W911XK-09-B-0006 Amendment 0004 Conform.pdf

PDF 194 KB Posted

Attached to
RECOVERY--Z--Sturgeon Bay South Revetment Repair, Section N, Sturgeon Bay, Wisconsin
Solicitation number
W911XK-09-B-0006
Issued by

About this file

Amendment 0004 - Copy 2 - Conformed NEW BID SCHEDULE

View the file

Other files

File Type Posted
W911XK-09-B-0006 Sturgeon Bay Repair - Bid Abstract.pdf PDF
W911XK-09-B-0006 Amendment 0005 conform.pdf PDF
W911XK-09-B-0006 Amendment 0005 SF30.pdf PDF
W911XK-09-B-0006 Questions & Answers 12 June.pdf PDF
W911XK-09-B-0006 Amendment 0005 SF30.pdf PDF
W911XK-09-B-0006 Amendment 0005 conform.pdf PDF
14stbay_AMEND_5JUN09.pdf PDF
03stbay_AMEND_5JUN09.pdf PDF
09stbayAMEND_5JUN09.pdf PDF
16STBAY_AMEND_5JUN09.pdf PDF
W911XK-09-B-0006 Questions & Answers 9 June.pdf PDF
W911XK-09-B-0006 Amendment 0004 SF 30.pdf PDF
W911XK-09-B-0006 Questions & Answers 2 June.pdf PDF
W911XK-09-B-0006 Questions & Answers 29 May.pdf PDF
W911XK-09-B-0006 Amendment 0003 SF30.pdf PDF
W911XK-09-B-0006 Amendment 0003 conform.pdf PDF
W911XK-09-B-0006 Questions & Answers 27 May.pdf PDF
W911XK-09-B-0006 Amendment 0002.pdf PDF
W911XK-09-B-0006 Questions & Answers 22 May.pdf PDF
AMEND0001.maxFR —
W911XK-09-B-0006 Amendment 0001.pdf PDF
W911XK-09-B-0006 Amendment 0001 - Project Sign & Safety Sign.pdf PDF
09stbayAMEND0001.cal —
09stbayAMEND0001.maxTK —
12stbay.cal —
W911XK-09-B-0006 Solicitation.pdf PDF
14stbay.cal —
09stbay.cal —
02stbay.cal —
16STBAY.cal —
13stbay.cal —
01stbay.cal —
05stbay.cal —
11stbay.cal —
08stbay.cal —
10stbay.cal —
07stbay.cal —
SVDTITLE.CAL —
W911XK-09-B-0006 Specifications.pdf PDF
06stbay.cal —
04stbay.cal —
entry.maxFR —
plans.maxfr.maxFR —
03stbay.cal —
15STBAY.cal —
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911XK-09-B-0006-0004

W56MES90962392

AMERICAN RECOVERY AND REINVESTMENT ACT

FY09 Sturgeon Bay South Revetment Repair, Section N, Sturgeon Bay, Wisconsin

The business size requirement for this project is UNRESTRICTED. The NAICS code is 237990, w ith a small business size standard of $33,500,000.

The estimated cost range is $5,000,000 to $10,000,000.

X

THOMAS O MCKAY 313 226-6433

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-May-2009

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________270 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________16 Jun 2009 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIVISION

DETROIT DISTRICT, USAED

477 MICHIGAN AVE.

DETROIT MI 48226

W911XK

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

(313) 226-2209FAX:TEL: (313) 226-5148 TEL: FAX:

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W911XK-09-B-0006

Section SF 30 - BLOCK 14 CONTINUATION PAGE

AMEND 0002 - SPEC CHANGES

CHANGES TO THE SPECIFICATIONS

SECTION 05 50 14 MISCELLANEOUS METAL

DELETE: Paragraph 3.4

“TIE ROD PROTECTION”

ADD: New Paragraph 3.4

”TIE ROD PROTECTION

The Contractor shall protect each tie rod during placement of stone and backfill. Each tie rod shall be encased in solid walled SDR Schedule 26 or 40 PVC pipe as specified in the plan drawings. Pipe shall be continuous between wales. PVC pipe shall not be cut along its longitudinal axis for placement over the tie rod. Stone and/or backfill shall be placed such that the bottom of the pipe is fully supported and the tie rod is positioned in at the invert of the pipe as shown on the drawings. The invert of the PVC pipe shall be perforated.”

END OF AMENDMENT

AMEND 0003 - SPEC CHANGES

CHANGES TO THE SPECIFICATIONS

SECTION 01 22 00.00 10 MEASUREMENT AND PAYMENT

PARAGRAPH 1.2.1 a.

DELETE TEXT “First 1,375 short ton (Item No. 0002AA) and Over 1,375 short ton (Item No. 0002AB).

ADD TEXT “First 825 short ton (Item No. 0002AA) and Over 825 short ton (Item No.

0002AB).

PARAGRAPH 1.2.1 b.

DELETE TEXT “First 120 short ton (Item No. 0003AA) and Over 120 short ton (Item No. 0003AB).

ADD TEXT “First 70 short ton (Item No. 0003AA) and Over 70 short ton (Item No.

0003AB).

PARAGRAPH 1.2.1 c.

DELETE TEXT “First 2,620 short ton (Item No. 0004AA) and Over 2,620 short ton (Item No. 0004AB).

ADD TEXT “First 1,570 short ton (Item No. 0004AA) and Over 1,570 short ton (Item No.

0004AB).

PARAGRAPH 1.2.1 d.

DELETE TEXT “First 50 cubic yards (Item No. 0005AA) and Over 50 cubic yards (Item No. 0005AB).

ADD TEXT “First 30 cubic yards (Item No. 0005AA) and Over 30 cubic yards (Item No.

0005AB).

AMEND 0004 - SPEC CHANGES

CHANGES TO THE PLANS

Delete: SHEET 3 OF 16, SITE/SURVEY PLAN, REPRESENTATIVE CROSS SECTION, SURVEY HORIZONTAL CONTROL POINTS

Add: REVISED SHEET 3 OF 16, SITE/SURVEY PLAN, REPRESENTATIVE CROSS

SECTION, SURVEY HORIZONTAL CONTROL POINTS

Delete: SHEET 9 OF 16, STRUCTURE PLAN, SECTION Add: REVISED SHEET 9 OF 16, STRUCTURE PLAN, SECTION

Delete: SHEET 14 OF 16, STRUCTURE PLAN, EXCAVATION/BACKFILL CROSS

SECTION

Add: REVISED SHEET 14 OF 16, STRUCTURE PLAN, EXCAVATION/BACKFILL CROSS

SECTION

Delete: SHEET 16 OF 16, SECTIONS & DETAILS Add: REVISED SHEET 16 OF 16, SECTIONS & DETAILS

CHANGES TO THE SPECIFICATIONS

SECTION 01 22 00.00 10 MEASUREMENT AND PAYMENT

Delete: Paragraph 1.2.1 “a. Steel Sheet Piling (Item No. 0002): First 1,375 short ton (Item No.

0002AA) and Over 1,375 short ton (Item No. 0002AB)” Add to 1.1.1 Lump Sum Items: Steel Sheet Piling (Item No. 0002)

(1) Payment shall constitute full compensation for the cost of equipment, material, and labor for driving front wall and anchor wall SSP required in SECTION 31 41 17 STEEL SHEET PILING, SECTION 05 05 23 WELDING, STRUCTURAL and SECTION 05 50 14 STRUCTURAL

METAL FABRICATIONS.

(2) Unit of measure: Lump Sum.

Delete: Paragraph 1.2.2 “b. Miscellaneous Metals (Item No. 0003): First 120 short ton (Item No. 0003AA) and Over 120 short ton (Item No. 0003AB)” Add to 1.1.1 Lump Sum Items: Miscellaneous Metals (Item No. 0003)

(1) Payment will be made for costs associated with the installation of front and anchor wall walers, steel plate attachments, tie rod placement and bolted connections as required in

SECTION 31 41 17 STEEL SHEET PILING, SECTION 05 05 23 WELDING, STRUCTURAL

and SECTION 05 50 14 STRUCTURAL METAL FABRICATIONS.

(2) Unit of measure: Lump Sum.

Delete: Paragraph 1.2.4 “d. Excavated Rock (Item No. 0005): First 50 Cubic yards (Item No.

0005AA) and Over 50 Cubic yards (Item No. 0005AB)”

SECTION 02 13 90 SITE PREPARATION

Delete: SECTION 02 13 90 SITE PREPARATION Add: New SECTION 02 13 90 SITE PREPARATION

SECTION 02 13 90

SITE PREPARATION

04/09

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

The work required under this Section includes furnishing all materials and equipment and performing operations such as, but not limited to, clearing to the limits as indicated on the construction drawings, grubbing as necessary in the areas of anchor wall and tie-rod placement, excavation of stone fill immediately behind the Wakefield sheeting and stockpiling for re-use, excavation for tie rod and anchor wall placement, disposal of cleared materials and re-use of stone fill behind the proposed SSP wall. All work shall be conducted in a manner to prevent damage to the structures which are to remain and to maintain or improve the aesthetics and ecology of the site in accordance with SECTION 01 57 20.00 20, "ENVIRONMENTAL PROTECTION"). All work and materials shall be in accordance with the requirements specified herein and shown on the contract drawings.

1.2 SUBMITTALS

Government approval is required for submittals with a "GA" designation; submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with SECTION 01 33 00, entitled

"SUBMITTAL PROCEDURES":

SD-01 Data Construction Equipment; FIO

Prior to starting work, a list of all equipment, tools and machines, including their sizes, capacities and operating speeds, to be used in the performance of the work, shall be submitted. All equipment shall be maintained in satisfactory working condition at all times.

Work Plan; GA-AOF

At least ten (10) calendar days prior to proceeding with the work at the site, submit a work plan for the work required under this Section. The plan shall include a description of the means, methods, procedures and sequence in which the required work will be performed. The protective measures which will be taken to prevent damaging, disturbing, undermining or causing cave-ins at the existing revetments shall be described. The proposed locations of temporary stockpiles of excavated material shall be described in detail. List source(s) of material obtained off-site, if applicable. The locations of staging areas, equipment storage, docking of barges, mooring areas, vehicle parking, office trailers and other Contractor facilities shall be described and shown.

SD-18 Records Check Survey Records; FIO

A copy of the records of each check survey shall be provided on the next work day following the survey.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 REMOVAL OF OBSTRUCTIONS

The existing items which are to be removed to allow for the required construction work shall be as indicated on the drawings and specified herein. All of the area within the limits of the required work, as shown on the drawings, shall be cleared of vegetation, scrap, organic debris and other unsatisfactory materials. The waste materials obtained from these operations shall be disposed of as specified in Paragraph

"DISPOSAL."

3.2 EXCAVATION

Excavation shall be performed as shown on the plans. Excavated satisfactory materials shall be used as backfill for excavated space inside of the piling after it is driven. Excess excavated satisfactory material shall be evenly distributed behind the sheet piling. Steel sheet piles shall be placed as specified in SECTION 31 41 17 STEEL SHEET PILING. The stone fill removed for placement of the steel sheet pile shall be stockpiled for reuse. Common excavation shall also be in conformance with

SECTION 31 00 00 EARTHWORK.

3.3 REMOVING AND REPOSITIONING EXISTING STONE FILL

3.3.1 Placement of Existing Stone Fill

Approximate existing stone fill ranges from 3 pounds to 170 pounds. Existing stone fill that meets quality requirements in SECTION 35 31 19.45 03 STONE MATERIALS shall be excavated, stockpiled and reused in the areas as indicated in the plans. The Contractor shall use existing stone fill as an underlayment beneath new splash stone. The elevation of the stone fill shall be as shown on the drawings.

3.3.2 Placement of Excess Existing Stone Fill

As the existing stone fill is being removed and repositioned as shown in plans, the amount of material encountered in some areas may exceed the space available. Excess satisfactory material from these areas shall first be used to fill any low areas along the length of the project. Any excess existing stone fill shall be stockpiled as directed by the Government's On-site Representative. All required transitions from areas of work to areas of no work shall be neat and uniform.

3.3.3 Limitation

Excavation of the pile driving line or Wakefield Sheeting shall not proceed more than 50 feet in advance of completely driven piles. Placement of the excavated materials as backfill shall not lag more than 30 feet behind the lead fully driven pile.

3.4 STOCKPILING

As satisfactory material is excavated, it may be temporarily stockpiled for reuse in the required work. Surface stockpiles shall be maintained in neat and well drained condition.

Stockpiling shall be in an approved location. The material may be temporarily stockpiled on barges. At the completion of the work all temporarily stockpiled materials shall have been placed in the work in the required location or at a location as directed by the Government's On-site Representative.

3.5 SECTION REMOVAL

The existing Wakefield revetment structure front wall shall be removed in its entirety as shown on the drawings and properly disposed of off-site. The existing tie rods shall be cut at a distance so as not to interfere with SSP driving operations or excavation. The Contractor shall not cut tie rods further than 8 feet in advance of the SSP driving operations. Tie rods shall not be cut for more than a four (4) hour period of time prior to placement of proposed SSP wall. The existing timber anchor wall shall be left in place unless removal is necessary during tie rod placement. Excavated stone materials may be reused in accordance with their gradation in lieu of new stone materials.

Excess excavated soil and stone materials may also be used as fill on the land side of the SSP front wall after the wall has been completely constructed. Splash stone shall be used to protect fill stone as specified in SECTION 35 31 19, "STONE

PLACEMENT AND CONSTRUCTION".

3.6 DISPOSAL

All waste, excess and unsatisfactory materials except stone resulting from work required under this Section shall be removed from the site unless otherwise specified and directed and upon removal shall become the property of the Contractor.

All disposal shall conform to the requirements of SECTION 01 57

20.00 20, "ENVIRONMENTAL PROTECTION", including any applicable local requirements.

3.7 QUALITY CONTROL

The Contractor shall establish and maintain a quality control system for all operations performed under this Section to assure compliance with contract requirements and maintain records of its quality control for all operations performed, including, but not limited to, the following:

a. Removal work.

b. Excavating existing stone and Wakefield sheeting to accommodate steel sheet pile placement.

c. Backfilling.

d. Disposal.

e. Observance of safety regulations.

-- End of Section --

SECTION 31 00 00 EARTHWORK

Delete: SECTION 31 00 00 EARTHWORK Add: New SECTION 31 00 00 EARTHWORK

SECTION 31 00 00

EARTHWORK

07/06

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

The work required under this section includes furnishing all materials and equipment and performing operations such as, but not limited to, excavation of driveline for SSP placement, common excavation, backfill, grading and seeding. All work shall be conducted in a manner to prevent damage to the structures which are to remain. All work and materials shall be in accordance with the requirements specified herein and shown on the contract drawings.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C 136 (2006) Standard Test Method for Sieve

Analysis of Fine and Coarse Aggregates

ASTM D 422 (1963; R 2007) Particle-Size Analysis of Soils

ASTM D 1140 (2000; R 2006) Amount of Material in

Soils Finer than the No. 200 (75-micrometer) Sieve

ASTM D 1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method

ASTM D 1557 (2007) Standard Test Methods for

Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D 2487 (2006e1) Soils for Engineering

Purposes (Unified Soil Classification System)

ASTM D 2922 (2005) Density of Soil and Soil-

Aggregate in Place by Nuclear Methods (Shallow Depth)

ASTM D 4318 (2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils

1.3 DEFINITIONS

1.3.1 Satisfactory Materials

Satisfactory materials shall comprise any materials classified as course-grained soil in ASTM D 2487. Satisfactory stone materials for grading and backfill shall be less than 8 inches in size. Splash and scour stone shall meet the requirements specified in SECTION 35 31 19 STONE PLACEMENT AND CONSTRUCTION and SECTION 35 31 19.45 03 STONE MATERIALS. Testing required for classifying materials shall be in accordance with ASTM D 4318, ASTM C 136, ASTM D 422, and ASTM D 1140.

1.3.2 Unsatisfactory Materials

Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; and material classified as Fine-Grained and Highly Organic soils in ASTM D 2487. The Government's On-site Representative shall be notified of any contaminated materials.

1.3.3 Degree of Compaction

Degree of compaction required is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557 abbreviated as a percent of laboratory maximum dry density.

1.4 SUBMITTALS

Government approval is required for submittals with a "GA" designation; submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-18 Records Earthwork; GA-AOF.

Notification of encountering rock in the project. Advance notice on the opening of excavation.

1.5 CLASSIFICATION OF EXCAVATION

1.5.1 Common Excavation

Common excavation shall include the satisfactory removal of all materials as shown on the drawings. Excavation of debris may be necessary along the SSP wall to provide a clear channel bottom.

The Contractor shall dispose of sheeting material, unsatisfactory material and debris in accordance with SECTION

02 13 90, "SITE PREPARATION".

1.6 UTILIZATION OF EXCAVATED MATERIALS

Unsatisfactory materials removed from excavations shall be disposed of off-site. Satisfactory material removed from excavations shall be used, insofar as practicable, in the construction of fills, embankments, subgrades, bedding (as backfill), and for similar purposes. No satisfactory excavated material shall be wasted without specific written authorization. Satisfactory material authorized to be wasted shall be disposed of off-site in designated areas approved for surplus material storage or designated waste areas as directed.

Stone from excavations shall be stockpiled as designated on the plans. No excavated material shall be disposed of to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 GENERAL EXCAVATION

The Contractor shall perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified.

Grading shall be in conformity with the typical sections shown and the tolerances specified in paragraph FINISHING.

Satisfactory excavated materials shall be transported to and placed in fill or embankment within the limits of the work.

Unsatisfactory materials encountered within the limits of the work shall be excavated below grade and replaced with satisfactory materials as directed. Such excavated material and the satisfactory material ordered as replacement shall be included in excavation. Surplus satisfactory excavated material not required for fill or embankment shall be disposed of in areas approved for surplus material storage or designated waste areas. During construction, excavation and fill shall be performed in a manner and sequence that will provide proper drainage at all times.

3.2 BACKFILL

Backfill material shall consist of satisfactory material as described in Paragraph 1.3.1. Backfilling shall not begin until construction below finish grade has been approved. Backfill shall be placed in layers not exceeding 6 inches loose thickness for compaction by hand operated machine compactors, and 8 inches loose thickness for other than hand operated machine, unless otherwise specified. Each layer shall be compacted to 90 percent maximum dry density unless otherwise specified. Backfill shall be compacted up to the tie rod elevation and to each side of the tie rod following completion of backfill to grade. The Contractor shall ensure that the tie rods are not subjected to any vertical loads from compaction equipment. Backfill shall be brought to indicated finish grade.

Backfill shall not be placed in wet or frozen areas. The Contractor shall dewater as necessary to achieve proper compaction. Areas shown on the drawings that require stone backfill do not require compaction.

3.3 FINISHING

The surface of excavations, embankments, and subgrades shall be finished to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. The degree of finish for graded areas shall be within 0.1 foot of the grades and elevations indicated.

3.4 TESTING

Testing shall be performed by an approved commercial testing laboratory or by the Contractor subject to approval. If the Contractor elects to establish testing facilities, no work requiring testing will be permitted until the Contractor's facilities have been inspected and approved by the Government's On-site Representative.

3.4.1 Testing of Backfill Materials

Classification of backfill materials shall be determined in accordance with ASTM D 2487 and the moisture-density relations of soils shall be determined in accordance with ASTM D 1557. A minimum of one soil classification and one moisture-density relation test shall be preformed on each different type of material used for bedding and backfill.

3.4.2 Density Tests

Test density in accordance with ASTM D 1556 or ASTM D 2922.

Conduct one test per 2500 square feet in each lift. Include density test results in daily quality control report.

3.5 EMBANKMENT PROTECTION

During construction, embankments and excavations shall be kept shaped and drained. Ditches and drains along subgrade shall be maintained to drain effectively at all times. The finished subgrade shall not be disturbed by traffic or other operation and shall be protected and maintained by the Contractor in a satisfactory condition at all times during construction. The storage or stockpiling of materials on the finished subgrade will not be permitted.

3.6 SEEDING

All areas indicating backfill as shown on the plans shall require seeding.

3.6.1 Inspection

Seed shall be inspected upon arrival at the job site for conformity to species and quality. Seed that is wet, moldy, or bears a test date five months or older, shall be rejected.

Other materials shall be inspected for compliance with specified requirements. The following shall be rejected: open soil amendment containers or wet soil amendments; topsoil that contains slag, cinders, stones, lumps of soil, sticks, roots, trash or other material over a minimum 1-1/2 inch diameter; and topsoil that contains viable plants and plant parts.

Unacceptable materials shall be removed from the job site.

3.6.2 Storage

Materials shall be stored in designated areas. Seed, lime, and fertilizer shall be stored in cool, dry locations away from contaminants. Chemical treatment material shall be stored according to manufacturer's instructions and not with seeding operation materials.

3.6.3 Seed Classification

State-certified seed of the latest season's crop shall be provided in original sealed packages bearing the producer's guaranteed analysis for percentages of mixture, purity, germination, hard seed, weed seed content, and inert material.

Labels shall be in conformance with applicable state seed laws.

3.6.4 Seeding Conditions

Seeding operations shall be performed only during periods when beneficial results can be obtained. When drought, excessive moisture, or other unsatisfactory conditions prevail, the work shall be stopped when directed. When special conditions warrant a variance to the seeding operations, proposed alternate times shall be submitted for approval.

3.6.5 Finished Grade and Topsoil

The Contractor shall verify that finished grades are as indicated on drawings, and smooth grading, and compaction requirements have been completed prior to the commencement of the seeding operation. The topsoil thickness shall be a minimum of 8 inches.

3.6.6 Prepared Surface

New surfaces shall be blended to existing areas. The prepared surface shall be completed with a light raking to remove debris.

3.6.7 Installing Seed

Seeding method shall be broadcast seeding, drill seeding or hydroseeding. Seeding procedure shall ensure even coverage.

Gravity feed applicators, which drop seed directly from a hopper onto the prepared soil, shall not be used because of the difficulty in achieving even coverage, unless otherwise approved. Absorbent polymer powder shall be mixed with the dry seed at the rate recommended by the manufacturer.

3.6.7.1 Broadcast Seeding

Seed shall be uniformly broadcast at the rate of 8 pounds per 1000 square feet using broadcast seeders. Half the total rate of seed application shall be broadcast in one direction, with the remainder of the seed rate broadcast at 90 degrees from the first direction. Seed shall be covered a maximum 1/4 inch depth by disk harrow, steel mat drag, cultipacker, or other approved device.

3.6.7.2 Drill Seeding

Seed shall be uniformly drilled to a maximum 1/2 inch depth and at the rate of 8 pounds per 1000 square feet, using equipment having drills a maximum 7 inches distance apart. Row markers shall be used with the drill seeder. Half the total rate of seed application shall be drilled in one direction, with the remainder of the seed rate drilled at 90 degrees from the first direction. The drilling equipment shall be maintained with half full seed boxes during the seeding operations.

3.6.7.3 Hydroseeding

Seed shall be mixed to ensure broadcast at the rate of 500 pounds per acre. Seed and fertilizer shall be added to water and thoroughly mixed to meet the rates specified. The time period for the seed to be held in the slurry shall be a maximum 24 hours. Wood cellulose fiber mulch and tackifier shall be added at the rates recommended by the manufacturer after the seed, fertilizer, and water have been thoroughly mixed to produce a homogeneous slurry. Slurry shall be uniformly applied under pressure over the entire area. The hydroseeded area shall not be rolled.

3.6.8 Hay or Straw Mulch

Hay or straw mulch shall be spread uniformly at the rate of 2 tons per acre. Mulch shall be spread by hand, blower-type mulch spreader, or other approved method. Mulching shall be started on the windward side of relatively flat areas or on the upper part of steep slopes and continued uniformly until the area is covered. The mulch shall not be bunched or clumped. Sunlight shall not be completely excluded from penetrating to the ground surface. All areas installed with seed shall be mulched on the same day as the seeding. Mulch shall be anchored immediately following spreading.

-- End of Section --

SECTION 35 31 19.45 03 STONE MATERIALS

Paragraph 2.1.2.2 Acceptability of Stone Materials TABLE 1 Criteria for Stone Quality Delete Line: Test-Los Angeles Abrasion (2); Test Method-ASTM C535; Acceptance Criteria- < 25 percent loss after 500 revs.

Add Line: Test: Los Angeles Abrasion (2); Test Method: ASTM C535; Acceptance Criteria: < 35 percent loss after 500 revs.

AMEND 0001 - SPEC CHANGES

CHANGES TO THE SPECIFICATIONS

SECTION 01 35 13.10 SPECIAL PROJECT PROCEDURES

DELETE PARAGRAPH 1.4.3 GROUND AND OVER-WATER TRANSPORT

“All required on-land and over-water transport shall be provided by the Contractor. Contractor must be aware of and abide by all road restrictions imposed by Local, State or Federal Authorities. Over-land access to the required work area from the mainland is available only via walking along the concrete capped cribs as shown in the project drawings. The Contractor shall not use breakwater structure for storage or moving any equipment or supplies.”

ADD PARAGRAPH 1.4.3 GROUND AND OVER-WATER TRANSPORT

“All required on-land and over-water transport shall be provided by the Contractor. Contractor must be aware that Lake Lane road leading toward project site is a class B road and must be used to get to Barge road which provides the only land vehicle access to the site. Contractor must abide by all road restrictions imposed by Local, State or Federal Authorities.”

DELETE PARAGRAPH 1.8 AMERICAN RECOVERY AND REINVESTMENT ACT

DELETE AMERICAN RECOVERY AND REINVESTMENT ACT ATTACHMENT AT END

OF SECTION 01 35 13.10

DELETE SECTION 01 58 00 CONSTRUCTION PROJECTS AND SAFETY

PERFORMANCE SIGNS

ADD SECTION 01 58 01 PROJECT SIGN AND SAFETY SIGN

SECTION 01 22 00.00 10 MEASUREMENT AND PAYMENT

DELETE: Paragraph 1.2.4

(1) “e. Scour Stone (Item No. 0006): First 6,500 Short ton (Item No. 0006AA) and Over 6,500 Short ton (Item No. 0006AB).”

SECTION 01 35 13.10 SPECIAL PROJECT PROCEDURES

DELETE: Paragraph 1.7 VIBRATION MONITORING AND CONTROL DELETE: All submittals referencing vibration monitoring.

SECTIONS 35 31 19.45 03 STONE MATERIALS AND 35 31 19 STONE PLACEMENT

AND CONSTRUCTION

DELETE: All references to “Scour Stone”.

CHANGES TO THE DRAWINGS

DRAWING NO. 9 OF 16, STRUCTURE PLAN, SECTION

DELETE: Original drawing 9 of 16, STRUCTURE PLAN, SECTION ADD: Revised drawing 9 of 16, STRUCTURE PLAN, SECTION

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lump Sum

TAS::96 3135::TAS

FFP

Site Preparation FOB: Destination

PURCHASE REQUEST NUMBER: W56MES90962392

NET AMT

TAS::96 3135::TAS

FFP

Steel Sheet Piling

0002AA 1 Lump Sum

TAS::96 3135::TAS

FFP

First 825 Tons

0002AB 1 Lump Sum

TAS::96 3135::TAS

FFP

Over 825 Tons

TAS::96 3135::TAS

FFP

Miscellaneous Metals

0003AA 1 Lump Sum

TAS::96 3135::TAS

FFP

First 70 Tons

0003AB 1 Lump Sum

TAS::96 3135::TAS

FFP

Over 70 Tons

TAS::96 3135::TAS

FFP

Splash Stone

0004AA 1,570 Short Ton

TAS::96 3135::TAS

FFP

First 1,570 Tons

0004AB 1,050 Short Ton

TAS::96 3135::TAS

FFP

Over 1,570 Tons

DELETED

FFP

0005AA

DELETED

0005AB

DELETED

DELETED

0006AA

DELETED

0006AB

DELETED

SCOPE OF WORK

The required work consists of, but is not limited to, the relocation and re-use of stone fill, placement of 2041 lineal feet of SSP front and anchor walls with wall support hardware, removal and disposal of the Wakefield sheet wall and placement of splash and scour stone.

Section 00100 - Bidding Schedule/Instructions to Bidders

CLAUSES INCORPORATED BY REFERENCE

52.214-3 Amendments To Invitations For Bids DEC 1989 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids MAR 1997 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-21 Descriptive Literature APR 2002 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.222-5 Davis-Bacon Act--Secondary Site of the Work JUL 2005 52.232-15 Progress Payments Not Included APR 1984 52.232-38 Submission of Electronic Funds Transfer Information with

Offer

MAY 1999

CLAUSES INCORPORATED BY FULL TEXT

52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS

CONCERNS (JUL 2005)

(a) Definition. HUBZone small business concern, as used in this clause, means a small business concern that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration.

(b) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except--

(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and

(ii) Otherwise successful offers from small business concerns.

(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.

(3) A concern that is both a HUBZone small business concern and a small disadvantaged business concern will receive the benefit of both the HUBZone small business price evaluation preference and the small disadvantaged business price evaluation adjustment (see FAR clause 52.219-23). Each applicable price evaluation preference or adjustment shall be calculated independently against an offeror's base offer.

These individual preference amounts shall be added together to arrive at the total evaluated price for that offer.

(c) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes. The agreements in paragraph

(d) of this clause do not apply if the offeror has waived the evaluation preference.

___ Offeror elects to waive the evaluation preference.

(d) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for

(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;

(2) Supplies (other than procurement from a nonmanufacturer of such supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;

(3) General construction, at least 15 percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other HUBZone small business concerns; or

(4) Construction by special trade contractors, at least 25 percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other HUBZone small business concerns.

(e) A HUBZone joint venture agrees that in the performance of the contract, the applicable percentage specified in paragraph (d) of this clause will be performed by the HUBZone small business participant or participants.

(f) A HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business manufacturer concerns. This paragraph does not apply in connection with construction or service contracts.

(End of clause)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

1.0% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Sturgeon Bay, Door County, Wisconsin.

(End of provision)

52.225-22 NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND OTHER MANUFACTURED

GOODS—BUY AMERICAN ACT—CONSTRUCTION MATERIALS (MAR 2009)

(a) Definitions. “Construction material,” “domestic construction material,” “foreign construction material,” “manufactured construction material,” “steel,” and “unmanufactured construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Required Use of Iron, Steel, and Other Manufactured Goods—Buy American Act—Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-21).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of section 1605 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5) (Recovery Act) or the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-21 in the request. If an offeror has not requested a determination regarding the inapplicability of 1605 of the Recovery Act or the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) If the Government determines that an exception based on unreasonable cost of domestic construction material applies, the Government will evaluate an offer requesting exception to the requirements of section 1605 of the Recovery Act or the Buy American Act by adding to the offered price of the contract—

(i) 25 percent of the offered price of the contract, if foreign iron, steel, or other manufactured goods are used as construction material based on unreasonable cost of comparable manufactured domestic construction material; and

(ii) 6 percent of the cost of foreign unmanufactured construction material included in the offer based on unreasonable cost of comparable domestic unmanufactured construction material.

(2) If two or more offers are equal in price, the Contracting Officer will give preference to an offer that does not include foreign construction material excepted at the request of the offeror on the basis of unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-21, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer and a separate cost comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-21 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-21 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 million, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the USACE Detroit District, 477 Michigan Ave, 7th Floor, Detroit, MI 48226.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Tom O’Bryan Address: Grand Haven Area Office Telephone: (616) 842-5510

Section 00600 - Representations & Certifications

252.209-7001 Disclosure of Ownership or Control by the Government of a

Terrorist Country

JAN 2009

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2009)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is $33,500,000.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

(__) Paragraph (d) applies.

(__) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless--

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $100,000.

(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the clause at 52.204-7, Central Contractor Registration.

(iv) 52.204-5, Women-Owned Business (Other Than Small Business).This provision applies to solicitations that--

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(v) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(vi) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(vii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(viii) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(ix) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(x) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xi) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xii) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xiii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xiv) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xv) 52.225-2, Buy American Act Certificate. This provision applies to solicitations containing the clause at 52.225- 1.

(xvi) 52.225-4, Buy American Act--Free Trade Agreements—Israeli Trade Act Certificate.