Manufacturer's certifications showing compliance with ANSI Z9.2 for:
a. Vacuums.
b. Water filtration equipment.
c. Ventilation equipment.
d. Other equipment required to contain airborne asbestos fibers.
Encapsulants G, RO
Certificates stating that encapsulants meet the applicable specified performance requirements.
Medical Surveillance Requirements
Required medical certification and the Physician's written opinion.
1.4 DESCRIPTION OF WORK
This section covers all operations in which asbestos-containing materials (ACM) are encountered. These procedures and equipment are required to protect workers and building occupants from airborne asbestos fibers and ACM dust and debris. Activities include OSHA Class II work operations.
This section also includes containment, storage, transportation and disposal of the generated ACM wastes. The Contractor shall submit Detailed Drawings as specified in the Submittals paragraph.
1.4.1 Abatement Work Tasks
be removed that could become friable (Regulated Asbestos Containing Material) during demolition." Therefore, the Category I non-friable ACM identified in this report may remain in place as long as the demolition operation is categorized and performed as an OSHA Class II asbestos abatement. The demolition work must be performed by a Asbestos Abatement Contractor. Any non-friable asbestos containing building materials that have remained in place during the demolition process must be identified for the disposal process. The ACM materials must be categorized and disposed of as asbestos waste and not included with building materials designated for recycling.
1.4.2 Unexpected Discovery of Asbestos
For any previously untested building components suspected to contain asbestos and located in areas impacted by the work, the Contractor shall notify the Contracting Officer (CO) who will have the option of ordering up to 5 bulk samples to be obtained at the Contractor's expense and delivered
SECTION 02 82 14.00 10 Page 10