verify all as-built conditions.

PART 16 - VERIFICATION OF DIMENSIONS

16.1. The contractor shall be responsible for the coordination and proper relation of all aspects of the work. He/she shall field verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with any phase of the work. Where exact locations are not given for the positioning of equipment and devices, they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts.

PART 17 - SECURITY REQUIREMENTS

17.1. The contractor shall comply with all security regulations imposed by the base/post commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.

17.2. It is expected that new security requirements to satisfy contractor personal identification requirements in Homeland Security Presidential Directive (HSPD-12), ''Policy for a Common Identification Standard for Federal Employees and Contractors,'' and Federal Information

GENERAL REQUIREMENTS 010000 - 7

Processing Standards Publication (FIPS PUB) Number 201, ''Personal Identity Verification (PIV) of Federal Employees and Contractors” are incorporated in the life of this contract. Contractor shall comply with all requirements, at no additional cost to the Government.

17.3. The contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.

17.4. Contractors shall follow instructions provided by the Security Forces for access to the Lincoln Air National Guard Base, Lincoln, NE. If access is not granted to a contractor allowing the delivery of goods, execution of warranty support, or performance of services please contact the contracting officer. Be sure that all of your employees have the proper ID (drivers license, state ID, immigration card, U.S. Passport, etc.). If they do not have the proper ID, they will be turned away.

17.5. The Prime Contractor and all of its subcontractors will be required to wear orange or lime colored safety vests while performing work on the installation.

17.6. U.S. Government will not be held liable for any delays or breach of contract caused by refusal of the Security Forces to allow entry to the installation.

17.7. All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S., and are authorized by the US government to work in the United States (i.e.

Green card, worker authorization, etc.). All prospective contractors MUST have at least one form of U.S. government issued photo identification (driver’s license, U.S. passport, U.S. work visa, etc.) for entry to the installation. Security Forces will review any questionable identification documents for determination as to whether or not said identification is authorized for access to the installation.

17.8. All prospective contractors/contractor employees, once it has been established that they maintain the appropriate credential as described in one above, are subject to a Criminal History Check.

17.9. Note: For the purposes of these services, it is implied that, that any and all parties agree to a Criminal History Background Check once entered into any contract. Any documents that are provided and found fraudulent to include, but not limited to driver’s licenses, contracting licenses, etc., will result in an arrest and potential termination for default from the contract. All contractors are subject to search in order to obtain entry onto the installation and while working on the installation. Any refusal to submit to a search of their person or vehicle will be deemed as a violent act of aggression against the installation and will be cause for dismissal from the installation and revocation of future privileges and installation access.

PART 18 - REGULATIONS

18.1. The contractor shall comply with all applicable Federal, State, Local, DOD, National Guard Bureau, Army and Air Force regulations pertaining to safety, traffic control and fire prevention.

18.2. The contractor may use the Civil Engineering library, which contains most applicable Army and Air Force publications as well as some commercial project data information, or the Defense Procurement and Acquisition Policy website, http://www.acq.osd.mil/dpap/, which has links for several other sites with available publications, forms and project data information. These may also be acquired from the Government Printing Office website, http://www.gpoaccess.gov/index.html

PART 19 - TRANSPORTATION, HANDLING AND STORAGE

19.1. The contractor shall coordinate with suppliers and shippers to ensure that incoming materials are properly identified with the contractor’s name, contract number and project title. The contractor

GENERAL REQUIREMENTS 010000 - 8

shall designate an authorized individual to be available to receive shipment. The Government will not provide storage other than that available at the project site.

19.2. Storage of supplies, materials and equipment on the project site shall be accomplished in such a manner so as to prevent mechanical and climatic damage and loss due to vandalism or theft.

Equipment temporarily removed in the performance of work and stored on the job site shall be stored and protected in accordance with previous paragraphs, and shall be replaced in a condition compatible with its original state. Security for equipment and material removed from the job site for temporary storage until reuse shall be the responsibility of the contractor.

PART 20 - CLEANUP AND DISPOSAL OF DEBRIS AND FILL MATERIALS

20.1. At the end of each workday, the contractor shall clean up the work and storage areas and stack all materials in a manner approved by the Contracting Officer or his designated representative.

Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the construction operations are removed from the work area. Unless directed otherwise in the contract or by the Contracting Officer, disposal of debris shall be made at the contractor’s expense and shall be delivered to a state approved disposal site located off base. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area (i.e., on nearby runways, ramps or taxiways).

20.2. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.

PART 21 - ENVIRONMENTAL IMPACT

21.1. All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law.

Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

PART 22 - HAZARDOUS MATERIALS

22.1. Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract.

22.2. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating. Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

GENERAL REQUIREMENTS 010000 - 9

PART 23 - POLLUTION ABATEMENT

23.1. All work shall be performed in a manner minimizing pollution of air, water and land as required.

23.2. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected.

Gravel, sand and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the contractor.

23.3. Burning of any material is strictly prohibited.

23.4. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials. Grading shall be accomplished to prevent surface drainage from the construction site containing harmful amounts of sediment from draining onto adjacent areas.

23.5. Flushing of concrete trucks is restricted to the location specifically designed for this purpose by the Contracting Officer’s Representative.

23.6. Excess mortar, plaster or drywall materials shall not be disposed of on Government property.

Water utilized for plastering or drywall equipment shall be disposed of in accordance with the instructions of the COR, and under no circumstances shall water be disposed of in areas which are planted or scheduled to be planted.

PART 24 - COORDINATION WITH GOVERNMENT ACTIVITIES

24.1. If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes, permission to do so must be requested in writing to the Contracting Officer seven (7) working days prior to commencing work on the planned interruption and shall be subject to Civil Engineering approval. Written requests for street closing shall be submitted for approval of the Civil Engineer seven (7) working days prior to closing the street.

24.2. Work in connection with this contract which requires utility outages, including electrical, water, gas, steam, etc., which will close down or limit (as determined by the Contracting Officer) normal activities in the building, construction area or other affected areas, shall be performed by the contractor at a time other than the regular work period of the organization occupying the facility.

Work required by the contractor on a non-standard basis or at premium pay shall be done at no additional cost to the Government. Request for utility outages shall be submitted to the Civil Engineer, in writing seven (7) working days prior to commencing work and shall be subject to his/her approval.

24.3. Any temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utility services shall be subject to Contracting Officer’s approval.

PART 25 - UNAUTHORIZED PERSONNEL

25.1. The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area;

excluding direct haul and access routes, contracting and Civil Engineering offices, and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

PART 26 - PERFORMANCE EVALUATION OF CONTRACTOR

GENERAL REQUIREMENTS 010000 - 10

26.1. As a minimum, the contractor’s performance will be evaluated upon final inspection. Any specific requirements for contract quality control and quality assurance by the Government personnel will be defined in the specifications. The contractor will be rated as outstanding, satisfactory or unsatisfactory in the areas of contract quality control, timely performance, effectiveness of management, compliance with labor standards, and compliance with safety standards. The contractor will be notified of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all contractor comments will be made a part of the official record. Performance evaluation reports will be available to all DoD Contracting Officers for their future use.

26.2. All DoD contractors are required to obtain a Public Key Infrastructure (PKI) certificate to access the CPARS/ACASS/CCASS applications. DoD contractors are required to purchase a certificate from an External Certificate Authority (ECA) at no additional cost to the Government. . Contractor must be proactive in obtaining certificates, as they will not have the ability to view and comment on performance evaluations without the certificate. . If you have questions on obtaining PKI certificates, please visit www.cpars.gov. Contractors who fail to have their certificates will not be able to access the system

PART 27 - CONTRACTOR QUALITY CONTROL

27.1. The contractor shall comply with the quality control provisions as specified herein. The Contractor shall perform all quality control inspection and/or testing required by this contract unless specifically designated to be performed by the Government. The quality control system consists of plans, workmanship, fabrication, construction, and operations that comply with contract requirements. The system shall cover construction operations, including fabrication both on-site and off-site, and shall be keyed to the proposed construction sequence. If the contractor fails to submit an acceptable quality control plan within the time herein prescribed, the Contracting Officer may refuse to allow construction to start if an acceptable interim plan is not furnished or may withhold funds from progress payments in accordance with the contract clause titled, “Payments under Fixed Price Construction Contracts”, until such time as the contractor submits an acceptable final plan.

27.2. Quality Control Plan

A. General. Upon receipt of the Notice of Contract Award, the contractor’s quality control plan (2 copies) shall be submitted for acceptance in accordance with the specifications.

B. Acceptance. The Contracting Officer’s Representative will review the quality control plan. The contractor shall make such changes and additions as necessary for clarity and completeness as requested by the Contracting Officer’s Representative through the Contracting Officer.

Acceptance of the contractor’s plan is predicated on satisfactory performance during construction. Acceptance is conditional and the Government reserves the right to require the contractor to make changes in quality control plans, personnel and operations to correct deficiencies and to assure contract compliance.

C. Changes. When the contractor proposes changes in the quality control plan or implementation during construction, the Contracting Officer shall be notified in writing. The contractor shall implement no changes prior to acceptance in writing by the Contracting Officer.

PART 28 - SAFETY ASSURANCE

28.1. Compliance with Regulations. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos;

and/or disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part

GENERAL REQUIREMENTS 010000 - 11

61, Subpart A. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply. The Safety Manual is available at the following web site:

http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.a spx

28.2. Contractor Responsibility. The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any actions on the part of the contractor, his employees or subcontractors, which result in illness, injury or death.

A. Inspections, Tests and Reports. The required inspections, tests and reports made by the contractor, subcontractors, specially trained technicians, equipment manufacturers and others as required, shall be at the contractor’s expense.

B. Materials and Equipment. Special facilities, devices, equipment, clothing and similar items used by the contractor in the execution of work shall comply with applicable regulations.

C. Traffic Control Devices. As directed per the specifications.

PART 29 - WORK BY THE GOVERNMENT

29.1. The Government reserves the right to undertake performance by Government forces, for the same type or similar work as contracted herein, as the Government deems necessary or desirable, and to do so will not breach or otherwise violate this contract.

PART 30 - VALUE ENGINEERING CHANGE PROPOSALS

30.1. All value engineering change proposals (VECP’s) shall be submitted in accordance with the requirements of FAR Clause 52.248-3, Value Engineering – Construction. All VECPs shall be submitted in TWO (2) copies.

PART 31 - PRE-CONSTRUCTION CONFERENCE

31.1. Before work commences on this contract, the Contracting Officer will conduct a conference to acquaint the contractor with Government policies and procedures that are to be observed during the execution of the work and to develop mutual understanding relative to the administration of the contract. Contractors and/or major subcontractors shall attend this meeting at no additional cost to the Government.

PART 32 - RESERVED

PART 33 - MILITARY REAL PROPERTY DATA – DD FORM 1354

33.1. Contractors shall furnish real property data to the Government for each new construction and/or renovation project awarded, unless otherwise notified. The real property data shall be furnished via DD Form 1354, Transfer and Acceptance of Military Real Property, or in a format prescribed on the DD Form 1354. The Contractor is responsible for accuracy of data current up to the time of submission.

33.2. For major renovation and/or complex projects, or those expected to exceed 12 months, the Contractor shall furnish real property data no less than on a quarterly basis. Frequency of submission shall be standard throughout the duration of the project. Contractors are advised to record information on the DD Form 1354 (or approved facsimile) as the project progresses, due

GENERAL REQUIREMENTS 010000 - 12

to the volume of data required to be furnished. Upon completion of the project, the Contractor shall furnish a final, comprehensive DD Form 1354.

33.3. DD Form 1354 accounts for five percent (5%) of the total contract amount and therefore, 5% must be shown on the AF Form 3065 or similar breakdown of costs submitted for payment purposes.

Upon acceptance of data by the real property specialist, the contractor may invoice for submission of real property data.

33.4. Questions pertaining to the DD Form 1354. For construction data assistance, the Contractor may consult the COR assigned to the project.

PART 34 - TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

34.1. This Paragraph specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

A. The weather experienced at the project site during the contract period…