FT_Eustis_CY17_Utility_Rates_Combined.pdf

PDF 72 KB Posted

Attached to
Aircraft Apron Airfield Site Improvements
Solicitation number
W91236-17-R-0001
Issued by

About this file

Ft. Eustis CY17 Utility Rates

View the file

Other files

File Type Posted
Amendment_0006_-_W91236-17-R-0001.pdf PDF
Amendment_0005_-_W91236-17-R-0001.pdf PDF
Amendment_0004_-_W91236-17-R-0001_Aircraft_Apron_Airfield_Site_Improvement.pdf PDF
Bidder_Inquiry_FINAL_23_Jan_18_-_ProjNet.pdf PDF
AM04_AVC_Phase_I.pdf PDF
Bidder_Inquiry_FINAL_22_Jan_18_-_ProjNet.pdf PDF
Amendment_0004_-_W91236-17-R-0001_Aircraft_Apron_Airfield_Site_Improvement.pdf PDF
Bidder_Inquiry_FINAL_22_Jan_18_-_ProjNet.pdf PDF
CJ113.pdf PDF
GC106.pdf PDF
CS113.pdf PDF
CS304.pdf PDF
LP113.pdf PDF
CS303.pdf PDF
CS107.pdf PDF
Amendment_0003_-_W91236-17-R-0001_Aircraft_Apron_Airfield_Site_Improvement.pdf PDF
CS301.pdf PDF
CP515.pdf PDF
CG143.pdf PDF
LP114.pdf PDF
LP107.pdf PDF
CS407.pdf PDF
Aircraft_Apron__Airfield_Timber_Inventory_-_Jul-2016.pdf PDF
CS402.pdf PDF
G-005.pdf PDF
CS403.pdf PDF
CS302.pdf PDF
CG137.pdf PDF
GC107.pdf PDF
GC105.pdf PDF
Sheets_621_631_721_731.pdf PDF
G-006.pdf PDF
AC_Revised_Sheets_2017-12-04.pdf PDF
AC_RTA_Geotech_Vert_2017-07-12.pdf PDF
DEQ_Plan_Approval_Letter_-_TRO-16-299_-_Aviation_Complex.pdf PDF
Amendment_0002_-_W91236-17-R-0001.pdf PDF
01_11_00.00_50_Revised_12.13.2017.pdf PDF
Aviation_Complex_Phase_I_Sign_in_Sheet_and_Summary.pdf PDF
ACPh1RTAPlansVol320171109.pdf PDF
ACPh1RTASpecsPart120171109.pdf PDF
AC_RTA_Geotech_Horiz_2017-07-12.pdf PDF
ACPh1RTAPlansVol1PartB20171109.pdf PDF
Amendment_0001_-_W91236-17-R-0001_Aircraft_Apron_Airfield_Site_Improvement.pdf PDF
W91236-17-R-0001_Aircraft_Apron_Airfield_Site_Improvement.pdf PDF
ACPh1RTAPlansVol1PartA20171109.pdf PDF
ACPh1RTASpecsPart320171109.pdf PDF
ACPh1RTAPlansVol220171109.pdf PDF
ACPh1RTASpecsPart220171109.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CY16 CY17 CY16 CY17 CY16 CY17 CY16 CY17 CY16 CY17

ELECTRICITY

0.07439/KWH 0.07008/KWH 0.11102/KWH 0.10674/KWH 0.10642/KWH 0.10325/KWH 0.10642/KWH 0.10325/KWH 0.09674/KWH 0.09386/KWH

WATER

5.49055/KGAL 5.52883/KGAL 9.62463/KGAL 14.06039/KGAL 9.34430/KGAL 13.65087/KGAL 9.34430/KGAL 13.65087/KGAL 8.49482/KGAL 12.40988/KGAL

WASTEWATER

5.87884/KGAL 6.28986/KGAL 10.15035/KGAL 12.23243/KGAL 9.85470/KGAL 11.87615/KGAL 9.85470/KGAL 11.87615/KGAL 8.95882/KGAL 10.79650/KGAL

REFUSE

N/A N/A 13.78/CUYD 15.73/CUYD 13.78/CUYD 15.73/CUYD 13.78/CUYD 15.73/CUYD 13.78/CUYD 15.73/CUYD

NATURAL GAS*

0.63386/CCF 0.58274/CCF 0.70922/CCF 0.67169/CCF 0.68856/CCF 0.65212/CCF 0.68856/CCF 0.65212/CCF 0.62596/CCF 0.59284/CCF

LP GAS*

FUEL OIL*

* Reimbursable customers are charged based upon actual bill from vendor

Highlighted in Green: Rate went DOWN for CY17

Highlighted in yellow: Rate went UP for CY17

SUMMARY

UTILITIES SALES RATES CY2017

CLASS C

NON-DOD FEDERAL

CLASS D

DOD FEDERAL

(INCL GOLF COURSE)

CLASS E

MWR

(EXCL GOLF COURSE)

MILITARY FAMILY

HOUSING

NON-FEDERAL &

COMMERCIAL

CLASS A CLASS B

12/14/2017

Virginia Electric and Power Company

Schedule GS-4

LARGE GENERAL SERVICE

PRIMARY VOLTAGE

(Continued)

Filed 04-29-15

Electric-Virginia

Superseding Filing Effective For Usage On and After 01-25-14. This Filing Effective

For Usage On and After 05-01-15.

I. APPLICABILITY AND AVAILABILITY

A. Except as modified herein, this schedule is applicable only to a non-residential transmission or primary voltage Customer (as defined in Paragraph XII.) (1) who elects (a) to receive Electricity Supply Service and Electric Delivery Service from the Company or (b) who is eligible for and elects to purchase Electricity Supply

Service from a Competitive Service Provider in accordance with Va. Code § 56-577

A and (2) whose peak measured demand has reached or exceeded 500 kW during at least three billing months within the current and previous 11 billing months.

B. For a Customer served under this schedule whose peak measured demand has decreased to less than 500 kW, this schedule shall remain applicable to the

Customer and the Customer shall not have the option to purchase electricity under

Schedule GS-1, GS-2, or GS-2T until such time as the maximum measured demand has remained at less than 500 kW during all billing months within the current and previous 11 billing months.

C. At such time the Customer no longer meets the above applicability requirements, the Customer shall remain on this schedule for the period (not exceeding two additional billing months) required to achieve an orderly transfer to the applicable schedule.

D. For new service, this schedule is applicable when the anticipated kW demand meets the above criteria.

E. For Customers who elect to purchase Electricity Supply Service from a Competitive

Service Provider, the provision of Electric Delivery Service only under this

Schedule shall not continue to be available to the Customer until an Agreement for

Electric Service the Company may require is executed between the Company and the Customer. Such agreement will be for Electric Delivery Service under this

Schedule or any other GS Rate Schedule (except Schedule GS-2T) the Customer may migrate to during the term of the agreement. Such agreement will have a minimum term of at least one year.

Superseding Filing Effective For Usage On

II. 30-DAY RATE

A. Distribution Service Charges

1. Basic Customer Charge

Basic Customer Charge $127.60 per billing month.

2. Plus Distribution Demand Charge

First 5000 kW of Distribution Demand @ $1.000 per kW

Additional kW of Distribution Demand @ $0.755 per kW

3. Plus rkVA Demand Charge @ $0.15 per rkVA

4. Plus Distribution kWh Charges

a. Distribution kWh Charge for All Customers

All kWh @ 0.006¢ per kWh

b. Plus Distribution kWh Charge for Non-exempt or Non-opt-out Customers

All kWh @ 0.000¢ per kWh

5. Plus each Distribution kilowatthour used is subject to all applicable riders, included in the Exhibit of Applicable Riders.

B. Electricity Supply (ES) Service Charges

Paragraph II.B. is not applicable to Customers receiving Electricity Supply Service from a

Competitive Service Provider.

1. On-Peak Generation Demand Charge

a. All On-Peak Electricity Supply Demand for

Primary Service Voltage @ $ 11.161 per kW

b. All On-Peak Electricity Supply Demand for

Transmission Service Voltage @ $ 10.873 per kW

Superseding Filing Effective For Usage On

II. 30-DAY RATE (Continued)

2. Plus Off-Peak Generation Demand Charge

All Off-Peak kW ES Demand @ $ 0.632 per kW

3. Plus Generation Adjustment Demand Charge

First 5000 kW of Demand @ ($0.421) per kW

Additional kW of Demand @ ($0.318) per kW

4. Plus Transmission Demand Charge

a. All On-peak Electricity Supply Demand for

Primary Service Voltage @ $ 2.371 per kW

b. All On-peak Electricity Supply Demand for

Transmission Service Voltage @ $ 2.310 per kW

5. Plus Generation kWh Charge

All On-peak ES kWh @ 0.404¢ per kWh

All Off-Peak ES kWh @ 0.272¢ per kWh

6. Plus each Electricity Supply kilowatthour used is subject to all applicable riders, included in the Exhibit of Applicable Riders.

7. Plus each kW of On-Peak Electricity Demand determined pursuant to

Paragraph VII., below, is subject to all applicable riders, included in the

Exhibit of Applicable Riders.

C. The minimum charge shall be as may be contracted for.

Superseding Filing Effective For Usage On

III. DETERMINATION OF ON-PEAK AND OFF-PEAK HOURS

The following on-peak and off-peak hours are applicable to the billing of all charges stated in this schedule.

A. On-peak hours are as follows:

1. For the period of June 1 through September 30, 10 a.m. to 10 p.m., Mondays through Fridays.

2. For the period of October 1 through May 31, 7 a.m. to 10 p.m., Mondays through Fridays.

B. All hours not specified in III.A. are off-peak.

IV. DETERMINATION OF DISTRIBUTION DEMAND

A. Distribution Demand shall be billed only where the normal service delivery voltage is less than 69 kV.

B. The Distribution Demand billed under Paragraph II.A.2. shall be such as may be contracted for but not less than the highest of:

1. The highest average kW measured at the location during any 30-minute interval of the current and previous 11 billing months.

2. 500 kW.

C. When the Customer's power factor is less than 85 percent, a minimum distribution demand of not less than 85 percent of the Customer's maximum kVA demand may be established.

V. DETERMINATION OF rkVA DEMAND

The rkVA of demand billed shall be the highest average rkVA measured in any 30-minute interval during the current billing.

VI. EXEMPTION AND OPT-OUT PROVISIONS FOR DISTRIBUTION KWH CHARGE

The Distribution kWh Charge in Paragraph II.A.4.b., above, shall not apply to Customers who are either exempt from or opt-out of such charge pursuant to Virginia Code § 56-585.1

A 5 c.

Superseding Filing Effective For Usage On

VII. DETERMINATION OF ON-PEAK ELECTRICITY SUPPLY DEMAND

The kW of demand billed under II.B.1. and II.B.4. shall be the highest of:

A. The highest average kW measured in any 30-minute interval of the current billing month during on-peak hours.

B. Seventy-five percent of the highest kW of demand at this location as determined under VII.A., above, during the billing months of June through September of the preceding 11 billing months.

C. 100 kW.

VIII. DETERMINATION OF OFF-PEAK ELECTRICITY SUPPLY DEMAND

The kW of demand billed under Paragraph II.B.2. shall be the off-peak demand which is in excess of 90% of the On-Peak Electricity Supply Demand determined under Paragraph VII.

IX. DETERMINATION OF ELECTRICITY SUPPLY ADJUSTMENT DEMAND

The kW of demand billed under Paragraph II.B.3. shall be the Distribution Demand determined under Paragraph IV.

X. METER READING AND BILLING

When the actual number of days between meter readings is more or less than 30 days, the

Basic Customer Charge, the Distribution Demand Charge, the rkVA Demand Charge, the On-

Peak Generation Demand Charge, the Off-peak Generation Demand Charge, the Generation

Adjustment Demand Charge, the Transmission Demand Charge, and the minimum charge of the

30-day rate will each be multiplied by the actual number of days in the billing period and divided by 30.

XI. STANDBY, MAINTENANCE OR PARALLEL OPERATION SERVICE

A Customer requiring standby, maintenance or parallel operation service may elect service under this schedule provided the Customer contracts for the maximum kW which the

Company is to supply. Standby, maintenance or parallel operation service is subject to the following provisions:

Superseding Filing Effective For Usage On

XI. STANDBY, MAINTENANCE OR PARALLEL OPERATION SERVICE (Continued)

A. Suitable relays and protective apparatus shall be furnished, installed, and maintained at the Customer's expense in accordance with specifications furnished by the

Company. The relays and protective equipment shall be subject, at all reasonable times, to inspection by the Company's authorized representative.

B. In case the Distribution Demand determined under Paragraph IV. exceeds the contract demand, the contract demand shall be increased by such excess demand.

C. The demand billed under II.A.2. and II.B.3. shall be the contract demand.

XII. DEFINITION OF TRANSMISSION, PRIMARY AND SECONDARY VOLTAGE

CUSTOMER

A. A transmission voltage Customer is any Customer whose delivery voltage is 69 kV or above and is the voltage that is generally available in the area.

B. A primary voltage Customer is any Customer (a) served from a circuit of 69 kV or more where the delivery voltage is 4,000 volts or more, (b) served from a circuit of less than 69 kV where Company-owned transformation is not required at the

Customer's site, (c) where Company-owned transformation has become necessary at the Customer's site because the Company has changed the voltage of the circuit from that originally supplied, or (d) at a location served prior to October 27, 1992 where the Customer's connection to the Company's facilities is made at 2,000 volts or more.

C. A secondary voltage Customer is any Customer not defined in XII.A. or XII.B. as a transmission or primary voltage Customer.

XIII. TERM OF CONTRACT

The contract shall be open order unless (a) standby, maintenance or parallel operation service is provided, or (b) the Customer or the Company requests a written contract. In such cases, the term of contract for the purchase of Electric Service under this schedule shall be as mutually agreed upon, but for not less than one year.