This document describes a federal contract opportunity for construction services. The U.S. Army Corps of Engineers seeks a contractor to build a new Consolidated Mission Control Center facility at Hill Air Force Base in Utah for approximately $25-100 million. Key requirements include a state-of-the-art facility to replace outdated infrastructure, with optimized layout and functional relationships for the Mission Control Center, Air Operations Center, and administration offices. The period of performance is anticipated to be 852 days upon contract award. The solicitation is expected to be issued on September 10, 2020 via beta.SAM.gov as an unrestricted competitive procurement, with proposals due October 12, 2020.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UTAH TEST AND TRAINING RANGE (UTTR) 100% FINAL/RTA SUBMITTAL

CONSOLIDATED MISSION CONTROL CENTER (CMCC) 11 OCTOBER 2019

SECTION TABLE OF CONTENTS

DIVISION 09 - FINISHES

SECTION 09 90 00

PAINTS AND COATINGS

05/11

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 CERTIFICATES

1.3.1 Indoor Air Quality

1.3.1.1 Paints and Coatings

1.4 APPLICATOR'S QUALIFICATIONS

1.4.1 Contractor Qualification

1.4.2 SSPC QP 1 Certification

1.5 QUALITY ASSURANCE

1.5.1 Field Samples and Tests

1.5.1.1 Sampling Procedure

1.5.1.2 Testing Procedure

1.6 REGULATORY REQUIREMENTS

1.6.1 Environmental Protection

1.6.2 Lead Content

1.6.3 Chromate Content

1.6.4 Asbestos Content

1.6.5 Mercury Content

1.6.6 Silica

1.6.7 Human Carcinogens

1.7 PACKAGING, LABELING, AND STORAGE

1.8 SAFETY AND HEALTH

1.8.1 Safety Methods Used During Coating Application

1.8.2 Toxic Materials

1.9 ENVIRONMENTAL CONDITIONS

1.9.1 Coatings

1.9.2 Post-Application

1.10 SCHEDULING

1.11 COLOR SELECTION

1.12 LOCATION AND SURFACE TYPE TO BE PAINTED

1.12.1 Painting Included

1.12.1.1 Exterior Painting

1.12.1.2 Interior Painting

1.12.2 Painting Excluded

1.12.3 Mechanical and Electrical Painting

1.12.3.1 Fire Extinguishing Sprinkler Systems

1.12.4 Definitions and Abbreviations

1.12.4.1 Qualification Testing

1.12.4.2 Coating

1.12.4.3 DFT or dft

1.12.4.4 DSD

1.12.4.5 EPP

1.12.4.6 EXT

1.12.4.7 INT

SECTION 09 90 00 Page 1

1.12.4.8 micron / microns

1.12.4.9 mil / mils

1.12.4.10 mm

1.12.4.11 MPI Gloss Levels

1.12.4.12 MPI System Number

1.12.4.13 Paint

1.12.4.14 REX

1.12.4.15 RIN

PART 2 PRODUCTS

2.1 MATERIALS

PART 3 EXECUTION

3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED

3.2 SURFACE PREPARATION

3.3 PREPARATION OF METAL SURFACES

3.3.1 New Ferrous Surfaces

3.3.2 Final Ferrous Surface Condition:

3.3.3 Galvanized Surfaces

3.3.4 Non-Ferrous Metallic Surfaces

3.4 PREPARATION OF CONCRETE AND CEMENTITIOUS SURFACE

3.4.1 Concrete

3.4.2 Gypsum Board

3.5 PREPARATION OF WOOD AND PLYWOOD SURFACES

3.5.1 New Plywood and Wood Surfaces, Except Floors:

3.6 APPLICATION

3.6.1 Coating Application

3.6.2 Mixing and Thinning of Paints

3.6.3 Two-Component Systems

3.6.4 Coating Systems

3.7 COATING SYSTEMS FOR METAL

3.8 COATING SYSTEMS FOR WOOD AND PLYWOOD

3.9 PIPING IDENTIFICATION

3.10 INSPECTION AND ACCEPTANCE

3.11 WASTE MANAGEMENT

3.12 PAINT TABLES

3.12.1 Exterior Paint Tables

3.12.2 Interior Paint Tables

-- End of Section Table of Contents --

SECTION 09 90 00 Page 2

SECTION 09 90 00

PAINTS AND COATINGS

05/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)

ACGIH 0100 (2015; Suppl 2002-2016) Documentation of the Threshold Limit Values and Biological Exposure Indices

ASTM INTERNATIONAL (ASTM)

ASTM D4263 (1983; R 2012) Indicating Moisture in Concrete by the Plastic Sheet Method

ASTM D4444 (2013) Use and Calibration of Hand-Held Moisture Meters

ASTM D523 (2014; R 2018) Standard Test Method for Specular Gloss

ASTM D6386 (2016) Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting

ASTM F1869 (2016) Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride

MASTER PAINTERS INSTITUTE (MPI)

MPI 1 (2012) Aluminum Paint

MPI 101 (2012) Primer, Epoxy, Anti-Corrosive, for Metal

MPI 107 (2012) Primer, Rust-Inhibitive, Water Based

MPI 108 (2012) Epoxy, High Build, Low Gloss

MPI 134 (2012) Primer, Galvanized, Water Based

MPI 139 (2012) Latex, Interior, High Performance Architectural, (MPI Gloss Level 3)

MPI 141 (2012) Latex, Interior, High Performance Architectural, Semi-Gloss (MPI Gloss Level

SECTION 09 90 00 Page 3

5)

MPI 161 (2012) Light Industrial Coating, Exterior, Water Based ( MPI Gloss Level 3)

MPI 163 (2012) Light Industrial Coating, Exterior, Water Based, Semi-Gloss (MPI Gloss Level 5)

MPI 164 (2012) Light Industrial Coating, Exterior, Water Based, Gloss (MPI Gloss Level 6)

MPI 19 (2012) Primer, Zinc Rich, Inorganic

MPI 2 (2012) Aluminum Heat Resistant Enamel (up to 427 C and 800 F

MPI 21 (2012) Heat Resistant Coating, (Up to 205°C/402°F), MPI Gloss Level 6

MPI 44 (2012) Latex, Interior, (MPI Gloss Level 2)

MPI 45 (2012) Primer Sealer, Interior Alkyd

MPI 47 (2012) Alkyd, Interior, Semi-Gloss (MPI Gloss Level 5)

MPI 48 (2012) Alkyd, Interior, Gloss (MPI Gloss Level 6-7)

MPI 50 (2012) Primer Sealer, Latex, Interior

MPI 52 (2012) Latex, Interior, (MPI Gloss Level 3)

MPI 79 (2012) Primer, Alkyd, Anti-Corrosive for Metal

MPI 8 (2012) Alkyd, Exterior Flat (MPI Gloss Level I)

MPI 9 (2012) Alkyd, Exterior Gloss (MPI Gloss Level 6)

MPI 94 (2012) Alkyd, Exterior, Semi-Gloss (MPI Gloss Level 5)

MPI 95 (2012) Primer, Quick Dry, for Aluminum

SCIENTIFIC CERTIFICATION SYSTEMS (SCS)

SCS SCS Global Services (SCS) Indoor Advantage

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC 7/NACE No.4 (2007; E 2004) Brush-Off Blast Cleaning

SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals

SECTION 09 90 00 Page 4

SSPC PA Guide 3 (1982; E 1995) A Guide to Safety in Paint Application

SSPC QP 1 (2012; E 2012) Standard Procedure for Evaluating Painting Contractors (Field Application to Complex Industrial Structures)

SSPC SP 1 (2015) Solvent Cleaning

SSPC SP 10/NACE No. 2 (2007) Near-White Blast Cleaning

SSPC SP 12/NACE No.5 (2002) Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating

SSPC SP 2 (1982; E 2000; E 2004) Hand Tool Cleaning

SSPC SP 3 (1982; E 2004) Power Tool Cleaning

SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning

SSPC VIS 1 (2002; E 2004) Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

SSPC VIS 3 (2004) Guide and Reference Photographs for Steel Surfaces Prepared by Hand and Power Tool Cleaning

SSPC VIS 4/NACE VIS 7 (1998; E 2000; E 2004) Guide and Reference Photographs for Steel Surfaces Prepared by Waterjetting

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. DEPARTMENT OF DEFENSE (DOD)

MIL-STD-101 (2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA Method 24 (2000) Determination of Volatile Matter Content, Water Content, Density, Volume Solids, and Weight Solids of Surface Coatings

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1000 Air Contaminants

UNDERWRITERS LABORATORIES (UL)

UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings

SECTION 09 90 00 Page 5

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

The current MPI, "Approved Product List" which lists paint by brand, label, product name and product code as of the date of contract award, will be used to determine compliance with the submittal requirements of this specification. The Contractor may choose to use a subsequent MPI "Approved Product List", however, only one list may be used for the entire contract and each coating system is to be from a single manufacturer.

Provide all coats on a particular substrate from a single manufacturer.

No variation from the MPI Approved Products List is acceptable.

Samples of specified materials may be taken and tested for compliance with specification requirements.

SD-02 Shop Drawings

Piping Identification

SD-03 Product Data

Coating ; G, AE

SD-04 Samples

Color ; G, AE

SD-07 Certificates

Applicator's Qualifications

Qualification Testing laboratory for coatings; G, AE

Indoor Air Quality for Paints and Primers

Indoor Air Quality for Consolidated Latex Paints

SD-08 Manufacturer's Instructions

Application Instructions

Mixing

Manufacturer's Safety Data Sheets

SD-10 Operation and Maintenance Data

Coatings ; G, AE

SECTION 09 90 00 Page 6

1.3 CERTIFICATES

1.3.1 Indoor Air Quality

Submit required indoor air quality certifications in one submittal package.

1.3.1.1 Paints and Coatings

Provide paint and coating products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification by other third-party programs.

Provide current product certification documentation from certification body.

1.4 APPLICATOR'S QUALIFICATIONS

1.4.1 Contractor Qualification

Submit the name, address, telephone number, FAX number, and e-mail address of the contractor that will be performing all surface preparation and coating application. Submit evidence that key personnel have successfully performed surface preparation and application of coatings on a minimum of three similar projects within the past three years. List information by individual and include the following:

a. Name of individual and proposed position for this work.

b. Information about each previous assignment including:

Position or responsibility

Employer (if other than the Contractor)

Name of facility owner

Mailing address, telephone number, and telex number (if non-US) of facility owner

Name of individual in facility owner's organization who can be contacted as a reference

Location, size and description of structure

Dates work was carried out

Description of work carried out on structure

1.4.2 SSPC QP 1 Certification

All contractors and subcontractors that perform surface preparation or coating application must be certified by the Society for Protective Coatings (formerly Steel Structures Painting Council) (SSPC) to the requirements of SSPC QP 1 prior to contract award, and must remain certified while accomplishing any surface preparation or coating application. If a contractor's or subcontractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be

SECTION 09 90 00 Page 7 considered and liquidated damages will apply. Notify the Contracting Officer of any change in contractor certification status.

1.5 QUALITY ASSURANCE

1.5.1 Field Samples and Tests

The Contracting Officer may choose up to two coatings that have been delivered to the site to be tested at no cost to the Government. Take samples of each chosen product as specified in the paragraph SAMPLING PROCEDURES. Test each chosen product as specified in the paragraph TESTING PROCEDURE. Remove products from the job site which do not conform, and replace with new products that conform to the referenced specification. Test replacement products that failed initial testing at no cost to the Government.

1.5.1.1 Sampling Procedure

The Contracting Officer will select paint at random from the products that have been delivered to the job site for sample testing. The Contractor will provide one quart samples of the selected paint materials. Take samples in the presence of the Contracting Officer, and label, and identify each sample. Provide labels in accordance with the paragraph PACKAGING, LABELING, AND STORAGE of this specification.

1.5.1.2 Testing Procedure

Provide Batch Quality Conformance Testing for specified products, as defined by and performed by MPI. As an alternative to Batch Quality Conformance Testing, the Contractor may provide Qualification Testing for specified products above to the appropriate MPI product specification, using the third-party laboratory approved under the paragraph "Qualification Testing" laboratory for coatings. Include the backup data and summary of the test results within the qualification testing lab report. Provide a summary listing of all the reference specification requirements and the result of each test. Clearly indicate in the summary whether the tested paint meets each test requirement. Note that Qualification Testing may take 4 to 6 weeks to perform, due to the extent of testing required.

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party laboratory selected to perform testing of coating samples for compliance with specification requirements. Submit documentation that laboratory is regularly engaged in testing of paint samples for conformance with specifications, and that employees performing testing are qualified. If MPI is chosen to perform the Batch Quality Conformance testing, the above submittal information is not required, only a letter is required from the Contractor stating that MPI will perform the testing.

1.6 REGULATORY REQUIREMENTS

1.6.1 Environmental Protection

In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution Control District and regional jurisdiction.

Notify Contracting Officer of any paint specified herein which fails to conform.

SECTION 09 90 00 Page 8

1.6.2 Lead Content

Do not use coatings having a lead content over 0.06 percent by weight of nonvolatile content.

1.6.3 Chromate Content

Do not use coatings containing zinc-chromate or strontium-chromate.

1.6.4 Asbestos Content

Provide asbestos-free materials.

1.6.5 Mercury Content

Provide materials free of mercury or mercury compounds.

1.6.6 Silica

Provide abrasive blast media containing no free crystalline silica.

1.6.7 Human Carcinogens

Provide materials that do not contain ACGIH 0100 confirmed human carcinogens (A1) or suspected human carcinogens (A2).

1.7 PACKAGING, LABELING, AND STORAGE

Provide paints in sealed containers that legibly show the contract specification number, designation name, formula or specification number, batch number, color, quantity, date of manufacture, manufacturer's formulation number, manufacturer's directions including any warnings and special precautions, and name and address of manufacturer. Furnish pigmented paints in containers not larger than 5 gallons . Store paints and thinners in accordance with the manufacturer's written directions, and as a minimum, stored off the ground, under cover, with sufficient ventilation to prevent the buildup of flammable vapors, and at temperatures between 40 to 95 degrees F . Do not store paint, polyurethane, varnish, or wood stain products with materials that have a high capacity to adsorb VOC emissions. Do not store paint, polyurethane, varnish, or wood stain products in occupied spaces.

1.8 SAFETY AND HEALTH

Apply coating materials using safety methods and equipment in accordance with the following:

Comply with applicable Federal, State, and local laws and regulations, and with the ACCIDENT PREVENTION PLAN, including the Activity Hazard Analysis as specified in Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS and in Appendix A of EM 385-1-1 . Include in the Activity Hazard Analysis the potential impact of painting operations on painting personnel and on others involved in and adjacent to the work zone.

1.8.1 Safety Methods Used During Coating Application

Comply with the requirements of SSPC PA Guide 3 .

SECTION 09 90 00 Page 9

1.8.2 Toxic Materials

To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

a. The applicable manufacturer's Safety Data Sheets (SDS) or local regulation.

b. 29 CFR 1910.1000 .

c. ACGIH 0100 , threshold limit values.

1.9 ENVIRONMENTAL CONDITIONS

Comply, at minimum, with manufacturer recommendations for space ventilation during and after installation. Isolate area of application from rest of building when applying high-emission paints or coatings.

1.9.1 Coatings

Do not apply coating when air or substrate conditions are:

a. Less than 5 degrees F above dew point;

b. Below 50 degrees F or over 95 degrees F , unless specifically pre-approved by the Contracting Officer and the product manufacturer.

Do not, under any circumstances, violate the manufacturer's application recommendations.

1.9.2 Post-Application

Vacate space for as long as possible after application. Wait a minimum of 48 hours before occupying freshly painted rooms. Maintain one of the following ventilation conditions during the curing period, or for 72 hours after application:

a. Supply 100 percent outside air 24 hours a day.

b. Supply airflow at a rate of 6 air changes per hour, when outside temperatures are between 55 degrees F and 85 degrees F and humidity is between 30 percent and 60 percent.

c. Supply airflow at a rate of 1.5 air changes per hour, when outside air conditions are not within the range stipulated above.

1.10 SCHEDULING

Allow paint, polyurethane, varnish, and wood stain installations to cure prior to the installation of materials that adsorb VOCs.

1.11 COLOR SELECTION

Provide colors of finish coats as indicated or specified. Allow Contracting Officer to select colors not indicated or specified.

Manufacturers' names and color identification are used for the purpose of color identification only. Named products are acceptable for use only if they conform to specified requirements. Products of other manufacturers are acceptable if the colors approximate colors indicated and the product

SECTION 09 90 00 Page 10 conforms to specified requirements.

Tint each coat progressively darker to enable confirmation of the number of coats.

Provide color, texture, and pattern of wall coating systems as indicated.

Submit manufacturer's samples of paint colors. Cross reference color samples to color scheme as indicated. Submit color stencil codes.

1.12 LOCATION AND SURFACE TYPE TO BE PAINTED

1.12.1 Painting Included

Where a space or surface is indicated to be painted, include the following unless indicated otherwise.

a. Surfaces behind portable objects and surface mounted articles readily detachable by removal of fasteners, such as screws and bolts.

b. New factory finished surfaces that require identification or color coding and factory finished surfaces that are damaged during performance of the work.

c. Existing coated surfaces that are damaged during performance of the work.

1.12.1.1 Exterior Painting

Includes new surfaces of the building and appurtenances. Also included are existing coated surfaces made bare by cleaning operations.

1.12.1.2 Interior Painting

Includes new surfaces of the building and appurtenances as indicated and existing coated surfaces made bare by cleaning operations. Where a space or surface is indicated to be painted, include the following items, unless indicated otherwise.

a. Exposed columns, girders, beams, joists, and metal deck; and

b. Other contiguous surfaces.

1.12.2 Painting Excluded

Do not paint the following unless indicated otherwise.

a. Surfaces concealed and made inaccessible by panelboards, fixed ductwork, machinery, and equipment fixed in place.

b. Surfaces in concealed spaces. Concealed spaces are defined as enclosed spaces above suspended ceilings, furred spaces, attic spaces, crawl spaces, elevator shafts and chases.

c. Steel to be embedded in concrete.

d. Copper, stainless steel, aluminum, brass, and lead except existing coated surfaces.

SECTION 09 90 00 Page 11

e. Hardware, fittings, and other factory finished items.

f. Do not paint surfaces in the following areas: Exposed underside of roof structure and deck above in areas with no finish ceiling, unless indicated otherwise on drawings.

1.12.3 Mechanical and Electrical Painting

Includes field coating of interior and exterior new surfaces.

a. Where a space or surface is indicated to be painted, include the following items unless indicated otherwise.

(1) Exposed piping, conduit, and ductwork;

(2) Supports, hangers, air grilles, and registers;

(3) Miscellaneous metalwork and insulation coverings.

b. Do not paint the following, unless indicated otherwise:

(1) New zinc-coated, aluminum, and copper surfaces under insulation

(2) New aluminum jacket on piping

(3) New interior ferrous piping under insulation.

1.12.3.1 Fire Extinguishing Sprinkler Systems

Clean, pretreat, prime, and paint new fire extinguishing sprinkler systems including valves, piping, conduit, hangers, supports, miscellaneous metalwork, and accessories. Apply coatings to clean, dry surfaces, using clean brushes. Clean the surfaces to remove dust, dirt, rust, and loose mill scale. Immediately after cleaning, provide the metal surfaces with one coat primer per schedules. Shield sprinkler heads with protective covering while painting is in progress. Upon completion of painting, remove protective covering from sprinkler heads. Remove sprinkler heads which have been painted and replace with new sprinkler heads. Provide primed surfaces with the following:

a. Piping in Unfinished Areas: Provide piping with 2 inch wide red enamel bands or self-adhering red plastic bands spaced at maximum of 20 foot intervals.

b. Piping in Finished Areas: Provide primed surfaces with two coats of paint to match adjacent surfaces, except provide valves and operating accessories with one coat of red alkyd gloss enamel applied to a minimum dry film thickness of 1.0 mil . Provide piping with 2 inch wide red enamel bands or self-adhering red plastic bands spaced at maximum of 20 foot intervals throughout the piping systems.

1.12.4 Definitions and Abbreviations

1.12.4.1 Qualification Testing

Qualification testing is the performance of all test requirements listed in the product specification. This testing is accomplished by MPI to qualify each product for the MPI Approved Product List, and may also be accomplished by Contractor's third party testing lab if an alternative to

SECTION 09 90 00 Page 12

Batch Quality Conformance Testing by MPI is desired.

1.12.4.2 Coating

A film or thin layer applied to a base material called a substrate. A coating may be a metal, alloy, paint, or solid/liquid suspensions on various substrates (such as metals, plastics, wood, paper, leather, cloth). They may be applied by electrolysis, vapor deposition, vacuum, or mechanical means such as brushing, spraying, calendaring, and roller coating. A coating may be applied for aesthetic or protective purposes or both. The term "coating" as used herein includes emulsions, enamels, stains, varnishes, sealers, epoxies, and other coatings, whether used as primer, intermediate, or finish coat. The terms paint and coating are used interchangeably.

1.12.4.3 DFT or dft

Dry film thickness, the film thickness of the fully cured, dry paint or coating.

1.12.4.4 DSD

Degree of Surface Degradation, the MPI system of defining degree of surface degradation. Five (5) levels are generically defined under the Assessment sections in the MPI Maintenance Repainting Manual.

1.12.4.5 EPP

Environmentally Preferred Products, a standard for determining environmental preferability in support of Executive Order 13101.

1.12.4.6 EXT

MPI short term designation for an exterior coating system.

1.12.4.7 INT

MPI short term designation for an interior coating system.

1.12.4.8 micron / microns

The metric measurement for 0.001 mm or one/one-thousandth of a millimeter.

1.12.4.9 mil / mils

The English measurement for 0.001 in or one/one-thousandth of an inch, equal to 25.4 microns or 0.0254 mm.

1.12.4.10 mm

The metric measurement for millimeter, 0.001 meter or one/one-thousandth of a meter.

1.12.4.11 MPI Gloss Levels

MPI system of defining gloss. Seven (7) gloss levels (G1 to G7) are generically defined under the Evaluation sections of the MPI Manuals.

Traditionally, Flat refers to G1/G2, Eggshell refers to G3, Semigloss refers to G5, and Gloss refers to G6.

SECTION 09 90 00 Page 13

Gloss levels are defined by MPI as follows:

Gloss Description Units Units Level at 60 degrees at 85 degrees

G1 Matte or Flat 0 to 5 10 max G2 Velvet 0 to 10 10 to 35 G3 Eggshell 10 to 25 10 to 35 G4 Satin 20 to 35 35 min G5 Semi-Gloss 35 to 70 G6 Gloss 70 to 85 G7 High Gloss

Gloss is tested in accordance with ASTM D523. Historically, the Government has used Flat (G1 / G2), Eggshell (G3), Semi-Gloss (G5), and Gloss (G6).

1.12.4.12 MPI System Number

The MPI coating system number in each Division found in either the MPI Architectural Painting Specification Manual or the Maintenance Repainting Manual and defined as an exterior (EXT/REX) or interior system (INT/RIN).

The Division number follows the CSI Master Format.

1.12.4.13 Paint

See Coating definition.

1.12.4.14 REX

MPI short term designation for an exterior coating system used in repainting projects or over existing coating systems.

1.12.4.15 RIN

MPI short term designation for an interior coating system used in repainting projects or over existing coating systems.

PART 2 PRODUCTS

2.1 MATERIALS

Conform to the coating specifications and standards referenced in PART 3.

Submit product data sheets for specified coatings and solvents. Provide preprinted cleaning and maintenance instructions for all coating systems.

Submit Manufacturer's Instructions on Mixing: Detailed mixing instructions, minimum and maximum application temperature and humidity, potlife, and curing and drying times between coats.

Provide certification of Indoor Air Quality for paints and primers .

Provide certification of Indoor Air Quality for consolidated latex paints .

SECTION 09 90 00 Page 14

PART 3 EXECUTION

3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED

Prior to surface preparation and coating applications, remove, mask, or otherwise protect hardware, hardware accessories, machined surfaces, radiator covers, plates, lighting fixtures, public and private property, and other such items not to be coated that are in contact with surfaces to be coated. Following completion of painting, reinstall removed items by workmen skilled in the trades. Restore surfaces contaminated by coating materials, to original condition and repair damaged items.

3.2 SURFACE PREPARATION

Remove dirt, splinters, loose particles, grease, oil, and other foreign matter and substances deleterious to coating performance as specified for each substrate before application of paint or surface treatments. Remove oil and grease prior to mechanical cleaning. Schedule cleaning so that dust and other contaminants will not fall on wet, newly painted surfaces.

Spot-prime exposed ferrous metals such as nail heads on or in contact with surfaces to be painted with water-thinned paints, with a suitable corrosion-inhibitive primer capable of preventing flash rusting and compatible with the coating specified for the adjacent areas.

3.3 PREPARATION OF METAL SURFACES

3.3.1 New Ferrous Surfaces

a. Ferrous Surfaces including Shop-coated Surfaces and Small Areas That Contain Rust, Mill Scale and Other Foreign Substances: Solvent clean or detergent wash in accordance with SSPC SP 1 to remove oil and grease. Where shop coat is missing or damaged, clean according to SSPC SP 2 , SSPC SP 3 , SSPC SP 6/NACE No.3 , or SSPC SP 10/NACE No. 2 .

Brush-off blast remaining surface in accordance with SSPC 7/NACE No.4 ;

Water jetting to SSPC SP 12/NACE No.5 WJ-4 may be used to remove loose coating and other loose materials. Use inhibitor as recommended by coating manufacturer to prevent premature rusting. Protect shop-coated ferrous surfaces from corrosion by treating and touching up corroded areas immediately upon detection.

b. Surfaces With More Than 20 Percent Rust, Mill Scale, and Other Foreign Substances: Clean entire surface in accordance with SSPC SP 6/NACE No.3 / SSPC SP 12/NACE No.5 WJ-3 SSPC SP 10/NACE No. 2 / SSPC SP 12/NACE No.5 WJ-2.

3.3.2 Final Ferrous Surface Condition:

For tool cleaned surfaces, the requirements are stated in SSPC SP 2 and SSPC SP 3 . Use as a visual reference, photographs in SSPC VIS 3 for the appearance of cleaned surfaces.

For abrasive blast cleaned surfaces, the requirements are stated in SSPC 7/NACE No.4 , SSPC SP 6/NACE No.3 , and SSPC SP 10/NACE No. 2 . Use as a visual reference, photographs in SSPC VIS 1 for the appearance of cleaned surfaces.

For waterjet cleaned surfaces, the requirements are stated in SSPC SP 12/NACE No.5 . Use as a visual reference, photographs in SSPC VIS 4/NACE VIS 7 for the appearance of cleaned surfaces.

SECTION 09 90 00 Page 15

3.3.3 Galvanized Surfaces

a. New or Existing Galvanized Surfaces With Only Dirt and Zinc Oxidation Products: Clean with solvent, steam, or non-alkaline detergent solution in accordance with SSPC SP 1 . Completely remove coating by brush-off abrasive blast if the galvanized metal has been passivated or stabilized. Do not "passivate" or "stabilize" new galvanized steel to be coated. If the absence of hexavalent stain inhibitors is not documented, test as described in ASTM D6386, Appendix X2, and remove by one of the methods described therein.

b. Galvanized with Slight Coating Deterioration or with Little or No Rusting: Water jetting to SSPC SP 12/NACE No.5 WJ3 to remove loose coating from surfaces with less than 20 percent coating deterioration and no blistering, peeling, or cracking. Use inhibitor as recommended by the coating manufacturer to prevent rusting.

3.3.4 Non-Ferrous Metallic Surfaces

Aluminum and aluminum-alloy, lead, copper, and other nonferrous metal surfaces.

Surface Cleaning: Solvent clean in accordance with SSPC SP 1 and wash with mild non-alkaline detergent to remove dirt and water soluble contaminants.

3.4 PREPARATION OF CONCRETE AND CEMENTITIOUS SURFACE

3.4.1 Concrete

a. Curing: Allow concrete, stucco and masonry surfaces to cure at least 30 days before painting, and concrete slab on grade to cure at least 90 days before painting.

b. Surface Cleaning: Remove the following deleterious substances.

(1) Dirt, Chalking, Grease, and Oil: Wash new surfaces with a solution composed of 1/2 cup trisodium phosphate, 1/4 cup household detergent, and 4 quarts of warm water. Then rinse thoroughly with fresh water. For large areas, water blasting may be used.

(2) Fungus and Mold: Wash surfaces with a solution composed of 1/2 cup trisodium phosphate, 1/4 cup household detergent, 1 quart 5 percent sodium hypochlorite solution and 3 quarts of warm water.

Rinse thoroughly with fresh water.

(3) Paint and Loose Particles: Remove by wire brushing.

(4) Efflorescence: Remove by scraping or wire brushing followed by washing with a 5 to 10 percent by weight aqueous solution of hydrochloric (muriatic) acid. Do not allow acid to remain on the surface for more than five minutes before rinsing with fresh water. Do not acid clean more than 4 square feet of surface, per workman, at one time.

c. Cosmetic Repair of Minor Defects: Repair or fill mortar joints and minor defects, including but not limited to spalls, in accordance with

SECTION 09 90 00 Page 16 manufacturer's recommendations and prior to coating application.

d. Allowable Moisture Content: Latex coatings may be applied to damp surfaces, but not to surfaces with droplets of water. Do not apply epoxies to damp vertical surfaces as determined by ASTM D4263 or horizontal surfaces that exceed 3 lbs of moisture per 1000 square feet in 24 hours as determined by ASTM F1869. In all cases follow manufacturers recommendations. Allow surfaces to cure a minimum of 30 days before painting.

3.4.2 Gypsum Board

a. Surface Cleaning: Verify that plaster and stucco surfaces are free from loose matter and that gypsum board is dry. Remove loose dirt and dust by brushing with a soft brush, rubbing with a dry cloth, or vacuum-cleaning prior to application of the first coat material. A damp cloth or sponge may be used if paint will be water-based.

b. Repair of Minor Defects: Prior to painting, repair joints, cracks, holes, surface irregularities, and other minor defects with patching plaster or spackling compound and sand smooth.

c. Allowable Moisture Content: Latex coatings may be applied to damp surfaces, but not surfaces with droplets of water. Do not apply epoxies to damp surfaces as determined by ASTM D4263. Verify that new plaster to be coated has a maximum moisture content of 8 percent, when measured in accordance with ASTM D4444, Method A, unless otherwise authorized. In addition to moisture content requirements, allow new plaster to age a minimum of 30 days before preparation for painting.

3.5 PREPARATION OF WOOD AND PLYWOOD SURFACES

3.5.1 New Plywood and Wood Surfaces, Except Floors:

a. Clean wood surfaces of foreign matter.

Surface Cleaning: Verify that surfaces are free from dust and other deleterious substances and in a condition approved by the Contracting Officer prior to receiving paint or other finish. Do not use water to clean uncoated wood. Scrape to remove loose coatings. Lightly sand to roughen the entire area of previously enamel-coated wood surfaces.

b. Do not exceed 12 percent moisture content of the wood as measured by a moisture meter in accordance with ASTM D4444, Method A, unless otherwise authorized.

c. Prime or touch up wood surfaces adjacent to surfaces to receive water-thinned paints before applying water-thinned paints.

d. Cracks and Nailheads: Set and putty stop nailheads and putty cracks after the prime coat has dried.

e. Cosmetic Repair of Minor Defects:

(1) Knots and Resinous Wood: Prior to application of coating, cover knots and stains with two or more coats of 3-pound-cut shellac varnish, plasticized with 5 ounces of castor oil per gallon .

Scrape away existing coatings from knotty areas, and sand before treating. Prime before applying any putty over shellacked area.

SECTION 09 90 00 Page 17

(2) Open Joints and Other Openings: Fill with whiting putty, linseed oil putty. Sand smooth after putty has dried.

(3) Checking: Where checking of the wood is present, sand the surface, wipe and apply a coat of pigmented orange shellac. Allow to dry before paint is applied.

3.6 APPLICATION

3.6.1 Coating Application

Comply with applicable federal, state and local laws enacted to insure compliance with Federal Clean Air Standards. Apply coating materials in accordance with SSPC PA 1 and manufacturer's application instructions .

SSPC PA 1 methods are applicable to all substrates, except as modified herein.

At the time of application, paint must show no signs of deterioration.

Maintain uniform suspension of pigments during application.

Unless otherwise specified or recommended by the paint manufacturer, paint may be applied by brush, roller, or spray. Use trigger operated spray nozzles for water hoses. Use rollers for applying paints and enamels of a type designed for the coating to be applied and the surface to be coated.

Wear protective clothing and respirators when applying oil-based paints or using spray equipment with any paints.

Only apply paints, except water-thinned types to surfaces that are completely free of moisture as determined by sight or touch.

Thoroughly work coating materials into joints, crevices, and open spaces.

Pay special attention to ensure that all edges, corners, crevices, welds, and rivets receive a film thickness equal to that of adjacent painted surfaces.

Apply each coat of paint so that dry film is of uniform thickness and free from runs, drops, ridges, waves, pinholes or other voids, laps, brush marks, and variations in color, texture, and finish. Completely hide all blemishes.

Touch up damaged coatings before applying subsequent coats. Broom clean and clear dust from interior areas before and during the application of coating material.

a. Drying Time: Allow time between coats, as recommended by the coating manufacturer, to permit thorough drying, but not to present topcoat adhesion problems. Provide each coat in specified condition to receive next coat.

b. Primers, and Intermediate Coats: Do not allow primers or intermediate coats to dry more than 30 days, or longer than recommended by manufacturer, before applying subsequent coats. Follow manufacturer's recommendations for surface preparation if primers or intermediate coats are allowed to dry longer than recommended by manufacturers of subsequent coatings. Cover each preceding coat or surface completely by ensuring visually perceptible difference in shades of successive coats.

SECTION 09 90 00 Page 18

c. Finished Surfaces: Provide finished surfaces free from runs, drops, ridges, waves, laps, brush marks, and variations in colors.

d. Thermosetting Paints: Topcoats over thermosetting paints (epoxies and urethanes) should be applied within the overcoating window recommended by the manufacturer.

3.6.2 Mixing and Thinning of Paints

Reduce paints to proper consistency by adding fresh paint, except when thinning is mandatory to suit surface, temperature, weather conditions, application methods, or for the type of paint being used. Obtain written permission from the Contracting Officer to use thinners. Verify that the written permission includes quantities and types of thinners to use.

When thinning is allowed, thin paints immediately prior to application with not more than 1 pint of suitable thinner per gallon. The use of thinner does not relieve the Contractor from obtaining complete hiding, full film thickness, or required gloss. Thinning cannot cause the paint to exceed limits on volatile organic compounds. Do not mix paints of different manufacturers.

3.6.3 Two-Component Systems

Mix two-component systems in accordance with manufacturer's instructions.

Follow recommendation by the manufacturer for any thinning of the first coat to ensure proper penetration and sealing for each type of substrate.

3.6.4 Coating Systems

a. Systems by Substrates: Apply coatings that conform to the respective specifications listed in the following Tables:

Table

Division 5. Exterior Metal, Ferrous and Non-Ferrous Paint Table

Division 5. Interior Metal, Ferrous and Non-Ferrous Paint Table Division 6. Interior Wood Paint Table Division 9: Interior Plaster, Gypsum Board, Textured Surfaces Paint Table

b. Minimum Dry Film Thickness (DFT): Apply paints, primers, varnishes, enamels, undercoats, and other coatings to a minimum dry film thickness of 1.5 mil each coat unless specified otherwise in the Tables. Coating thickness where specified, refers to the minimum dry film thickness.

c. Coatings for Surfaces Not Specified Otherwise: Coat surfaces which have not been specified, the same as surfaces having similar conditions of exposure.

3.7 COATING SYSTEMS FOR METAL

Apply coatings of Tables in Division 5 for Exterior and Interior.

a. Apply specified ferrous metal primer on the same day that surface is cleaned, to surfaces that meet all specified surface preparation requirements at time of application.

SECTION 09 90 00 Page 19

b. Inaccessible Surfaces: Prior to erection, use one coat of specified primer on metal surfaces that will be inaccessible after erection.

c. Shop-primed Surfaces: Touch up exposed substrates and damaged coatings to protect from rusting prior to applying field primer.

d. Pipes and Tubing: The semitransparent film applied to some pipes and tubing at the mill is not to be considered a shop coat. Overcoat these items with the specified ferrous-metal primer prior to application of finish coats.

e. Exposed Nails, Screws, Fasteners, and Miscellaneous Ferrous Surfaces.

On surfaces to be coated with water thinned coatings, spot prime exposed nails and other ferrous metal with latex primer MPI 107 .

3.8 COATING SYSTEMS FOR WOOD AND PLYWOOD

a. Apply coatings of Tables in Division 6 for Exterior and Interior.

b. Prior to erection, apply two coats of specified primer to treat and prime wood and plywood surfaces which will be inaccessible after erection.

c. Apply stains in accordance with manufacturer's printed instructions.

3.9 PIPING IDENTIFICATION

Piping Identification, Including Surfaces In Concealed Spaces: Provide in accordance with MIL-STD-101 . Place stenciling in clearly visible locations. On piping not covered by MIL-STD-101 , stencil approved names or code letters, in letters a minimum of 1/2 inch high for piping and a minimum of 2 inches high elsewhere. Stencil arrow-shaped markings on piping to indicate direction of flow using black stencil paint.

3.10 INSPECTION AND ACCEPTANCE

In addition to meeting previously specified requirements, demonstrate mobility of moving components, including swinging and sliding doors, cabinets, and windows with operable sash, for inspection by the Contracting Officer. Perform this demonstration after appropriate curing and drying times of coatings have elapsed and prior to invoicing for final payment.

3.11 WASTE MANAGEMENT

As specified in the Waste Management Plan and as follows. Do not use kerosene or any such organic solvents to clean up water based paints.

Properly dispose of paints or solvents in designated containers. Close and seal partially used containers of paint to maintain quality as necessary for reuse. Store in protected, well-ventilated, fire-safe area at moderate temperature. Place materials defined as hazardous or toxic waste in designated containers. Coordinate with manufacturer for take-back program. Set aside scrap to be returned to manufacturer for recycling into new product. When such a service is not available, contact local recyclers to reclaim the materials. Set aside extra paint for future color matches or reuse by the Government. Where local options exist for leftover paint recycling, collect all waste paint by type and provide for delivery to recycling or collection facility for reuse by local

SECTION 09 90 00 Page 20 organizations.

3.12 PAINT TABLES

All DFT's are minimum values. Use only materials with a GPS green check mark having a minimum MPI "Environmentally Friendly" E2 or E3 rating based on VOC ( EPA Method 24 ) content levels. Acceptable products are listed in the MPI Green Approved Products List, available at http://www.specifygreen.com/APL/ProductIdxByMPInum.asp .

3.12.1 Exterior Paint Tables

DIVISION 5: EXTERIOR METAL, FERROUS AND NON-FERROUS PAINT TABLE

STEEL / FERROUS SURFACES

D. New steel blast cleaned to SSPC SP 10/NACE No. 2 :

1. MPI EXT 5.1R-G6 (Gloss) Primer: Intermediate: Topcoat:

MPI 101 MPI 108 MPI 164

System DFT: 8.5 mils

F. New Galvanized surfaces:

3. Waterborne Primer / Waterborne Light Industrial Coating MPI EXT 5.3J-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 134 MPI 163 MPI 163

System DFT: 4.5 mils

G. Galvanized surfaces with slight coating deterioration; little or no rusting:

1. Waterborne Light Industrial Coating MPI REX 5.3J-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 134 N/A MPI 163

System DFT: 4.5 mils

EXTERIOR SURFACES, OTHER METALS (NON-FERROUS)

I. Aluminum, aluminum alloy and other miscellaneous non-ferrous metal items not otherwise specified except hot metal surfaces, roof surfaces, and new prefinished equipment. Match surrounding finish:

2. Waterborne Light Industrial Coating MPI EXT 5.4G-G5(Semigloss) Primer: Intermediate: Topcoat:

MPI 95 MPI 163 MPI 163

System DFT: 5 mils

1. Alkyd MPI EXT 5.1D-G1 (Flat) Primer: Intermediate: Topcoat:

MPI 79 MPI 8 MPI 8

SECTION 09 90 00 Page 21

EXTERIOR SURFACES, OTHER METALS (NON-FERROUS)

System DFT: 5.25 mils

MPI EXT 5.1D-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 79 MPI 94 MPI 94

System DFT: 5.25 mils

MPI EXT 5.1D-G6 (Gloss) Primer: Intermediate: Topcoat:

MPI 79 MPI 9 MPI 9

System DFT: 5.25 mils

2. Waterborne Light Industrial Coating MPI EXT 5.1C-G3(Eggshell) Primer: Intermediate: Topcoat:

MPI 79 MPI 161 MPI 161

System DFT: 5 mils

MPI EXT 5.1C-G5(Semigloss) Primer: Intermediate: Topcoat:

MPI 79 MPI 163 MPI 163

System DFT: 5 mils

MPI EXT 5.1C-G6(Gloss) Primer: Intermediate: Topcoat:

MPI 79 MPI 164 MPI 164

System DFT: 5 mils

K. Hot metal surfaces subject to temperatures up to 400 degrees F :

1. Heat Resistant Enamel

MPI EXT 5.2A

Primer: Intermediate: Topcoat:

MPI 21 Surface preparation and number of coats per manufacturer's instructions.

System DFT: Per Manufacturer

L. Ferrous metal subject to high temperature, up to 750 degrees F :

1. Inorganic Zinc Rich Coating

MPI EXT 5.2C

Primer: Intermediate: Topcoat:

MPI 19 Surface preparation and number of coats per manufacturer's instructions.

System DFT: Per Manufacturer

2. Heat Resistant Aluminum Enamel MPI EXT 5.2B (Aluminum Finish) Primer: Intermediate: Topcoat:

MPI 2 Surface preparation and number of coats per manufacturer's instructions.

System DFT: Per Manufacturer

SECTION 09 90 00 Page 22

3.12.2 Interior Paint Tables

DIVISION 3: INTERIOR CONCRETE PAINT TABLE

A. New concrete floors:

1. Water-Based Concrete Floor Sealer System MPI INT 3.2G:

Primer: Topcoat:

MPI 99 MPI 99

System DFT: Per Manufacturer

DIVISION 5: INTERIOR METAL, FERROUS AND NON-FERROUS PAINT TABLE

INTERIOR STEEL / FERROUS SURFACES

A. Metal, Mechanical,Electrical,Fire extinguishing sprinkler systems including valves, conduit, hangers, supports,Surfaces adjacent to painted surfaces (Match surrounding finish),exposed copper piping,and miscellaneous metal items not otherwise specified except floors, hot metal surfaces, and new prefinished equipment:

1. High Performance Architectural Latex MPI INT 5.1R-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 79 MPI 141 MPI 141

System DFT: 5 mils

B. Ferrous metal in concealed damp spaces or in exposed areas having unpainted adjacent surfaces as follows:

1. Aluminum Paint

MPI INT 5.1M

Primer: Intermediate: Topcoat:

MPI 79 MPI 1 MPI 1

System DFT: 4.25 mils

C. Miscellaneous non-ferrous metal items not otherwise specified except floors, hot metal surfaces, and new prefinished equipment. Match surrounding finish:

1. MPI INT 5.4F-G3 (Eggshell) Primer: Intermediate: Topcoat:

MPI 95 MPI 139 MPI 139

System DFT: 5 mils

D. Hot metal surfaces subject to temperatures up to 400 degrees F :

1. Heat Resistant Enamel

MPI INT 5.2A

Primer: Intermediate: Topcoat:

MPI 21 Surface preparation and number of coats per manufacturer's instructions.

System DFT: Per Manufacturer

DIVISION 6: INTERIOR WOOD PAINT TABLE

A. New Wood and plywood not otherwise specified:

1. Alkyd MPI INT 6.4B-G6 (Gloss)

SECTION 09 90 00 Page 23

DIVISION 6: INTERIOR WOOD PAINT TABLE

Primer: Intermediate: Topcoat:

MPI 45 MPI 48 MPI 48

System DFT: 4.5 mils

DIVISION 9: INTERIOR PLASTER, GYPSUM BOARD, TEXTURED SURFACES PAINT

TABLE

A. New not otherwise specified:

1. Latex New; MPI INT 9.2A-G2 (Flat at ceilings) Primer: Intermediate: Topcoat:

MPI 50 MPI 44 MPI 44

System DFT: 4 mils

New; MPI INT 9.2A-G3 (Eggshell at walls) Primer: Intermediate: Topcoat:

MPI 50 MPI 52 MPI 52

System DFT: 4 mils

2. Alkyd New; MPI INT 9.2C-G5 (Semigloss) Primer: Intermediate: Topcoat:

MPI 50 MPI 47 MPI 47

System DFT: 4 mils

-- End of Section --

SECTION 09 90 00 Page 24

09 90 00 - PAINTS AND COATINGS
09 90 00 - PAINTS AND COATINGS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CERTIFICATES
1.3.1 Indoor Air Quality
1.3.1.1 Paints and Coatings
1.4 APPLICATOR'S QUALIFICATIONS
1.4.1 Contractor Qualification
1.4.2 SSPC QP 1 Certification
1.5 QUALITY ASSURANCE
1.5.1 Field Samples and Tests
1.5.1.1 Sampling Procedure
1.5.1.2 Testing Procedure
1.6 REGULATORY REQUIREMENTS
1.6.1 Environmental Protection
1.6.2 Lead Content
1.6.3 Chromate Content
1.6.4 Asbestos Content
1.6.5 Mercury Content
1.6.6 Silica
1.6.7 Human Carcinogens
1.7 PACKAGING, LABELING, AND STORAGE
1.8 SAFETY AND HEALTH
1.8.1 Safety Methods Used During Coating Application
1.8.2 Toxic Materials
1.9 ENVIRONMENTAL CONDITIONS
1.9.1 Coatings
1.9.2 Post-Application
1.10 SCHEDULING
1.11 COLOR SELECTION
1.12 LOCATION AND SURFACE TYPE TO BE PAINTED
1.12.1 Painting Included
1.12.1.1 Exterior Painting
1.12.1.2 Interior Painting
1.12.2 Painting Excluded
1.12.3 Mechanical and Electrical Painting
1.12.3.1 Fire Extinguishing Sprinkler Systems
1.12.4 Definitions and Abbreviations
1.12.4.1 Qualification Testing
1.12.4.2 Coating
1.12.4.3 DFT or dft
1.12.4.4 DSD
1.12.4.5 EPP
1.12.4.6 EXT
1.12.4.7 INT
1.12.4.8 micron / microns
1.12.4.9 mil / mils
1.12.4.10 mm
1.12.4.11 MPI Gloss Levels
1.12.4.12 MPI System Number
1.12.4.13 Paint
1.12.4.14 REX
1.12.4.15 RIN
PART 2 PRODUCTS
2.1 MATERIALS
PART 3 EXECUTION
3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED
3.2 SURFACE PREPARATION
3.3 PREPARATION OF METAL SURFACES
3.3.1 New Ferrous Surfaces
3.3.2 Final Ferrous Surface Condition:
3.3.3 Galvanized Surfaces
3.3.4 Non-Ferrous Metallic Surfaces
3.4 PREPARATION OF CONCRETE AND CEMENTITIOUS SURFACE
3.4.1 Concrete
3.4.2 Gypsum Board
3.5 PREPARATION OF WOOD AND PLYWOOD SURFACES
3.5.1 New Plywood and Wood Surfaces, Except Floors:
3.6 APPLICATION
3.6.1 Coating Application
3.6.2 Mixing and Thinning of Paints
3.6.3 Two-Component Systems
3.6.4 Coating Systems
3.7 COATING SYSTEMS FOR METAL
3.8 COATING SYSTEMS FOR WOOD AND PLYWOOD
3.9 PIPING IDENTIFICATION
3.10 INSPECTION AND ACCEPTANCE
3.11 WASTE MANAGEMENT
3.12 PAINT TABLES
3.12.1 Exterior Paint Tables
3.12.2 Interior Paint Tables