A.07.24_W9123718R0004_-_0002_FBO.pdf

PDF 2 MB Posted

Attached to
National Inland Floating Plant and Land Drilling Services
Solicitation number
W91237-18-R-0004
Issued by

About this file

Solicitation Amendment 02 - U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise National Inland Floating Plant and Land Drilling Services

View the file

Other files

File Type Posted
A.07.24_W9123718R0004_-_0003.pdf PDF
A.07.24_W9123718R0004_-_0002_FBO.pdf PDF
A.07.23_W9123718R0004_-_0001.pdf PDF
A.07.23_W9123718R0004.pdf PDF
A.01.30_Forms_and_Drawings.pdf PDF
A.01.30_PPQ.pdf PDF
A.02.02_Synopsis-signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 11:00 AM local t ime 18 Oct 2018

X

A X B X C

D

EX

X G F 99 - 105

106 - 115 X H 116 - 124

Allison.Lewis@usace.army .mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 124

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

W91237 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

Room 419 conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

ALLISON LEWIS (304)399-5046

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 33

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT

PACKAGING AND MARKING

34 - 74 J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

76 X K REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 77 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 78 - 83 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

84 - 98

PART II - CO NTRACT CLAUSES

USACE, CONTRACTING BRANCH

ALLISON LEWIS, 502 8TH STREET

HUNTINGTON WV 25701

304-399-5046

304-399-5281FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

18 Sep 2018

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

W9123718R0004

Section B - Supplies or Services and Prices

PRICE BREAKOUT SCHEDULE

NATIONAL INLAND FLOATING PLANT AND LAND DRILLING SERVICES

NOTE: The quantities listed in the price breakout schedule are approximate and are provided as information only to assist in the preparation of proposals. The quantities are not guaranteed and the actual quantities provided under this contract shall not be justification for modification to the contract for additional payment above the amount negotiated on individual Task Orders.

In reference to FAR Clause 52.217-5, Evaluation of Options, the Government will evaluate offers for award purposes by adding the total price for all option periods to the total price for the base period. A target of 2 contracts may be awarded with a shared capacity amount not-to-exceed $20M. It should be noted given the significant contingencies in the estimated quantities, if awarded a contract for this requirement, the offeror's proposed overall total price (base and all option periods) will not be reflective of the contract value for this procurement.

In accordance to FAR Clause 52.217-8, Option to Extend Services, the rates to be used during the continued performance of any services will be the rates in effect at the time of the extension and will be evaluated at the time of contract award.

BASE PERIOD

Item DESCRIPTION UNIT EST

QTY

U/P Estimated Price

0001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

0002 0-60 Feet LF 125 0003 60-120 Feet LF 50 0004 120-400 Feet LF 20

Drive Sampling with HS Augers:

0005 0-60 Feet LF 125 0006 60-120 Feet LF 50 0007 120-400 Feet LF 25

General Sampling 0008 Undisturbed Sampling 3" EA 10 0009 Undisturbed Sampling 5" EA 15 0010 Drilling in Rock and Concrete without

Sampling

LF

0011 Drilling in reinforced concrete without

0012 Coring in Rock and Concrete, 2.125" or Conventional Cores

0013 Coring in rock and concrete, NQ Wireline

0014 Coring in reinforced concrete, 2.125" or NQ Wireline

0015 Coring in rock and concrete, Vertical 4" LF 300 0016 Coring in rock and concrete, 4" Nominal PQ

0017 Coring in reinforced concrete, 4" or PQ

0018 Coring in rock and concrete, 6" cores LF 75

0019 Coring in reinforced concrete, 6" cores LF 25 0020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 0021 Sonic Drilling, in Soil, 4" Nominal, 200-400

Feet

0022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 0023 Sonic Drilling, in Soil, 8" Nominal, 200-400

0024 Sonic Drilling, in Rock, 4" Nominal, 0-200

TBN

0025 Sonic Drilling, in Rock, 4" Nominal, 200-400

0026 Sonic Drilling, in Rock, 8" Nominal, 0-200

0027 Sonic Drilling, in Rock, 8" Nominal, 200-400

Instrumentation 0028 Piezometer Installation - Regular EA 8 0029 Piezometer Installation - Flush Mount EA 8 0030 Piezometer Surface Protection Rehab EA 4 0031 Inclinometer Installation EA 4 0032 Surface Displacement Monument EA 4

Other 0033 Directed Installation of Casing LF 10 0034 Cribbing Construction HR 100 0035 Flagger HR 100 0036 Movement of Equipment MI 1000 0037 Mob/Demob of Drill Rig (Land) EA 10 0038 Mob/Demob of Drill Rig (Sonic) EA 10 0039 Mob & Demob of ATV Rig EA 10 0040 Surveying EA 10 0041 Geophysical Logging Mobilization EA 20 0042 Geophysical Logging Video LF 2000 0043 Geophysical Logging Acoustic LF 2000 0044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 0045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

0046 0-60 feet LF 125 0047 60-120 feet LF 50 0048 120-400 feet LF 25

Drive Sampling with HS Augers:

0049 0-60 feet LF 125 0050 60-120 feet LF 50 0051 120-400 feet LF 25

General Sampling 0052 Drilling in rock and concrete without sampling

0053 Drilling in reinforced concrete without sampling

0054 Coring in rock and concrete, 2.125" conventional cores

0055 Coring in rock and concrete, NQ Wireline LF 500 0056 Coring in reinforced concrete, 2.125" or NQ

0057 Coring in rock and concrete, Vertical 4" LF 500 0058 Coring in rock and concrete, 4" Nominal PQ

0059 Coring in reinforced concrete, 4" or PQ

0060 Coring in rock and concrete, 6" cores LF 500 0061 Coring in reinforced concrete, 6" cores LF 500 0062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet

To Be Negotiated

0063 Sonic Drilling, in Soil, 4" Nominal, 200-400

0064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 0065 Sonic Drilling, in Soil, 8" Nominal, 200-400

0066 Sonic Drilling, in Rock, 4" Nominal, 0-200

0067 Sonic Drilling, in Rock, 4" Nominal, 200-400

0068 Sonic Drilling, in Rock, 8" Nominal, 0-200

0069 Sonic Drilling, in Rock, 8" Nominal, 200-400

Other 0070 Movement of Equipment MI 825 0071 Surveying EA 10 0072 Mobilization and Demobilization of Helper

Boat

EA

0073 Mob/Demob of Floating Plant EA 5 0074 Floating Plant DA 100 0075 Helper Boat 1 DA 100 0076 Helper Boat 2 DA 0 0077 Geophysical Logging Mobilization EA 20 0078 Geophysical Logging Video LF 1000 0079 Geophysical Logging Acoustic LF 1000 0080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 0081 Security Clearance & Training EA 50 0082 Inspection Registered Professional SH 500 0083 Inspection non-Registered Professional TBN 0 0084 Other Direct costs (to be negotiated) To Be Negotiated 0085 gINT Logs EA 200 0086 Mileage To Be Negotiated 0087 Energy Calibration of Hammers EA 3 0088 Hydraulic Pressure Test Abbreviated EA 350

0089 Hydraulic Pressure Test Standard EA 500

TOTAL BASE PERIOD:

OPTION PERIOD ONE

QTY

U/P Estimated Price

1001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

1002 0-60 Feet LF 125 1003 60-120 Feet LF 50 1004 120-400 Feet LF 20

Drive Sampling with HS Augers:

1005 0-60 Feet LF 125 1006 60-120 Feet LF 50 1007 120-400 Feet LF 25

General Sampling 1008 Undisturbed Sampling 3" EA 10 1009 Undisturbed Sampling 5" EA 15 1010 Drilling in Rock and Concrete without

1011 Drilling in reinforced concrete without

1012 Coring in Rock and Concrete, 2.125" or

1013 Coring in rock and concrete, NQ Wireline

1014 Coring in reinforced concrete, 2.125" or NQ

1015 Coring in rock and concrete, Vertical 4" LF 300 1016 Coring in rock and concrete, 4" Nominal PQ

1017 Coring in reinforced concrete, 4" or PQ

1018 Coring in rock and concrete, 6" cores LF 75 1019 Coring in reinforced concrete, 6" cores LF 25 1020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 1021 Sonic Drilling, in Soil, 4" Nominal, 200-400

1022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 1023 Sonic Drilling, in Soil, 8" Nominal, 200-400

1024 Sonic Drilling, in Rock, 4" Nominal, 0-200

1025 Sonic Drilling, in Rock, 4" Nominal, 200-400

1026 Sonic Drilling, in Rock, 8" Nominal, 0-200

1027 Sonic Drilling, in Rock, 8" Nominal, 200-400

1028 Piezometer Installation - Regular EA 8 1029 Piezometer Installation - Flush Mount EA 8 1030 Piezometer Surface Protection Rehab EA 4 1031 Inclinometer Installation EA 4 1032 Surface Displacement Monument EA 4

Other 1033 Directed Installation of Casing LF 10 1034 Cribbing Construction HR 100 1035 Flagger HR 100 1036 Movement of Equipment MI 1000 1037 Mob/Demob of Drill Rig (Land) EA 10 1038 Mob/Demob of Drill Rig (Sonic) EA 10 1039 Mob & Demob of ATV Rig EA 10 1040 Surveying EA 10 1041 Geophysical Logging Mobilization EA 20 1042 Geophysical Logging Video LF 2000 1043 Geophysical Logging Acoustic LF 2000 1044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 1045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

1046 0-60 feet LF 125 1047 60-120 feet LF 50 1048 120-400 feet LF 25

Drive Sampling with HS Augers:

1049 0-60 feet LF 125 1050 60-120 feet LF 50 1051 120-400 feet LF 25

General Sampling 1052 Drilling in rock and concrete without sampling

1053 Drilling in reinforced concrete without

1054 Coring in rock and concrete, 2.125"

1055 Coring in rock and concrete, NQ Wireline LF 500 1056 Coring in reinforced concrete, 2.125" or NQ

1057 Coring in rock and concrete, Vertical 4" LF 500 1058 Coring in rock and concrete, 4" Nominal PQ

1059 Coring in reinforced concrete, 4" or PQ

1060 Coring in rock and concrete, 6" cores LF 500 1061 Coring in reinforced concrete, 6" cores LF 500 1062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated

1063 Sonic Drilling, in Soil, 4" Nominal, 200-400

1064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 1065 Sonic Drilling, in Soil, 8" Nominal, 200-400

1066 Sonic Drilling, in Rock, 4" Nominal, 0-200

1067 Sonic Drilling, in Rock, 4" Nominal, 200-400

1068 Sonic Drilling, in Rock, 8" Nominal, 0-200

1069 Sonic Drilling, in Rock, 8" Nominal, 200-400

1070 Movement of Equipment MI 825 1071 Surveying EA 10 1072 Mobilization and Demobilization of Helper

1073 Mob/Demob of Floating Plant EA 5 1074 Floating Plant DA 100 1075 Helper Boat 1 DA 100 1076 Helper Boat 2 DA 0 1077 Geophysical Logging Mobilization EA 20 1078 Geophysical Logging Video LF 1000 1079 Geophysical Logging Acoustic LF 1000 1080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 1081 Security Clearance & Training EA 50 1082 Inspection Registered Professional SH 500 1083 Inspection non-Registered Professional TBN 0 1084 Other Direct costs (to be negotiated) To Be Negotiated 1085 gINT Logs EA 200 1086 Mileage To Be Negotiated 1087 Energy Calibration of Hammers EA 3 1088 Hydraulic Pressure Test Abbreviated EA 350 1089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD ONE:

OPTION PERIOD TWO

QTY

U/P Estimated Price

2001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

2002 0-60 Feet LF 125 2003 60-120 Feet LF 50 2004 120-400 Feet LF 20

Drive Sampling with HS Augers:

2005 0-60 Feet LF 125 2006 60-120 Feet LF 50 2007 120-400 Feet LF 25

General Sampling 2008 Undisturbed Sampling 3" EA 10 2009 Undisturbed Sampling 5" EA 15 2010 Drilling in Rock and Concrete without

2011 Drilling in reinforced concrete without

2012 Coring in Rock and Concrete, 2.125" or

2013 Coring in rock and concrete, NQ Wireline LF 300 2014 Coring in reinforced concrete, 2.125" or NQ

2015 Coring in rock and concrete, Vertical 4" LF 300 2016 Coring in rock and concrete, 4" Nominal PQ

2017 Coring in reinforced concrete, 4" or PQ

2018 Coring in rock and concrete, 6" cores LF 75 2019 Coring in reinforced concrete, 6" cores LF 25 2020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 2021 Sonic Drilling, in Soil, 4" Nominal, 200-400

2022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 2023 Sonic Drilling, in Soil, 8" Nominal, 200-400

2024 Sonic Drilling, in Rock, 4" Nominal, 0-200

2025 Sonic Drilling, in Rock, 4" Nominal, 200-400

2026 Sonic Drilling, in Rock, 8" Nominal, 0-200

2027 Sonic Drilling, in Rock, 8" Nominal, 200-400

2028 Piezometer Installation - Regular EA 8 2029 Piezometer Installation - Flush Mount EA 8 2030 Piezometer Surface Protection Rehab EA 4 2031 Inclinometer Installation EA 4 2032 Surface Displacement Monument EA 4

Other 2033 Directed Installation of Casing LF 10 2034 Cribbing Construction HR 100 2035 Flagger HR 100 2036 Movement of Equipment MI 1000 2037 Mob/Demob of Drill Rig (Land) EA 10

2038 Mob/Demob of Drill Rig (Sonic) EA 10 2039 Mob & Demob of ATV Rig EA 10 2040 Surveying EA 10 2041 Geophysical Logging Mobilization EA 20

2042 Geophysical Logging Video LF 2000 2043 Geophysical Logging Acoustic LF 2000 2044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 2045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

2046 0-60 feet LF 125 2047 60-120 feet LF 50 2048 120-400 feet LF 25

Drive Sampling with HS Augers:

2049 0-60 feet LF 125 2050 60-120 feet LF 50 2051 120-400 feet LF 25

General Sampling 2052 Drilling in rock and concrete without sampling

2053 Drilling in reinforced concrete without

2054 Coring in rock and concrete, 2.125"

2055 Coring in rock and concrete, NQ Wireline LF 500 2056 Coring in reinforced concrete, 2.125" or NQ

2057 Coring in rock and concrete, Vertical 4"

2058 Coring in rock and concrete, 4" Nominal PQ

2059 Coring in reinforced concrete, 4" or PQ

2060 Coring in rock and concrete, 6" cores LF 500 2061 Coring in reinforced concrete, 6" cores LF 500 2062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated 2063 Sonic Drilling, in Soil, 4" Nominal, 200-400

2064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 2065 Sonic Drilling, in Soil, 8" Nominal, 200-400

2066 Sonic Drilling, in Rock, 4" Nominal, 0-200

2067 Sonic Drilling, in Rock, 4" Nominal, 200-400

2068 Sonic Drilling, in Rock, 8" Nominal, 0-200

2069 Sonic Drilling, in Rock, 8" Nominal, 200-400

2070 Movement of Equipment MI 825 2071 Surveying EA 10 2072 Mobilization and Demobilization of Helper

Boat

EA 2

2073 Mob/Demob of Floating Plant EA 5 2074 Floating Plant DA 100 2075 Helper Boat 1 DA 100 2076 Helper Boat 2 DA 50

2077 Geophysical Logging Mobilization EA 20 2078 Geophysical Logging Video LF 1000 2079 Geophysical Logging Acoustic LF 1000 2080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 2081 Security Clearance & Training EA 50 2082 Inspection Registered Professional SH 500 2083 Inspection non-Registered Professional TBN 0 2084 Other Direct costs (to be negotiated) To Be Negotiated

2085 gINT Logs EA 200 2086 Mileage To Be Negotiated 2087 Energy Calibration of Hammers EA 3 2088 Hydraulic Pressure Test Abbreviated EA 350 2089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD TWO:

OPTION PERIOD THREE

QTY

U/P Estimated Price

3001 Overburden Drilling without Sampling

Drive Sampling without HS Augers:

3002 0-60 Feet LF 125 3003 60-120 Feet LF 50 3004 120-400 Feet LF 20

Drive Sampling with HS Augers:

3005 0-60 Feet LF 125 3006 60-120 Feet LF 50 3007 120-400 Feet LF 25

General Sampling 3008 Undisturbed Sampling 3" EA 10 3009 Undisturbed Sampling 5" EA 15 3010 Drilling in Rock and Concrete without

3011 Drilling in reinforced concrete without

3012 Coring in Rock and Concrete, 2.125" or

3013 Coring in rock and concrete, NQ Wireline LF 300 3014 Coring in reinforced concrete, 2.125" or NQ

3015 Coring in rock and concrete, Vertical 4" LF 300 3016 Coring in rock and concrete, 4" Nominal PQ

3017 Coring in reinforced concrete, 4" or PQ

3018 Coring in rock and concrete, 6" cores LF 75 3019 Coring in reinforced concrete, 6" cores LF 25 3020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 3021 Sonic Drilling, in Soil, 4" Nominal, 200-400

3022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 3023 Sonic Drilling, in Soil, 8" Nominal, 200-400

3024 Sonic Drilling, in Rock, 4" Nominal, 0-200

3025 Sonic Drilling, in Rock, 4" Nominal, 200-400

3026 Sonic Drilling, in Rock, 8" Nominal, 0-200

3027 Sonic Drilling, in Rock, 8" Nominal, 200-400

3028 Piezometer Installation - Regular EA 8 3029 Piezometer Installation - Flush Mount EA 8 3030 Piezometer Surface Protection Rehab EA 4 3031 Inclinometer Installation EA 4 3032 Surface Displacement Monument EA 4

Other 3033 Directed Installation of Casing LF 10 3034 Cribbing Construction HR 100 3035 Flagger HR 100 3036 Movement of Equipment MI 1000 3037 Mob/Demob of Drill Rig (Land) EA 10 3038 Mob/Demob of Drill Rig (Sonic) EA 10 3039 Mob & Demob of ATV Rig EA 10 3040 Surveying EA 10 3041 Geophysical Logging Mobilization EA 20 3042 Geophysical Logging Video LF 2000 3043 Geophysical Logging Acoustic LF 2000 3044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 3045 Overburden Drilling without Sampling LF 50

3046 0-60 feet LF 125 3047 60-120 feet LF 50 3048 120-400 feet LF 25

Drive Sampling with HS Augers:

3049 0-60 feet LF 125 3050 60-120 feet LF 50 3051 120-400 feet LF 25

General Sampling 3052 Drilling in rock and concrete without sampling

3053 Drilling in reinforced concrete without

3054 Coring in rock and concrete, 2.125"

3055 Coring in rock and concrete, NQ Wireline LF 500 3056 Coring in reinforced concrete, 2.125" or NQ

3057 Coring in rock and concrete, Vertical 4" LF 500 3058 Coring in rock and concrete, 4" Nominal PQ

3059 Coring in reinforced concrete, 4" or PQ

3060 Coring in rock and concrete, 6" cores LF 500 3061 Coring in reinforced concrete, 6" cores LF 500 3062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated 3063 Sonic Drilling, in Soil, 4" Nominal, 200-400

3064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 3065 Sonic Drilling, in Soil, 8" Nominal, 200-400

3066 Sonic Drilling, in Rock, 4" Nominal, 0-200

3067 Sonic Drilling, in Rock, 4" Nominal, 200-400

3068 Sonic Drilling, in Rock, 8" Nominal, 0-200

3069 Sonic Drilling, in Rock, 8" Nominal, 200-400

3070 Movement of Equipment MI 825 3071 Surveying EA 10 3072 Mobilization and Demobilization of Helper

3073 Mob/Demob of Floating Plant EA 5 3074 Floating Plant DA 100 3075 Helper Boat 1 DA 100 3076 Helper Boat 2 DA 0 3077 Geophysical Logging Mobilization EA 20

3078 Geophysical Logging Video LF 1000 3079 Geophysical Logging Acoustic LF 1000 3080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 3081 Security Clearance & Training EA 50 3082 Inspection Registered Professional SH 500 3083 Inspection non-Registered Professional TBN 0 3084 Other Direct costs (to be negotiated) To Be Negotiated 3085 gINT Logs EA 200 3086 Mileage To Be Negotiated 3087 Energy Calibration of Hammers EA 3 3088 Hydraulic Pressure Test Abbreviated EA 350 3089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD THREE:

OPTION PERIOD FOUR

QTY

U/P Estimated Price

4001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

4002 0-60 Feet LF 125 4003 60-120 Feet LF 50 4004 120-400 Feet LF 20

Drive Sampling with HS Augers:

4005 0-60 Feet LF 125 4006 60-120 Feet LF 50 4007 120-400 Feet LF 25

General Sampling 4008 Undisturbed Sampling 3" EA 10 4009 Undisturbed Sampling 5" EA 15 4010 Drilling in Rock and Concrete without

4011 Drilling in reinforced concrete without

4012 Coring in Rock and Concrete, 2.125" or

4013 Coring in rock and concrete, NQ Wireline LF 300 4014 Coring in reinforced concrete, 2.125" or NQ

4015 Coring in rock and concrete, Vertical 4" LF 300 4016 Coring in rock and concrete, 4" Nominal PQ

4017 Coring in reinforced concrete, 4" or PQ

4018 Coring in rock and concrete, 6" cores LF 75

4019 Coring in reinforced concrete, 6" cores LF 25 4020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 4021 Sonic Drilling, in Soil, 4" Nominal, 200-400

4022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 4023 Sonic Drilling, in Soil, 8" Nominal, 200-400

4024 Sonic Drilling, in Rock, 4" Nominal, 0-200

4025 Sonic Drilling, in Rock, 4" Nominal, 200-400

4026 Sonic Drilling, in Rock, 8" Nominal, 0-200

4027 Sonic Drilling, in Rock, 8" Nominal, 200-400

4028 Piezometer Installation - Regular EA 8 4029 Piezometer Installation - Flush Mount EA 8 4030 Piezometer Surface Protection Rehab EA 4 4031 Inclinometer Installation EA 4 4032 Surface Displacement Monument EA 4

Other 4033 Directed Installation of Casing LF 10 4034 Cribbing Construction HR 100 4035 Flagger HR 100 4036 Movement of Equipment MI 1000 4037 Mob/Demob of Drill Rig (Land) EA 10 4038 Mob/Demob of Drill Rig (Sonic) EA 10 4039 Mob & Demob of ATV Rig EA 10 4040 Surveying EA 10 4041 Geophysical Logging Mobilization EA 20 4042 Geophysical Logging Video LF 2000 4043 Geophysical Logging Acoustic LF 2000 4044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 4045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

4046 0-60 feet LF 125 4047 60-120 feet LF 50 4048 120-400 feet LF 25

Drive Sampling with HS Augers:

4049 0-60 feet LF 125 4050 60-120 feet LF 50 4051 120-400 feet LF 25

General Sampling

4052 Drilling in rock and concrete without sampling

4053 Drilling in reinforced concrete without

4054 Coring in rock and concrete, 2.125"

4055 Coring in rock and concrete, NQ Wireline LF 500 4056 Coring in reinforced concrete, 2.125" or NQ

4057 Coring in rock and concrete, Vertical 4" LF 500 4058 Coring in rock and concrete, 4" Nominal PQ

4059 Coring in reinforced concrete, 4" or PQ

4060 Coring in rock and concrete, 6" cores LF 500 4061 Coring in reinforced concrete, 6" cores LF 500 4062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet

4063 Sonic Drilling, in Soil, 4" Nominal, 200-400

4064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 4065 Sonic Drilling, in Soil, 8" Nominal, 200-400

4066 Sonic Drilling, in Rock, 4" Nominal, 0-200

4067 Sonic Drilling, in Rock, 4" Nominal, 200-400

4068 Sonic Drilling, in Rock, 8" Nominal, 0-200

4069 Sonic Drilling, in Rock, 8" Nominal, 200-400

Movement of Equipment

MI

4071 Surveying

4072 Mobilization and Demobilization of Helper

4073 Mob/Demob of Floating Plant EA 5 4074 Floating Plant DA 100 4075 Helper Boat 1 DA 100 4076 Helper Boat 2 DA 0 4077 Geophysical Logging Mobilization EA 20 4078 Geophysical Logging Video LF 1000 4079 Geophysical Logging Acoustic LF 1000 4080 Geophysical Logging Acoustic and Video

Combined Other

4081 Security Clearance & Training EA 50 4082 Inspection Registered Professional SH 500 4083 Inspection non-Registered Professional TBN 0 4084 Other Direct costs (to be negotiated) To Be Negotiated 4085 gINT Logs EA 200 4086 Mileage To Be Negotiated 4087 Energy Calibration of Hammers EA 3 4088 Hydraulic Pressure Test Abbreviated EA 350 4089 Hydraulic Pressure Test Standard

TOTAL OPTION PERIOD FOUR

GRAND TOTAL: BASE and ALL OPTION PERIODS _______________

Legend: TBN = To Be Negotiated DA = Day HR = Hour LF = Linear Feet MI = Miles EA = Each SH = Shift

PRICE BREAKOUT SCHEDULE_REV01

NATIONAL INLAND FLOATING PLANT AND LAND DRILLING SERVICES

REVISED PRICE BREAKOUT SCHEDULE

NOTE: The quantities listed in the price breakout schedule are approximate and are provided as information only to assist in the preparation of proposals. The quantities are not guaranteed and the actual quantities provided under this contract shall not be justification for modification to the contract for additional payment above the amount negotiated on individual Task Orders.

In reference to FAR Clause 52.217-5, Evaluation of Options, the Government will evaluate offers for award purposes by adding the total price for all option periods to the total price for the base period. A target of 2 contracts may be awarded with a shared capacity amount not-to-exceed $20M. It should be noted given the significant contingencies in the estimated quantities, if awarded a contract for this requirement, the offeror's proposed overall total price (base period and all option periods) will not be reflective of the contract value for this procurement.

In accordance with FAR Clause 52.217-8, Option to Extend Services, the rates to be used during the continued performance of any services will be the rates in effect at the time of the extension and will be evaluated at the time of contract award.

BASE PERIOD

QTY

U/P Estimated Price

0001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

0002 0-60 Feet LF 125 0003 60-120 Feet LF 50 0004 120-400 Feet LF 20

0005 0-60 Feet LF 125

0006 60-120 Feet LF 50 0007 120-400 Feet LF 25

General Sampling 0008 Undisturbed Sampling 3" EA 10 0009 Undisturbed Sampling 5" EA 15 0010 Drilling in Rock and Concrete without

0011 Drilling in reinforced concrete without

0012 Coring in Rock and Concrete, 2.125" or

0013 Coring in rock and concrete, NQ Wireline

0014 Coring in reinforced concrete, 2.125" or NQ

0015 Coring in rock and concrete, Vertical 4" LF 300 0016 Coring in rock and concrete, 4" Nominal PQ

0017 Coring in reinforced concrete, 4" or PQ

0018 Coring in rock and concrete, 6" cores LF 75 0019 Coring in reinforced concrete, 6" cores LF 25 0020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 0021 Sonic Drilling, in Soil, 4" Nominal, 200-400

0022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 0023 Sonic Drilling, in Soil, 8" Nominal, 200-400

0024 Sonic Drilling, in Rock, 4" Nominal, 0-200

0025 Sonic Drilling, in Rock, 4" Nominal, 200-400

0026 Sonic Drilling, in Rock, 8" Nominal, 0-200

0027 Sonic Drilling, in Rock, 8" Nominal, 200-400

0028 Piezometer Installation - Regular EA 8 0029 Piezometer Installation - Flush Mount EA 8 0030 Piezometer Surface Protection Rehab EA 4 0031 Inclinometer Installation EA 4 0032 Surface Displacement Monument EA 4

Other 0033 Directed Installation of Casing LF 10 0034 Cribbing Construction HR 100 0035 Flagger HR 100 0036 Movement of Equipment MI 1000 0037 Mob/Demob of Drill Rig (Land) EA 10 0038 Mob/Demob of Drill Rig (Sonic) EA 10

0039 Mob & Demob of ATV Rig EA 10 0040 Surveying EA 10 0041 Geophysical Logging Mobilization EA 20 0042 Geophysical Logging Video LF 2000 0043 Geophysical Logging Acoustic LF 2000 0044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 0045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

0046 0-60 feet LF 125 0047 60-120 feet LF 50 0048 120-400 feet LF 25

Drive Sampling with HS Augers:

0049 0-60 feet LF 125 0050 60-120 feet LF 50 0051 120-400 feet LF 25

General Sampling 0052 Drilling in rock and concrete without sampling

0053 Drilling in reinforced concrete without

0054 Coring in rock and concrete, 2.125"

0055 Coring in rock and concrete, NQ Wireline LF 500 0056 Coring in reinforced concrete, 2.125" or NQ

0057 Coring in rock and concrete, Vertical 4" LF 500 0058 Coring in rock and concrete, 4" Nominal PQ

0059 Coring in reinforced concrete, 4" or PQ

0060 Coring in rock and concrete, 6" cores LF 500 0061 Coring in reinforced concrete, 6" cores LF 500 0062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet

0063 Sonic Drilling, in Soil, 4" Nominal, 200-400

0064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 0065 Sonic Drilling, in Soil, 8" Nominal, 200-400

0066 Sonic Drilling, in Rock, 4" Nominal, 0-200

0067 Sonic Drilling, in Rock, 4" Nominal, 200-400

0068 Sonic Drilling, in Rock, 8" Nominal, 0-200

0069 Sonic Drilling, in Rock, 8" Nominal, 200-400

0070 Movement of Equipment MI 825 0071 Surveying EA 10 0072 Mobilization and Demobilization of Helper

0073 Mob/Demob of Floating Plant EA 5 0074 Floating Plant DA 100 0075 Helper Boat 1 DA 100 0076 Helper Boat 2 DA 0 0077 Geophysical Logging Mobilization EA 20 0078 Geophysical Logging Video LF 1000 0079 Geophysical Logging Acoustic LF 1000 0080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 0081 Security Clearance & Training EA 50 0082 Inspection Registered Professional SH 500 0083 Inspection non-Registered Professional TBN 0 0084 Other Direct costs (to be negotiated) To Be Negotiated 0085 gINT Logs EA 200 0086 Mileage To Be Negotiated 0087 Energy Calibration of Hammers EA 3 0088 Hydraulic Pressure Test Abbreviated EA 350 0089 Hydraulic Pressure Test Standard EA 500

TOTAL BASE PERIOD:

OPTION PERIOD ONE

QTY

U/P Estimated Price

1001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

1002 0-60 Feet LF 125 1003 60-120 Feet LF 50 1004 120-400 Feet LF 20

Drive Sampling with HS Augers:

1005 0-60 Feet LF 125 1006 60-120 Feet LF 50 1007 120-400 Feet LF 25

General Sampling 1008 Undisturbed Sampling 3" EA 10 1009 Undisturbed Sampling 5" EA 15 1010 Drilling in Rock and Concrete without

1011 Drilling in reinforced concrete without

1012 Coring in Rock and Concrete, 2.125" or

1013 Coring in rock and concrete, NQ Wireline

1014 Coring in reinforced concrete, 2.125" or NQ

1015 Coring in rock and concrete, Vertical 4" LF 300 1016 Coring in rock and concrete, 4" Nominal PQ

1017 Coring in reinforced concrete, 4" or PQ

1018 Coring in rock and concrete, 6" cores LF 75 1019 Coring in reinforced concrete, 6" cores LF 25 1020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 1021 Sonic Drilling, in Soil, 4" Nominal, 200-400

1022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 1023 Sonic Drilling, in Soil, 8" Nominal, 200-400

1024 Sonic Drilling, in Rock, 4" Nominal, 0-200

1025 Sonic Drilling, in Rock, 4" Nominal, 200-400

1026 Sonic Drilling, in Rock, 8" Nominal, 0-200

1027 Sonic Drilling, in Rock, 8" Nominal, 200-400

1028 Piezometer Installation - Regular EA 8 1029 Piezometer Installation - Flush Mount EA 8 1030 Piezometer Surface Protection Rehab EA 4 1031 Inclinometer Installation EA 4 1032 Surface Displacement Monument EA 4

Other 1033 Directed Installation of Casing LF 10 1034 Cribbing Construction HR 100 1035 Flagger HR 100 1036 Movement of Equipment MI 1000 1037 Mob/Demob of Drill Rig (Land) EA 10 1038 Mob/Demob of Drill Rig (Sonic) EA 10 1039 Mob & Demob of ATV Rig EA 10 1040 Surveying EA 10 1041 Geophysical Logging Mobilization EA 20 1042 Geophysical Logging Video LF 2000 1043 Geophysical Logging Acoustic LF 2000 1044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 1045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

1046 0-60 feet LF 125 1047 60-120 feet LF 50 1048 120-400 feet LF 25

1049 0-60 feet LF 125 1050 60-120 feet LF 50 1051 120-400 feet LF 25

General Sampling 1052 Drilling in rock and concrete without sampling

1053 Drilling in reinforced concrete without

1054 Coring in rock and concrete, 2.125"

1055 Coring in rock and concrete, NQ Wireline LF 500 1056 Coring in reinforced concrete, 2.125" or NQ

1057 Coring in rock and concrete, Vertical 4" LF 500 1058 Coring in rock and concrete, 4" Nominal PQ

1059 Coring in reinforced concrete, 4" or PQ

1060 Coring in rock and concrete, 6" cores LF 500 1061 Coring in reinforced concrete, 6" cores LF 500 1062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated 1063 Sonic Drilling, in Soil, 4" Nominal, 200-400

1064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 1065 Sonic Drilling, in Soil, 8" Nominal, 200-400

1066 Sonic Drilling, in Rock, 4" Nominal, 0-200

1067 Sonic Drilling, in Rock, 4" Nominal, 200-400

1068 Sonic Drilling, in Rock, 8" Nominal, 0-200

1069 Sonic Drilling, in Rock, 8" Nominal, 200-400

1070 Movement of Equipment MI 825 1071 Surveying EA 10 1072 Mobilization and Demobilization of Helper

1073 Mob/Demob of Floating Plant EA 5 1074 Floating Plant DA 100 1075 Helper Boat 1 DA 100 1076 Helper Boat 2 DA 0 1077 Geophysical Logging Mobilization EA 20 1078 Geophysical Logging Video LF 1000 1079 Geophysical Logging Acoustic LF 1000 1080 Geophysical Logging Acoustic and Video LF 1000

1081 Security Clearance & Training EA 50

1082 Inspection Registered Professional SH 500 1083 Inspection non-Registered Professional TBN 0 1084 Other Direct costs (to be negotiated) To Be Negotiated 1085 gINT Logs EA 200 1086 Mileage To Be Negotiated 1087 Energy Calibration of Hammers EA 3 1088 Hydraulic Pressure Test Abbreviated EA 350 1089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD ONE:

OPTION PERIOD TWO

QTY

U/P Estimated Price

2001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

2002 0-60 Feet LF 125 2003 60-120 Feet LF 50 2004 120-400 Feet LF 20

Drive Sampling with HS Augers:

2005 0-60 Feet LF 125 2006 60-120 Feet LF 50 2007 120-400 Feet LF 25

General Sampling 2008 Undisturbed Sampling 3" EA 10 2009 Undisturbed Sampling 5" EA 15 2010 Drilling in Rock and Concrete without

2011 Drilling in reinforced concrete without

2012 Coring in Rock and Concrete, 2.125" or

2013 Coring in rock and concrete, NQ Wireline LF 300 2014 Coring in reinforced concrete, 2.125" or NQ

2015 Coring in rock and concrete, Vertical 4" LF 300 2016 Coring in rock and concrete, 4" Nominal PQ

2017 Coring in reinforced concrete, 4" or PQ

2018 Coring in rock and concrete, 6" cores LF 75 2019 Coring in reinforced concrete, 6" cores LF 25 2020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 2021 Sonic Drilling, in Soil, 4" Nominal, 200-400

2022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50

2023 Sonic Drilling, in Soil, 8" Nominal, 200-400

2024 Sonic Drilling, in Rock, 4" Nominal, 0-200

2025 Sonic Drilling, in Rock, 4" Nominal, 200-400

2026 Sonic Drilling, in Rock, 8" Nominal, 0-200

2027 Sonic Drilling, in Rock, 8" Nominal, 200-400

2028 Piezometer Installation - Regular EA 8 2029 Piezometer Installation - Flush Mount EA 8 2030 Piezometer Surface Protection Rehab EA 4 2031 Inclinometer Installation EA 4 2032 Surface Displacement Monument EA 4

Other 2033 Directed Installation of Casing LF 10 2034 Cribbing Construction HR 100 2035 Flagger HR 100 2036 Movement of Equipment MI 1000 2037 Mob/Demob of Drill Rig (Land) EA 10 2038 Mob/Demob of Drill Rig (Sonic) EA 10 2039 Mob & Demob of ATV Rig EA 10 2040 Surveying EA 10 2041 Geophysical Logging Mobilization EA 20

2042 Geophysical Logging Video LF 2000 2043 Geophysical Logging Acoustic LF 2000 2044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 2045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

2046 0-60 feet LF 125 2047 60-120 feet LF 50 2048 120-400 feet LF 25

Drive Sampling with HS Augers:

2049 0-60 feet LF 125 2050 60-120 feet LF 50 2051 120-400 feet LF 25

General Sampling 2052 Drilling in rock and concrete without sampling

2053 Drilling in reinforced concrete without

2054 Coring in rock and concrete, 2.125"

2055 Coring in rock and concrete, NQ Wireline LF 500

2056 Coring in reinforced concrete, 2.125" or NQ

2057 Coring in rock and concrete, Vertical 4"

2058 Coring in rock and concrete, 4" Nominal PQ

2059 Coring in reinforced concrete, 4" or PQ

2060 Coring in rock and concrete, 6" cores LF 500 2061 Coring in reinforced concrete, 6" cores LF 500 2062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated 2063 Sonic Drilling, in Soil, 4" Nominal, 200-400

2064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 2065 Sonic Drilling, in Soil, 8" Nominal, 200-400

2066 Sonic Drilling, in Rock, 4" Nominal, 0-200

2067 Sonic Drilling, in Rock, 4" Nominal, 200-400

2068 Sonic Drilling, in Rock, 8" Nominal, 0-200

2069 Sonic Drilling, in Rock, 8" Nominal, 200-400

2070 Movement of Equipment MI 825 2071 Surveying EA 10 2072 Mobilization and Demobilization of Helper

Boat

EA 2

2073 Mob/Demob of Floating Plant EA 5 2074 Floating Plant DA 100 2075 Helper Boat 1 DA 100 2076 Helper Boat 2 DA 50

2077 Geophysical Logging Mobilization EA 20 2078 Geophysical Logging Video LF 1000 2079 Geophysical Logging Acoustic LF 1000 2080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 2081 Security Clearance & Training EA 50 2082 Inspection Registered Professional SH 500 2083 Inspection non-Registered Professional TBN 0 2084 Other Direct costs (to be negotiated) To Be Negotiated

2085 gINT Logs EA 200 2086 Mileage To Be Negotiated 2087 Energy Calibration of Hammers EA 3 2088 Hydraulic Pressure Test Abbreviated EA 350 2089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD TWO:

OPTION PERIOD THREE

QTY

U/P Estimated Price

3001 Overburden Drilling without Sampling

3002 0-60 Feet LF 125 3003 60-120 Feet LF 50 3004 120-400 Feet LF 20

Drive Sampling with HS Augers:

3005 0-60 Feet LF 125 3006 60-120 Feet LF 50 3007 120-400 Feet LF 25

General Sampling 3008 Undisturbed Sampling 3" EA 10 3009 Undisturbed Sampling 5" EA 15 3010 Drilling in Rock and Concrete without

3011 Drilling in reinforced concrete without

3012 Coring in Rock and Concrete, 2.125" or

3013 Coring in rock and concrete, NQ Wireline LF 300 3014 Coring in reinforced concrete, 2.125" or NQ

3015 Coring in rock and concrete, Vertical 4" LF 300 3016 Coring in rock and concrete, 4" Nominal PQ

3017 Coring in reinforced concrete, 4" or PQ

3018 Coring in rock and concrete, 6" cores LF 75 3019 Coring in reinforced concrete, 6" cores LF 25 3020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 3021 Sonic Drilling, in Soil, 4" Nominal, 200-400

3022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 3023 Sonic Drilling, in Soil, 8" Nominal, 200-400

3024 Sonic Drilling, in Rock, 4" Nominal, 0-200

3025 Sonic Drilling, in Rock, 4" Nominal, 200-400

3026 Sonic Drilling, in Rock, 8" Nominal, 0-200

3027 Sonic Drilling, in Rock, 8" Nominal, 200-400

3028 Piezometer Installation - Regular EA 8 3029 Piezometer Installation - Flush Mount EA 8 3030 Piezometer Surface Protection Rehab EA 4 3031 Inclinometer Installation EA 4 3032 Surface Displacement Monument EA 4

Other 3033 Directed Installation of Casing LF 10 3034 Cribbing Construction HR 100 3035 Flagger HR 100 3036 Movement of Equipment MI 1000 3037 Mob/Demob of Drill Rig (Land) EA 10 3038 Mob/Demob of Drill Rig (Sonic) EA 10 3039 Mob & Demob of ATV Rig EA 10 3040 Surveying EA 10 3041 Geophysical Logging Mobilization EA 20 3042 Geophysical Logging Video LF 2000 3043 Geophysical Logging Acoustic LF 2000 3044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 3045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

3046 0-60 feet LF 125 3047 60-120 feet LF 50 3048 120-400 feet LF 25

Drive Sampling with HS Augers:

3049 0-60 feet LF 125 3050 60-120 feet LF 50 3051 120-400 feet LF 25

General Sampling 3052 Drilling in rock and concrete without sampling

3053 Drilling in reinforced concrete without

3054 Coring in rock and concrete, 2.125"

3055 Coring in rock and concrete, NQ Wireline LF 500 3056 Coring in reinforced concrete, 2.125" or NQ

3057 Coring in rock and concrete, Vertical 4" LF 500 3058 Coring in rock and concrete, 4" Nominal PQ

3059 Coring in reinforced concrete, 4" or PQ

3060 Coring in rock and concrete, 6" cores LF 500 3061 Coring in reinforced concrete, 6" cores LF 500 3062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet To Be Negotiated

3063 Sonic Drilling, in Soil, 4" Nominal, 200-400

3064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 3065 Sonic Drilling, in Soil, 8" Nominal, 200-400

3066 Sonic Drilling, in Rock, 4" Nominal, 0-200

3067 Sonic Drilling, in Rock, 4" Nominal, 200-400

3068 Sonic Drilling, in Rock, 8" Nominal, 0-200

3069 Sonic Drilling, in Rock, 8" Nominal, 200-400

3070 Movement of Equipment MI 825 3071 Surveying EA 10 3072 Mobilization and Demobilization of Helper

3073 Mob/Demob of Floating Plant EA 5 3074 Floating Plant DA 100 3075 Helper Boat 1 DA 100 3076 Helper Boat 2 DA 0 3077 Geophysical Logging Mobilization EA 20 3078 Geophysical Logging Video LF 1000 3079 Geophysical Logging Acoustic LF 1000 3080 Geophysical Logging Acoustic and Video LF 1000

Combined Other 3081 Security Clearance & Training EA 50 3082 Inspection Registered Professional SH 500 3083 Inspection non-Registered Professional TBN 0 3084 Other Direct costs (to be negotiated) To Be Negotiated 3085 gINT Logs EA 200 3086 Mileage To Be Negotiated 3087 Energy Calibration of Hammers EA 3 3088 Hydraulic Pressure Test Abbreviated EA 350 3089 Hydraulic Pressure Test Standard EA 500

TOTAL OPTION PERIOD THREE:

OPTION PERIOD FOUR

QTY

U/P Estimated Price

4001 Overburden Drilling without Sampling LF 250 Drive Sampling without HS Augers:

4002 0-60 Feet LF 125 4003 60-120 Feet LF 50

4004 120-400 Feet LF 20

4005 0-60 Feet LF 125 4006 60-120 Feet LF 50 4007 120-400 Feet LF 25

General Sampling 4008 Undisturbed Sampling 3" EA 10 4009 Undisturbed Sampling 5" EA 15 4010 Drilling in Rock and Concrete without

4011 Drilling in reinforced concrete without

4012 Coring in Rock and Concrete, 2.125" or

4013 Coring in rock and concrete, NQ Wireline LF 300 4014 Coring in reinforced concrete, 2.125" or NQ

4015 Coring in rock and concrete, Vertical 4" LF 300 4016 Coring in rock and concrete, 4" Nominal PQ

4017 Coring in reinforced concrete, 4" or PQ

4018 Coring in rock and concrete, 6" cores LF 75 4019 Coring in reinforced concrete, 6" cores LF 25 4020 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet LF 50 4021 Sonic Drilling, in Soil, 4" Nominal, 200-400

4022 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet LF 50 4023 Sonic Drilling, in Soil, 8" Nominal, 200-400

4024 Sonic Drilling, in Rock, 4" Nominal, 0-200

4025 Sonic Drilling, in Rock, 4" Nominal, 200-400

4026 Sonic Drilling, in Rock, 8" Nominal, 0-200

4027 Sonic Drilling, in Rock, 8" Nominal, 200-400

4028 Piezometer Installation - Regular EA 8 4029 Piezometer Installation - Flush Mount EA 8 4030 Piezometer Surface Protection Rehab EA 4 4031 Inclinometer Installation EA 4 4032 Surface Displacement Monument EA 4

Other 4033 Directed Installation of Casing LF 10 4034 Cribbing Construction HR 100 4035 Flagger HR 100 4036 Movement of Equipment MI 1000

4037 Mob/Demob of Drill Rig (Land) EA 10 4038 Mob/Demob of Drill Rig (Sonic) EA 10 4039 Mob & Demob of ATV Rig EA 10 4040 Surveying EA 10 4041 Geophysical Logging Mobilization EA 20 4042 Geophysical Logging Video LF 2000 4043 Geophysical Logging Acoustic LF 2000 4044 Geophysical Logging Acoustic and Video LF 2000

Floating Plant 4045 Overburden Drilling without Sampling LF 50

Drive Sampling without HS Augers:

4046 0-60 feet LF 125 4047 60-120 feet LF 50 4048 120-400 feet LF 25

Drive Sampling with HS Augers:

4049 0-60 feet LF 125 4050 60-120 feet LF 50 4051 120-400 feet LF 25

General Sampling

4052 Drilling in rock and concrete without sampling

4053 Drilling in reinforced concrete without

4054 Coring in rock and concrete, 2.125"

4055 Coring in rock and concrete, NQ Wireline LF 500 4056 Coring in reinforced concrete, 2.125" or NQ

4057 Coring in rock and concrete, Vertical 4" LF 500 4058 Coring in rock and concrete, 4" Nominal PQ

4059 Coring in reinforced concrete, 4" or PQ

4060 Coring in rock and concrete, 6" cores LF 500 4061 Coring in reinforced concrete, 6" cores LF 500 4062 Sonic Drilling, in Soil, 4" Nominal, 0-200 Feet

4063 Sonic Drilling, in Soil, 4" Nominal, 200-400

4064 Sonic Drilling, in Soil, 8" Nominal, 0-200 Feet To Be Negotiated 4065 Sonic Drilling, in Soil, 8" Nominal, 200-400

4066 Sonic Drilling, in Rock, 4" Nominal, 0-200

4067 Sonic Drilling, in Rock, 4" Nominal, 200-400

4068 Sonic Drilling, in Rock, 8" Nominal, 0-200

4069 Sonic Drilling, in Rock, 8" Nominal, 200-400

Movement of Equipment

MI

4071 Surveying

4072 Mobilization and Demobilization of Helper

4073 Mob/Demob of Floating Plant EA 5 4074 Floating Plant DA 100 4075 Helper Boat 1 DA 100 4076 Helper Boat 2 DA 0 4077 Geophysical Logging Mobilization EA 20 4078 Geophysical Logging Video LF 1000 4079 Geophysical Logging Acoustic LF 1000 4080 Geophysical Logging Acoustic and Video

4081 Security Clearance & Training EA 50 4082 Inspection Registered Professional SH 500 4083 Inspection non-Registered Professional TBN 0 4084 Other Direct costs (to be negotiated) To Be Negotiated 4085 gINT Logs EA 200 4086 Mileage To Be Negotiated 4087 Energy Calibration of Hammers EA 3 4088 Hydraulic Pressure Test Abbreviated EA 350 4089 Hydraulic Pressure Test Standard

TOTAL OPTION PERIOD FOUR

GRAND TOTAL: BASE and ALL OPTION PERIODS _______________

Legend: TBN = To Be Negotiated DA = Day HR = Hour LF = Linear Feet MI = Miles EA = Each SH = Shift

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 1 Job Base Period

FFP

Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel and vehicles, except as otherwise noted in the Performane Work Statement, required to perform national inland floating plant and land drilling services for the U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise. All work shall be completed in accordance with the Performance Work Statement and conditions of the contract.

FOB: Destination

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 1 Job OPTION Option Period 1

FFP

Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel and vehicles, except as otherwise noted in the Performane Work Statement, required to perform national inland floating plant and land drilling services for the U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise. All work shall be completed in accordance with

UNIT UNIT PRICE MAX AMOUNT

0003 1 Job OPTION Option Period 2

FFP

Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel and vehicles, except as otherwise noted in the Performane Work Statement, required to perform national inland floating plant and land drilling services for the U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise. All work shall be completed in accordance with

UNIT UNIT PRICE MAX AMOUNT

0004 1 Job OPTION Option Period 3

FFP

Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel and vehicles, except as otherwise noted in the Performane Work Statement, required to perform national inland floating plant and land drilling services for the U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise. All work shall be completed in accordance with

UNIT UNIT PRICE MAX AMOUNT

0005 1 Job OPTION Option Period 4

FFP

Contractor shall furnish all necessary management, personnel, materials, supplies, tools, equipment, fuel and vehicles, except as otherwise noted in the Performane Work Statement, required to perform national inland floating plant and land drilling services for the U.S. Army Corps of Engineers Dam Safety Modification Mandatory Center of Expertise. All work shall be completed in accordance with

Section C - Descriptions and Specifications

PWS_REV01

U.S. ARMY CORPS OF ENGINEERS (USACE) DAM SAFETY MODIFICATION MANDATORY

CENTER OF EXPERTISE (DSMMCX) NATIONAL INLAND FLOATING PLANT AND LAND

DRILLING SERVICES - REVISED

1. CHARACTER AND EXTENT OF SERVICES

This contract is for use by the U.S. Army Corps of Engineers (USACE) Dam Safety Modification Mandatory Center of Expertise (MCX), the Great Lakes and Ohio River Division (LRD), and other Districts and Divisions within the continental United States granted capacity by the Contracting Officer. The Contractor shall perform all or part of the services described in these specifications, and those added by Task Orders that fall within the scope of this base contract.

This contract is for all types of geotechnical exploratory land drilling and inland floating plant drilling within the contiguous United States. Where special regulations exist, the Contractor shall notify the USACE prior to submitting a proposal in order to allow the USACE to clarify its needs based on the Contractor’s knowledge.

Work required under this Contract will generally fall under these categories:

a. Subsurface exploration, potentially in areas where Hazardous Toxic or Radioactive Waste may be encountered.

(HTRW work will be negotiated according to level of production and conditions.)

b. Subsurface exploration from a floating plant,

c. Inspection of Subsurface Explorations,

d. Instrumentation of exploratory borings,

e. Other tasked exploratory drilling services.

The purpose of the work described in this document is to determine the type, nature, characteristics, extent, and condition of various subsurface materials located in the borings drilled. The USACE anticipates that most of the land drilling will be at depths less than 200 feet and will in no case exceed 400 feet and most of the barge drilling will be performed at depths less than 100 feet, and will in no case exceed 200 feet.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.