PERIOD OF PERFORMANCE

Sacramento River Bank Protection Project (105606)

Construction contract for Feather River FHR 1.0L Bank Protection (W9123819R0047)

Contract Period of Performance: 320 days from NTP

Following approval of bonding documents, issuance of notice to proceed (NTP), and approval of contractor’s submittals requiring affirmative Government approval, the contractor should mobilize to begin clearing and initiate other on-site work needed for performance of the contract.

In-water construction must be completed no later than October 31, 2019. Accordingly, the following items from the pricing schedule must be completed by October 31, 2019:

0002 Clearing 0004 Quarry Stone 0006 In-Stream Wood Material 0009 Gravel Interface Layer

Construction of bank protection must be completed by November 30, 2019. This includes completion of the following pricing schedule items:

0001 Mobilization and Demobilization 0003 Soil-Filled Quarry Stone 0005 Soil Cover 0007 Erosion Control Seeding 0008 Beaver Barrier Fence 0011 Revegetation Sign

Contractor’s project close-out must be completed by the end of the Contract Period of Performance indicated above. This includes completion of the following pricing schedule item:

0010 Temporary Storm Water Pollution Control