POM_Env_Specs_01_57_20_(Apdx_GG)_(3).pdf

PDF 133 KB Posted

Attached to
Design-Build (D-B) Advanced Individual Training (AIT) Barracks, Presidio of Monterey (POM), California
Solicitation number
W91238-13-R-0027
Issued by

About this file

Amendment 10 Spec Section 01 57 20

View the file

Other files

File Type Posted
Award_Announcement__Synopsis_.pdf PDF
Attachment_2_-_Updated_Wage_Determination_06-05-2015.pdf PDF
W91238-13-R-0027_Amend_0022.pdf PDF
W91238-13-R-0027_Amend_0022.pdf PDF
Attachment_2_-_Updated_Wage_Determination_06-05-2015.pdf PDF
W91238-13-R-0027_Amend_0021.pdf PDF
Attachment_2_Updated_Construction_Wage_Determination_02-20-2015.pdf PDF
Notice_of_Pending_Amendment.docx DOCX document
https //www.fbo.gov/spg/USA/COE/DACA05/W91238-13-R-0027/listing.html HTML file
W91238-13-R-0027-0018.pdf PDF
Site_Visit_Sign-in_00.pdf PDF
W91238-13-R-0027-U0019.pdf PDF
Amendment_0018_POM_Barrack_Due_Date_Extended_26Jan15.pdf PDF
W91238-13-R-0027_Amend_0014.pdf PDF
W91238-13-R-0027_Amend_0015.pdf PDF
13-R-0027-0014.pdf PDF
Attachment_6_Bldg_629_DEMOLITION_DRAWINGS_AM0013.pdf PDF
W91238-13-R-0027-0013_Amend.doc DOC document
Attachment_2_Updated_Construction_Wage_Determination.pdf PDF
W91238-13-R-0027-0013_Conform.doc DOC document
Attachment_8_Bldg_629_Survey_Maps_(V-Sheets)_from_P83_DFAC.pdf PDF
Attachment_5_Bldg_629_DEMOLITION_SPECIFICATIONS_AM0013.pdf PDF
Attachment_7_Bldg_629_Demolition_As-Builts.pdf PDF
W91238-13-R-0027-0012.pdf PDF
Wage_Determination.pdf PDF
A02_W91238-13-R-0027-0011.pdf PDF
CAD_Amd_10.pdf PDF
A02_W91238-13-R-0027-0010.pdf PDF
A02_Amendment_9_Wage_Determinations.pdf PDF
A02_W91238-13-R-0027-0009.pdf PDF
A02_POM_53789_Amendment_009_Spec_Change.pdf PDF
A02_W91238-13-R-0027-0008.pdf PDF
A02_POM_53789_Amendment_007_Spec_Change.pdf PDF
A02_W91238-13-R-0027-0007.pdf PDF
Wage_Determinations_(Amendment_0007_Update).pdf PDF
W91238-13-R-0027-U0006.pdf PDF
W91238-13-R-0027-0005.pdf PDF
W91238-13-R-0027-0004.pdf PDF
W91238-13-R-0027-0003.pdf PDF
Justification_and_Approval_Kaba-Ilco_Locks_(Redacted)_Redacted.pdf PDF
A02_13-R-0027-U0002_Amendment_2.pdf PDF
Wage_Determinations.pdf PDF
13-R-0027-U0001.pdf PDF
FY-11_AIT_Barracks_RFP_Locked_2_Phase_adjusted_specs_130530 1 .pdf PDF
W91238-13-R-0027_POM_Barracks.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section: Appendix GG W91238-13-R-0027-007

FY 11 Barracks Complex Phase 1 ( Barracks Building)

SECTION TABLE OF CONTENTS DIVISION

01 - GENERAL REQUIREMENTS SECTION

01 57 20

ENVIRONMENTAL PROTECTION

05/10

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Environmental Pollution and Damage

1.2.2 Environmental Protection

1.2.2.1 Environmental Protection Plan

1. 2. 3

1. 2. 4 1.2.5

1. 2. 6 1.2.7

Contractor Generated Hazardous Waste Installation Pest Management Coordinator Land Application for Discharge Water Pesticide Pests

1.2.8 Surface Discharge

1.2.9 Waters of the United States

1.2.10 Wetlands

1.3 GENERAL REQUIREMENTS

1.4 SUBCONTP CTORS

1.5 PAYMENT

1.6 SUBMITTALS

1.7 El\J"VIRONMENTAL PROTECTION PLAN

1.7.1 Compliance

1.7.2 Contents

1.7.3 Appendix

1.8 PROTECTION FEATURES

1.9 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS

1.10 NOTIFICATION

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 ENVIRONMENTAL PERMITS AND COMMITMENTS

3.2 LAND RESOURCES

3.2.1 3.2.2 3.2.3

Work Area Limits Landscape Erosion and Sediment Controls

3.2.4 Contractor Facilities and Work Areas

3.3 WATER RESOURCES

3.3.1 Cofferdams, Diversions, and Dewatering Operations

3.3.2 Stream Crossings

3.3.3 Wetlands

3.4 AIR RESOURCES

3.4.1 3.4.2 3.4.3

Particulates Odors Sound Intrusions

01 57 20 - 1

Thursday, February 13, 2014

1742FY 11 Barracks Complex Phase 1 ( Barracks Building)

3o4o4 Burning 3o5 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL 3o5o1 30502 3o5o3 30504

Solid Wastes Chemicals and Chemical Wastes Contractor Generated Hazardous Wastes/Excess Hazardous Materials Fuel and Lubricants

30505 Waste Water 3o6 RECYCLING AND WASTE MINIMIZATION 3o7 NON-HAZARDOUS SOLID WASTE DIVERSION REPORT 3o8 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES 3o9 BIOLOGICAL RESOURCES

30901 Fish and Wildlife 30902 3o9o3 30904 3 0 9 0 5 3 0 9 0 6

Existing Trees Preservation Fencing Existing Trees for Preservation Monterey Pine Tree Preservation Preservation of Trees During Utility Installation Approved Construction Work Within Root Zones

3o10 INTEGRATED PEST MANAGEMENT 301001 Pesticide Delivery and Storage 301002 Qualifications 301003 Pesticide Handling Requirements 301004 Application

3011 PREVIOUSLY USED EQUIPMENT

3o12 MAINTENANCE OF POLLUTION FACILITIES 3o13 MILITARY MUNITIONS 3o14 3o15 3o16

TRAINING OF CONTRACTOR PERSONNEL

CONTAMINATED MEDIA MANAGEMENT

POST CONSTRUCTION CLEANUP

-- End of Section Table of Contents

01 57 20 - 2

SECTION 01 57 20

ENVIRONMENTAL PROTECTION

05/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publication are referred to within the text by the basic designation only.

U.S. DEPARTMENT OF DEFENSE (DOD)

DD FORM 1532 (1996) PEST MANAGEMENT REPORT

U.S. ARMY (DA)

DA AR 200-1 (2007) Environmental Protection and Enhancement

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010;

Changes 4-6 2011) Safety and Health Requirements Manual

WETLANDS DELINEATION MANUAL (1987) Corps of Engineers Wetlands

Delineation Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 328 Definitions of Waters of the United States

40 CFR 150 - 189 Pesticide Programs

40 CFR 260 Hazardous Waste Management System: General

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of

Hazardous Waste

40 CFR 279 Standards for the Management of Used Oil

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 355 Emergency Planning and Notification

40 CFR 68 Chemical Accident Prevention Provisions

49 CFR 171 - 178 Hazardous IY!aterials Regulations

01 57 20 - 3

1.2 DEFINITIONS

1.2.1 Environmental Pollution and Damage

Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;

affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.

1.2. 2 Environmental Protection

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioact.ive material as well as other pollutants.

1.2.2.1 Environmental Protection Plan

Submit an environmental protection plan within 15 days after receipt of the notice to proceed. Approval of the Contractor's plan will not relieve the Contractor of responsibility for adequate and continuing con.trol of pollutants and other environmental protection measures. The environmental protection plan shall include, but shall not be limited to, the following:

a. A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control and abatement that are applicable to the Contractor's proposed operations and the requirements imposed by those laws, regulat.ions, and permits.

b. Methods for protection of features to be preserved within authorized work areas like trees, shrubs, vines, grasses and ground cover, landscape features, air and water quality, :(:ish and wildlife, soil, historical, archaeological, and cultural resources.

c. A Recycling and solid waste inimization plan and non-hazardous solid waste diversion reports. (Note: A 50% minimum diversion of construction and demolition C&D waste by weight is required from landfill disposal. Report amounts on monthly basis to Bill Genova at DPW (831-242-5327).

1.2.3 Contractor Generated Hazardous Waste

Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners,excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.

l. 2.4 Installation Pest Management Coordinator

Installation Pest Management Coordinator (IPMC) is the individual officially designated by the Installation Commander to oversee the

01 57 20 - 4

W91238-13-R-0027-007

Section: Appendix GG

Installation Pest Management Program and the Installation Pest Management Plan.

All pesticide application -related issues shall be processed through the POM IPMC. The following is contact information for POM IPMC.

Natural Resource Specialist Presidio of Monterey Directorate of Public Works Environmental Division P.O. Box 5004 Monterey, CA 93944 831-242-6736 Fax {831) 242-7019

If the designated natural Resource Specialist is not avaiable, the alternate point. of contact is the Environmental Division Chief at (831)-242-7925.

1. 2. 5 Land Application for Discharge Water

The term "Land Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and regulations.

1.2.6 Pesticide

Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.

1.2.7 Pests

The term "pests" means arthropods, birds, rodents, nematodes, fungi, bacteria, viruses, algae, snails, marine borers, snakes, weeds and other organisms (except for human or animal disease-causing organisms) that adversely affect readiness, military operations, or the well-being of personnel and animals; attack or damage real property, supplies, equipment, or vegetation; or are otherwise undesirable.

1.2.8 Surface Discharge

The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers,creeks, and/or "waters of the United States" and would require a permit to discharge water from the governing agency.

1. 2. 9 Waters of the United States

All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328.

1.2.10 Wetlands

Those areas that are inundated or saturated by surface or ground water at a

01 57 20 - 5 frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, and bogs. Official determination of whether or not an area is classified as a wetland must be done in accordance with

WETLANDS DELINEATION MANUAL.

1.3 GENERAL REQUIREMENTS

Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations.

Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.

1.4 SUBCONTRACTORS

Ensure compliance with this section by subcontractors.

1.5 PAYMENT

No separate payment will be made for work covered under this section.

Payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor, and payment of all fines/fees for violation or non-compliance with Federal, State, Regional and local laws and regulations are the Contractor's responsibility. All costs associated with this section must be included in the contract price.

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Environmental Protection Plan; G

1.7 ENVIRONMENTAL PROTECTION PLAN

Prior to commencing construction activities or delivery of materials to the site, submit an Environmental Protection Plan for review and approval by the Department of Public Works-Environmental (DPW-Environmental) the IPMC and by the Contracting Officer. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the Contractor must address during construction. Issues of concern must be defined within the Environmental Protection Plan as outlined in this section. Address each topic at a level of detail commensurate with the environmental issue and required construction task(s). Topics or issues which are not identified in this section, but are considered necessary, must be identified and discussed after those items formally identified in this section. Prior to submittal of the Environmental Protection Plan, meet with the Contracting Officer (who may invite the IPMC) for the purpose of discussing the implementation of the initial Environmental Protection Plan; possible subsequent additions and revisions to the plan including any reporting requirements; and methods

01 57 20 - 6 for administration of the Contractor's Environmental Plans. The Environmental Protection Plan must be current and maintained onsite by the Contractor.

1.7.1 Compliance

No requirement in this Section will relieve the Contractor of any applicable Federal, State, and local environmental protection laws and regulations. During Construction, the Contractor will be responsible for identifying, implementing, and submitting for approval any additional requirements to be included in the Environmental Protection Plan.

1. 7. 2 Contents

Include in the environmental protection plan, but not limit it to, the following:

a. Name(s) of person(s) within the Contractor's organization who is(are) responsible for ensuring adherence to the Environmental Protection Plan.

b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site, if applicable.

c. Name(s) and qualifications of person(s) responsible for training the

Contractor's environmental protection personnel.

d. Description of the Contractor's environmental protection personnel training program.

e. An erosion and sediment control plan which identifies the type and location of the erosion and sediment controls to be provided. The plan must include monitoring and reporting requirements to assure that the control measures are in compliance with the erosion and sediment control plan, Federal, State, and local laws and regulations. A Storm Water Pollution Prevention Plan (SWPPP) may be substituted for this plan.

f. Drawings showing locations of proposed temporary excavations or embankments for haul roads, stream crossings, material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials including methods to control runoff and to contain materials on the site.

g. Traffic control plans including measures to reduce erosion of temporary roadbeds by construction traffic, especially during wet weather. Plan shall include measures to minimize the amount of mud transported onto paved public roads by vehicles or runoff.

h. Work area plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas including methods for protection of features to be preserved within authorized work areas.

i. Drawing showing the location of borrow areas.

j. Include in the Spill Control plan the procedures, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by 40 CFR 68, 40 CFR 302, 40 CFR 355, and/or regulated under State or Local laws and regulations. The Spill Control Plan

01 57 20 - 7 supplements the requirements of EM 385-1-1. Include in this plan, as a minimum:

(1) The name of the individual who will report any spills or hazardous substance releases and who will follow up with complete documentation. This individual will immediately notify the Contracting Officer and the local Fire Department in addition to the legally required Federal, State, and local reporting channels (including the National Response Center 1-800-424-8802) if a reportable quantity is released to the environment. Include in the plan a list of the required reporting channels and telephone numbers.

(2) The name and qualifications of the individual who will be responsible for implementing and supervising the containment and cleanup.

(3) Training requirements for Contractor's personnel and methods of accomplishing the training.

(4) A list of materials and equipment to be immediately available at the job site, tailored to cleanup work of the potential hazard(s) identified.

(5) The names and locations of suppliers of containment materials and locations of additional fuel oil recovery, cleanup, restoration, and material-placement equipment available in case of an unforeseen spill emergency.

(6) The methods and procedures to be used for expeditious contaminant cleanup.

k. A non-hazardous solid waste disposal plan identifying methods and locations for solid waste disposal including clearing debris and schedules for disposal.

(1) Identify any subcontractors responsible for the transportation and disposal of solid waste. Submit licenses or permits for solid waste disposal sites that are not a commercial operating facility.

(2) Evidence of the disposal facility's acceptance of the solid waste must be attached to this plan during the construction. Attach a copy of each of the Non-hazardous Solid Waste Diversion Reports to the disposal plan. Submit the report for the previous quarter on the first working day after the first quarter that non-hazardous solid waste has been disposed and/or diverted (e.g. the first working day of January, April, July, and October).

(3) Indicate in the report the total amount of waste generated and total amount of waste diverted in cubic yards or tons along with the percent that was diverted.

(4) A recycling and solid waste minimization plan with a list of measures to reduce consumption of energy and natural resources.

Detail in the plan the Contractor's actions to comply with and to participate in Federal, State, Regional, and local government sponsored recycling programs to reduce the volume of solid waste at the source.

01 57 20 - 8

l. An air pollution control plan detailing provisions to assure that dust, debris, materials, trash, etc., do not become air borne and travel off the project site.

m. A contaminant prevention plan that: identifies potentially hazardous substances to be used on the job site; identifies the intended actions to prevent introduction of such materials into the air, water, or ground; and details provisions for compliance with Federal, State, and local laws and regulations for storage and handling of these materials. In accordance with EM 385-1-1, a copy of the Material Safety Data Sheets (MSDS) and the maximum quantity of each hazardous material to be onsite at any given time must be included in the contaminant prevention plan. Update the plan as new hazardous materials are brought onsite or removed from the site.

n. A waste water management plan that identifies the methods and procedures for management and/or discharge of waste waters which are directly derived from construction activities, such as concrete curing water, clean-up water, dewatering of ground water, disinfection water, hydrostatic test water, and water used in flushing of lines. If a settling/retention pond is required, the plan must include the design of the pond including drawings, removal plan, and testing requirements for possible pollutants. If land application will be the method of disposal for the waste water, the plan must include a sketch showing the location for land application along with a description of the pretreatment methods to be implemented. If surface discharge will be the method of disposal, include a copy of the permit and associated documents as an attachment prior to discharging the waste water. If disposal is to a sanitary sewer, the plan must include documentation that the Waste Water Treatment Plant Operator has approved the flow rate, volume, and type of discharge.

o. A historical, archaeological, cultural resources biological resources and wetlands plan that defines procedures for identifying and protecting historical, archaeological, cultural resources, biological resources and wetlands known to be on the project site: and/or identifies procedures to be followed if historical archaeological, cultural resources, biological resources and wetlands not previously known to be onsite or in the area are discovered during construction.

Include in the plan methods to assure the protection of known or discovered resources, identifying lines of communication between Contractor personnel and the Contracting Officer.

p. Include and update a pesticide treatment plan, as information becomes available. Some pesticide treatments require installation wide notice through the base command structure so the plan should be submitted as far in advance of the proposed application date as possible. Include in the plan: sequence of treatment, dates, times, locations, pesticide trade name, EPA registration numbers, authorized uses, chemical composition, formulation, original and applied concentration, application rates of active ingredient (i.e. pounds of active ingredient applied), equipment used for application and calibration of equipment. Federal, State, Regional and Local pest management record keeping and reporting requirements as well as any additional Installation Project Office specific requirements are the Contractor's responsibility in conformance with DA AR 200-1 Chapter 5--Pest Management, Section 5-4 "Program requirements" for data required to be reported to the Installation. Submit the pesticide treatment documentation on DD FORM 1532 which can be obtained from the IPMC.

01 57 20 - 9

Submit the pesticide treatment documentation and form DD FORM 1532 to the COR five (5) working days after application. Coordinate with the COR for review by the IPMC. The IPMC and the Army Environmental Command have the final approval of all pesticides, contractor pesticide applicators, and methods of pesticide application. Submit the pesticide applicators' state certification card/license for POM IPMC "DoD equivalanecy" approval prior to any pesticide application.

1. 7. 3 Appendix

Attach to the Environmental Protection Plan, as an appendix, copies of all environmental permits, permit application packages, approvals to construct, notifications, certifications, reports, and termination documents.

1.8 PROTECTION FEATURES

This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to start of any onsite construction activities, the Contractor and the Contracting Officer will make a joint condition survey. This survey shall comply with and identify all sensitive environmental resources as presented in the Integrated Natural Resource Management Plan (INRMP). Immediately following the survey, the Contractor will prepare a brief report including a plan describing the features requiring protection under the provisions of the Contract Clauses, which are not specifically identified on the drawings as environmental features requiring protection along with the condition of trees, shrubs and grassed areas immediately adjacent t.o the site of work and adjacent to the Contractor's assigned storage area and access route(s), as applicable. This survey report will be signed by both the the Contractor and the Contracting Officer upon mutual agreement as to its accuracy and completeness, and provide a copy to the Installation DPW Environmental Office. The Contractor must protect those environmental features included in the survey report and any indicated on the drawings, regardless of interference which their preservation may cause to the work under the contract. Representative from Environmental Division needs to take part in, and sign off on, condition survey (along with contractor and Contract Officer) to identify any features requiring protection.

1.9 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS

Any deviations from the drawings,plans and specifications, requested by the Contractor and which may have an environmental impact, will be subject to approval by the Contracting Officer and may require an extended review, processing, and approval time. The Contracting Officer reserves the right to disapprove alternate methods, even if they are more cost effective, if the Contracting Officer determines that the proposed alternate method will have an adverse environmental impact.

1.10 NOTIFICATION

The Contracting Officer will notify the Contractor in writing of any observed noncompliance with Federal, State or local environmental laws or regulations, permits, and other elements of the Contractor's Environmental Protection plan. After receipt of such notice, the Contractor will inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer. The Contracting Officer 1nay issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in

01 57 20 - 10 addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

3.1 ENVIRONMENTAL PERMITS AND COMMITMENTS

Obtaining and complying with all environmental permits and commitments required by Federal, State, Regional, and local environmental laws and regulations is the Contractor's responsibility.

3.2 LAND RESOURCES

Confine all activities to areas defined by the drawings and specifications. Identify any land resources to be preserved within the work area prior to the beginning of any construction. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and land forms without approval, except in areas indicated on the drawings or specified to be cleared. Ropes, cables, or guys will not be fastened to or attached to any trees for anchorage unless specifically authorized. Provide effective protection for land and vegetation resources at all times, as defined in the following subparagraphs. Remove stone, soil, or other materials displaced into uncleared areas. Protect tress, vegetation and other designated features by erecting high-visibility fencing. Locate fence no closer to trees than the drip line. The fenced area is off limits to material and equipment storage and vehicle and pedestrian traffic.

3.2.1 Work Area Limits

Mark the areas that need not be disturbed under this contract prior to commencing construction activities. Mark or fence isolated areas within the general work area which are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction operations are to be conducted during darkness, any markers must be visible in the dark. The Contractor's personnel must be knowledgeable of the purpose for marking and/or protecting particular objects.

3.2.2 Landscape

Trees, shrubs, vines, grasses, land forms and other landscape features indicated and defined on the drawings to be preserved must be clearly identified by marking, fencing, or wrapping with boards, or any other approved techniques. Restore landscape features damaged or destroyed during construction operations outside the limits of the approved work area.

3.2.3 Erosion and Sediment Controls

Providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations is the Contractor's responsibility.

Select and maintain the erosion and sediment controls such that water quality standards are not violated as a result of construction activities.

The area of bare soil exposed at any one time by construction operations should be kept to a minimum. See specification 01 57 23 TEMPORARY STORM

01 57 20 - 11

WATER POLLUTION CONTROL for all storm water permit and storm water discharge requirements. Any temporary measures shall be removed after the area has been stabilized.

3.2.4 Stormwater

The proposed improvements will be constructed in ways that would not exacerbate flooding conditions downstream and would maximize stormwater infiltration and/or storage and minimize stormwater runoff and sediment erosion. The California Stormwater Construction General Permit has developed specific BMPs to achieve strict compliance with federal technology-based and water quality-based standards. The minimum BMPs required by the permit are contingent on the applicable sediment risk level as described by the permit and would include erosion control and sediment control BMPs. Other measures to improve stormwater quality include good housekeeping practices, non-stormwater management on-site, run-on and run-off control, inspection, maintenance and repair measures, and implementation of a Rain Event Action Plan.

Engineering controls include hay bales, silt fencing, and inspection and monitoring will be implemented. Detailed construction plans must be developed and implementation. The details of each of these measures must be site-specific and described in the SWPPP for construction.

a. As part of the site design, BMPs include non-structural controls as described in the California Stormwnter Construction General Permit, such as green rooftops, impervious pavements,. vegetated swales .. setbacks and buffers that filter and settle out pollutants and provide for infiltration and/or storage at the POM and the OM C. Designs for the proposed projects may also include elongated trench drains, use of porous pavers in some existing and proposed areas of impervious surface, bio-retention cells, and chamber storage of stormwater (underground stormwater collection systems) in low elevation areas.

Selection of a combination of these controls will be made during design of the proposed projects. By implementing these increases in storage, the peak runoff to Monterey Bay will be reduced to being either equal to preconstruction levels or lower as in compliance with the California Stormwater Construction General Permit.

b. Changes from construction can result in increased erosion and sediment transport capacity. Post-construction stormwater performance standards in the California Stormwater Construction General Permit specifically address water quality and channel protection events. Post-construction BMPs for water quality improvement include structural and non-structural controls, which detain, retain, or filter the release of pollutants to receiving waters after final stabilization is attained. Examples include downspout disconnection, soil quality presePJation/enhancement, interceptor trees). Specific post-construction BMPs will be selected during project design and comply with the post-construction runoff requirements of the California Stormwater Construction General Permit.

c. The California Stormwater Construction General Permit has developed specific

BMPs to achieve strict compliance with federal technology-based anrl water quality-based standards. For each construction project, Permit Registration Documents would be prepared for submission to the SWRCB and would include a Notice of Intent, Risk Assessment, Site Map, SWPPP, a signed certification statement, post-construction documentation, and payment of fees. The findings of the Risk Assessment will determine the hazards associated with the site conditions and establish the specific compliance conditions of the permit. A SWPPP is required to be developed prior to construction to address the control of pollutant discharges using BMPs selected for the specific project and to address stormwater monitoring. The BMPs include but not limited to the following:

- Schedule construction sequences to minimize land disturbance during rainy and dry seasons

- Provide soli stabilization to steep slope areas

- Provide sediment controls to intercept and slow down stormwater flows

- Cover stockpiled soil

- Use dust suppressants, such as watering soils and unpaved roadways

- Preserve existing vegetation where no construction activities are planned

- Wherever possible, Replant/revegetate all exposed disturbed areas immediately upon completion of construction

Following the completion of the development project, the site must meet the conditions for Termination of Coverage by certifying the site has been stabilized and there is no potential for construction-related stormwater discharges. On September 2, 2012, the new postconstruction standards will be in effect, and post-construction BMPs and long-term maintenance plans will be required.

d. LID techniques would be applied to the extent practical in replicating the predevelopment natural hydrology of an area by using small-scale stormwater management design measures that mimic natural processes that slow, filter, infiltrate and detain runoff. These measures will help ensure that receiving waters are not negatively affected by changes in runoff temperature, volumes, durations, and flow rates. Several LID BMPs include but not limited to the following:

- Permeable pavement

- Rain gardens, bioretention and infiltration planters

- Vegetated swales

- Green roofs

- Integration of native riparian buffers

- Rain water harvesting or reuse where permissible

3.2.5 Contractor Facilities and Work Areas

Place field offices, staging areas, stockpile storage, and temporary buildings in areas designated on the drawings or as directed by the Contracting Officer. Temporary movement or relocation of Contractor facilities will be made only when approved. Erosion and sediment controls must be provided for onsite borrow and spoil areas to prevent sediment from entering nearby waters. Temporary excavation and embankments for plant and/or work areas must be controlled to protect adjacent areas.

The area designated as the contractor staging area, later a parking lot, is located on a section of a formerly caped landfill. The Contractor shall not degrade the integrity of the landfill soil and vegetative covers, or any landfill structure (drainage control system, retaining wall, V-ditches, graded inlets at the catch basin, culvert underneath Mason Road, etc). The Contractor is responsible for repairing any damages to the soil and vegetative covers or any landfill appurtenance.

3.3 WATER RESOURCES

Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated. For construction activities immediately adjacent to impaired surface waters, the Contractor must be capable of quantifying sediment or pollutant loading to that surface water when required by State or Federally issued Clean Water Act permits.

3.3.1 Cofferdams, Diversions, and Dewatering Operations

Construction operations for dewatering, removal of cofferdams, tailrace excavation, and tunnel closure will be controlled at all times to maintain compliance with existing State water quality standards and designated uses of the surface water body. Comply with the State of California water quality standards and anti-degradation provisions .

3. 3. 2 Stream Crossings

Stream crossings must allow movement of materials or equipment without violating water pollution control standards of the Federal, State, and local governments. Construction of stream crossing structures will be in compliance with Clean Water Act Section 404

3.3.3 Wetlands

DO not enter, disturb, destroy, or allow discharge of contaminants into any wetlands. The protection of wetlands in accordance with paragraph

01 57 20 - 12

ENVIRONMENTAL PERMITS AND COMMITMENTS is the Contractor's responsibility.

Authorization to enter specific wetlands identified will not relieve the Contractor from any obligation to protect other wetlands within, adjacent to, or in the vicinity of the construction site and associated boundaries.

3.4 AIR RESOURCES

Equipment operation, activities, or processes will be in accordance with all Federal and State air emission and performance laws and standards.

Comply with Monterey Bay Unified Air Pollution Control District (MBUAPCD) rules and permit requirements concerning utility equipment for new construction. Obtain permits for all equipment, including but not limited to boilers, generators, or other potential sources of air emissions for which permits are required under the District Air Quality Permit Program at least 10 days prior to installation of equipment. Provide copies of all APCD permits to DPW Environmental Division prior to equipment installation.

a. Schedule construction sequences to minimize land disturbance during rainy and dry seasons

b. Provide soil stabilization to steep slope areas

c. Cover stockpiled soil

d. Use dust suppressants such as watering soils and unpaved roadways

e. Preserve existing vegetation where no construction activities are planned and wherever possible Replant/revegetate all exposed disturbed areas immediately upon completion of construction

f. Apply water to surfaces three times a day

g. Apply non-toxic binders (e.g., latex acrylic copolymer) to exposed areas after cut and fill operations, and hydro-seed areas

h. Haul trucks shall maintain at least 2 feet of freeboard (the empty space below top of the trailer)

i. Cover all trucks hauling dirt, sand, or loose materials

j. Locate construction equipment and staging areas away from sensitive receptors and fresh air intakes to buildings and air conditions

k. Reduce use, trips, and unnecessary idling from heavy equipment

l. Maintain and tune engines per manufacturer's specifications to perform at the CARB- and USEPA-certification levels and at verified standards applicable to retrofit technologies

m. Limit idling for all vehicles

n. Prohibit tampering with engines and require continuing adherence tomanufacturer's recommendations

o. If practicable, lease new, clean equipment meeting the most stringent of applicable federal and state standards

p. If practicable, use USEPA-registered particulate traps and other appropriate controls, where suitable, to reduce emissions.

3.4.1 Particulates

Dust particles; aerosols and gaseous by-products from construction activities; and processing and preparation of materials, such as from asphaltic batch plants; must be controlled at all times, including weekends, holidays and hours when work is not in progress. Maintain excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and other work areas within or outside the project boundaries free from particulates which would cause the Federal, State, and local air pollution standards to be exceeded or which would cause a hazard or a nuisance. Sprinkling, chemical treatment of an approved type, baghouse, scrubbers, electrostatic precipitators or other methods will be permitted to control particulates in the work area.

Sprinkling, to be efficient, must be repeated to keep the disturbed area damp at all times. Provide sufficient, competent equipment available to accomplish these tasks. Perform particulate control as the work proceeds and whenever a particulate nuisance or hazard occurs. Comply with all State and local visibility regulations.

3.4.2 Odors

Odors from construction activities must be controlled at all times. The odors must be in compliance with State regulations and/or local ordinances and may not constitute a health hazard.

3.4.3 Sound Intrusions

Keep construction activities under surveillance and control to minimize environment damage by noise. Comply with the provisions of the State of California rules.

a. Appropriate level of sound attenuation must be used or constructed to meet local ordinances, whenever possible. A potential sound attenuation measure that could be considered is temporary sound barriers near the construction activity noise source.

b. The construction contractor will be responsible for ensuring that all equipment itemshave the manufacturers' recommended noise abatement measures, such as mufflers, engine enclosures, and engine vibration isolators, intact and operational. All construction equipment must be inspected at periodic intervals to ensure proper maintenance and presence of noise control devices (e.g., mufflers and shrouding).

c. Construction will take place during weekday, daytime hours (Monday through

Friday from 7:00A.M. to 5:00P.M.). In addition to the above mitigation measure, the POM currently promotes quiet hours during the normal work week for some construction projects. This could include quiet hours between 6:00A.M. and 10:00 A.M. on specific work days, if requested by affected staff.

d. Provision of public notification of the project to local area neighborhoods and posting ofsign age that provides a phone number for the public to call to register complaints about construction-related noise problems.

3.4.4 Burning

Burning is prohibited on the Government premises.

3.5 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL

Disposal of wastes will be as directed below, unless otherwise specified in other sections and/or shown on the drawings.

01 57 20- 13·

3.5.1 Solid Wastes

Place solid wastes (excluding clearing debris) in containers which are emptied on a regular schedule. Handling, storage, and disposal must be conducted to prevent contamination. Employ segregation measures so that no hazardous or toxic waste will become co-mingled with solid waste.

Transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill will be the minimum acceptable offsite solid waste disposal option. Verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. Comply with Federal, State, and local laws and regulations pertaining to the use of landfill areas.

3.5.2 Chemicals and Chemical Wastes

Dispense chemicals ensuring no spillage to the ground or water. Perform and document periodic inspections of dispensing areas to identify leakage and initiate corrective action. This documentation will be periodically reviewed by the Government. Collect chemical waste in corrosion resistant, compatible containers. Collection drums must be monitored and removed to a staging or storage area when contents are within 6 inches of the top.

Wastes will be classified, managed, stored, and disposed of in accordance with Federal, State, and local laws and regulations.

3.5.3 Contractor Generated Hazardous Wastes/Excess Hazardous Materials

Hazardous wastes are defined in 40 CFR 261, or are as defined by applicable State and local regulations. Hazardous materials are defined in 49 CFR 171 - 178. At a minimum, manage and store hazardous waste in compliance with 40 CFR 262 in accordance with the Installation hazardous waste management plan. Take sufficient measures to prevent spillage of hazardous and toxic materials during dispensing. Segregate hazardous waste from other materials and wastes, protect it from the weather by placing it in a safe covered location, and take precautionary measures such as berming or other appropriate measures against accidental spillage. Storage, describing, packaging, labeling, marking, and placarding of hazardous waste and hazardous material in accordance with 49 CFR 171 - 178, State, and local laws and regulations is the Contractor's responsibility. Transport Contractor generated hazardous waste off Government property within 30 days in accordance with the Environmental Protection Agency and the Department of Transportation laws and regulations. Dispose of hazardous waste in compliance with Federal, State and local laws and regulations. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Facility Environmental Office. Cleanup and cleanup costs due to spills are the Contractor's responsibility. The disposition of Contractor generated hazardous waste and excess hazardous materials are the Contractor's responsibility.

3.5.4 Fuel and Lubricants

Storage, fueling and lubrication of equipment and motor vehicles must be conducted in a manner that affords the maximum protection against spill and evaporation. Manage and store fuel, lubricants and oil in accordance with all Federal, State, Regional, and local laws and regulations. Used lubricants and used oil to be discarded must be stored in marked corrosion-resistant containers and recycled or disposed in accordance with 40 CFR 279, State, and local laws and regulations. Storage of fuel on the project site is not allowed. Fuel must be brought to the project site each

01 57 20 - 14 day that work is performed.

3.5.5 Waste Water

Disposal of waste water will be as specified below.

a. Waste water from construction activities, such as onsite material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, forms, etc. will not be allowed to enter water ways or to be discharged prior to being treated to remove pollutants.

Dispose of the construction related waste water off-Government property in accordance with all Federal, State, Regional and Local laws and regulations.

b. For discharge of ground water, the Contractor shall obtain a State or

Federal permit specific for pumping and discharging ground water prior to surface discharging in accordance with all Federal, State, and local laws and regulations and with the requirements of the NPDES or State STORM WATER DISCHARGES FROM CONSTRUCTION SITES permit.

c.

3.6 RECYCLING AND WASTE MINIMIZATION

Participate in State and local government sponsored recycling programs.

The Contractor is further encouraged to minimize solid waste generation throughout the duration of the project. All Hauling for disposal and disposal area shall be coordinated through City of Monterey. Report the following, but not limited to the DPW (831-242-5327) in accordance with Section 1.2.2.1 c, Appendix GG:.

a. Construction and Demolition (C&D) Debris Disposed in cubic yards or tons, as appropriate. The Contractor shall provide the disposal site information such as name, permits/licenses, address, contact information and date of disposal, name of the ransporter(s) and bill of lading.

b. Construction and Demolition (C&D) Debris Recycled in cubic yards or tons, as appropriate. The Contractor shall provide the recycling site information such as name, permits/licenses, address, contact information and date of disposal, name of the transporter(s) and bill of lading.

c. Total C&D Debris Generated in cubic yards or tons, as appropriate.

d. Construction Waste Sent to Waste-To-Energy Incineration Plant (This amount should not be included in the recycled amount) in cubic yards or tons, as appropriate. The Contractor shall provide the plant information such as name, address, permits/licenses, contact information and date of disposal, name of the transporter(s) and bill of lading.

3.7 NON-HAZARDOUS SOLID WASTE DIVERSION REPORT

Maintain an inventory of non-hazardous solid waste diversion and disposal of construction and demolition debris. Submit a report to Contracting Office through the Contracting Officer on the first working day after each fiscal year quarter, starting the first quarter that non-hazardous solid waste has been generated. Include the following in the report at minimum

01 57 20 - 15 in accordance with Section 1.2.2.lc, Appendix GG:

a. Name of non-hazardous waste.

b. Quantity.

c. How the waste was generated.

d. Location of the waste generated (including map showing nearby buildings or GPS coordinates).

e. Date of the waste generation.

f. Type and Size of container, if applicable.

g. POC for the waste.

h. Date of disposal of the waste or planned disposal date.

i. Date of the report submittal.

j. Author of the report and contact information.

k. Contract #.

a. Construction and Demolition (C&D) Debris Disposed yards or tons, as appropriate.

in cubic

b. Construction and Demolition (C&D) Debris Recycled in cubic

c. Total C&D Debris Generated = appropriate.

in cubic yards or tons, as

d. Wast:e Sent to Waste-To-Energy Incineration Plant (This amount should not be included in the recycled amount) in cubic

3.8 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES

Existing historical, archaeological, and cultural resources within the Presidio of Monterey are available on maps at the DPW-E office. Work performed within the historic district shall be executed in accordance with Section 106 State Historical Preservation Office consultation requirements.

Protect these resources and be responsible for their preservation during the life of the Contract. If during excavation or other construction activities any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, all activities that may damage or alter such resources will be temporarily suspended. Resources covered by this paragraph include but are not limited to: any human skeletal remains or burials; artifacts; shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer so that the appropriate authorities may be notified and a determination made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in impact to or the destruction of these resources. Secure the area and prevent employees or other persons from trespassing on, removing, or otherwise disturbing such resources.

The Contractor shall comply with the following:

(1) Construction activities associated with this undertaking have the potential to expose unknown subsurface cultural resources and/or affect known historic properties (i.e., the landfill) in an unanticipated manner.

As such, the Contractor shall provide a qualified archeologist to be present during all excavation activities.

01 57 20 - 16

If cultural resources are inadvertently discovered, work shall be redirected 30-meters (100-feet) away from the find until it can be evaluated by the U.S. Army Cultural Resource Manager (Laura Prishmont Quimby 831 242-7926) and/or a qualified professional archaeologist. Per 36 CFR 61, the minimum professional qualifications in archeology are a graduate degree in archeology, anthropology, or closely related field plus:

la. At least one year of full-time professional experience or equivalent specialized training in archeological research, administration or management;

lb. At least four months of supervised field and analytic experience in general North American archeology, and

lc. Demonstrated ability to carry research to completion.

In addition to these minimum qualifications, a professional in prehistoric archeology shall have at least one year of full-time professional experience at a supervisory level in the study of archeological resources of the prehistoric period. A professional in historic archeology shall have at least one year of full-time professional experience at a supervisory level in the study of archeological resources of the historic period.

(2) Inadvertent discoveries will require implementation of procedures set forth in the Presidio of Monterey's Integrated Cultural Resource Management Plan (ICRMP)…